You are on page 1of 2

7/28/2023

7/29/2023
7/30/2023
7/31/2023
8/1/2023
8/2/2023
8/3/2023
8/4/2023
8/5/2023
8/6/2023
8/7/2023
8/8/2023
8/9/2023
Task Name
Manure
Pumps and supports installation 6
Plumbing (Complete pump discharge piping) 7
Procure
Support Plumbing 9
Agitators and suports install 10
Compaction and Fill 11 x
Prep area around manure pit for concrete: clean up
edges and get accurate measure 12
Concrete near manure pit 13
Bollards 14 x
Receive Metal from AZZ
Metal Structure 16
Soil Haul off 17
Grating 18
Guardrail 19
Paint touch up 20
Procure cold galv
Chloride Tank
Set ladder and fill tank 23 x
Emergency shower 24
Install anchor cables 25
H2S
Anchor and epoxy 26
Grout 27 x
Remove existing piping 29
Reinstall new piping 30
Fill the H2S Towers 31
Tanks Area
Remove existing piping 32
Installation Vent piping 33 x
Repair misaligned flange 34
Add condensate drain to Digester riser. 36
Reinstall and complete 37
Fabrication of support for Vent piping 38 x
Procure?
Installation of supports for Vent piping 40
Painting pipe supprts 41
BioRem tower with carbon fill 42
Drywell
Fabricate Drywell suction pipe 44 x
Sleeve and grout and linkseal drywell 45
Procure sleeve, grout, epoxy sealant
Install Drywell pump 46
Grout Suction pump 47
Finish Fabrication discharge piping 48
Procure ? flex joint
Fabricate
Metal Structure 49
Paint touch up 50
CAL
Bolt up CAL piping finish 55
Finish CAL Piping pipe supports 56
Procure? Irod
Install
Blast and coated 16" pipe 59
LWR feed pump 60
Gas line pipe 61
Feed Pumps 62
Effluent Pumps 63
Fill Chloride tank 64
Motores 65
maquinaria

You might also like