Day 0 of the Project - Receipt of PO and Inputs 0

3D Model Frozen for PSA 0

Instructions for BoA 0

Issue PSA BoA ( input data - queries and assumptions ) 10


Approval on BoA 2

PSA Recommendations 10

Review / Approval on PSA recommendations 2


.. Days Plan

Piping Loads for SSA 1

issue BoD ( .doc with ± 8 sections for PSA report ( 10 )

Approval on BOD (4)


PSA Report 7
Approval/comments on PSA report 3
Final PSA Report
Client Comments received
updated PSA report with Client commnets
21/08/2023

21/08/2023

21/08/2023

30/08/2023
02/09/2023

15/09/2023

19/09/2023

21/09/2023

26/09/2023

03/10/2023
09/10/2023
13/10/2023