Professional Documents
Culture Documents
Project Finance
© EduPristine – www.edupristine.com
© EduPristine Financial Modeling
Agenda
From inception of an idea to Financial Close, a Project Finance deal can take years to negotiate
All about identifying risks, allocating them appropriately and ensuring that the responsible parties are
adequately incentivized to manage their risks efficiently
Construction time, costs & specification
Operational cost, reliability
Supply reliability, quality, cost
Off-take volume, price
Political environment, war, local hostility, currency inconvertibility
Socio-environmental responsibilities
4
© EduPristine Financial Modeling
Risks & Mitigants
Funding Risk
Identification of sources for equity contribution.
Stipulation for minimum upfront equity contribution.
Disbursement only after financial tie-up for the project.
Regulatory Risk
All major statutory approvals including MoEF and forest clearance stipulated as a pre - disbursement condition
Concession agreement is reviewed commercially and risks identified
Suitable undertakings/guarantees are obtained from sponsors to negate any adverse affect of concession provisions
Financing of projects on time-tested concession formats approved by the Planning Commission
Market Risk
Independent consultant appointed by Lenders to conduct market potential/ traffic study
Project funding is structured based on cashflow projections to ensure smooth Debt servicing
5
© EduPristine Financial Modeling
Risks & Mitigants
Execution Risk
Contracts for Civil works/Procurement of equipment on a fixed time fixed price basis.
Contracts to be finalized before any disbursement
Reputation of EPC contractor considered
Suitable provisions for Liquidated damages/ penalty are incorporated in contract documents
Technology Risk
Projects based on proven technology are financed
Recourse stipulated in case of emerging technologies
6
© EduPristine Financial Modeling
Key Stakeholders
SPONSORS INSURERS
HOST LENDERS
GOVERNMENT
GUARANTORS OPERATOR
PURCHASER SUPPLIER
7
© EduPristine Financial Modeling
Contractual Arrangements to Mitigate Risk
8
© EduPristine Financial Modeling
Assumptions
11
© EduPristine Financial Modeling
Yearly Statement
12
© EduPristine Financial Modeling
Concept of Interest During Construction (IDC)
When an asset is developed, and there is a considerable period between the start of a project and its completion, the interest
costs related to the construction are generally included in the cost of the asset, that is, the interest cost is capitalized
The capitalization period ends when the asset is ready for use
While modeling in excel, Interest During Construction (IDC) introduces a circular loop into the sheet due to the circular
references explained below (1-2-3-4)
Equity and Grant commitments can be either a specific amount, or a certain percentage of the total project funds required (that
is, a fixed percentage in the capital structure)
We begin by inputting the project cost assumptions and the equity and grant commitments during
the period of construction
Next, we put the formula for total project cost (as sum of all project cost elements, including IDC)
Total Funding is made equal to the total project cost, by referencing it to corresponding cell
Debt to be raised is calculated as the funding gap in the project, after factoring equity and grant
commitments
We calculate the equity and grant commitments during the years of construction from the assumptions
Then, we calculate the total project cost which is the sum of all project cost elements and the Interest
During Construction (IDC). Note that IDC cells are left blank at this point, as they are yet ot be calculated
The Total Fund requirement is made equal to the Total Project Cost requirement
Finally, the Debt to be Raised is made equal to the Funding Gap in that particular year
The Interest During Construction (IDC) is calculated by multiplying interest rate on the outstanding debt
component and fed to corresponding cost element in project cost schedule
The sum of all the IDCs in each of the years of construction is then linked to the total IDC under Project
Cost break-up.
Shortfall in
DSRA/MMR DSR
Govt. Bodies
Balance
SPV Co. Surplus
17
© EduPristine Financial Modeling
Charting with Excel – modeling revenue recognition
Revenue Recognized
800
on the percentage completed 700
Case: An Infrastructure company has undertaken a project of 600
500
completing a bridge, construction work for which is going to 400
continue for the 5 years, and expected revenue earned at the 300
end of five years is Rs. 1,000,000,000 200
100
• The co. is expecting to build 10%, 25%, 25%, 25% and 15% in 0
each of the years 1 2
Year
3 4 5
Revenue Recognition
(Completed Contract)
Completed contract method 1000
900
Revenue Recognized
Revenue is recognized at the completion as a bullet 800
700
600
500
400
300
200
100
0
1 2 3 4 5
Year
Create Excel Models and Graphs to gain expertise in formulas and graphs
18
© EduPristine Financial Modeling
Cash Distribution and Tranches
ABC Investments and PQR Developers enter into a JV to develop and operate a project having the following characteristics
Initial Investments: INR 50 Mn
• ABC Investment: INR 45 Mn
• PQR Investment: INR 5 Mn
Project to be sold at the end of 5th Year (Net Profit from Sale: INR 75 Mn)
Cash Flow from Operations as shown in table
19
© EduPristine Financial Modeling
Total Cash generated in the project can be calculated
20
© EduPristine Financial Modeling
Cash Flow Tranches
22
© EduPristine Financial Modeling
Thank you!
Contact:
EduPristine
702, Raaj Chambers, Old Nagardas Road, Andheri (E), Mumbai-400 069. INDIA
www.edupristine.com
© EduPristine – www.edupristine.com
© EduPristine Financial Modeling