Professional Documents
Culture Documents
Contract Change Order
Contract Change Order
Some experts argue that Amendment and Addendum are the same terms or have
equivalent meanings. Both of these terms have the meaning of changes or additions
and subtractions.
So that it can be said that addendums and amendments are not substantially
different, only the use of the two terms is more commonly used in one topic, namely
addendums are used in an agreement/agreement or contract, while amendments are
used for changes to laws or written legal basis.
2.) Additional work is carried out under the following conditions: not exceeding 10%
(ten percent) of the price stated in the initial agreement/contract; and there must be
a budget available to carry out additional work.
3.) The Contractor is prohibited from diverting the implementation of the main work
under the Contract, by subcontracting to other parties, except for some of the main
work to specialist Goods/Services providers. If it violates, it will be subject to
sanctions in the form of fines in the form and amount in accordance with the
provisions as stipulated in the Contract Documents.
4.) Changes to the contract caused by administrative problems, can be made as long
as it is agreed by both parties
IMPACT OF CONTRACT CHANGE ORDER (CCO)
The impact of CCO on construction projects is very large if not properly
anticipated. Examples of direct impacts are disrupted workflow, increased
construction costs due to volume and material additions and time adjustments,
rescheduling of implementation after changes in work, conflicts between contractors
and owners, and so on.
In general, the impact of CCO can be divided into five categories, namely:
1. CCO impacts time
Contract change orders in construction projects are one of the causes of time delays
due to time overruns. Impacts related to time include delays in completing work,
delays in logistics, delays in material and procurement requirements, rework,
demolition and re-planning.
2. CCO has an impact on costs
The impacts of CCO related to costs include additional costs, additional overhead
costs, compensation funds, changes in cash flow, loss of profits and additional
payments for contractors.
3. CCO has an impact on productivity
The CCO of construction work will affect productivity, including a decrease in work
productivity both in equipment and in human labor, there is compaction in the project
implementation schedule.
4. CCO has an impact on increasing the level of risk. Legal Basis and Definition of
Contract
CCO will also result in an increase in the impact of the level of risk on the project,
including delays in project progress, reduced opportunities for project acceleration,
loss of float, increased sensitivity to delays, obstacles in the field/work location and
disruptions to each work.
5. The relationship between the impact of CCO and others.
The other impacts of having a CCO on a project include a low professionalism
relationship between the PPK and the Provider, the occurrence of claims and
disputes, the low quality and quality of work, damaging the good name of the
contractor, and the occurrence of poor security conditions.
In the implementation of construction work, it is certain that CCO will occur. CCO is
carried out so that a project can be completed with the aim of fulfilling the wishes
and expectations of service users. However, on the other hand, if there are lots of
CCO, it will be detrimental to construction projects. Therefore, efforts are needed to
minimize changes along with the impact of CCO, namely there must be the most
effective and targeted CCO management/control in order to achieve the objectives
of the construction project.
Source: https://www.pengadaanbarang.co.id/2019/08/contract-change-order-cco.html