Professional Documents
Culture Documents
13 Environmental Impact Assessment: 13.1.1 Purpose of This Document
13 Environmental Impact Assessment: 13.1.1 Purpose of This Document
doc 101
CHAPTER
13
Environmental Impact
Assessment
13.1 Introduction
The KTI Project would implement a series of modifications and additions focused on three
objectives:
Produce lube oil containing less than 15 parts per million (ppm) sulfur.
Allow the Refinery to efficiently use a broader array of used oil as feedstock.
Improve Refinery efficiency and increase crude throughput capacity. As a result of
this change, gasoline production levels would be maintained at current levels and
there would be an increase in lube oil production.
The KTI Project components would consume 194 gallons per minute of freshwater for
cooling tower service in the new hydrotreater, and would increase Refinery wastewater flows
685248382.doc 102
to the water treatment plant by 60 gallons per minute. As a part of the Project, we propose
concurrent reductions in fresh water use at the Refinery (a reduction of 200 gallons per
minute). The result would be no net increase in freshwater consumption or wastewater flow.
Electrical power consumption at the Refinery would approximately increase by 5.5
megawatt (MW); the additional power would be generated in the facility’s on-site
cogeneration plant. Normal operations would produce small quantities of hazardous waste
(selenium cake, copper cake and oily contaminated material). In addition, relatively small
amounts (40 cubic yards) of hazardous waste will be created during periodic maintenance
turnarounds.
The incremental used oil that would be processed at the Refinery as a result of the
proposed facilities would generally be imported and transported to the Refinery by an
existing pipeline. The Project would involve very small increases in vehicle, rail, and barge
traffic. The Project would create one additional full-time position (4 to 5 employees) at the
Refinery.
measures that are included as a part of the proposed project have been extracted from the
analyses and evaluations presented. To assist readers with a brief overview of the results of
the analysis contained in this document, Section 13.2.2 presents summary statements of
impacts from each environmental area of study. Each summary statement is a formal
statement of impact and proposed mitigation as well as level of significance before and after
mitigations is applied.
13.2.2.d Energy
The Project, as proposed, would not encourage activities that result in the use of large
amounts of fuel or energy, nor would it use fuel or energy in a wasteful or inefficient manner.
The overall impact of the proposed Project on energy resources would be less than
significant. The net increase in electrical energy would be approximately 5.5 MW. This
power would be supplied from the onsite cogeneration Project.
685248382.doc 104
In addition, the additional heat input for these processes would typically be provided
by refinery gas, but under some supply or market conditions, natural gas would be used to
supplement the use of refinery gas at these facilities.
13.2.2.j Noise
The Project would impact the ambient noise environment during both the construction
and operational phases of the Project. Since the Project would be located on refinery
property, Project-related noise impacts would primarily be to offsite residential receptors.
Noise during construction of the proposed Project would temporarily increase the ambient
noise levels at the residential receptors to levels above those specified in the Pak EPA
standards. This impact would be mitigated to a less than significant level with the
incorporation of the proposed mitigation measures.
13.2.2.l Transportation
The construction phase of the Project during the major turnaround (which includes both
the turnaround and the Project construction traffic) at the Refinery would generate additional
daily and peak hour trips.
The proposed construction phase of the Project would result in a potentially
significant impact to the a.m. peak hour operations during peak Project construction.
Operation of the Project would add up to four to five new employees, generating up to
two new a.m. peak hour trips, and two p.m. peak hour trips. The project will increase
operational truck traffic for coke, sulfur and waste trucking.
685248382.doc 106
13.2.2.n Agriculture
The Project is located entirely within the developed area of the Refinery. There are no
agricultural resources on or in the vicinity of the project site. All construction and operation
activities would take place in the already developed portions of refinery property. Thus, the
Project’s impact on agricultural land use would be less than significant. The project would
have no impact. No mitigation measures are required.
implementing the full Project, which is construction and operation of each and every
component described as part of the project. In nearly all cases, the analysis of the full project
reveals the greatest or worst-case impacts that could occur under any combination of
components and leads to the mitigations that would be necessary to reduce those worst-case
impacts to less than significant.
In a few instances, however, the worst-case impact for a given environmental issue
might not occur under the full Project, but would occur as a result of one of the project
variables. Thus the impact analysis in this EIR also considers the possible effects of the
project “variables”—Design, Location, Schedule and Certainty—in the Project as
proposed, on environmental impacts. If any aspect of these four variables would result in a
substantive difference in the environmental impact of the Project or in the mitigation that
might be applied, those aspects are discussed and the individual effects are traced. If these
variables would not result in an increase in impact or require a material change in mitigation,
they may not be discussed.
In the event that specific operational considerations, dimensions of the components,
equipment locations, and variations in the timing of construction or the absence of any
project component were critical to identifying or mitigating a potential environmental impact
of the project, these considerations are discussed under the related impact or mitigation
presentations in this section.
These processes are to be used when metallic impurities in the waste oil are in
appreciable amount. In these processes the by-products metallic phosphates and
sulphates are formed which have very adverse effects on the environment. So that’s
why it is preferable to use KTI Process.