Professional Documents
Culture Documents
GT600 Installation Rev3
GT600 Installation Rev3
INSTALLATION MANUAL
FOR THE
Including:
CONFIGURATION :
A Dreyer Date
QUALITY :
ASSURANCE
P Pretorius Date
MARKETING :
KL Simpson Date
ENGINEERING :
N Truter Date
ISSUE NUMBER : 03
REVISED BY : N Truter
UPDATES
Grintek TCI reserves the right to update its equipment and/or documentation without prior
notification.
RECORD OF CHANGES
Personnel incorporating current changes to this manual are responsible for ensuring that all
previous changes are incorporated.
WARNINGS
Th e f o l l o w i n g a r e general safety precautions that are not related to any specific procedure and
therefore do not appear elsewhere in this publication.
HIGH VOLTAGES
TABLE OF CONTENTS
TITLE PAGE
1.3.1 R a c k p r e p a ra t i o n . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
1.4.1 C o n n e c t c a b i n e t t o ma i n s s w i t c h b o a r d . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.4.2 C o n n e c t b u i l d i n g e a rt h . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.5.1 C o n n e c t r e mo t e a l a r ms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
1.5.5 I n s t a l l s w i t c h mo d e r e c t i f i e r s ( S M R s ) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1.5.6 C o mmi s s i o n i n g c h e c k l i s t . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
LIST OF APPENDICES
APPENDIX A: Installation and commissioning checklists Page A1
LIST OF FIGURES
Figure 1: AC connection Page 2
LIST OF TABLES
Table 1: Alarm relay connections Page 3
1.1 INTRODUCTION
This manual describes the procedures to be followed when installing a GT600 Rack Power
S ys t e m .
The equipment is shipped from the factory properly tested and carefully packaged. Damage
may, however, occur during transit and careful inspection of all items received is required to
ensure that all equipment is in a serviceable condition.
Before deciding on the final placement of the rack the following must be taken into
consideration:
• Connection to AC input
• Rack clearances/height
• Rack accessibility
• Ventilation
Before starting the installation the following information is required:
• AC input voltage. The GT600 power system is designed to operate at a nominal input
voltage of 220VAC phase-neutral (380VAC, 3-phases + neutral). The input voltage
range should be between 195VAC and 264VAC under all conditions.
• E s t i m a t e t h e m a x i m u m c u r r e n t t h a t t h e s ys t e m w i l l d r a w f r o m t h e m a i n s i n p u t . T h e
m a x i m u m i n p u t c u r r e n t o f t h e G T 6 0 0 p o w e r s ys t e m w i l l b e d r a w n w h e n t h e s ys t e m
delivers full load and the input voltage is at the lower limit (195VAC). This is
approximately 65A per phase (3-phase). Make sure that the mains connection to the AC
switchboard can supply this current.
1.3 PREPARATION
1.3.2 Ventilation
The air-flow through the cabinet is from the front to the back. Please ensure that there is
enough clearance (400mm in the front) to facilitate sufficient air-flow.
Ensure that the site is clear of obstructions and ready for the cabinet to be placed. Cables
should be cut to length and made off and any cable trays or ducting prepared and mounted.
Ensure that the switches are switched off. Position the rack at the designated position.
Remove the retaining screws and AC distribution covers as indicated in figure 1.
Using cables of correct cross section, connect the three phases (L1, L2, L3), neutral (N) and
earth (E) from the switchboard to the rack in the positions shown in figure 1. The cables can
be routed through the top apertures, bottom aperture or side or back panels of the rack.
Do not apply power to the rack at this time. At this point check all supply connections,
including the earth connection, and all nuts and bolts for tightness.
Retaining
screws, 4 of.
AC
distribution
cover.
Figure 1: AC connection
Connect the building earth wire to the positive distribution bus-bar as indicated in figure 3.
I f t h e s ys t e m w i l l b e u s e d t o c h a r g e b a t t e r i e s , e a c h b a t t e r y b a n k s h o u l d b e f i t t e d w i t h a n
isolating switch. It is recommended that the switch be equipped with normally open auxiliary
contacts to monitor the position of the switch.
1.5 INSTALLATION
Once the rack is in place with cage nuts and cables in correct positions, proceed as follows:
Remove the two retaining screws on the CSU tray and slide it out. Connect the remote alarms
to the connector on the MUIB board as shown below.
Alarm connector
Label showing
alarm
breaker on.
Connect the load positive(s) to the positive load return bars and the load negatives to the
negative load connections (through circuit breakers) as indicated in figure 3.
If required, connect the auxiliary positive(s) to the positive (+) auxiliary bus bar and the load
negative(s) to the output of the distribution circuit breaker(s). If there are more than 2
separate auxiliary loads, up to 6 additional circuit breakers can be added.
Battery negative
connection
Battery positive
connection
Load distribution
switches
Load negative
connection
Load positive
connection
Remove SMRs from packaging. Conduct a visual inspection of the SMRs for mechanical
damage. Take care not to damage the connectors at the back of the SMR. See figure 4.
• Ensure that the circuit breakers on the DC and AC distribution modules are off.
• Place SMRs into the rack in accordance with the instructions in the Operators Manual.
Connectors
Complete Commissioning checklist (Appendix A) and fax to Grintek TCI, for the attention of
the configuration department on fax no (012) 674-3515.
APPENDIX A
INSTALLATION AND
COMMISSIONING CHECKLISTS
COMMISSIONING CHECKLIST
SITE NAME
SITE LOCATION
CABINET SERIAL NO
MCSU NUMBER
MODULE 1 SERIAL NO
MODULE 2 SERIAL NO
MODULE 3 SERIAL NO
MODULE 4 SERIAL NO
MODULE 5 SERIAL NO
MODULE 6 SERIAL NO
INSTALLATION BY
INSTALLATION DATE
COMMISSIONING DATE
2 C h e c k t h a t t h e s y s t e m s a r e p o s i t i oned as per
floor plan.
12 C h e c k t h a t t h e w i r i n g i s n o t e x p o s e d t o s harp
points & cutting edges.
COMMISSIONING CHECKLIST
Refer to the manuals supplied with the equipment for more detailed information.
8. Check that all the settings in the Mini-CSU are correct. NOTE 5.
HOME SCREEN
SMR SCREEN
BATTERY SCREEN
14.5 AC FAIL
NOTE 1:
Set addresses sequentially starting from the top of the rack. (Press and hold the “MENU”
button during the whole operation. Scroll between screens by pressing the “INC” or “DEC”
b u t t o n u n t i l S M R # a p p e a r s . P r e s s “ E N T E R ” t o c hange the address. The SMR address will then
flicker. Press “INC” or “DEC” until desired address is displayed. Press “ENTER” to accept the
n e w a d d r e s s . N o t e : I f t h e s e c u r i t y l o c k i s o n , p r e s s “ I N C ” , “ D E C” and “ENTE R” simultaneously
for more than 5 seconds to unlock).
NOTE 2:
x is a number between 0 and 9. xx.x designates the output voltage of the SMR. If no load is
connected the SMR and the mCSU will display a Lo alarm. This alarm will disappear as soon
as a load is applied.
NOTE 3:
The access code can be changed by scrolling through the HOME (default) screen of the
mCSU. Press the “INC” or “DEC” buttons until CSU# is displayed. To change the code, press
E N T E R u n t i l t h e d e s i r e d d i g i t f l i c k ers. P res s t he “INC” and “DEC” pushbuttons until the correct
value is displayed, press “ENTER” to accept and move to the next digit. Press enter after the
NOTE 4:
(Except the no-load (Lo) alarm.). The orange LED on the SMR and on the mCSU will flash
when there is an alarm. To view the alarm press “ENTER” on the mCSU. Press “INC” or ”DEC”
to view more alarms.
NOTE 5:
I f a P C i s a va i l a b l e a l l t h e v a l u e s c a n b e c h a n g e d b y u s i n g t h e s u p p l i e d W I N C S U s o f t w a r e .
Disconnect the modem from the mCSU and connect a RS232 cable from the PC to the mCSU.
Make sure that the access code that was entered in paragraph 6 is the same as in WinCSU. If
not, change the access code in WinCSU.
Go to CSU parameters.
Click on EDIT PARAMETERS. Values can now be changed to the values listed below.
Close the screen and go to WRITE PARAMETERS in the CSU PARAMETERS screen
(CTRL W can also be pressed on the PC). Press yes when prompted to overwrite
parameters. The changed values will now be written to the mCSU.
Go to SMR PARAMETERS
Go to WRITE PARAMETERS in the SMR screen. Press yes when prompted to overwrite ALL
SMRs.
NOTE 6:
O n t h e G T 1 2 0 0 ( P / N 8 4 0 1 0 7 - 0 0 0 0 0 ) t h e v a l u e 1 2 0 0 m u s t b e r e a d f r o m t h e c u r r e n t t r a n s d u c er.
On the GT600 (P/N 8400057-00000) the value 600 must be read from the current transducer.
NOTE 7:
NOTE 8:
Connect a dummy load to the system and check that current sharing is done. It may be
n e c e s s a r y t o i n c r e a s e t h e l o a d t o a b o v e 7 5 % o f f u ll loa d for the a ctive current sharing to come
into operation.
NOTE 9:
I f n o M i n i - C S U i s c o n n e c t e d t h e s ys t e m w i l l d o p a s s i v e c u r r e n t s h a r i n g . I f a n m C S U i s
connected and for some reason active sharing is not done, an x w i l l b e d i s p l a ye d
NOTE 10:
NOTE 11:
Set the float voltage 0.5V higher than the high volt alarm value.
NOTE 12:
Set the float voltage 0.5V lower than the low volt alarm value. Set the float voltage to the
correct value after this test is done.
NOTE 13:
Set the LVDS to 48V and switch the AC circuit breaker OFF. While the AC circuit breaker is
OFF, apply load to the system to let the voltage drop and check that the load sheds at the set
voltage.
NOTE 14:
APPROVAL SHEET
I n s t a l l a t i o n p e r f o r m e d b y:
Company :
Designation :
Name :
Sign :
Date :
C o m m i s s i o n i n g p e r f o r m e d b y:
Company :
Designation :
Name :
Sign :
Date :
S ys t e m i n s p e c t e d b y G R I N T E K Q A :
Company :
Designation :
Name :
Sign :
Date :
S ys t e m I n s p e c t e d b y C U S T O M E R Q A :
Company :
Designation :
Name :
Sign :
Date :