DAFTAR HARGA BAHAN + UPAH KERJA

NO URAIAN SATUAN HARGA SATUAN

A UPAH KERJA
1 Pekerja hari/orang 185,000.00
2 Tukang hari/orang 230,000.00
3 Kepala Tukang hari/orang 260,000.00
4 Mandor hari/orang 280,000.00

B BAHAN
1 Tanah Urug m3 300,000.00
2 Pasir Urug m3 342,857.14
3 Pasir Pasang m3 342,857.14
4 PB / Pasir Beton m3 342,857.14
5 PB / Pasir Beton kg 244.90
6 Batu Pecah 2/3 m3 733,333.33
7 Batu Pecah 2/3 kg 543.21
8 Kr / Krikil m3 540,000.00
9 Kr / Krikil kg 400.00
10 Batu Bela / Batu Kali m3 333,333.33
11 Air Ltr 50.00
12 Aluminiun gel tebal 0,3 lembar 95,000.00
13 Nok standar 40 x 18 Buah 50,000.00
14 Bata Tela bh 2,500.00
15 PC / Portland Cement kg 1,900.00
16 Semen Warna kg 21,000.00
17 Keramik Ukuran 60 x 60 Dos 157,000.00
18 Keramik Ukuran 30 x 30 Dos 90,000.00
19 Keramik Ukuran 20 x 20 Dos 80,000.00
20 Keramik Ukuran 20 x 25 Bh 5,450.00
21 Papan Ky Linggua m3 5,450,000.00
22 Papan Ky Besi m3 5,450,000.00
23 Papan Ky. Matoa m3 3,150,000.00
24 Papan Ky. Bekisting m3 2,950,000.00
25 Kayu Dolken batang 25,000.00
26 Tripleks 3 mm - 4 mm lembar 85,000.00
27 Multipleks 9 mm lembar 220,000.00
28 Gypsum 9 mm lembar 115,000.00
29 Besi Beton kg 20,100.00
30 Kawat Ikat Beton kg 32,000.00
31 spandek BJLS 0,25 mm lembar 65,000.00
32 Seng Plat BJLS 0,2 mm lembar 50,000.00
33 Paku Campur kg 27,250.00
34 Pake Skrup bh 200.00
35 Besi Tempa m1 20,200.00
36 Baja Ringan Kg 10,500.00
37 Besi Hollow 40x40 mm m1 10,500.00
38 Besi Hollow 20x20 mm m1 10,750.00
39 Kaca Bening 5 mm m2 107,633.71
40 Sealant Kg 25,000.00
41 Lem Aica Aibon kg 80,000.00
42 Kunci Tanam 2 Slaag bh 150,000.00
43 Engsel Pintu bh 20,000.00
44 Engsel Jendela bh 8,250.00
45 Grendel Pintu bh 20,000.00
46 Grendel Jendela bh 11,000.00
47 Besi Hollow 40x40 mm m2 350,000.00
48 Profil Tank 1100 Liter Buah 3,250,000.00
49 Hak Angin bh 12,500.00
50 Plamir tembok kg 30,000.00
51 Cat Dasar Tembok kg 37,500.00
52 Cat Tembok kg 37,500.00
53 Meni Kayu kg 32,000.00
54 Plamir kayu kg 45,000.00
55 Cat Dasar (Kayu) kg 65,000.00
56 Cat Penutup (Kayu) kg 65,000.00
57 Pengencer kg 25,000.00
58 Ampelas lembar 7,500.00
59 Kuas bh 9,500.00
60 List Kayu Profil m1 9,500.00
61 Pipa Galvanis Dia. 1" (Tebal) m1 31,833.33
NO URAIAN SATUAN HARGA SATUAN

62 Pipa Galvanis Dia. 2" (Tebal) m1 73,833.33


63 Pipa PVC Dia. 2" AW m1 26,500.00
64 Pipa PVC Dia. 3" AW m1 56,125.00
65 Pipa PCV Dia. 4" AW m1 85,000.00
66 Wastafel Gantung Buah 1,500,000.00
67 Kloset Jongkok Porselen buah 690,000.00
68 Floor Drain buah 75,000.00
69 Kran Dia. 1/2" buah 38,500.00
70 Sealtipe buah 5,000.00
71 Minyak Bekisting liter -
73 Lampu SL 45 Watt bh 50.00
74 Lampu SL 30 Watt bh 150,000.00
75 Lampu SL 25 Watt bh 90,000.00
76 Lampu Fitting 14 Watt bh 26,000.00
77 Fitting Lampu bh 15,000.00
78 Stop Kontak Dinding bh 36,000.00
79 Stop Kontak Lantai bh 650,000.00
80 Stop Kontak AC bh 270,000.00
81 Saklar Ganda bh 40,000.00
82 Saklar Tunggal bh 33,000.00
83 Kabel NYM 2 x 2,5 mm m1 15,700.00
DAFTAR ANALISA HARGA SATUAN

A.2.2.1.4. 1 m1 Pengukuran dan Pemasangan Bouwplank

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.100 185,000.00 18,500.00
2 Tukang Kayu L.02 OH 0.100 230,000.00 23,000.00
2 Kepala Tukang L.03 OH 0.010 260,000.00 2,600.00
2 Mandor L.04 OH 0.005 280,000.00 1,400.00
Jumlah Harga Tenaga Kerja 45,500.00
B Bahan
1 Balok Kayu Matoa m3 0.005 3,150,000.00 15,750.00
2 Paku 2" - 3" kg 0.015 27,250.00 408.75
3 Papan Kayu Matoa m3 0.005 3,150,000.00 15,750.00
Jumlah Harga Bahan 31,908.75
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 77,408.75
E Overhead + Profit (Contoh 15%) (Contoh 15%) 10% x D 7,740.88
F Harga Satuan Pekerjaan per - m2 (D+E) 85,149.63

A.2.2.1.5 1 m2 Direksi Keet

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 2,00 185,000.00 #VALUE!
2 Tukang Kayu L.02 OH 2,00 230,000.00 #VALUE!
3 Tukang Batu L.02 OH 1,00 230,000.00 #VALUE!
4 Kepala Tukang L.03 OH 0,35 260,000.00 #VALUE!
5 Mandor L.04 OH 0,50 280,000.00 #VALUE!
Jumlah Harga Tenaga Kerja #VALUE!
B Bahan
1 Dolken kayu  8-10/400 cm Batang 1 25,000.00 31,250.00
2 Kayu m3 0,180 3,150,000.00 567,000,000.00
3 Paku Biasa Kg 0,080 27,250.00 2,180,000.00
4 Besi Strip Kg 1.100 20,100.00 22,110.00
5 Semen Portland Kg 35.0 1,900.00 66,500.00
6 Pasir Pasang m3 0,150 342,857.14 51,428,571.43
7 Pasir Beton m3 0,100 342,857.14 34,285,714.29
8 Koral m3 0,150 540,000.00 81,000,000.00
9 Batu Tela Bh 30.000 2,500.00 75,000.00
10 Seng Plat Lbr 0,250 65,000.00 16,250,000.00
11 Jendela Naco Bh 0,200 220,000.00 44,000,000.00
12 Kaca Polos m2 0,080 107,633.71 8,610,697.14
13 Kunci Tanam Bh 0,150 50,000.00 7,500,000.00
14 Plywood 4 mm Lbr 0,060 85,000.00 5,100,000.00
Jumlah Harga Bahan 162,535,697.14
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) #VALUE!
E Overhead + Profit (Contoh 15%) 10% x D #VALUE!
F Harga Satuan Pekerjaan per - m3 (D+E) #VALUE!

A.2.2.1.9 1 m2 Pembersihan Lapangan dan Perataan

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.100 185,000.00 18,500.00
2 Mandor L.04 OH 0.05 280,000.00 14,000.00
Jumlah Harga Tenaga Kerja 32,500.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
1 Alat Bantu Ls 1.000 - -
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 32,500.00
E Overhead + Profit (Contoh 15%) (Contoh 15%) 10% x D 3,250.00
F Harga Satuan Pekerjaan per - m2 (D+E) 35,750.00

A.2.2.1.14 Pembongkaran 1 m3 dinding tembok bata

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 6.667 185,000.00 1,233,395.00
2 Mandor L.04 OH 0,333 280,000.00 93,240,000.00
Jumlah Harga Tenaga Kerja 94,473,395.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 94,473,395.00
E Overhead + Profit (Contoh 15%) 10% x D 9,447,339.50
F Harga Satuan Pekerjaan per - m3 (D+E) 103,920,734.50

1 m3 Galian Tanah (Mekanis)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja OH 0.400 185,000.00 74,000.00
2 Mandor OH 0.200 280,000.00 56,000.00
Jumlah Harga Tenaga Kerja 130,000.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
1 Mini Excavator Sewa-Jam 0.430 450,000.00 193,500.00
3 Dump Truck Sewa-Jam 0.030 400,000.00 12,000.00
Jumlah Harga Peralatan 205,500.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 335,500.00
E Overhead + Profit (Contoh 15%) 10% x D 33,550.00
F Harga Satuan Pekerjaan per - m' (D+E) 369,050.00

A.2.3.1.2 1 m3 Galian tanah biasa sedalam s.d. 2 m

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.9000 185,000.00 166,500.00
2 Mandor L.04 OH 0.0450 280,000.00 12,600.00
Jumlah Harga Tenaga Kerja 179,100.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 179,100.00
E Overhead + Profit (Contoh 15%) 10% x D 17,910.00
F Harga Satuan Pekerjaan per - m3 (D+E) 197,010.00
A.2.3.1.9 1 m3 Urugan Tanah Kembali

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.500 185,000.00 92,500.00
2 Mandor L.04 OH 0.050 280,000.00 14,000.00
Jumlah Harga Tenaga Kerja 106,500.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 106,500.00
E Overhead + Profit (Contoh 15%) 10% x D 10,650.00
F Harga Satuan Pekerjaan per - m3 (D+E) 117,150.00

T.14a 1 m3 Timbunan Urugan Tanah Biasa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.250 185,000.00 46,250.00
2 Mandor L.04 OH 0.025 280,000.00 7,000.00
Jumlah Harga Tenaga Kerja 53,250.00
B Bahan
1 Urugan Tanah Biasa M3 1.200 300,000.00 360,000.00
Jumlah Harga Bahan 360,000.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 413,250.00
E Overhead + Profit (Contoh 15%) 10% x D 41,325.00
F Harga Satuan Pekerjaan per - m3 (D+E) 454,575.00

A.2.3.1.11 1 m3 Pengurug Dengan Pasir Urug

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.300 185,000.00 55,500.00
2 Mandor L.04 OH 0.010 280,000.00 2,800.00
Jumlah Harga Tenaga Kerja 58,300.00
B Bahan
1 Pasir Urug M.14.b m3 1.200 342,857.14 411,428.57
Jumlah Harga Bahan 411,428.57
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 469,728.57
E Overhead + Profit (Contoh 15%) 10% x D 46,972.86
F Harga Satuan Pekerjaan per - m3 (D+E) 516,701.43

P.05 Pasangan Batu Kosong (1 m3)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.780 185,000.00 144,300.00
2 Tukang batu L.02 OH 0.390 230,000.00 89,700.00
3 Kepala Tukang L.03 OH 0.039 260,000.00 10,140.00
4 Mandor L.04 OH 0.039 280,000.00 10,920.00
Jumlah Harga Tenaga Kerja 255,060.00
B Bahan
1 Batu/batu belah m3 1.200 333,333.33 400,000.00
2 Pasir Urug m3 0.432 342,857.14 148,114.29
Jumlah Harga Bahan 548,114.29
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 803,174.29
E Overhead + Profit (Contoh 15%) 10% x D 80,317.43
F Harga Satuan Pekerjaan per - m3 (D+E) 883,491.71

A.3.2.1.1 1 M3 Pasang Pondasi Batu Bela 1 : 4

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.500 185,000.00 277,500.00
2 Tukang batu L.02 OH 0.750 230,000.00 172,500.00
3 Kepala Tukang L.03 OH 0.075 260,000.00 19,500.00
4 Mandor L.04 OH 0.075 280,000.00 21,000.00
Jumlah Harga Tenaga Kerja 490,500.00
B Bahan
1 Batu belah m3 1.200 333,333.33 400,000.00
2 Semen Portland kg 163.000 1,900.00 309,700.00
3 Pasir pasang m3 0.520 342,857.14 178,285.71
Jumlah Harga Bahan 887,985.71
C Peralatan
1 Molen E.28.b Sewa-hari 0.167 - -
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 1,378,485.71
E Overhead + Profit (Contoh 15%) 10% x D 137,848.57
F Harga Satuan Pekerjaan per - m3 (D+E) 1,516,334.29
A.4.1.1.24 1 m1 Kolom Praktis Beton Bertulang (11 x 11) cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.660 185,000.00 122,100.00
2 Tukang batu L.02 OH 0.330 230,000.00 75,900.00
Tukang kayu L.02 OH 0.330 230,000.00 75,900.00
Tukang besi L.02 OH 0.330 230,000.00 75,900.00
3 Kepala tukang L.03 OH 0.033 260,000.00 8,580.00
4 Mandor L.04 OH 0.033 280,000.00 9,240.00
Jumlah Harga Tenaga Kerja 367,620.00
B Bahan *
1 Kayu kelas II m3 0.002 3,150,000.00 6,300.00
2 Paku 5 cm – 12 cm kg 0.010 27,250.00 272.50
3 Minyak bekisting Liter 0.000 - -
4 Besi beton polos kg 3.000 20,100.00 60,300.00
5 Kawat beton kg 0.450 32,000.00 14,400.00
6 Semen Portland kg 4.000 1,900.00 7,600.00
7 Pasir Beton m3 0.006 342,857.14 2,057.14
8 Kerikil m3 0.009 540,000.00 4,860.00
Jumlah Harga Bahan 95,789.64
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 463,409.64
E Overhead + Profit (Contoh 15%) 10% x D 46,340.96
F Harga Satuan Pekerjaan per - m2 (D+E) 509,750.61

A.4.1.1.24 1 m1 Ringbalk Praktis Bertulang (10 x 15) cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.297 185,000.00 54,945.00
2 Tukang batu L.02 OH 0.033 230,000.00 7,590.00
3 Tukang kayu L.02 OH 0.033 230,000.00 7,590.00
4 Tukang besi L.02 OH 0.033 230,000.00 7,590.00
5 Kepala tukang L.03 OH 0.010 260,000.00 2,600.00
6 Mandor L.04 OH 0.015 280,000.00 4,200.00
Jumlah Harga Tenaga Kerja 84,515.00
B Bahan *
1 Kayu kelas III m3 0.003 3,150,000.00 9,450.00
2 Paku 5 cm – 12 cm kg 0.020 27,250.00 545.00
3 Minyak bekisting Liter 0.000 - -
4 Besi beton polos kg 3.600 20,100.00 72,360.00
5 Kawat beton kg 0.050 32,000.00 1,600.00
6 Semen Portland kg 5.500 1,900.00 10,450.00
7 Pasir Beton m3 0.009 342,857.14 3,085.71
8 Kerikil m3 0.015 540,000.00 8,100.00
Jumlah Harga Bahan 105,590.71
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 190,105.71
E Overhead + Profit (Contoh 15%) 10% x D 19,010.57
F Harga Satuan Pekerjaan per - m2 (D+E) 209,116.29

A.A.4.1.1.4 1 m3 beton untuk lantai kerja (bedding)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.200 185,000.00 222,000.00
2 Tukang batu L.02 OH 0.200 230,000.00 46,000.00
3 Kepala tukang batu L.03 OH 0.020 260,000.00 5,200.00
4 Mandor L.04 OH 0.060 280,000.00 16,800.00
Jumlah Harga Tenaga Kerja 290,000.00
B Bahan
1 PC / Portland Cement kg 230.000 1,900.00 437,000.00
2 PB / Pasir Beton kg 893.000 244.90 218,693.88
3 Kr / Krikil kg 1027.000 400.00 410,800.00
4 Air Liter 200.000 50.00 10,000.00
Jumlah Harga Bahan 1,076,493.88
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 1,366,493.88
E Overhead + Profit (Contoh 15%) 10% x D 136,649.39
F Harga Satuan Pekerjaan per - m3 (D+E) 1,503,143.27

A.A.4.1.1.5 1 m3 beton mutu f'c = 19,3 Mpa (K-225), (Slump 120±20) mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.650 185,000.00 305,250.00
2 Tukang batu L.02 OH 0.275 230,000.00 63,250.00
3 Kepala tukang batu L.03 OH 0.028 260,000.00 7,150.00
4 Mandor L.04 OH 0.083 280,000.00 23,240.00
Jumlah Harga Tenaga Kerja 398,890.00
B Bahan
1 PC / Portland Cement kg 371.000 1,900.00 704,900.00
2 PB / Pasir Beton kg 698.000 244.90 170,938.78
3 Batu Pecah 2-3 cm kg 1047.000 543.21 568,740.74
4 Air Liter 215.000 50.00 10,750.00
Jumlah Harga Bahan 1,455,329.52
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 1,854,219.52
E Overhead + Profit (Contoh 15%) 10% x D 185,421.95
F Harga Satuan Pekerjaan per - m3 (D+E) 2,039,641.47

A.4.1.1.18 10 Kg Pembesian dengan Besi Ulir / Polos

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.070 185,000.00 12,950.00
2 Tukang besi L.02 OH 0.070 230,000.00 16,100.00
3 Kepala tukang batu L.03 OH 0.007 260,000.00 1,820.00
4 Mandor L.04 OH 0.004 280,000.00 1,120.00
Jumlah Harga Tenaga Kerja 31,990.00
B Bahan
1 Besi Beton kg 10.500 20,100.00 211,050.00
2 Kawat Beton kg 0.150 32,000.00 4,800.00
Jumlah Harga Bahan 215,850.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 247,840.00
E Overhead + Profit (Contoh 15%) 10% x D 24,784.00
F Harga Satuan Pekerjaan per - 10 kg (D+E) 272,624.00
F Harga Satuan Pekerjaan per - kg (F/10) 27,262.40

A.4.1.1.20 1 m2 Pemasangan Bekisting untuk Pondasi

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.520 185,000.00 96,200.00
2 Tukang batu L.02 OH 0.260 230,000.00 59,800.00
3 Kepala tukang batu L.03 OH 0.026 260,000.00 6,760.00
4 Mandor L.04 OH 0.026 280,000.00 7,280.00
Jumlah Harga Tenaga Kerja 170,040.00
B Bahan
1 Kayu Bekisting m3 0.040 2,950,000.00 118,000.00
2 Paku 5 cm - 10 cm kg 0.300 27,250.00 8,175.00
3 Minyak Bekisting liter 0.100 - -
Jumlah Harga Bahan 126,175.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 296,215.00
E Overhead + Profit (Contoh 15%) 10% x D 29,621.50
F Harga Satuan Pekerjaan per - m3 (D+E) 325,836.50
A.4.1.1.21 1 m2 Pemasangan Bekisting untuk Sloof

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.520 185,000.00 96,200.00
2 Tukang batu L.02 OH 0.260 230,000.00 59,800.00
3 Kepala tukang batu L.03 OH 0.026 260,000.00 6,760.00
4 Mandor L.04 OH 0.026 280,000.00 7,280.00
Jumlah Harga Tenaga Kerja 170,040.00
B Bahan
1 Kayu Bekisting m3 0.045 2,950,000.00 132,750.00
2 Paku 5 cm - 10 cm kg 0.300 27,250.00 8,175.00
3 Minyak Bekisting liter 0.100 - -
Jumlah Harga Bahan 140,925.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 310,965.00
E Overhead + Profit (Contoh 15%) 10% x D 31,096.50
F Harga Satuan Pekerjaan per - m3 (D+E) 342,061.50

A.4.1.1.22 1 m2 Pemasangan Bekisting untuk Kolom

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.520 185,000.00 96,200.00
2 Tukang batu L.02 OH 0.260 230,000.00 59,800.00
3 Kepala tukang batu L.03 OH 0.026 260,000.00 6,760.00
4 Mandor L.04 OH 0.026 280,000.00 7,280.00
Jumlah Harga Tenaga Kerja 170,040.00
B Bahan
1 Kayu Bekisting m3 0.040 2,950,000.00 118,000.00
2 Paku 5 cm - 10 cm kg 0.400 27,250.00 10,900.00
3 Minyak Bekisting liter 0.200 - -
4 Balok Kayu Matoa m3 0.015 3,150,000.00 47,250.00
5 Plywood tebal 9 mm lembar 0.350 220,000.00 77,000.00
6 Dolken kayu Dia.8 - 10 cm batang 2.000 25,000.00 50,000.00
Jumlah Harga Bahan 303,150.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 473,190.00
E Overhead + Profit (Contoh 15%) 10% x D 47,319.00
F Harga Satuan Pekerjaan per - m3 (D+E) 520,509.00

A.4.1.1.22 1 m2 Pemasangan Bekisting untuk Balok

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.660 185,000.00 122,100.00
2 Tukang batu L.02 OH 0.330 230,000.00 75,900.00
3 Kepala tukang batu L.03 OH 0.033 260,000.00 8,580.00
4 Mandor L.04 OH 0.033 280,000.00 9,240.00
Jumlah Harga Tenaga Kerja 215,820.00
B Bahan
1 Kayu Bekisting m3 0.040 2,950,000.00 118,000.00
2 Paku 5 cm - 10 cm kg 0.400 27,250.00 10,900.00
3 Minyak Bekisting liter 0.200 - -
4 Balok Kayu Matoa m3 0.018 3,150,000.00 56,700.00
5 Plywood tebal 9 mm lembar 0.350 220,000.00 77,000.00
6 Dolken kayu Dia.8 - 10 cm batang 2.000 25,000.00 50,000.00
Jumlah Harga Bahan 312,600.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 528,420.00
E Overhead + Profit (Contoh 15%) 10% x D 52,842.00
F Harga Satuan Pekerjaan per - m3 (D+E) 581,262.00
A.4.1.1.24 1 m2 Pemasangan Bekisting untuk Lantai

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.660 185,000.00 122,100.00
2 Tukang batu L.02 OH 0.330 230,000.00 75,900.00
3 Kepala tukang batu L.03 OH 0.033 260,000.00 8,580.00
4 Mandor L.04 OH 0.033 280,000.00 9,240.00
Jumlah Harga Tenaga Kerja 215,820.00
B Bahan
1 Kayu Bekisting m3 0.040 2,950,000.00 118,000.00
2 Paku 5 cm - 10 cm kg 0.400 27,250.00 10,900.00
3 Minyak Bekisting liter 0.200 - -
4 Balok Kayu Matoa m3 0.015 3,150,000.00 47,250.00
5 Plywood tebal 9 mm lembar 0.350 220,000.00 77,000.00
6 Dolken kayu Dia.8 - 10 cm batang 6.000 25,000.00 150,000.00
Jumlah Harga Bahan 403,150.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 618,970.00
E Overhead + Profit (Contoh 15%) 10% x D 61,897.00
F Harga Satuan Pekerjaan per - m3 (D+E) 680,867.00

1 M3 BETON POER PLAT


0.9500 M3 Beton K.225 2,039,641.47 1,937,659.39
109.1296 Kg Besi beton 27,262.40 2,975,134.81
2.2220 M2 Bekisting 325,836.50 724,008.70
Jumlah 5,636,802.90
A.4.1.1.26 1 m2 Pemasangan Bekisting untuk Tangga

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.660 185,000.00 122,100.00
2 Tukang batu L.02 OH 0.330 230,000.00 75,900.00
3 Kepala tukang batu L.03 OH 0.033 260,000.00 8,580.00
4 Mandor L.04 OH 0.033 280,000.00 9,240.00
Jumlah Harga Tenaga Kerja 215,820.00
B Bahan
1 Kayu Bekisting m3 0.030 2,950,000.00 88,500.00
2 Paku 5 cm - 10 cm kg 0.400 27,250.00 10,900.00
3 Minyak Bekisting liter 0.150 - -
4 Balok Kayu Matoa m3 0.015 3,150,000.00 47,250.00
5 Plywood tebal 9 mm lembar 0.350 220,000.00 77,000.00
6 Dolken kayu Dia.8 - 10 cm batang 2.000 25,000.00 50,000.00
Jumlah Harga Bahan 273,650.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 489,470.00
E Overhead + Profit (Contoh 15%) 10% x D 48,947.00
F Harga Satuan Pekerjaan per - m3 (D+E) 538,417.00

1 m3 Cor Beton Pondasi Sloef 50/100

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
1 Beton fc' 19,3 Mpa m3 1.000 2,039,641.47 2,039,641.47
2 Besi Tulangan kg 101.218 27,262.40 2,759,439.93
3 Bekisting Pondasi m2 3.000 325,836.50 977,509.50
Jumlah Harga 5,776,590.90

1 m3 Cor Beton Sloof 20 x 25 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
1 Beton fc' 19,3 Mpa m3 1.000 2,039,641.47 2,039,641.47
2 Besi Tulangan kg 111.003 27,262.40 3,026,204.92
3 Bekisting sloef 2x Pakai m2 5.000 342,061.50 1,710,307.50
Jumlah Harga 6,776,153.88

1 m3 Cor Beton Sloof 30 x 25 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
1 Beton fc' 19,3 Mpa m3 1.000 2,039,641.47 2,039,641.47
2 Besi Tulangan kg 128.364 27,262.40 3,499,497.63
3 Bekisting sloef (2X pakai) m2 8.000 342,061.50 2,736,492.00
Jumlah Harga 8,275,631.10

1 m3 Cor Beton Kolom 15 x 15 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
1 Beton fc' 19,3 Mpa m3 1.000 2,039,641.47 2,039,641.47
2 Besi Tulangan kg 172.730 27,262.40 4,709,023.45
3 Bekisting Kolom (2x pakai) m2 6.667 520,509.00 3,470,060.00
Jumlah Harga 10,218,724.91

1 m3 Cor Beton Kolom 25 x 25 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
1 Beton fc' 19,3 Mpa m3 1.000 2,039,641.47 2,039,641.47
2 Besi Tulangan kg 172.730 27,262.40 4,709,023.45
3 Bekisting Kolom (2x pakai) m2 6.667 520,509.00 3,470,060.00
Jumlah Harga 10,218,724.91

1 m3 Cor Beton Kolom 25 x 25 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
1 Beton fc' 19,3 Mpa m3 1.000 2,039,641.47 2,039,641.47
2 Besi Tulangan kg 149.828 27,262.40 4,084,659.53
3 Bekisting Kolom (2x pakai) m2 8.000 520,509.00 4,164,072.00
Jumlah Harga 10,288,372.99

1 m3 Cor Beton Balok 20 x 30 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
1 Beton fc' 19,3 Mpa m3 1.000 2,039,641.47 2,039,641.47
2 Besi Tulangan kg 159.578 27,262.40 4,350,468.36
3 Bekisting Balok (2x pakai) m2 6.667 581,262.00 3,875,080.00
Jumlah Harga 10,265,189.83

1 m3 Cor Beton Balok 15 x 20 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
1 Beton fc' 19,3 Mpa m3 1.000 2,039,641.47 2,039,641.47
2 Besi Tulangan kg 184.128 27,262.40 5,019,771.19
3 Bekisting Balok m2 4.074 581,262.00 2,368,104.44
Jumlah Harga 9,427,517.10

1 m3 Cor Beton Ring Balok 30 x 30 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
1 Beton fc' 19,3 Mpa m3 1.000 2,039,641.47 2,039,641.47
2 Besi Tulangan kg 107.554 27,262.40 2,932,183.80
3 Bekisting Balok (2x pakai) m2 5.000 581,262.00 2,906,310.00
Jumlah Harga 7,878,135.27

1 m3 Cor Beton Ring Balok 20 x 15 cm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
1 F m3 0.950 2,039,641.47 1,937,659.39
2 Besi Tulangan kg 174.483 27,262.40 4,756,830.79
3 Bekisting Balok (2x pakai) m2 9.167 581,262.00 5,328,235.00
Jumlah Harga 12,022,725.19

1 m3 Cor Beton Plat T = 13 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
1 Beton fc' 19,3 Mpa m3 1.000 2,039,641.47 2,039,641.47
2 Besi Tulangan kg 136.578 27,262.40 3,723,456.65
3 Bekisting Plat m2 7.692 680,867.00 5,237,438.46
Jumlah Harga 11,000,536.58

1 m3 Cor Beton Dak T = 10 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
1 Beton fc' 19,3 Mpa m3 1.000 2,039,641.47 2,039,641.47
2 Besi Tulangan kg 61.650 27,262.40 1,680,726.96
3 Bekisting Plat m2 10.000 680,867.00 6,808,670.00
Jumlah Harga 10,529,038.43

1 m3 Cor Beton Tangga

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
1 Beton fc' 19,3 Mpa m3 1.000 2,039,641.47 2,039,641.47
2 Besi Tulangan kg 119.000 27,262.40 3,244,225.60
3 Bekisting sloef m2 6.000 538,417.00 3,230,502.00
Jumlah Harga 8,514,369.07

1 m3 Cor Beton Praktis

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
1 Beton fc' 7,4 Mpa m3 1.000 1,503,143.27 1,503,143.27
2 Besi Tulangan kg 110.000 27,262.40 2,998,864.00
3 Bekisting sloef m2 5.000 342,061.50 1,710,307.50
Jumlah Harga 6,212,314.77

A.4.2.1.22 (K3) Pemasangan 1 m² Atap Pelana Rangka Atap Baja Ringan

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.734 185,000.00 135,790.00
2 Tukang besi L.02 OH 0.734 230,000.00 168,820.00
3 Kepala Tukang L.03 OH 0.073 260,000.00 18,980.00
4 Mandor L.04 OH 0.037 280,000.00 10,360.00
Jumlah Harga Tenaga Kerja 333,950.00
B Bahan
1 Baja Ringan Kg 3.065 10,500.00 32,182.50
Jumlah Harga Bahan 32,182.50
C Peralatan
1 Alat Bantu % 10 3,218.25 3,218.25
Jumlah Harga Peralatan 3,218.25
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 369,350.75
E Overhead + Profit (Contoh 15%) 10% x D 36,935.08
F Harga Satuan Pekerjaan per - m3 (D+E) 406,285.83

A.4.4.1.9 1 M2 Pasang Dinding Batu Tela 1/2 Batu 1 : 4

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.300 185,000.00 55,500.00
2 Tukang batu L.02 OH 0.100 230,000.00 23,000.00
3 Kepala Tukang L.03 OH 0.010 260,000.00 2,600.00
4 Mandor L.04 OH 0.015 280,000.00 4,200.00
Jumlah Harga Tenaga Kerja 85,300.00
B Bahan
1 Bata Tela bh 20.000 2,500.00 50,000.00
2 Portland Cement kg 11.500 1,900.00 21,850.00
3 Pasir pasang m3 0.043 342,857.14 14,742.86
Jumlah Harga Bahan 86,592.86
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 171,892.86
E Overhead + Profit (Contoh 15%) 10% x D 17,189.29
F Harga Satuan Pekerjaan per - m2 (D+E) 189,082.14

A.4.4.2.3 Pemasangan 1 m² plesteran 1SP : 3PP tebal 15 mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.200 185,000.00 37,000.00
2 Tukang batu L.03 OH 0.100 230,000.00 23,000.00
3 Kepala Tukang L.03 OH 0.015 260,000.00 3,900.00
4 Mandor L.04 OH 0.015 280,000.00 4,200.00
Jumlah Harga Tenaga Kerja 68,100.00
B Bahan
1 Portland Cement Kg 7.576 1,900.00 14,394.40
2 Pasir pasang m³ 0.022 342,857.14 7,542.86
Jumlah Harga Bahan 21,937.26
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 90,037.26
E Overhead + Profit (Contoh 15%) 10% x D 9,003.73
F Harga Satuan Pekerjaan per - m3 (D+E) 99,040.98
A.4.4.2.4 1 M2 Plesteran 1 : 4 Tebal 15 mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.200 185,000.00 37,000.00
2 Tukang batu L.02 OH 0.100 230,000.00 23,000.00
3 Kepala Tukang L.03 OH 0.015 260,000.00 3,900.00
4 Mandor L.04 OH 0.015 280,000.00 4,200.00
Jumlah Harga Tenaga Kerja 68,100.00
B Bahan
1 Pasir Pasang m3 0.024 342,857.14 8,228.57
2 Portland Cement kg 6.240 1,900.00 11,856.00
Jumlah Harga Bahan 20,084.57
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 88,184.57
E Overhead + Profit (Contoh 15%) 10% x D 8,818.46
F Harga Satuan Pekerjaan per - m2 (D+E) 97,003.03

A.4.4.2.26 Pemasangan 1 m² finishing siar pasangan batu kali, campuran 1SP : 2PP

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.300 185,000.00 55,500.00
2 Tukang batu L.03 OH 0.150 230,000.00 34,500.00
3 Kepala Tukang L.03 OH 0.015 260,000.00 3,900.00
4 Mandor L.04 OH 0.015 280,000.00 4,200.00
Jumlah Harga Tenaga Kerja 98,100.00
B Bahan
1 Semen PC Kg 0.500 1,900.00 950.00
2 Pasir Pasang m³ 0.013 342,857.14 4,457.14
Jumlah Harga Bahan 5,407.14
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 103,507.14
E Overhead + Profit (Contoh 15%) 10% x D 10,350.71
F Harga Satuan Pekerjaan per - m3 (D+E) 113,857.86

A.4.4.2.27 1 m2 Acian Tembok

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.150 185,000.00 27,750.00
2 Tukang batu L.02 OH 0.100 230,000.00 23,000.00
3 Kepala Tukang L.03 OH 0.010 260,000.00 2,600.00
4 Mandor L.04 OH 0.010 280,000.00 2,800.00
Jumlah Harga Tenaga Kerja 56,150.00
B Bahan
1 Portland Cement kg 3.000 1,900.00 5,700.00
Jumlah Harga Bahan 5,700.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 61,850.00
E Overhead + Profit (Contoh 15%) 10% x D 6,185.00
F Harga Satuan Pekerjaan per - m2 (D+E) 68,035.00

A.4.6.1.13. 1 m3 Pemasangan Konstruksi Kuda-Kuda Konvensional Ky. Besi

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 4.000 185,000.00 740,000.00
2 Tukang batu L.02 OH 12.000 230,000.00 2,760,000.00
3 Kepala Tukang L.03 OH 1.200 260,000.00 312,000.00
4 Mandor L.04 OH 0.200 280,000.00 56,000.00
Jumlah Harga Tenaga Kerja 3,868,000.00
B Bahan
1 Balok Kayu Besi m3 1.100 5,450,000.00 5,995,000.00
2 Besi Strip Tebal 5 mm kg 15.000 20,100.00 301,500.00
3 Paku 12 cm kg 5.600 27,250.00 152,600.00
Jumlah Harga Bahan 6,449,100.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 10,317,100.00
E Overhead + Profit (Contoh 15%) 10% x D 1,031,710.00
F Harga Satuan Pekerjaan per - m2 (D+E) 11,348,810.00

A.4.6.1.15. 1 m3 Pemasangan Gording Kayu Matoa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 6.700 185,000.00 1,239,500.00
2 Tukang batu L.02 OH 20.100 230,000.00 4,623,000.00
3 Kepala Tukang L.03 OH 2.010 260,000.00 522,600.00
4 Mandor L.04 OH 0.335 280,000.00 93,800.00
Jumlah Harga Tenaga Kerja 6,478,900.00
B Bahan
1 Balok Kayu Matoa m3 1.100 3,150,000.00 3,465,000.00
2 Besi Strip Tebal 5 mm kg 15.000 20,100.00 301,500.00
3 Paku 12 cm kg 3.000 27,250.00 81,750.00
Jumlah Harga Bahan 3,848,250.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 10,327,150.00
E Overhead + Profit (Contoh 15%) 10% x D 1,032,715.00
F Harga Satuan Pekerjaan per - m2 (D+E) 11,359,865.00
A.4.5.2.41. 1 m2 Pemasangn Atap Aluminium

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.150 185,000.00 27,750.00
2 Tukang Kayu L.02 OH 0.750 230,000.00 172,500.00
3 Kepala Tukang L.03 OH 0.080 260,000.00 20,800.00
4 Mandor L.04 OH 0.006 280,000.00 1,680.00
Jumlah Harga Tenaga Kerja 222,730.00
B Bahan
1 Aluminiun gel tebal 0,4 Lbr 1.050 95,000.00 99,750.00
2 Paku hak panjang 15 cm Kg 0.020 27,250.00 545.00
Jumlah Harga Bahan 100,295.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 323,025.00
E Overhead + Profit (Contoh 15%) 10% x D 32,302.50
F Harga Satuan Pekerjaan per - m2 (D+E) 355,327.50

A.4.5.2.39. 1 m2 Pemasangn Atap spandek BJS 25

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.120 185,000.00 22,200.00
2 Tukang batu L.02 OH 0.060 230,000.00 13,800.00
3 Kepala Tukang L.03 OH 0.006 260,000.00 1,560.00
4 Mandor L.04 OH 0.006 280,000.00 1,680.00
Jumlah Harga Tenaga Kerja 39,240.00
B Bahan
1 spandek BJLS 0,25 mm lbr 0.700 65,000.00 45,500.00
2 Paku Biasa 1/2" - 1" kg 0.020 27,250.00 545.00
Jumlah Harga Bahan 46,045.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 85,285.00
E Overhead + Profit (Contoh 15%) 10% x D 8,528.50
F Harga Satuan Pekerjaan per - m2 (D+E) 93,813.50

A.4.5.2.42. 1 m' Pemasangn Nok Atap Aluminium

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.100 185,000.00 18,500.00
2 Tukang Kayu L.02 OH 1.000 230,000.00 230,000.00
3 Kepala Tukang L.03 OH 0.100 260,000.00 26,000.00
4 Mandor L.04 OH 0.050 280,000.00 14,000.00
Jumlah Harga Tenaga Kerja 288,500.00
B Bahan
1 Nok standar 40 x 18 lbr 1.200 50,000.00 60,000.00
2 Paku hak panjang 15 cm kg 0.040 27,250.00 1,090.00
Jumlah Harga Bahan 61,090.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 349,590.00
E Overhead + Profit (Contoh 15%) 10% x D 34,959.00
F Harga Satuan Pekerjaan per - m2 (D+E) 384,549.00

A.4.5.2.40. 1 m' Pemasangn Nok Atap Seng BJLS 0,2 mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.150 185,000.00 27,750.00
2 Tukang batu L.02 OH 0.070 230,000.00 16,100.00
3 Kepala Tukang L.03 OH 0.007 260,000.00 1,820.00
4 Mandor L.04 OH 0.006 280,000.00 1,680.00
Jumlah Harga Tenaga Kerja 47,350.00
B Bahan
1 Seng Plat BJLS 0,2 mm lbr 0.300 50,000.00 15,000.00
2 Paku Biasa 1/2" - 1" kg 0.040 27,250.00 1,090.00
Jumlah Harga Bahan 16,090.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 63,440.00
E Overhead + Profit (Contoh 15%) 10% x D 6,344.00
F Harga Satuan Pekerjaan per - m2 (D+E) 69,784.00

A.4.6.1.20. 1 m2 rangka langit-langit (60 x 60) cm, Kayu Matoa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.200 185,000.00 37,000.00
2 Tukang L.02 OH 0.300 230,000.00 69,000.00
3 Kepala tukang L.03 OH 0.030 260,000.00 7,800.00
4 Mandor L.04 OH 0.010 280,000.00 2,800.00
Jumlah Harga Tenaga Kerja 116,600.00
B Bahan *
1 Kaso kaso 5 - 7 cm m³ 0.016 3,150,000.00 51,345.00
3 Paku Sekrup 7 cm – 10 cm Kg 0.250 27,250.00 6,812.50
Jumlah Harga Bahan 58,157.50
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 174,757.50
E Overhead + Profit (Contoh 15%) 10% x D 17,475.75
F Harga Satuan Pekerjaan per - m2 (D+E) 192,233.25

A.4.5.1.7. 1 m2 langit-langit Gypsum ukuran (120x240) cm, tebal 9 mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.100 185,000.00 18,500.00
2 Tukang L.02 OH 0.050 230,000.00 11,500.00
3 Kepala tukang L.03 OH 0.005 260,000.00 1,300.00
4 Mandor L.04 OH 0.005 280,000.00 1,400.00
Jumlah Harga Tenaga Kerja 32,700.00
B Bahan *
1 Gypsum Board Lbr 0.364 115,000.00 41,860.00
2 Paku Skrup kg 0.110 27,250.00 2,997.50
Jumlah Harga Bahan 44,857.50
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 77,557.50
E Overhead + Profit (Contoh 15%) 10% x D 7,755.75
F Harga Satuan Pekerjaan per - m2 (D+E) 85,313.25
A.4.5.1.6. 1 m1 List Plafond Kayu Profil

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.050 185,000.00 9,250.00
2 Tukang L.02 OH 0.050 230,000.00 11,500.00
3 Kepala tukang L.03 OH 0.005 260,000.00 1,300.00
4 Mandor L.04 OH 0.003 280,000.00 840.00
Jumlah Harga Tenaga Kerja 22,890.00
B Bahan *
1 List Kayu Profil m 1.050 9,500.00 9,975.00
2 Paku kg 0.010 27,250.00 272.50
Jumlah Harga Bahan 10,247.50
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 33,137.50
E Overhead + Profit (Contoh 15%) 10% x D 3,313.75
F Harga Satuan Pekerjaan per - m2 (D+E) 36,451.25

1 m1 Lisplank Kayu Besi (2 x 20) cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.100 185,000.00 18,500.00
2 Tukang L.02 OH 0.200 230,000.00 46,000.00
3 Kepala tukang L.03 OH 0.020 260,000.00
4 Mandor L.04 OH 0.005 280,000.00 1,400.00
Jumlah Harga Tenaga Kerja 65,900.00
B Bahan *
1 Papan Kayu Besi m3 0.0108 5,450,000.00 58,860.00
2 Paku Campur kg 0.100 27,250.00 2,725.00
Jumlah Harga Bahan 61,585.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 127,485.00
E Overhead + Profit (Contoh 15%) 10% x D 12,748.50
F Harga Satuan Pekerjaan per - m1 (D+E) 140,233.50

A.4.4.3.34 1 m2 Keramik Lantai (60 x 60 cm)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.700 185,000.00 129,500.00
2 Tukang L.02 OH 0.350 230,000.00 80,500.00
3 Kepala tukang L.03 OH 0.035 260,000.00 9,100.00
4 Mandor L.04 OH 0.035 280,000.00 9,800.00
Jumlah Harga Tenaga Kerja 228,900.00
B Bahan *
1 Keramik Ukuran 60 X 60 Dos 1.050 157,000.00 164,850.00
2 Portland Cement (PC) kg 8.190 1,900.00 15,561.00
4 Pasir Pasang (PS) m3 0.045 342,857.14 15,428.57
5 Semen Warna kg 0.500 21,000.00 10,500.00
Jumlah Harga Bahan 206,339.57
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 435,239.57
E Overhead + Profit (Contoh 15%) 10% x D 43,523.96
F Harga Satuan Pekerjaan per - m2 (D+E) 478,763.53

A.4.4.3.35 1 m2 Keramik Lantai (40 x 40 cm)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.500 185,000.00 92,500.00
2 Tukang L.02 OH 0.250 230,000.00 57,500.00
3 Kepala tukang L.03 OH 0.030 260,000.00 7,800.00
4 Mandor L.04 OH 0.030 280,000.00 8,400.00
Jumlah Harga Tenaga Kerja 166,200.00
B Bahan *
1 Keramik Ukuran 30 X 30 Dos 1.000 90,000.00 90,000.00
2 Portland Cement (PC) kg 9.000 1,900.00 17,100.00
4 Pasir Pasang (PS) m3 0.045 342,857.14 15,428.57
5 Semen Warna kg 0.500 21,000.00 10,500.00
Jumlah Harga Bahan 133,028.57
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 299,228.57
E Overhead + Profit (Contoh 15%) 10% x D 29,922.86
F Harga Satuan Pekerjaan per - m2 (D+E) 329,151.43

A.4.4.3.36 1 m2 Keramik Lantai (20 x 20 cm)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.700 185,000.00 129,500.00
2 Tukang L.02 OH 0.350 230,000.00 80,500.00
3 Kepala tukang L.03 OH 0.035 260,000.00 9,100.00
4 Mandor L.04 OH 0.035 280,000.00 9,800.00
Jumlah Harga Tenaga Kerja 228,900.00
B Bahan *
1 Keramik Ukuran 20 X 20 Dos 1.050 80,000.00 84,000.00
2 Portland Cement (PC) kg 10.400 1,900.00 19,760.00
4 Pasir Pasang (PS) m3 0.045 342,857.14 15,428.57
5 Semen Warna kg 0.500 21,000.00 10,500.00
Jumlah Harga Bahan 129,688.57
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 358,588.57
E Overhead + Profit (Contoh 15%) 10% x D 35,858.86
F Harga Satuan Pekerjaan per - m2 (D+E) 394,447.43

A.4.4.3.54 1 m2 Keramik Dinding (20 x 25 cm)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.900 185,000.00 166,500.00
2 Tukang L.02 OH 0.450 230,000.00 103,500.00
3 Kepala tukang L.03 OH 0.045 260,000.00 11,700.00
4 Mandor L.04 OH 0.045 280,000.00 12,600.00
Jumlah Harga Tenaga Kerja 294,300.00
B Bahan *
1 Keramik Ukuran 30 X 30 buah 21.200 5,450.00 115,540.00
2 Portland Cement (PC) kg 9.300 1,900.00 17,670.00
4 Pasir Pasang (PS) m3 0.018 342,857.14 6,171.43
5 Semen Warna kg 1.940 21,000.00 40,740.00
Jumlah Harga Bahan 180,121.43
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 474,421.43
E Overhead + Profit (Contoh 15%) 10% x D 47,442.14
F Harga Satuan Pekerjaan per - m2 (D+E) 521,863.57

1 m3 Kusen Pintu dan Jendela Ky. Besi

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 7.000 185,000.00 1,295,000.00
2 Tukang L.02 OH 21.000 230,000.00 4,830,000.00
3 Kepala tukang L.03 OH 2.100 260,000.00 546,000.00
4 Mandor L.04 OH 0.350 280,000.00 98,000.00
Jumlah Harga Tenaga Kerja 6,769,000.00
B Bahan *
1 Balok Ky Besi m3 1.100 5,450,000.00 5,995,000.00
2 Paku 10 cm kg 1.250 27,250.00 34,062.50
4 Lem Aica Aibon kg 1.000 80,000.00 80,000.00
Jumlah Harga Bahan 6,109,062.50
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 12,878,062.50
E Overhead + Profit (Contoh 15%) 10% x D 1,287,806.25
F Harga Satuan Pekerjaan per - m2 (D+E) 14,165,868.75

1 m2 Daun Pintu Panil Ky. Linggua

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.000 185,000.00 185,000.00
2 Tukang L.02 OH 3.000 230,000.00 690,000.00
3 Kepala tukang L.03 OH 0.300 260,000.00 78,000.00
4 Mandor L.04 OH 0.050 280,000.00 14,000.00
Jumlah Harga Tenaga Kerja 967,000.00
B Bahan *
1 Papan Ky Linggua m3 0.040 5,450,000.00 218,000.00
2 Lem Aica Aibon kg 0.500 80,000.00 40,000.00
Jumlah Harga Bahan 258,000.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 1,225,000.00
E Overhead + Profit (Contoh 15%) 10% x D 122,500.00
F Harga Satuan Pekerjaan per - m2 (D+E) 1,347,500.00
1 m2 Daun Pintu Tripleks Rangkap Lapis Seng, Rangka Kayu Matoa

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.700 185,000.00 129,500.00
2 Tukang L.02 OH 2.100 230,000.00 483,000.00
3 Kepala tukang L.03 OH 0.210 260,000.00 54,600.00
4 Mandor L.04 OH 0.035 280,000.00 9,800.00
Jumlah Harga Tenaga Kerja 676,900.00
B Bahan *
1 Papan Ky Matoa m3 0.025 3,150,000.00 78,750.00
2 Paku 1 cm - 2,5 cm kg 0.030 27,250.00 817.50
3 Lem Kayu kg 0.500 80,000.00 40,000.00
4 Tripleks tebal 4 mm lembar 1.000 85,000.00 85,000.00
5 Seng Plat BJLS 0,3 mm lembar 0.850 50,000.00 42,500.00
Jumlah Harga Bahan 79,567.50
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 756,467.50
E Overhead + Profit (Contoh 15%) 10% x D 75,646.75
F Harga Satuan Pekerjaan per - m2 (D+E) 832,114.25

1 m2 Daun Pintu dan Jendela Kaca Ky. Linggua

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.800 185,000.00 148,000.00
2 Tukang L.02 OH 2.400 230,000.00 552,000.00
3 Kepala tukang L.03 OH 0.240 260,000.00 62,400.00
4 Mandor L.04 OH 0.040 280,000.00 11,200.00
Jumlah Harga Tenaga Kerja 773,600.00
B Bahan *
1 Papan Ky Linggua m3 0.024 5,450,000.00 130,800.00
2 Lem Aica Aibon kg 0.300 80,000.00 24,000.00
Jumlah Harga Bahan 154,800.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 928,400.00
E Overhead + Profit (Contoh 15%) 10% x D 92,840.00
F Harga Satuan Pekerjaan per - m2 (D+E) 1,021,240.00

A.4.6.1.10 1 m2 Jalusi Kusen, Kayu Besi

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.670 185,000.00 123,950.00
2 Tukang L.02 OH 2.000 230,000.00 460,000.00
3 Kepala tukang L.03 OH 0.200 260,000.00 52,000.00
4 Mandor L.04 OH 0.335 280,000.00 93,800.00
Jumlah Harga Tenaga Kerja 729,750.00
B Bahan *
1 Papan Ky Besi m3 0.060 5,450,000.00 327,000.00
2 Paku 1 - 25 cm kg 0.150 27,250.00 4,087.50
Jumlah Harga Bahan 331,087.50
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 1,060,837.50
E Overhead + Profit (Contoh 15%) 10% x D 106,083.75
F Harga Satuan Pekerjaan per - m2 (D+E) 1,166,921.25

A.4.6.2.2. 1 Bh Pasang Kunci Tanam 2 Slaag

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.010 185,000.00 1,850.00
2 Tukang L.02 OH 0.500 230,000.00 115,000.00
3 Kepala tukang L.03 OH 0.050 260,000.00 13,000.00
4 Mandor L.04 OH 0.005 280,000.00 1,400.00
Jumlah Harga Tenaga Kerja 131,250.00
B Bahan *
1 Kunci Tanam 2 Slaag Bh 1.000 150,000.00 150,000.00
Jumlah Harga Bahan 150,000.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 281,250.00
E Overhead + Profit (Contoh 15%) 10% x D 28,125.00
F Harga Satuan Pekerjaan per - m2 (D+E) 309,375.00

A.4.6.2.6. 1 Bh Pasang Engsel Pintu

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.015 185,000.00 2,775.00
2 Tukang L.02 OH 0.150 230,000.00 34,500.00
3 Kepala tukang L.03 OH 0.015 260,000.00 3,900.00
4 Mandor L.04 OH 0.0008 280,000.00 224.00
Jumlah Harga Tenaga Kerja 41,399.00
B Bahan *
1 Engsel Pintu Bh 1.000 20,000.00 20,000.00
Jumlah Harga Bahan 20,000.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 61,399.00
E Overhead + Profit (Contoh 15%) 10% x D 6,139.90
F Harga Satuan Pekerjaan per - m2 (D+E) 67,538.90
A.4.6.2.6. 1 Bh Pasang Engsel Jendela

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.015 185,000.00 2,775.00
2 Tukang L.02 OH 0.150 230,000.00 34,500.00
3 Kepala tukang L.03 OH 0.015 260,000.00 3,900.00
4 Mandor L.04 OH 0.0008 280,000.00 224.00
Jumlah Harga Tenaga Kerja 41,399.00
B Bahan *
1 Engsel Jendela Bh 1.000 8,250.00 8,250.00
Jumlah Harga Bahan 8,250.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 49,649.00
E Overhead + Profit (Contoh 15%) 10% x D 4,964.90
F Harga Satuan Pekerjaan per - m2 (D+E) 54,613.90

A.4.6.2.9. 1 Bh Pasang Grendel Pintu

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.015 185,000.00 2,775.00
2 Tukang L.02 OH 0.150 230,000.00 34,500.00
3 Kepala tukang L.03 OH 0.015 260,000.00 3,900.00
4 Mandor L.04 OH 0.008 280,000.00 2,240.00
Jumlah Harga Tenaga Kerja 43,415.00
B Bahan *
1 Grendel Pintu Bh 1.000 20,000.00 20,000.00
Jumlah Harga Bahan 20,000.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 63,415.00
E Overhead + Profit (Contoh 15%) 10% x D 6,341.50
F Harga Satuan Pekerjaan per - m2 (D+E) 69,756.50

A.4.6.2.9. 1 Bh Pasang Grendel Jendela

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.015 185,000.00 2,775.00
2 Tukang L.02 OH 0.150 230,000.00 34,500.00
3 Kepala tukang L.03 OH 0.015 260,000.00 3,900.00
4 Mandor L.04 OH 0.008 280,000.00 2,240.00
Jumlah Harga Tenaga Kerja 43,415.00
B Bahan *
1 Grendel Jendela Bh 1.000 11,000.00 11,000.00
Jumlah Harga Bahan 11,000.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 54,415.00
E Overhead + Profit (Contoh 15%) 10% x D 5,441.50
F Harga Satuan Pekerjaan per - m2 (D+E) 59,856.50

A.4.6.2.7. 1 Bh Pasang Hak Angin

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.100 185,000.00 18,500.00
2 Tukang L.02 OH 0.200 230,000.00 46,000.00
3 Kepala tukang L.03 OH 0.020 260,000.00 5,200.00
4 Mandor L.04 OH 0.008 280,000.00 2,240.00
Jumlah Harga Tenaga Kerja 71,940.00
B Bahan *
1 Hak Angin Bh 1.000 12,500.00 12,500.00
Jumlah Harga Bahan 12,500.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 84,440.00
E Overhead + Profit (Contoh 15%) 10% x D 8,444.00
F Harga Satuan Pekerjaan per - m2 (D+E) 92,884.00

A.4.6.2.17 Pemasangan 1 m² kaca tebal 5 mm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.015 185,000.00 2,775.00
2 Tukang Kayu L.03 OH 0.15 230,000.00 34,500.00
3 Kepala Tukang L.03 OH 0.015 260,000.00 3,900.00
4 Mandor L.04 OH 0.0008 280,000.00 224.00
Jumlah Harga Tenaga Kerja 41,399.00
B Bahan
1 Kaca tebal 5 mm m² 1.10 107,633.71 118,397.09
2 Sealant Kg 0.05 25,000.00 1,250.00
Jumlah Harga Bahan 119,647.09
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 161,046.09
E Overhead + Profit (Contoh 15%) 10% x D 16,104.61
F Harga Satuan Pekerjaan per - m3 (D+E) 177,150.69

1 m2 Pengecatan Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup )

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.020 185,000.00 3,700.00
2 Tukang L.02 OH 0.063 230,000.00 14,490.00
3 Kepala tukang L.03 OH 0.006 260,000.00 1,638.00
4 Mandor L.04 OH 0.003 280,000.00 700.00
Jumlah Harga Tenaga Kerja 20,528.00
B Bahan *
1 Plamir tembok Kg 0.100 30,000.00 3,000.00
2 Cat Dasar Tembok Kg 0.100 37,500.00 3,750.00
3 Cat Tembok Kg 0.260 37,500.00 9,750.00
Jumlah Harga Bahan 16,500.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 37,028.00
E Overhead + Profit (Contoh 15%) 10% x D 3,702.80
F Harga Satuan Pekerjaan per - m2 (D+E) 40,730.80
1 m2 Pengecatan Plafond

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.028 185,000.00 5,180.00
2 Tukang L.02 OH 0.042 230,000.00 9,660.00
3 Kepala tukang L.03 OH 0.004 260,000.00 1,092.00
4 Mandor L.04 OH 0.003 280,000.00 840.00
Jumlah Harga Tenaga Kerja 16,772.00
B Bahan *
1 Cat tembok Kg 0.260 37,500.00 9,750.00
Jumlah Harga Bahan 9,750.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 26,522.00
E Overhead + Profit (Contoh 15%) 10% x D 2,652.20
F Harga Satuan Pekerjaan per - m2 (D+E) 29,174.20

1 m2 Pengecatan Bidang Kayu Baru ( 1 Lapis Plamir ), 1 Lapis Cat Dasar, 2 Lapis Cat Penutup

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.070 185,000.00 12,950.00
2 Tukang L.02 OH 0.105 230,000.00 24,150.00
3 Kepala tukang L.03 OH 0.004 260,000.00 1,040.00
4 Mandor L.04 OH 0.003 280,000.00 700.00
Jumlah Harga Tenaga Kerja 38,840.00
B Bahan *
1 Meni Kayu Kg 0.200 32,000.00 6,400.00
2 Plamir kayu Kg 0.150 45,000.00 6,750.00
3 Cat Dasar (Kayu) Kg 0.170 65,000.00 11,050.00
4 Cat Penutup (Kayu) Kg 0.350 65,000.00 22,750.00
5 Pengencer Kg 0.350 25,000.00 8,750.00
6 Ampelas Lembar 0.350 7,500.00 2,625.00
Jumlah Harga Bahan 58,325.00
C Peralatan
1 Kuas Buah 0.010 9,500.00 95.00
Jumlah Harga Peralatan 95.00
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 97,260.00
E Overhead + Profit (Contoh 15%) 10% x D 9,726.00
F Harga Satuan Pekerjaan per - m1 (D+E) 106,986.00

A.5.1.1.5 (K3) Pemasangan 1 buah wastafel

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.2000 185,000.00 222,000.00
2 Tukang Batu L.02 OH 1.4500 230,000.00 333,500.00
3 Kepala Tukang L.03 OH 0.1500 260,000.00 39,000.00
4 Mandor L.04 OH 0.0600 280,000.00 16,800.00
Jumlah Harga Tenaga Kerja 611,300.00
B Bahan
1 Wastafel Unit 1.200 1,500,000.00 1,800,000.00
2 Semen Portland Kg 6.000 1,900.00 11,400.00
3 Pasir Pasang m³ 0.010 342,857.14 3,428.57
4 Perlengkapan % 12.000 180,000.00 180,000.00
Jumlah Harga Bahan 1,994,828.57
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 2,606,128.57
E Overhead + Profit (Contoh 15%) 10% x D 260,612.86
F Harga Satuan Pekerjaan per - m3 (D+E) 2,866,741.43

A.5.1.1.18 1 M Pipa Galvanis Ø 1/2"

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)


1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.054 185,000.00 9,990.00
2 Tukang Pipa L.02 OH 0.090 230,000.00 20,700.00
3 Kepala Tukang L.03 OH 0.009 260,000.00 2,340.00
4 Mandor L.04 OH 0.027 280,000.00 7,560.00
Jumlah Harga Tenaga Kerja 40,590.00
B Bahan *
1 Pipa GIP Ø 1/2" - 6 m, Medium A m' 1.200 31,833.33 38,200.00
2 Perlengkapan Ls 35% x pipa 11,141.67 11,141.67
Jumlah Harga Bahan 49,341.67
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 89,931.67
E Overhead + Profit (Contoh 15%) 10% x D 8,993.17
F Harga Satuan Pekerjaan per - m2 (D+E) 98,924.83

1 M Pipa Galvanis Ø 2"

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.054 185,000.00 9,990.00
2 Tukang Pipa L.02 OH 0.090 230,000.00 20,700.00
3 Kepala Tukang L.03 OH 0.009 260,000.00 2,340.00
4 Mandor L.04 OH 0.027 280,000.00 7,560.00
Jumlah Harga Tenaga Kerja 40,590.00
B Bahan *
1 Pipa GIP Ø 1" - 6 m, Medium A m' 1.200 31,833.33 38,200.00
1 Pipa GIP Ø 2" - 6 m, Medium A m' 1.200 73,833.33 88,600.00
2 Perlengkapan Ls 35% x pipa 25,841.67 25,841.67
Jumlah Harga Bahan 152,641.67
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 193,231.67
E Overhead + Profit (Contoh 15%) 10% x D 19,323.17
F Harga Satuan Pekerjaan per - m2 (D+E) 212,554.83

A.5.1.1.29 Pemasangan 1 m' pipa PVC tipe AW diameter 2 "

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.054 185,000.00 9,990.00
2 Tukang Batu L.02 OH 0.09 230,000.00 20,700.00
3 Kepala Tukang L.03 OH 0.009 260,000.00 2,340.00
4 Mandor L.04 OH 0.003 280,000.00 840.00
Jumlah Harga Tenaga Kerja 33,870.00
B Bahan
1 Pipa PVC 2 " M 1.20 26,500.00 31,800.00
2 Perlengkapan % 35.00 0 -
Jumlah Harga Bahan 31,800.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 65,670.00
E Overhead + Profit (Contoh 15%) 10% x D 6,567.00
F Harga Satuan Pekerjaan per - m3 (D+E) 72,237.00

A.5.1.1.31. 1 M Pipa PVC Ø 3"

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.054 185,000.00 9,990.00
2 Tukang Pipa L.02 OH 0.090 230,000.00 20,700.00
3 Kepala Tukang L.03 OH 0.009 260,000.00 2,340.00
4 Mandor L.04 OH 0.001 280,000.00 364.00
Jumlah Harga Tenaga Kerja 33,394.00
B Bahan *
1 Pipa PVC Ø 3" - 4m tipe AW m' 1.200 56,125.00 67,350.00
2 Perlengkapan Ls 35% x pipa 19,643.75 19,643.75
Jumlah Harga Bahan 86,993.75
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 120,387.75
E Overhead + Profit (Contoh 15%) 10% x D 12,038.78
F Harga Satuan Pekerjaan per - m2 (D+E) 132,426.53

A.5.1.1.29. 1 M Pipa PVC Ø 4"

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.081 185,000.00 14,985.00
2 Tukang Pipa L.02 OH 0.135 230,000.00 31,050.00
3 Kepala Tukang L.03 OH 0.0135 260,000.00 3,510.00
4 Mandor L.04 OH 0.004 280,000.00 1,120.00
Jumlah Harga Tenaga Kerja 50,665.00
B Bahan *
1 Pipa PVC Ø 4" - 4m tipe AW m' 1.200 85,000.00 102,000.00
2 Perlengkapan Ls 35% x pipa 29,750.00 29,750.00
Jumlah Harga Bahan 131,750.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 182,415.00
E Overhead + Profit (Contoh 15%) 10% x D 18,241.50
F Harga Satuan Pekerjaan per - m1 (D+E) 200,656.50
A.5.1.1.2. 1 Bh Kloset Jongkok Porselen

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.000 185,000.00 185,000.00
2 Tukang Batu L.02 OH 1.500 230,000.00 345,000.00
3 Kepala Tukang L.03 OH 0.150 260,000.00 39,000.00
4 Mandor L.04 OH 0.160 280,000.00 44,800.00
Jumlah Harga Tenaga Kerja 613,800.00
B Bahan *
1 Kloset Jongkok Porselen Unit 1.000 690,000.00 690,000.00
2 Portland Cement Kg 6.000 1,900.00 11,400.00
3 Pasir Pasang m3 0.010 342,857.14 3,428.57
Jumlah Harga Bahan 704,828.57
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 1,318,628.57
E Overhead + Profit (Contoh 15%) 10% x D 131,862.86
F Harga Satuan Pekerjaan per - m2 (D+E) 1,450,491.43

A.5.1.1.14. 1 Bh Pasang Floor Drain

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.010 185,000.00 1,850.00
2 Tukang Batu L.02 OH 0.100 230,000.00 23,000.00
3 Kepala Tukang L.03 OH 0.010 260,000.00 2,600.00
4 Mandor L.04 OH 0.005 280,000.00 1,400.00
Jumlah Harga Tenaga Kerja 28,850.00
B Bahan *
1 Floor Drain Unit 1.000 75,000.00 75,000.00
Jumlah Harga Bahan 75,000.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 103,850.00
E Overhead + Profit (Contoh 15%) 10% x D 10,385.00
F Harga Satuan Pekerjaan per - m2 (D+E) 114,235.00

A.5.1.1.14. 1 Bh Pasang Kran Dia. 1/2"

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.010 185,000.00 1,850.00
2 Tukang Batu L.02 OH 0.400 230,000.00 92,000.00
3 Kepala Tukang L.03 OH 0.040 260,000.00 10,400.00
4 Mandor L.04 OH 0.005 280,000.00 1,400.00
Jumlah Harga Tenaga Kerja 105,650.00
B Bahan *
1 Kran Air Dia. 1/2" Unit 1.000 38,500.00 38,500.00
1 Sealtipe Buah 0.025 5,000.00 125.00
Jumlah Harga Bahan 38,625.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 144,275.00
E Overhead + Profit (Contoh 15%) 10% x D 14,427.50
F Harga Satuan Pekerjaan per - m2 (D+E) 158,702.50

1 Ttk Pasang Lampu SL 52 Watt

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.000 185,000.00 185,000.00
2 Tukang Listrik L.02 OH 1.000 230,000.00 230,000.00
3 Kepala tukang L.03 OH 0.100 260,000.00 26,000.00
4 Mandor L.04 OH 0.050 280,000.00 14,000.00
Jumlah Harga Tenaga Kerja 455,000.00
B Bahan *
1 Lampu SL 52 Watt + Komplit Bh 1.000 Err:509 Err:509
2 Kabel NYM 2x2,5 mm M' 10.000 15,700.00 157,000.00
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) Err:509
E Overhead + Profit (Contoh 15%) 10% x D Err:509
F Harga Satuan Pekerjaan per - m2 (D+E) Err:509

1 Ttk Pasang Lampu SL 45 Watt

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.000 185,000.00 185,000.00
2 Tukang Listrik L.02 OH 1.000 185,000.00 185,000.00
3 Kepala tukang L.03 OH 0.100 230,000.00 23,000.00
4 Mandor L.04 OH 0.050 260,000.00 13,000.00
Jumlah Harga Tenaga Kerja 406,000.00
B Bahan *
1 Lampu SL 45 Watt + Komplit Bh 1.000 50.00 50.00
2 Kabel NYM 2x2,5 mm M' 10.000 15,700.00 157,000.00
Jumlah Harga Bahan 157,050.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 563,050.00
E Overhead + Profit (Contoh 15%) 10% x D 56,305.00
F Harga Satuan Pekerjaan per - m2 (D+E) 619,355.00
1 Ttk Pasang Lampu SL 30 Watt

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.000 185,000.00 185,000.00
2 Tukang Listrik L.02 OH 1.000 185,000.00 185,000.00
3 Kepala tukang L.03 OH 0.100 230,000.00 23,000.00
4 Mandor L.04 OH 0.050 260,000.00 13,000.00
Jumlah Harga Tenaga Kerja 406,000.00
B Bahan *
1 Lampu SL 30 Watt + Komplit Bh 1.000 150,000.00 150,000.00
2 Kabel NYM 2x2,5 mm M' 10.000 15,700.00 157,000.00
Jumlah Harga Bahan 307,000.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 713,000.00
E Overhead + Profit (Contoh 15%) 10% x D 71,300.00
F Harga Satuan Pekerjaan per - m2 (D+E) 784,300.00

1 Ttk Pasang Lampu SL 25 Watt

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.000 185,000.00 185,000.00
2 Tukang Listrik L.02 OH 1.000 185,000.00 185,000.00
3 Kepala tukang L.03 OH 0.100 230,000.00 23,000.00
4 Mandor L.04 OH 0.050 260,000.00 13,000.00
Jumlah Harga Tenaga Kerja 406,000.00
B Bahan *
1 Lampu SL 25 Watt + Komplit Bh 1.000 90,000.00 90,000.00
2 Kabel NYM 2x2,5 mm M' 10.000 15,700.00 157,000.00
Jumlah Harga Bahan 247,000.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 653,000.00
E Overhead + Profit (Contoh 15%) 10% x D 65,300.00
F Harga Satuan Pekerjaan per - m2 (D+E) 718,300.00

1 Ttk Pasang Lampu Fittng 14 Watt

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.000 185,000.00 185,000.00
2 Tukang Listrik L.02 OH 1.000 230,000.00 230,000.00
3 Kepala tukang L.03 OH 0.100 260,000.00 26,000.00
4 Mandor L.04 OH 0.050 280,000.00 14,000.00
Jumlah Harga Tenaga Kerja 455,000.00
B Bahan *
1 Lampu Fitting 14 Watt Bh 1.000 26,000.00 26,000.00
2 Fitting Bh 1.000 15,000.00 15,000.00
3 Kabel NYM 2x2,5 mm M' 10.000 15,700.00 157,000.00
Jumlah Harga Bahan 198,000.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 653,000.00
E Overhead + Profit (Contoh 15%) 10% x D 65,300.00
F Harga Satuan Pekerjaan per - m2 (D+E) 718,300.00
1 Ttk Pasang Stop Kontak Dinding

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.000 185,000.00 185,000.00
2 Tukang Listrik L.02 OH 1.000 230,000.00 230,000.00
3 Kepala tukang L.03 OH 0.100 260,000.00 26,000.00
4 Mandor L.04 OH 0.050 280,000.00 14,000.00
Jumlah Harga Tenaga Kerja 455,000.00
B Bahan *
1 Stop Kontak Dinding Bh 1.000 36,000.00 36,000.00
2 Kabel NYM 2x2,5 mm M' 10.000 15,700.00 157,000.00
Jumlah Harga Bahan 193,000.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 648,000.00
E Overhead + Profit (Contoh 15%) 10% x D 64,800.00
F Harga Satuan Pekerjaan per - m2 (D+E) 712,800.00

1 Ttk Pasang Stop Kontak Lantai

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.000 - -
2 Tukang Listrik L.02 OH 1.000 - -
3 Kepala tukang L.03 OH 0.100 - -
4 Mandor L.04 OH 0.050 - -
Jumlah Harga Tenaga Kerja -
B Bahan *
1 Stop Kontak Lantai Bh 1.000 - -
2 Kabel NYM 2x2,5 mm M' 10.000 - -
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) -
E Overhead + Profit (Contoh 15%) 10% x D -
F Harga Satuan Pekerjaan per - m2 (D+E) -

1 Ttk Pasang Stop Kontak AC

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.000 185,000.00 185,000.00
2 Tukang Listrik L.02 OH 1.000 230,000.00 230,000.00
3 Kepala tukang L.03 OH 0.100 260,000.00 26,000.00
4 Mandor L.04 OH 0.050 280,000.00 14,000.00
Jumlah Harga Tenaga Kerja 455,000.00
B Bahan *
1 Stop Kontak AC Bh 1.000 270,000.00 270,000.00
2 Kabel NYM 2x2,5 mm M' 10.000 15,700.00 157,000.00
Jumlah Harga Bahan 427,000.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 882,000.00
E Overhead + Profit (Contoh 15%) 10% x D 88,200.00
F Harga Satuan Pekerjaan per - m2 (D+E) 970,200.00

1 Ttk Pasang Saklar Ganda

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.000 185,000.00 185,000.00
2 Tukang Listrik L.02 OH 1.000 230,000.00 230,000.00
3 Kepala tukang L.03 OH 0.100 260,000.00 26,000.00
4 Mandor L.04 OH 0.050 280,000.00 14,000.00
Jumlah Harga Tenaga Kerja 455,000.00
B Bahan *
1 Saklar Double Bh 1.000 40,000.00 40,000.00
2 Kabel NYM 2x2,5 mm M' 10.000 15,700.00 157,000.00
3 Pipa Kabel Union (Conduit) M' 3.000 - -
Jumlah Harga Bahan 197,000.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 652,000.00
E Overhead + Profit (Contoh 15%) 10% x D 65,200.00
F Harga Satuan Pekerjaan per - m2 (D+E) 717,200.00

1 Ttk Pasang Saklar Tunggal

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.000 185,000.00 185,000.00
2 Tukang Listrik L.02 OH 1.000 230,000.00 230,000.00
3 Kepala tukang L.03 OH 0.100 260,000.00 26,000.00
4 Mandor L.04 OH 0.050 280,000.00 14,000.00
Jumlah Harga Tenaga Kerja 455,000.00
B Bahan *
1 Saklar Tunggal Bh 1.000 33,000.00 33,000.00
2 Kabel NYM 2x2,5 mm M' 10.000 15,700.00 157,000.00
3 Pipa Kabel Union (Conduit) M' 3.000 - -
Jumlah Harga Bahan 190,000.00
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 645,000.00
E Overhead + Profit (Contoh 15%) 10% x D 64,500.00
F Harga Satuan Pekerjaan per - m2 (D+E) 709,500.00
1 m2 Pasang Teralis + Pengecatan

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja OH 0.200 185,000.00 37,000.00
2 Tukang OH 0.500 230,000.00 115,000.00
3 Kepala tukang OH 0.050 260,000.00 13,000.00
4 Mandor OH 0.018 280,000.00 5,040.00
Jumlah Harga Tenaga Kerja 170,040.00
B Bahan
1 Besi Plat Strip 4 cm m1 4.378 25,000.00 109,453.78
2 Besi Tempa Dia.10 m1 10.395 20,200.00 209,978.15
4 Las Listrik cm 12.509 14,537.16 181,850.89
5 Pengecatan m2 1.172 106,986.00 125,341.78
Jumlah Harga Bahan 626,624.60
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 796,664.60
E Overhead + Profit (Contoh 15%) 10% x D 79,666.46
F Harga Satuan Pekerjaan per - m1 (D) 876,331.06

A.2.2.1.9 1 m2 Pembersihan Lapangan dan Perataan

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.100 185,000.00 18,500.00
2 Mandor L.04 OH 0.050 280,000.00 14,000.00
Jumlah Harga Tenaga Kerja 32,500.00
B Bahan
Jumlah Harga Bahan -
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) 32,500.00
E Overhead + Profit (Contoh 15%) (Contoh 15%) 10% x D 3,250.00
F Harga Satuan Pekerjaan per - m2 (D+E) 35,750.00

A.2.3.1.11 1 m3 Pengurug Dengan Pasir Urug

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.300 185,000.00 55,500.00
2 Mandor L.04 OH 0.010 280,000.00 2,800.00
Jumlah Harga Tenaga Kerja 58,300.00
B Bahan
1 Pasir Urug m3 1.200 Err:509 Err:509
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan -
D Jumlah Harga tenaga, Bahan dan Peralatan (A+B+C) Err:509
E Overhead + Profit (Contoh 15%) 10% x D Err:509
F Harga Satuan Pekerjaan per - m3 (D+E) Err:509

A.4.6.2.20. 1 m2 Pasang Paving Natural Tebal 6 cm

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 0.250 185,000.00 46,250.00
2 Tukang Batu L.02 OH 0.500 230,000.00 115,000.00
3 Kepala Tukang L.03 OH 0.050 260,000.00 13,000.00
4 Mandor L.04 OH 0.0013 280,000.00 364.00
Jumlah Harga Tenaga Kerja 174,614.00
B Bahan *
1 Paving Block 6 cm m2 1.010 Err:509 Err:509
2 Pasir Beton m3 0.050 342,857.14 17,142.86
Jumlah Harga Bahan Err:509
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) Err:509
E Overhead + Profit (Contoh 15%) 10% x D Err:509
F Harga Satuan Pekerjaan per - m2 (D+E) Err:509

A.A.4.1.1.4 1 m3 beton untuk lantai kerja (bedding)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.200 185,000.00 222,000.00
2 Tukang batu L.02 OH 0.200 230,000.00 46,000.00
3 Kepala tukang batu L.03 OH 0.020 260,000.00 5,200.00
4 Mandor L.04 OH 0.060 280,000.00 16,800.00
Jumlah Harga Tenaga Kerja 290,000.00
B Bahan
1 PC / Portland Cement kg 326.000 1,900.00 619,400.00
2 PB / Pasir Beton kg 760.000 244.90 186,122.45
3 Kr / Krikil kg 1029.000 543.21 558,962.96
4 Air Liter 215.000 50.00 10,750.00
Jumlah Harga Bahan 1,375,235.41
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 1,665,235.41
E Overhead + Profit (Contoh 15%) 10% x D 166,523.54
F Harga Satuan Pekerjaan per - m3 (D+E) 1,831,758.95
1 m3 beton Camp. 1:2:3

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.650 185,000.00 305,250.00
2 Tukang batu L.02 OH 0.275 230,000.00 63,250.00
3 Kepala tukang batu L.03 OH 0.028 260,000.00 7,280.00
4 Mandor L.04 OH 0.083 280,000.00 23,240.00
Jumlah Harga Tenaga Kerja 399,020.00
B Bahan
1 PC / Portland Cement Sak 4.600 95,000.00 437,000.00
2 PB / Pasir Beton M3 0.520 342,857.14 178,285.71
3 Kr / Krikil M3 0.870 540,000.00 469,800.00
4 Air Liter 215.000 50.00 10,750.00
Jumlah Harga Bahan 1,095,835.71
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 1,494,855.71
E Overhead + Profit (Contoh 15%) 10% x D 149,485.57
F Harga Satuan Pekerjaan per - m3 (D+E) 1,644,341.29

1 Unit Pasang Profil Tank 1100 + Aksesories

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.200 185,000.00 222,000.00
2 Tukang batu L.02 OH 0.200 230,000.00 46,000.00
3 Kepala tukang batu L.03 OH 0.020 260,000.00 5,200.00
4 Mandor L.04 OH 0.060 280,000.00 16,800.00
Jumlah Harga Tenaga Kerja 290,000.00
B Bahan
1 Profil Tank 1100 Liter Unit 1.000 3,250,000.00 3,250,000.00
2 Aksesories % 20% 3,250,000.00 650,000.00
Jumlah Harga Bahan 3,900,000.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 4,190,000.00
E Overhead + Profit (Contoh 15%) 10% x D 419,000.00
F Harga Satuan Pekerjaan per - m3 (D+E) 4,609,000.00

1 M2 Pekerjaan Pintu Lipat (Folding Door) Bahan Besi

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja L.01 OH 1.050 185,000.00 194,250.00
2 Tukang L.02 OH 1.050 230,000.00 241,500.00
3 Kepala tukang batu L.03 OH 1.000 260,000.00 260,000.00
4 Mandor L.04 OH 0.005 280,000.00 1,456.00
Jumlah Harga Tenaga Kerja 697,206.00
B Bahan
1 Pintu Lipat Besi Hollow 40x40x4mm M2 1.000 350,000.00 350,000.00
Jumlah Harga Bahan 350,000.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 1,047,206.00
E Overhead + Profit (Contoh 15%) 10% x D 104,720.60
F Harga Satuan Pekerjaan per - m3 (D+E) 1,151,926.60

1 M2 Pekerjaan Pagar Besi Hollow

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
2 Tukang besi L.02 OH 1.050 230,000.00 241,500.00
3 Kepala tukang batu L.03 OH 0.105 260,000.00 27,300.00
4 Mandor L.04 OH 0.052 280,000.00 14,560.00
Jumlah Harga Tenaga Kerja 283,360.00
B Bahan
1 Besi Hollow 40.40.4 mm M' 5.000 10,500.00 52,500.00
2 Assesories (perkuataan, las, dll) Ls 1.000 250,000.00 250,000.00
Jumlah Harga Bahan 302,500.00
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga Kerja, Bahan dan Peralatan (A+B+C) 585,860.00
E Overhead + Profit (Contoh 15%) 10% x D 58,586.00
F Harga Satuan Pekerjaan per - m3 (D+E) 644,446.00
1 unit pekerjaan sepitenk + resapan

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah (Rp)

1 2 3 4 5 6 7
1 galian tanah M3 5.400 369,050.00 1,992,870.00
2 urugan pasir M3 0.180 516,701.43 93,006.26
3 pasangan batu tela 1:3 M2 11.400 189,082.14 2,155,536.43
4 cor beton 1:2:3 M3 0.360 1,503,143.27 541,131.58
5 plat beton bertulang M3 0.432 11,000,536.58 4,752,231.80
6 plesteran 1;3 M2 11.400 99,040.98 1,129,067.20
7 ijuk LS 1.000 300,000.00 300,000.00
8 krikil M3 0.120 540,000.00 64,800.00

Jumlah 11,028,643.27
E Overhead + Profit (Contoh 15%) 10% x D 1,102,864.33
F Harga Satuan Pekerjaan per - m3 (D+E) 12,131,507.59
ESTIMATE ENGINEERING (EE)
PEKERJAAN : PONDASI
KEGIATAN : POR PLAT/ CAKAR AYAM PER 1 UNIT RUMAH
LOKASI : KOYA BARAT
TAHUN ANGGARAN : 2023

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOLUME
SATUAN HARGA
A. Pekerjaan Persiapan
1 Pek. Pembersihan Lokasi ls 1.00 500,000.00 500,000.00
2 Pek. Pemasangan Bowplank M1 5.00 85,149.63 425,748.13
925,748.13
B. Pekerjaan Tanah & Urugan
1 Pek. Galian Tanah M3 3.37 369,050.00 1,242,222.30
2 Pek. Urugan Tanah Kembali M3 1.12 117,150.00 131,442.30
3 Pek. Urugan Pasir Bawah Pondasi M3 0.20 516,701.43 102,306.88
1,475,971.48
C. Pekerjaan Por Plat/ Cakar Ayam
1 Pek. Cor Lantai Kerja 1:3:5 (pondasi titik) M3 0.40 1,503,143.27 595,244.73
3 Pek. Pondasi Poor Plate (cakar ayam)
a.pekerjaan beton M 3
1.19 1,503,143.27 1,785,734.20
b. pekerjaan pembesian Ø 12 Kg 129.65 27,262.40 3,534,460.15
c. bekesting M2 2.63974 325,836.50 860,122.34
6,775,561.42
ESTIMATE ENGINEERING (EE)
PEKERJAAN : PONDASI
KEGIATAN : POR PLAT/ CAKAR AYAM PER 1 UNIT RUMAH
LOKASI : KOYA BARAT
TAHUN ANGGARAN : 2023

HARGA JUMLAH
NO URAIAN PEKERJAAN SAT VOLUME
SATUAN HARGA
II. PEMBANGUNAN LANTAI 2
A. Pekerjaan Pasangan & Beton
1 Pek. Kolom 25/25
a.pekerjaan beton M3 13.50 #NAME? #NAME?
b. pekerjaan pembesian kg 2,331.85 #NAME? #NAME?
c. bekesting M2 22.50 #NAME? #NAME?
#NAME?
2 Pek. Kolom 15/15
a.pekerjaan beton M3 8.42 #NAME? #NAME?
b. pekerjaan pembesian kg 1,453.52 #NAME? #NAME?
c. bekesting M2 14.03 #NAME? #NAME?
#NAME?
3 Pek.Reng Balok 20/15
a.pekerjaan beton M3 19.86 #NAME? #NAME?
b. pekerjaan pembesian kg 3,465.24 #NAME? #NAME?
c. bekesting M2 30.34 581,262.00 17,636,457.85
#NAME?

4 Pek. Pas batu tela M2 #NAME? 189,082.14 #NAME?

5 Pek. Pas Keramik 40 x 40 M 2


882.70 329,151.43 290,541,966.00

#NAME?
B. Pekerjaan Atap
1 Pek. Kuda-Kuda Kayu Besi 5/10 M3 5.28 11,348,810.00 59,921,716.80
2 Pek. Gording 5/10 M3 5.98 11,359,865.00 67,931,992.70
3 Pek. Atap Spandek BJ25 M2 1,297.67 93,813.50 121,739,379.07
4 Pek. Nok Atap Seng M1 115.00 69,784.00 8,025,160.00
5 pekerjaan lisplank 2 x20 cm M1 210.00 140,233.50 29,449,035.00
287,067,283.57
C. Pekerjaan Kusen, Pintu, Jendela, Plafond
1 Pek. Kusen Kayu Besi 5/10 M3 #NAME? 14,165,868.75 #NAME?
2 Pek. Pintu Panil M2 #NAME? 1,021,240.00 #NAME?
3 Pek. Jendela Kaca M2 #NAME? 1,021,240.00 #NAME?
4 Pek. Langit Langit gipsum M2 1,116.00 85,313.25 95,209,587.00
5 Pek. Rangka Langit Lanigt Kayu Matoa M2 1,116.00 192,233.25 214,532,307.00
#NAME?
D. Pekerjaan Plesteran & Acian
1 Pek. Plesteran 1:3 Tebal 15mm M2 #NAME? 99,040.98 #NAME?
2 Pek. Acian M2 #NAME? 68,035.00 #NAME?
#NAME?
E. Pekerjaan Penggantung, Sanitair & sepitenk
1 Pek. Engsel Pintu Bh #NAME? 67,538.90 #NAME?
2 Pek. Engsel Jendela Bh #NAME? 54,613.90 #NAME?
3 Pek. Grendel Pintu Bh #NAME? 69,756.50 #NAME?
4 Pek. Grendel Jendela Bh #NAME? 59,856.50 #NAME?
6 Pek. Pemasangan kloset jongkok Bh #NAME? 1,450,491.43 #NAME?
7 Pek. Pemasangan lampu SL 25 watt Bh #NAME? 619,355.00 #NAME?
8 Pek. Pemasangan saklar tunggal Bh #NAME? 709,500.00 #NAME?
9 Pek. Pemasangan saklar ganda Bh #NAME? 717,200.00 #NAME?
10 Pek. Pemasangan stop kontak Bh #NAME? 712,800.00 #NAME?
#NAME?
F. Pekerjaan Pengecatan & Pas. Tralis
1 Pek. Pengecetan dinding M2 #NAME? 40,730.80 #NAME?
2 Pek. Pengecatan Kusen, Pintu & Jendela M2 #NAME? 106,986.00 #NAME?
3 Pek. Pengecatan Plafond M2 1,116.00 29,174.20 32,558,407.20
4 Pek. Pas. Tralis besi Hollow M2 91.00 644,446.00 58,644,586.00
#NAME?
REKAPITULASI
ENGINEERING ESTIMATE (EE)

PEKERJAAN : PONDASI
LOKASI : KOYA BARAT
TAHUN ANGGARAN : 2023

JUMLAH HARGA
NO JENIS PEKERJAAN
(Rp)

POR PLAT/ CAKAR AYAM PER 1 UNIT RUMAH


A. Pekerjaan Persiapan 925,748.13
B. Pekerjaan Tanah & Urugan 1,475,971.48
C. Pekerjaan Por Plat/ Cakar Ayam 6,775,561.42
REAL COST 9,177,281.03
DIBULATKAN 9,177,000.00

Terbilang : Sembilan Juta Seratus Tujuh Puluh Tujuh Ribu Rupiah

Jayapura, ……………………..2023
REKAPITULASI
ENGINEERING ESTIMATE (EE)

PEKERJAAN : PONDASI
LOKASI : KOYA BARAT
TAHUN ANGGARAN : 2023

JUMLAH HARGA
NO JENIS PEKERJAAN
(Rp)

PEMBANGUNAN LANTAI 2
A. Pekerjaan Pasangan & Beton #NAME?
B. Pekerjaan Atap 287,067,283.57
C. Pekerjaan Kusen, Pintu, Jendela, Plafond #NAME?
D. Pekerjaan Plesteran & Acian #NAME?
E. Pekerjaan Penggantung, Sanitair & sepitenk #NAME?
F. Pekerjaan Pengecatan & Pas. Tralis #NAME?
REAL COST #NAME?
DIBULATKAN #NAME?
TOTAL 2 UNIT #NAME?

Terbilang : Lima Miliyar Enam Ratus Sembilan Puluh Lima Juta Rupiah

Jayapura, ……………………..2022
No. Uraian pekerjaan Panjang Lebar Tinggi Jumlah Volume M2 Volume M3 Koef.Hit. Quant.Hit. Sat.

Galian tanah pondasi 27.66 m3


52.00 0.70 0.76 1.00 27.66

Aanstamping 4.68
52.00 0.60 0.15 1.00 4.68
Pondasi menerus 11.65 m3
52.00 0.40 0.56 1.00 11.65

Urugan tanah Kembali 6.92 m3

Urugan tanah peniggian lantai 8.03 m3


0.10 80.25 8.03

Urugan pasir dibawah lantai 4.01 m3


0.05 80.25 4.01

Cor Lantai Beton Tumbuk 5.62 m3


0.07 80.25 5.62

Cor Sloof 20/25 2.60 m3


52.00 0.20 0.25 1.00 2.60

Cor Kolom 20/20 3.04 m3


0.20 0.20 4.00 19.00 3.04

Cor Kolom praktis 15/15 0.25 m3


0.15 0.15 3.75 3.00 0.25

Cor Ringbalk 20/25 2.60 m3


52.00 0.20 0.25 1.00 2.60

Cor atap dak beton 4.60 m3


0.10 46.00 4.60

Cor Lisplank beton 3.44 m3


43.00 0.10 0.80 1.00 3.44

Pekerjaan kuda-kuda 0.90 m3


180.60 0.05 0.10 0.90

Gording 0.70
5.00 0.05 0.10 28.00 0.70

Pekerjaan atap 161.60 m2


7.00 4.70 4.00 131.60
2.50 3.00 4.00 30.00

Pekerjaan lispalank kayu 56.00 m1


56.00 1.00

Pasangan batu tela 109.22 m2


2.30 3.75 13.00 112.13 53.91
3.30 3.75 2.00 24.75
1.20 3.75 3.00 13.50
1.80 3.75 1.00 6.75
0.80 3.75 2.00 6.00
163.13

Plasteran Dinding tembok 218.43 m2

Plasteran beton 74.30 m2


Kolom 0.56 3.75 19.00 39.90
Lispalank 43.00 0.80 1.00 34.40

Plasteran atap dak beton/water profing 46.00 46.00 m2

Pekerjaan Acian 292.73 m2

Pekerjaan Kusen 0.49 m3


p1 7.00
P2 12.80
J1 72.80
V 5.70
98.30 0.05 0.10 0.49

Pekerjaan Pintu Panil 3.00 m2


p1 2.10 0.80 2.00
P2 2.10 0.80 1.00

Pekerjaan jendela Panil kaca 17.92 m2


J1 0.80 1.40 16.00

Pekerjaan ventilasi kaca 6.19 m3


V1 0.35
J1 5.84

Jalusi Kayu 2/10 0.40 0.80 1.00 0.32 0.32 m2

Pekerjaan Plafon Gypsum 76.29 m2


7.88 7.88 1.00 62.09
1.38 3.38 1.00 4.66
1.38 1.88 1.00 2.59
7.88 0.88 1.00 6.93

Pekerjaan List Plafon Gypsum 56.56 m1


31.52
15.76
1.76
4.14
3.38
56.56
80.35 m2
Pekerjaan Keramik lantai
7.88 7.88 1.00 62.09
1.38 3.38 1.00 4.66
1.38 1.88 1.00 2.59
7.88 0.88 1.00 6.93
8.12 0.50 1.00 4.06

Pekerjaan Engsel Pintu 9.00 bh

Pekerjaan Engsel Jendela 32.00 bh

Kunci Pintu 2 Slaag 2.00 bh

Gerendel Tanam pintu 2 daun 1.00 set

Haak Angin Jendela 32.00 bh

Gerendel Jendela 16.00 bh

Pekerjaa cat Dinding tembok 292.73 m2

Pekerjaan cat Kusen 19.66 m2


98.30 0.20 19.66

Pekerjaan Cat Pintu Panil


3.00 2.00 6.00 m2

Pekerjaan Cat Jendela panil 12.54 m2


17.92 5.38

Pekerjaan Cat Jalusi kayu 0.91 m2


3.80 0.24 1.00 0.91

Pekerjaan cat Lispalank kayu 16.80 m2


56.00 0.30

Pipa Air Hujan PVC 3" 20.00 m1