You are on page 1of 2

Date of the event Event

 Para 5 10th February 2016 HH Nepal signed PTA with GPC India
 Para 5 (Exhibit C1) 14th Jamkabhet post published the information
February 2016 about PTA Agreement
 Para 4 2021 Mr. Rastra Premi Prasad (former secretary of
Ministry of Power GOI) was succeed by
Binod KKR (from KKR group) as successor
of CEO.
 Para 8 (C2) 16th July 2020 PSA Agreement was signed between BPDB,
HH Nepal and GPC India
 Para 10 31st July 2020 Commercial operation of electricity
transmission began
 Para 10 29th July 2022 advance financial payment for the year
2022/23
 Para 11 Feb, 2023 Gov. of Bangladesh opened the tender for
commercial port in Bangladesh
 Para 11 1st March, 2023 China won the tender by outbidding India
 Para 12 5th March 2023 Bill to amend the Electricity Act 2023 was
introduced
 Para 13 20th March 2023 The bill was passed
 Para 14 21st March 2023 HH Nepal halted the supply of electricity to
the claimant
 Para 14(C 4) 22nd March 2023 HH Nepal mailed the claimant regarding the
halt and force majeure event (12:30 PM)
 Para 15 (C 5) 22nd March 2023 The reply was sent by BPDB on the same day
(4:30 PM)
 Para 16 (C6) 2nd April 2023 Claimant requested for the resumption of
supply (10:30 AM)
 1ST May 2023 Notice of Arbitration was sent by BPDB
(Mohammed Hussain)
 12th May 2023 Response to Notice of Arbitration (Prajwalata
Dangol)
 12th June 2023 Arbitral tribunal conducted preliminary
meeting with the parties for finalizing the
adjudicating issues.
 15th June 2023 Procedural order no.1 (Presiding Arbitrator
Dr. Mary Oliver)

You might also like