[ AOPIP RRHH-THESCA-SUPERV] Linea de Tiempo

[AOPIP]

Fecha Inicio Programacion P


2/9/2022 (Wednesday) Display Week 1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
Coordinacion R
GRUPO THESCA:PRES_GEREN_RRHH_SUPERV 7 Feb 2022 14 Feb 2022 21 Feb 2022 28 Feb 2022 7 Mar 2022 14 Mar 2022 21 Mar 2022 28 Mar 2022
E
D 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3
E
% WORK
WBS ITEM LEAD C ISSUE START END DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
E DONE DAYS
1 [inicio de Coordiancion] S - -
S
[Correo THESCA-PRES- O
1.1 [J. Beingolea] R FASE 0 Incio Wed 2/09/22 Thu 2/10/22 2 100% 2
GEREN-RRHH]
[Correo Thesca-
1.2 [J. Beingolea] REQ Fase 0 , MOF,ROF… Fri 2/11/22 Mon 2/28/22 18 100% 14
Gerencia]
[Deadline de acuerdo a
1.3 [J. Beingolea] Deadline MOF ROF Tue 2/08/22 Fri 2/11/22 4 100% 4
Thesca]

1.4 Correo- THESCA-RRHH] [J. Beingolea] Cronograma Fase 1 Tue 2/01/22 Fri 2/04/22 4 100% 4

Correo- THESCA-
1.4.1 [J. Beingolea] Reiteracion MOF ROF mie 02/18/22 mie 02/18/22 1 100% 1
RRHH]
Correo[THESCA_RRH
1.4.2 [J. Beingolea] Req. Listado Colaboradores mie 2/23/22 mie 2/23/22 1 100% 1
H]
Indica dealine 23-02, pero de
1.5 Correo[THESCA-RRHH] [J. Beingolea] entrega de colaboradores a Fri 2/25/22 Tue 3/01/22 5 100% 5
RRHH
Correo[THESCA-
1.6 [J. Beingolea] RQ. Plan estrategico Wed 2/09/22 Tue 2/15/22 7 100% 5
GEREN]
Nuevo RQ sobre personal
1.7 Correo[THESCA-RRHH] [J. Beingolea] estable (no considerado por Thu 2/10/22 Thu 2/10/22 1 100% 1
THESCA)
Thesca indica solo 24 CV, se
Correo[RRHH-CEO-
1.8 [J. Beingolea] observa 24 carpetas con 74 Fri 3/25/22 Fri 3/25/22 1 100% 1
CHOSICA]
CVs dentro de ellas.

Indica al Administrador de
1.9 Correo[RRHH-CEO_] [J. Beingolea] Wed 4/06/22 Wed 4/06/22 1 100% 1
Chosica prog. Entrevistas

Indica al Administrador de
2 Correo[THESCA-RRHH] [J. Beingolea] Wed 4/06/22 Wed 4/06/22 1 100% 1
Santa Maria prog. Entrevistas

2.1 Correo[THESCA-RRHH] [J. Beingolea] Publicacion DRIVE de carga Mon 3/07/22 Mon 3/07/22 1 100% 1

3 [Supervisor Tecnico Ing. Meza] - -


Correo[SUPERV-
3.1 [J. Cesar Meza] Resp. RQ a THESCA Thu 3/03/22 Thu 3/03/22 1 100% 1
GEREN]