Professional Documents
Culture Documents
Project-Schedule-Development (Part-2)
Project-Schedule-Development (Part-2)
SCHEDULE
DEVELOPMENT
www.coachirwan.com
Topics to be Covered
❑ PMBoK Scheduling process
❑ Key scheduling process
❑ Scope definition
❑ Work Breakdown Structure (WBS)
❑ Activity sequencing
❑ Activity resource planning
❑ Activity duration estimate
❑ Create project schedule
❑ Cost estimating & budgeting
2
1. PMBoK Scheduling process
Plan schedule management
Sequence activities
Estimate durations
3
2. Key scheduling process
Schedule
Management
Activity
Scope Sequencing
Definition
Create
Schedule
Create WBS
Activity Activity
Resource Duration
Planning Estimating
Cost Cost
Scope Estimating Budgeting
Management
Cost Management
4
Scope Definition
6
WBS Example
UNIVERSITY PROJECT
PROJECT 1.
PHASE
1.1 1.2 1.3 1.4 1.5
Planning Design Procurement Consruction Handing over
1.1.2 1.1.3
ACTIVITY 1.1.1
Estimate cost Approval of
Define Scope
of project scope and budget
7
WBS Example
WZ Project
Work Package
1.2.1.1
8
9
10
Activity Sequencing
Method of
Construction
Construction &
Shop Drawing
Work Procedures
12
Link: Contractual requirements
Temporary utility
services
Development order
13
Link: Resource optimisation
Repetitive
activities
Resource
smoothing
Resource levelling
14
■ Specify the sequence/logical relationship
between project activities/works
■ Attributes to be considered:
1. Predecessor
2. Successor
3. Link/relationship type
Sequencing attributes 4. Lead time
5. Lag time
6. Task constraint
15
1. Predecessor & 2. Successor
1 Predecessor 2 Successor
Predecessor Act. A
Act. B Successor
16
Example of predecessor & successor
17
3. Relationship (link) types
18
3. Relationship (link) types
19
4. Lead time
■ Starting the activity earlier
■ Example:
Structure work to start 5 days before earthwork completed
FS – 5d Earthwork
Structure work
5d
Lead time
20
5. Lag time
■ Delaying the activity
■ Example:
Structure work to start 5 days after earthwork completed
FS + 5d Earthwork
Structure work
5d
Lag time
21
6. Task constraint
■ Restrictions that are imposed on tasks to start or finish on a certain date
■ There are three types: soft, flexible, and hard constraints
– Soft: does not have any date restriction (ASAP, ALAP)
– Flexible: imposed date restriction, but only control the earliest or latest
start or finish dates (SNET, FNET, SNLT, FNLT)
– Hard: impose a date restriction and can be seen as a “must” (MSO,
MFO)
■ To maintain the dynamic of the schedule, it's advisable to use the default
setting (ASAP)
22
Activity Resource
Planning
v
Application of 4M in
Manpower, machinery, estimation Contract cost Vs Cost
material & money (4M)
24
Activity Duration
Estimate
25
Duration estimation technique
26
Duration estimation technique
27
Duration estimation technique
PERT Delphi
28
Example: Parametric estimation + risk
Duration = (Quantity/Production rate) + risk consideration
Parametric = 100,000 m3
Duration 2G x 1,000 m3/day
= 100,000/2,000
= 50 days
Risk (20%) = 50 days x 0.2
= 10 days
Duration = 50 + 10 days
= 60 days
29
Exercise: Duration estimate using parametric + risk
Procurement:
4 M&E 2 40 2,400 80 35 d
5d
30
Create Project
Schedule
32
Critical path analysis
2 Step:
ES Dur EF
1. Forward pass EFpre = 1/6
ES = 2/6; Duration = 5
Description
ES = EFpre + 1 EF = 2/6 + 5 – 1 = 6/6
EF = ES + Dur – 1
LS Total Slack LF LSsuc = 12/6
2. Backward pass
LF = 11/6; Duration = 5
LF = LSsuc - 1 LS = 11/6 – 5 + 1 = 7/6
LS = LF – Dur + 1
11/6 – 6/6 = 5 d
Total slack (Float)
7/6 – 2/6 = 5 d
= LF – EF or
= LS – ES
33
Activity details
Activity Predecessor Duration
Start - 0
C – Write specification A 7
D – Notify factory A 4
E – Build prototype B, C 5
F – Setup production D 4
G – Commence production C, E, F 3
Finish G 0
34
Critical path analysis
6/6 6 11/6 13/6 5 17/6
B E
7/6 1 12/6 13/6 0 17/6
D F
10/6 4 13/6 14/6 4 17/6
35
36
■ Technique to shorten project duration
■ Consist of two methods: Fast tracking &
crashing
■ At planning stage: to shorten the
schedule in order to meet Start Date &
Finish Date as stipulated in the Letter of
2. Schedule compression Tender Acceptance
■ At construction stage: to shorten the
schedule in order to mitigate delay in
project progress
■ Technique involves setting deadline and
identifying negative float
37
Fast Tracking
38
Crashing
Shorten duration by:
i. Increase working hours; or
ii. Increase resources
Duration = Quantity / Production rate
39
3. Resource
Levelling
40
Over allocated & under allocated resource
Over-allocated
Allocated
41
Cost Estimating
and Budgeting
42
Cost & budget estimation
43
Example: Cost estimation
44