Professional Documents
Culture Documents
December 2013
CHAdeMO Association
< Table of Contents >
5. User Service
5.1 Methods for Informing Users about Quick Charger Installation Locations
6. Afterword
Power cable
Lead-in
Road
Power Instrument Converter
Line
Switch
Road
Building Quick
Parking
Charger
Foundation
(a)
However, the acceptable current tends to decrease 20kW
as the charged amount is recovered. Therefore, in
(b)
an area that the battery can be charged with the
maximum current, charging time will be shortened Time(min)
depending on the maximum current that quick (A)When remaining battery level is low
charger outputs.
Difference in charging time
With reference to the time that charging is
CurrentA(
b. Initial cost
When you calculate an initial cost to install quick chargers, you need to consider a cost of
power-supply equipment in addition to a cost of chargers.
c. Running cost
When you calculate a running cost after installing chargers, electricity bill and maintenance
cost shall be considered.
EVs, charger location map, etc. Table July 172 7.8 34:24
since November 2011. The total usage Sep. 157 7.6 34:10
6
Times
Spare
Spare
< Figure 3-3-2 Low Voltage Input Board (Example) Figure 3-3-3 Low Voltage Input Board (Example) >
Indicator
Empty Space
Inlet Location on EV
]Leaf: Front-center Stella: Back-right i-MiEV: Back-left
Stella: i-MiEV:
Leaf: Front-center
Figure 3-6-1
However, consideration must be given to the side the cable extraction port is located on the
quick charger because even if the quick charger is installed in the same location the connector
may not reach to the inlet. (Refer to Appendix 3)
1. QC installation location
Photo 3-6-2
In the case of cable length is 3 meters;
i-MiEV and LEAF were able to be charged
without any problem. Figure 3-6-2
Photo 3-6-3
3. Reverse parking
Lengthening the cable about 0.8 meters is necessary for reverse parking. (Photo 3-6-4)
Photo 3-6-4
Photo 3-6-5
To prevent vehicles from driving over cables, when charging cable is lengthened, considering
how to wind cables and a distance between chargers and car stoppers are important, and a
caution to charger users is also necessary. Photo 3-6-5 is a charger with a 10-meter cable which
was installed for our demonstration test.
Longer cables make the handling difficult, and there is a tendency that cables are left without
being put back on the proper position. This increases a risk of tripping, damage to cables by
driving over, etc.
Leaf
Making the space as wide as possible also
aids in improving convenience to the user
by securing operation space.
On the other hand, vehicles are getting
larger, and positions of charge ports are
different depending on vehicles. These
Stella
out a vehicle.
Photo 3-6-10
In the case of an underground parking lot as shown in Photo 3-7-4~5, cables can be passed
through conduits attached to the wall thereby decreasing construction costs as opposed to if
digging was required.
Photo 3-7-7
Photo 3-7-6
Figure 3-7-2
a. Car stop installation
Car stops are installed to prevent the vehicle
from colliding with the quick charger, so the
farther away they are installed the better,
however the length of the charging cable on
current quick chargers is often approximately
five meters so they cannot be too far away.
Automobiles and electric vehicles (EV) these
days have long wheelbases and the distance from
the back wheels to the bumper is relatively short
so installing car stops approximately one meter Photo 3-7-8
QC Top View
Pole
Pole
Figure 3-7-9
Photo 3-7-20
Photo 3-7-21
Photo 3-7-22
*Should be implemented after consultation with the manufacturer in cases where low voltage is
supplied.
Abnormal Shut-Off
Display Panel:
Sorry for the inconvenience.
Please contact the manager. If unable to
Display panel for indicating contact the managing company, hold the
operation status “STOP” for button down for 3 seconds.
Figure 4-3-2
Locked
Interphone
Connector folder
Installation
Figure 4-4-1
An example of a sign in common use is “CHARGING PONT” (Figure 5-1-1). The sign shown
in the figure is a registered TEPCO trademark. So to use it, you must apply with TEPCO and
execute a usage authorization contract that stipulates the terms of usage.
These signs may only be used to indicate the installation locations of chargers that can be
accessed by an undetermined number of people.
Figure 5-1-1
Figure 5-2-2
6. Afterword
We have discussed the background and objectives, but it will be difficult to completely
optimize the recharging infrastructure if each business operator acts independently. Hence,
collaborative efforts that lead to EV user convenience are necessary. At the CHAdeMO
Association Infrastructure Workshop, these issues have been compiled into this manual through
Infrastructure Workshop WG Activities, so that they will be of use when considering the
introduction of EV/recharging facilities and charging services. We hope that this will lead to the
sharing of information between more people and the spread of EV.
Given that the “Guidebook for Charging Facility Installation” created by the Ministry of
Economy, Trade and Industry will be released in November, this manual had to be put together
in a very short amount of time. We would like to offer our gratitude to all those that helped in its
creation.
(4) Wiring a. Confirm that the cable routes to the charger a. Confirm that there are no
Route Survey installation location can be secured. obstacles in the way of the
b. Deliberate cable installation method. cable route.
(a) If the electric room is indoors: b. Refer to 3.4 Deliberation
Electric room→Inside→Outside→Charger of the Power Source Cable
(b) If the electric room is outside: Installation Route
Electric room→Outside→Charger.
(4) Wiring a. From the power lead-in to the newly a. Refer to 3.4 Deliberation of
Design built electric room. Power Source Cable Installation
(a) Confirm electricity lead-in point and Route
lead-in method. b. Confirm route from existing
(b) Confirm location of power source panel to
receiving/transforming equipment receiving/transforming equipment
installation. c. Confirm that there are no
(c) Confirm power cable route for the obstacles to the cable installation
existing load. route.
(d) Deliberate the installation method and
route from the receiving/transforming
equipment~existing power source panel.
b. From the newly built electric room to
the quick charger installation location.
(a) Confirm that the cable route to quick a. Confirm that there are no
the charger installation location can be obstacles in the way of the cable
secured. route.
(b) Deliberate the installation method. b. Refer to 3.4 Deliberation of
(same as for high voltage receiving.) the Power Source Cable
Installation Route
(5) Wiring a. Design of receiving equipment (newly
Route Survey built electric room)
(a) Deliberate the power configuration a. Deliberate the transformer
from the existing load to newly installed type by an outside or inside
quick charger capacity. location.
(b) Selection of transformer capacity/type.
b. Low voltage trunk line design b. Independent wiring is
(a) Configure input trunk line system. recommended for chargers.
(b) Confirm distance from electric room. c. Deliberate shortest route in
NO Check List
1 Have you selected a conduit that fits the size of the power cables?
2 Does the size take into account wiring connections, wires that pass through, cable
bending radius and the number of conduits in the pull box?
3 In the case of cables pulled horizontally, can the box be installed within 30m?
4 Are no more than 3 right angle bends necessary between the boxes?
5 Can the protruding conduit pull box be installed at an interval that fits the power cable
Conduits
size?
6 Is the box installed in a location that enables inspections?
7 Are conduit support intervals appropriate?
8 Is there space between conduits around the panel/EPS?
9 Are the cable holes in the wall positioned to prevent water seepage?
10 Can cables be installed away from rooms that use water such as the kitchen or machine
room?
11 Does the building have an expansion joint?
12 Is the area prone to damage from salt, snow, water or wind?
1 Can you install a cable rack suited for cable size, the number of cables, and installation
location?
Cable Racks
2 Is the cable rack a width that considers the interval between cables?
3 Can holes in the floor or walls (especially within EPS) be made fireproof easily?
4 Are cable rack support intervals appropriate?
5 Is the area prone to damage from salt, snow, water or wind?
1 Can you dig deeper than expected?
Buried Conduits
2 Are there any obstacles near the lead-in poles, poles on the premises or near the
installation location of feeder lines?
3 Are there any height restrictions on the premises?
4 Is the area prone to damage from salt, snow, water or wind?
* Expansion joint: Releases the energy generated by an earthquake to prevent buildings from
deforming.
Centered
Cable Leaf Normal 2,640 4,166 3,813
Right side (Parked Does not ― 2,985 ― Car stop Car stop
(Cable is frontward) touch ground
extracted from i-MiEV Normal 3,524 3,190 4,215 Placed Placed
on left on right
right side of QC (Parked Does not ― ― 3,935
when facing it) backwards) touch ground
Stella Normal 4,216 (1)4,688 3,190
(Parked Does not 3,043 4,322 ―
backwards) touch ground
Cable Leaf Normal 2,640 3,813 4,166
Left side (Parked Does not ― ― 2,985
(Cable is frontward) touch ground
extracted from i-MiEV Normal 4,216 3,190 (2)4,688
left side of QC (Parked Does not 3,043 ― 4,322
when facing it) backwards) touch ground
Stella Normal 3,524 4,215 3,190
(Parked Does not ― 3,935 ―
backwards) touch ground
1) Cable Status:Normal=Cable extends from inlet, lays on ground and connects to QC (Photo 1)
Does not touch ground= The cable does not touch the ground (hanging mid-air) (photo 2)
2) QC Installation Loccation
<Centered> Car stops (tire side)~Front of QC: 1.2m→Cable length of 4m suitable for allvechicles
<Right/Left> Center of parking spot~Front of QC: 1.5m QC installed above car stop tire side line)
Only part exceeds 4m. (4m cable is not long enough)
(Photo 1)Normal (Photo 2)Does not touch ground
Plug-in i-MiEV