Professional Documents
Culture Documents
Lecture 2 (Site Servicing - Part 1)
Lecture 2 (Site Servicing - Part 1)
Week 2: Lecture 2
Site Grading and Part 1 of Site Servicing
Learning Outcomes
2
Site Grading
3
Site Grading
Topographic Survey:
Topographic survey results are required for site grading work.
Definition:
❖ Determines the relative locations of places on the earth's surface
with respect to horizontal distances, differences in elevation, and
directions.
Purpose:
❖ Produce topographic maps
❖ Construct topographic (cross-sectional) profiles
❖ Establish vertical and horizontal control to definelocations
accurately
4
Topographic
Drawing
Givesall
Existing
Elevations
on Site
Site Grading
Grading Drawing:
❖ Grading Drawing provides the following key information:
– Proposed elevations
– Finished floor elevation of thebuilding
– Parking lot elevations
– Sidewalk and curb elevations
– Drainage flow elevations, etc.
❖ Grading drawing can also include existing elevation (refer to
Kelson Project Drawings).
❖ Based on the existing and proposed elevations, the top
elevations of the subgrade are determined for both building
pad and parking lot areas → Needs Cutting and Filling.
6
Site Grading
7
Site Grading
11
Site Grading
12
Site Grading
Fine Grading:
❖ Second stage of grading work.
❖ The proposed elevations are
precisely achieved.
❖ There are equipment known as
“Fine Grader” to carry out fine
grading operation. A Multipurpose Utility Fine Grader
(Source: ForConstructionPros.com);
❖ Fine grading can be achieved Suitable for asphalt paving
contractors, general contractors,
using a bulldozer equipped with landscape contractors, and
Global Positioning System (GPS). municipalities.
13
Fine Grading with a GPSBulldozer
14
Fine Grading with a GPSBulldozer
– Haulage trucks
– Fine grader
– Levels (rough & precise)
17
Site Grading Equipment
19
Site Grading Equipment
❖ Site servicing means bringing mainly the following services into the
site and up to the buildings and is carried out by a site servicing
contractor:
• – Potable water line
– Sprinkler line •CCairvriileSditoeuStebryvitchinegc:ivilsite
servicing contractor in
– Sanitary line accordance with the site
servicing drawing
– Storm line
– Electrical line
Electrical Site Servicing
– Communication line
22
Civil Site Servicing
Drawing provides
information on:
➢ Potable water line
➢ Sprinkler line
➢ Sanitary line
➢ Storm line
➢ Invert/Obvert
➢ Service line plugs
➢ Flow type
➢ Flow direction,etc.
Civil Site Servicing Work
26
Civil Site Servicing Work
27
Civil Site ServicingWork
28
Civil Site Servicing Work
29
Civil Site Servicing Work
Nominal Minimum Recommended
Diameter,Ø, Trench Width,
in. (mm) in. (mm)
4 (100) 21 (535)
6 (150) 23 (585) Pipe Trenching – Minimum
8 (200) 25 (635)
10 (250) 28 (710)
Trench Width:
12 (300) 31 (790)
15 (375) 34 (865)
❖ Unless otherwise specified,
18 (450) 39 (990) the minimum trench width
24 (600) 48 (1220) shall be as to provide a
30 (750) 56 (1422)
36 (900) 64 (1625)
clearance of 150 mm on each
42 (1050) 72 (1828) side of the pipe.
48 (1200) 80 (2032)
54 (1350) 88 (2235)
60 (1500) 96 (2438
Source: http://www.ads-pipecanada.com
30
Civil Site Servicing Work
31
Civil Site Servicing Work
Pipe Bedding:
❖Pipe's ability to supportthe
overlying earth loads is
influenced by the bedding
support that the pipe has
under it and at its sides.
❖Improperly supported pipe
will be either damaged or
deformed (depending on the
type), causing leakage at the
pipe joints. ❖ The Haunch Zone is located directly above the
❖Bedding material should beat Bed Zone and extends to a height of between
the specified standard 10% and 30% of the outside diameter of the
density before laying down pipe above the Bed Zone.
the pipe. ❖ It provides support to the underside of the pipe
and shifts loads to the bed zone.
32
dm = 75 mm for I.D. ≤ 675 mm; dm = 100 mm for I.D. 750-1500 mm; dm = 150 mm for I.D. ≥ 1650 mm
33
Civil Site Servicing Work
Soil Compaction:
❖ Soil compaction is defined as
densification of soils by
removing air voids using
mechanical equipment such as
trench compactor or roller.
❖ In soils, compaction brings
about an increase in bulk
density, bearing capacity, and
unit weight, accompanied by a
decrease in air volume.
❖ Compaction also decreases the
undesirable settlement of soils
due to loading.
34
Civil Site ServicingWork
Soil Compaction:
❖ Compaction depends on the type of soil, compactive energy, and soil water
❖ The types of soil based on compactability: Type 1 – Consolidated clay; Type 2 –
Silty clay; Type 3 – Sand; Type 4 – Wet and muddy soil
❖ Type 1 and Type 2 soils are compactable whereas Type 3 and Type 4 are non-
compactable
35
Civil Site ServicingWork
Soil Compaction:
❖ Compaction is a function of water content;
water added to the soil during compaction
acts as a lubricant for the soil particles.
❖ Optimum moisture content (OMC) is that
content of water in soil at which the
maximum dry unit weight can be attained
as a result of a given compaction effort.
❖ Dry density = (Wet density)/(1 + Moisture
content as a fraction)
❖ The optimum moisture content of soil is
determined in the lab through a test
widely known as “Modified Proctor Test”.
❖ Bedding and backfill materials should be
compacted properly at the OMC. Source: LandscapeOnline.com
36
Civil Site Servicing Work
Pipe Laying:
▪ A crawler pipe
layer is used to
lower the pipes
on compacted
bedding in a
trench.
▪ Most common
in ICI
construction
works.
(Source: www.oilandgasproductnews.com)
37
Civil Site ServicingWork
Service Line Plugs:
❖ Once the civil site services are brought to the buildingsite
➢ They are taken at or close to the building pad of each buildingto
be constructed.
➢ Are capped about 2 feet above the finished floor level and left
there by the civil site servicing contractor (plumbingcontractor)
➢ These capped connection points are called “service line plugs”.
❖ At a future stage of the project, the capped services are distributed
further inside the building by the plumbingcontractor.
❖ It is also the responsibility of the plumbing contractor toget services
connected with the city mains and to get all the tests passed before
the services can be opened up for use.
38
Civil Site ServicingWork
Source:
http://knockdownrebuildcosmopolitan.blogspot.ca
39
Civil Site ServicingWork
❖ Some of the materials and components used in civil site servicing
include:
– Ultra-rib PVC pipe
– Pressure rated steel and PVC pipes
– Concrete pipe
– Embedment materials (bedding & backfill materials)
– Catch basins and manholes
– Benching
– Unshrinkable fill
– Oil/grit separator (Stormceptor)
– Sub-drain/weeping tile
– Tracer wire
– Valve and box
– Siamese connection
40
Ultra Rib PVCpipe
42
Concrete Pipe Used inOntario
44
Strength Classes of ConcretePipe
Three-Edge-Bearing Strength (lb/ft) of Non-Reinforced Concrete Pipe
45
Strength Classes of ConcretePipe
Non-Reinforced Sewer and Culver Concrete Pipe according
to CSA
46
Strength Classes of ConcretePipe
Classes of Reinforced Concrete Pipe:
❖ Classified based on the design load
that causes 0.3 mm wide crack
without failure during flexuretest.
❖ Five strength classes of reinforced
concrete pipe according to ASTM.
❖ Four strength classes of reinforced Flexure Test of Concrete Pipe
(Source: www.ikt-online.org)
concrete pipe according to CSA.
47
Pressure RatedPipes
❖ Pressure Rated Copper and Steel Pipes
❖ Pressure Rated PVC pipes – normally used for water mains; rated based
on pressure (psi) and standard dimension ratio (SDR) or dimension ratio
(DR); commercial example: BlueBrute Piping Systems
Note: The numbers 100, 150, and 200 represent pressure in psi that a pipe can withstand without
leakage; higher the pressure rating number, better the quality of the pipe.
48
Standard Dimension Ratio(SDR)
❖ "Standard Dimension Ratio" - SDR – is a method of rating
pressure piping
49
Standard Dimension Ratio(SDR)
50
Alternative Site Servicing Materials
and Methods
❖ Alternative materials to produce site servicing products such as
different types of concrete pipe: for example, industrial wastes–
fly ash, ground slag, etc. and quarry waste – quarry dust can be
used in concrete making
❖ Alternative bedding materials such as recycled concrete
aggregate obtained from waste concrete and building demolition
as well as quarry waste aggregate can be used in pipe bedding
❖ Alternative backfill materials: locally available coral, slag, cinders,
and crushed shells; unshrinkable flowablefill
❖ Alternative installation techniques: trenchless technologies –pipe
jacking, micro-tunneling, boring, etc.
51
Coordination Requirementsand
Typical Inspections
❖Good coordination is required among civil, electrical and mechanical
site servicing contractors to avoid any mistake and accident.
❖A coordination document is prepared for the workers of more than
one employers who perform work in the same project site.
➢ Identify coordinated works, duties of workers, communication
methods, adequate means of entering and exiting, etc.
❖Typical Site Servicing Inspections:
➢ Grading and excavation works
➢ Potable water and sprinkler lines
➢ Storm and sanitary sewers
➢ Catch basins and manholes
➢ Fire hydrants
52
Coordination Requirementsand
Typical Inspections
❖ Final Approval - Requires the submission of engineeringinspection
and testing reports as applicable,including
➢ Chlorination documentation
➢ Water line leakage test
➢ Sprinkler line leakage test
➢ Sanitary sewer air leakagetest
➢ Storm and sanitary smoke test whereapplicable
❖ Occupancy will not be granted until site servicing works are
approved, and all the requirements of the Building Permithave
been met.
53
Lesson Summary
1. Site grading
2. Different civil site servicing works
3. Materials, components, and equipment used in
civil site servicing works
4. Alternative site servicing materials and
methods
5. Coordination requirements
6. Typical inspections