PVsyst - Simulation report
Grid-Connected System

Project: Aire Acondicionado


Variant: Nueva variante de simulación
No 3D scene defined, no shadings
System power: 4200 Wp

PVsyst TRIAL Topacio - Colombia

PVsyst TRIAL

PVsyst TRIAL
Author

PVsyst TRIAL
Project: Aire Acondicionado
Variant: Nueva variante de simulación

PVsyst V7.2.21
VC0, Simulation date:
06/12/22 23:14

PVsyst TRIAL
with v7.2.21

Project summary
Geographical Site Situation Project settings
Topacio Latitude 4.25 °N Albedo 0.20
Colombia Longitude -74.83 °W
Altitude 286 m
Time zone UTC-5

Meteo data
Topacio
Meteonorm 8.0 (2010-2014), Sat=100% - Sintético

System summary

PVsyst TRIAL
Grid-Connected System No 3D scene defined, no shadings
Simulation for year no 10

PV Field Orientation Near Shadings User's needs


Fixed plane No Shadings Fixed constant load
Tilt/Azimuth 9/0° 3000 W
Global
26.28 MWh/Year

System information
PV Array Inverters
Nb. of modules 28 units Nb. of units 1 unit
Pnom total 4200 Wp Pnom total 4000 W
Pnom ratio 1.050

PVsyst TRIAL
Results summary
Produced Energy 5.59 MWh/year Specific production 1330 kWh/kWp/year Perf. Ratio PR 76.49 %
Used Energy 26.28 MWh/year Solar Fraction SF 21.15 %

Table of contents
Project and results summary 2
General parameters, PV Array Characteristics, System losses 3
Main results 4
Loss diagram 5
Special graphs 6

PVsyst TRIAL

PVsyst TRIAL
06/12/22 PVsyst Evaluation mode Page 2/6
Project: Aire Acondicionado
Variant: Nueva variante de simulación

PVsyst V7.2.21
VC0, Simulation date:
06/12/22 23:14

PVsyst TRIAL
with v7.2.21

General parameters
Grid-Connected System No 3D scene defined, no shadings

PV Field Orientation
Orientation Sheds configuration Models used
Fixed plane No 3D scene defined Transposition Perez
Tilt/Azimuth 9/0° Diffuse Perez, Meteonorm
Circumsolar separate

Horizon Near Shadings User's needs


Free Horizon No Shadings Fixed constant load
3000 W
Global

PVsyst TRIAL
26.28 MWh/Year

PV Array Characteristics
PV module Inverter
Manufacturer Generic Manufacturer Generic
Model SRP-150-6PD Model HNS4000TL (2022)
(Original PVsyst database) (Original PVsyst database)
Unit Nom. Power 150 Wp Unit Nom. Power 4.00 kWac
Number of PV modules 28 units Number of inverters 1 unit
Nominal (STC) 4200 Wp Total power 4.0 kWac
Modules 2 Strings x 14 In series Operating voltage 70-550 V
At operating cond. (50°C) Max. power (=>40°C) 4.40 kWac
Pmpp 3725 Wp Pnom ratio (DC:AC) 1.05

PVsyst TRIAL
U mpp 223 V
I mpp 17 A

Total PV power Total inverter power


Nominal (STC) 4.20 kWp Total power 4 kWac
Total 28 modules Number of inverters 1 unit
Module area 28.1 m² Pnom ratio 1.05

Array losses
Array Soiling Losses Thermal Loss factor DC wiring losses
Loss Fraction 3.0 % Module temperature according to irradiance Global array res. 226 mΩ
Uc (const) 30.0 W/m²K Loss Fraction 1.5 % at STC
Uv (wind) 0.0 W/m²K/m/s

Module Quality Loss Module mismatch losses Strings Mismatch loss

PVsyst TRIAL
Loss Fraction 1.5 % Loss Fraction 2.0 % at MPP Loss Fraction 0.1 %

Module average degradation IAM loss factor


Year no 10 ASHRAE Param.: IAM = 1 - bo (1/cosi -1)
Loss factor 0.4 %/year bo Param. 0.05
Mismatch due to degradation
Imp RMS dispersion 0.4 %/year
Vmp RMS dispersion 0.4 %/year

System losses
Auxiliaries loss

PVsyst TRIAL
06/12/22 PVsyst Evaluation mode Page 3/6
Project: Aire Acondicionado
Variant: Nueva variante de simulación

PVsyst V7.2.21
VC0, Simulation date:
06/12/22 23:14

PVsyst TRIAL
with v7.2.21

Main results
System Production
Produced Energy 5.59 MWh/year Specific production 1330 kWh/kWp/year
Used Energy 26.28 MWh/year Performance Ratio PR 76.49 %
Solar Fraction SF 21.15 %

Normalized productions (per installed kWp) Performance Ratio PR

PVsyst TRIAL
Balances and main results

GlobHor DiffHor T_Amb GlobInc GlobEff EArray E_User E_Solar E_Grid EFrGrid
kWh/m² kWh/m² °C kWh/m² kWh/m² MWh MWh MWh MWh MWh

PVsyst TRIAL
January 150.3 65.48 24.39 159.5 150.6 0.521 2.232 0.505 0.005 1.727
February 130.5 74.11 24.66 135.0 127.1 0.444 2.016 0.433 0.002 1.583
March 146.1 73.26 24.47 147.1 138.8 0.481 2.232 0.465 0.006 1.767
April 160.1 69.29 23.89 155.8 146.6 0.510 2.160 0.495 0.004 1.665
May 165.7 76.35 24.23 157.3 147.4 0.517 2.232 0.506 0.000 1.726
June 162.3 62.91 24.00 151.1 141.1 0.496 2.160 0.485 0.000 1.675
July 163.8 74.07 24.65 154.5 144.6 0.506 2.232 0.495 0.000 1.737
August 150.6 76.98 24.87 145.6 136.7 0.477 2.232 0.466 0.001 1.766
September 140.4 71.79 24.32 139.3 131.2 0.457 2.160 0.445 0.003 1.715
October 131.3 74.21 24.03 133.4 125.7 0.439 2.232 0.426 0.003 1.806
November 114.7 70.15 23.51 119.0 111.9 0.394 2.160 0.383 0.002 1.777
December 133.5 75.80 24.06 140.9 132.7 0.466 2.232 0.453 0.002 1.779
Year 1749.2 864.40 24.26 1738.4 1634.3 5.709 26.280 5.558 0.027 20.722

PVsyst TRIAL
Legends
GlobHor
DiffHor
T_Amb
GlobInc
GlobEff
Global horizontal irradiation
Horizontal diffuse irradiation
Ambient Temperature
Global incident in coll. plane
Effective Global, corr. for IAM and shadings
EArray
E_User
E_Solar
E_Grid
EFrGrid
Effective energy at the output of the array
Energy supplied to the user
Energy from the sun
Energy injected into grid
Energy from the grid

PVsyst TRIAL
06/12/22 PVsyst Evaluation mode Page 4/6
Project: Aire Acondicionado
Variant: Nueva variante de simulación

PVsyst V7.2.21
VC0, Simulation date:
06/12/22 23:14

PVsyst TRIAL
with v7.2.21

Loss diagram
1749 kWh/m² Global horizontal irradiation

-0.62% Global incident in coll. plane

-3.08% IAM factor on global

-3.00% Soiling loss factor

1634 kWh/m² * 28 m² coll. Effective irradiation on collectors

efficiency at STC = 14.97% PV conversion

6.86 MWh Array nominal energy (at STC effic.)

PVsyst TRIAL -3.80%

-0.66%

-8.02%

-1.50%
Module Degradation Loss ( for year #10)

PV loss due to irradiance level

PV loss due to temperature

Module quality loss

-2.97% Mismatch loss, modules and strings


(including 0.9% for degradation dispersion

-0.95% Ohmic wiring loss


5.71 MWh Array virtual energy at MPP
-2.11% Inverter Loss during operation (efficiency)
0.00% Inverter Loss over nominal inv. power

PVsyst TRIAL
0.00% Inverter Loss due to max. input current
0.00% Inverter Loss over nominal inv. voltage
-0.06% Inverter Loss due to power threshold
0.00% Inverter Loss due to voltage threshold
5.59 MWh Available Energy at Inverter Output

grid
0.00% Auxiliaries (fans, other)
consumption

20.72 5.56 0.03


MWh Dispatch: user and grid reinjection

PVsyst TRIAL
to user
from grid
to user
from solar
to grid

PVsyst TRIAL
06/12/22 PVsyst Evaluation mode Page 5/6
Project: Aire Acondicionado
Variant: Nueva variante de simulación

PVsyst V7.2.21
VC0, Simulation date:
06/12/22 23:14

PVsyst TRIAL
with v7.2.21

Special graphs
Diagrama entrada/salida diaria

PVsyst TRIAL

PVsyst TRIAL Distribución de potencia de salida del sistema

PVsyst TRIAL

PVsyst TRIAL
06/12/22 PVsyst Evaluation mode Page 6/6