Professional Documents
Culture Documents
541 Series 2 Montando Hélice - 083050
541 Series 2 Montando Hélice - 083050
Welcome: u060ah1
Product: TRACK FELLER BUNCHER
Model: 541 2 TRACK FELLER BUNCHER F7D
Configuration: 541 Series 2 Track Feller Buncher F7D00001-UP (MACHINE)
POWERED BY C9 Engine
i04324111
Assembly Procedure
Table 1
Required Tools
D - Loctite 620 1
E 1P-0520 Driver Gp 1
Illustration 1 g01023039
Illustration 3 g01023033
Illustration 4 g01023027
4. Install bolts (43) into shaft assembly (42) before the shaft is installed into the bearing
carrier.
Illustration 5 g01022809
5. Position the square portion of shaft assembly (42) into a vise, as shown. Install bearing
carrier (9) onto shaft assembly (42).
Illustration 6 g01023025
6. Install spacer (41) and shim (40) into the bearing carrier.
Illustration 7 g01023006
8. Apply clean oil to the threads of nut (38). Install lock (37) and install nut (38). Tighten nut
(38) to a torque of 272 N·m (200 lb ft).
Illustration 9 g01023118
9. Check the bearing end play by using Tooling (F), as shown. Rotate the bearing carrier for
several turns in order to seat the bearing. Rotate the bearing carrier and pull upward on the
bearing carrier in order to check the end play of the bearing. The bearing end play should be
0.0254 mm (.00100 inch) to 0.08 mm (.003 inch). Add or subtract shims, if necessary.
10. Check the torque of nut (38) once the proper bearing end play is achieved. Bend the tab of
lock (37) into slot of nut (38) after the proper torque is applied to nut (38).
Illustration 10 g01023121
11. Apply Tooling (D) to the threads of hexagonal through shaft (35). Install hexagonal through
shaft (35) into the main shaft assembly, as shown.
Illustration 11 g01023000
12. Install hexagonal rod shaft (27) into the hexagonal through shaft (35), as shown. Tighten the
hexagonal rod shaft (27) to 34 N·m (25 lb ft). Install O-ring seal (36).
Illustration 12 g01022995
13. Install flange (33) onto bearing carrier (9) by using bolts (34).
Illustration 13 g01016265
15. Remove the bearing carrier and shaft assembly from the vise. Place the bearing carrier on a
flat surface. Install one O-ring seal (28) and two backup rings (29) onto piston (30). Install
the seal (not shown) into the inside of piston (30).
Illustration 15 g01016257
16. Apply Tooling (D) to the threads of nut (26). Install nut (26) onto hexagonal rod shaft (27).
Tighten nut (26) to a torque of 34 N·m (25 lb ft).
Illustration 16 g01016254
17. Install O-ring seal (24) and backup ring (25) onto the plug.
Illustration 17 g01016252
18. Install plug (23). Use Tooling (C) in order to install retaining ring (22).
Illustration 18 g01016199
19. Install through bearing (20). Install any shims (21). Install bolt (19). Tighten bolt (19) to a
torque of 68 N·m (50 lb ft).
Illustration 19 g01016197
21. Install race (16) and bearing (17) onto shaft (15).
Illustration 21 g01016192
Illustration 22 g01016188
Illustration 24 g01016183
Illustration 25 g01016179
27. Install locking tab (5) and install nut (6) by using Tooling (A). Tighten the nut to a torque of
34 N·m (25 lb ft). Bend up a tab in the lock into the slot in nut (6) after the proper torque is
achieved.
Illustration 27 g01016173
Illustration 28 g01016170
31. Fill the fan with clean oil. Refer to Operation and Maintenance Manual, "Refill Capacities
(Flexxaire Fan)".
End By:
Copyright 1993 - 2020 Caterpillar Inc. Tue Jan 21 2020 23:21:32 GMT-0300 (Hora oficial do Brasil)
All Rights Reserved.
u060ah1
Private Network For SIS Licensees.