1. Introduction

The Brazilian government has published the NF-e Technical Note 2023.001 introducing fields and
validation rules. This document guides you through the post-implementation steps that are
necessary to perform Sales and Distribution changes related to this technical note.
1.1 Purpose
The purpose of this document is to guide you on the implementation steps to create new objects
for the NF-e Technical Note 2023.001.
1.2 Scope
This document guides you through the steps that you need to follow for the NOTE_3310181 UDO
report.

2. UDO Report
2.1 Execution of NOTE_3310181 Report

Perform the manual steps in each system into which you transport the SAP Note for
implementation.

2.1.1. Since report NOTE_3310181 has been developed to be executed in English


only, we recommend that you log on in English.
2.1.2. Access the ABAP Editor: Initial Screen (SE38) transaction, enter
“NOTE_3310181” in the Program field and press Execute.
2.1.3. Select TESTRUN and execute the report.
2.1.4. Check the Simulation Log and ensure that all the messages have a green traffic
light. If there are any warnings and/or error messages that you cannot solve
yourself, create a customer incident under the corresponding component of
NOTE_3310181.
2.1.5. Go back (choose Back or press F3 on your keyboard), select UPDATE &
ACTIVATE, and execute the report again.
2.1.6. The system prompts you to either activate your objects online or in batch mode.
The online mode is recommended as this enables you to see any activation
issues immediately. Use the batch mode option only if activation in online mode
fails with a time out.
2.1.7. Within the Change Log, the system displays a list of all objects processed.
Ensure that all the displayed messages are warnings or information messages. If
there are any warnings and/or error messages that you cannot solve yourself,
create a customer incident under the corresponding component of
NOTE_3310181. If you have selected to activate the objects in batch mode (see
step 2.1.6), check the activation log of the job as explained in the message text
of the Detailed Log.
2.1.8. Select the node with the last execution log (according to the date and time) and
ensure that there are only information messages (green traffic lights). If there are
any warnings and/or error messages that you cannot solve yourself, create a
customer incident under the corresponding component of NOTE_3310181.
2.1.9. If any inactive objects are detected during the release of your transports, execute
the step 2.1.5 to update and activate again.