Timeline of The Event
Timeline of The Event
Para 5 10th February 2016 HH Nepal signed PTA with GPC India
Para 5 (Exhibit C1) 14th Jamkabhet post published the information
February 2016 about PTA Agreement
Para 4 2021 Mr. Rastra Premi Prasad (former secretary of
Ministry of Power GOI) was succeed by
Binod KKR (from KKR group) as successor
of CEO.
Para 8 (C2) 16th July 2020 PSA Agreement was signed between BPDB,
HH Nepal and GPC India
Para 10 31st July 2020 Commercial operation of electricity
transmission began
Para 10 29th July 2022 advance financial payment for the year
2022/23
Para 11 Feb, 2023 Gov. of Bangladesh opened the tender for
commercial port in Bangladesh
Para 11 1st March, 2023 China won the tender by outbidding India
Para 12 5th March 2023 Bill to amend the Electricity Act 2023 was
introduced
Para 13 20th March 2023 The bill was passed
Para 14 21st March 2023 HH Nepal halted the supply of electricity to
the claimant
Para 14(C 4) 22nd March 2023 HH Nepal mailed the claimant regarding the
halt and force majeure event (12:30 PM)
Para 15 (C 5) 22nd March 2023 The reply was sent by BPDB on the same day
(4:30 PM)
Para 16 (C6) 2nd April 2023 Claimant requested for the resumption of
supply (10:30 AM)
1ST May 2023 Notice of Arbitration was sent by BPDB
(Mohammed Hussain)
12th May 2023 Response to Notice of Arbitration (Prajwalata
Dangol)
12th June 2023 Arbitral tribunal conducted preliminary
meeting with the parties for finalizing the
adjudicating issues.
15th June 2023 Procedural order no.1 (Presiding Arbitrator
Dr. Mary Oliver)