You are on page 1of 8

Construction Clinic 23

Concurrent Delay
Presented by
Paul Gibbons
CONCURRENT DELAY

“A Period of project overrun which is caused by two or more effective causes of delay
which are of approximately equal causative potency”

Concurrent Delay by John Marrin QC (2002), 18 Const LJ No. 6 436.

• True concurrency rare.

• However opposing expert will nearly always raise alternative causes of delay to negate
and cast doubt over the EOT / L&E entitlement.

• Complicated by the SCL Protocol providing two alternative views on concurrency (see
para 10.7 to 10.10).
THE ORTHODOX APPROACH TO CONCURRENCY

• Malmaison, etc:

Two concurrent delays 1 week EOT due to


Relevant Event – Exceptionally the Contractor (5
5 working day
Inclement Weather concurrent
working days)
Contractor Delay – Shortage of Labour delay
THE ALTERNATIVE (NEW) APPROACH

• Royal Brompton, Adyard, Jerram Falkus, Saga Cruises:

Contractor Delay – Contractor


10 day
Shortage of Labour contractor delay
Culpable
causing 10 days delay delay
THE ALTERNATIVE (NEW) APPROACH
Relevant Event– No Concurrent delay –
Variation to Steelwork The completion date is
• Royal Brompton, Adyard, Jerram Falkus, Saga Cruises: occurs slightly later but not delayed any further
equally delaying than already delayed

10 day delay remains

Relevant Event– Concurrent delay – The


Variation to Steelwork completion date is
10 day
extends beyond the delayed further than that contractor
Contractor Delay already delayed delay
5 day employer delay
CONCURRENT DELAY - SUMMARY

• Delaying act must affect the critical path.

• Delaying act must cause actual delay to the progress of the works.

• Delaying act must prevent contractor from achieving an earlier completion date. If
earlier completion date would not have been met (due to contractor delay), then no
concurrency exists.

• First event problem – Will new approach prevent parties from raising issues, whilst awaiting
the other side’s delay to materialise?

• Concurrency argument often won on the factual evidence rather than from the delay analysis
itself.

• Pragmatic Approach is required


QUESTIONS

QUESTIONS?
CONTACT DETAILS

TELL ME MORE

To learn more about the ICCP please visit:


www.instituteccp.com.

For general enquiries please contact Nina


Hewitt-Tyrrell: nina.hewitt@instituteccp.com.

For membership specific enquiries please


contact: membership@instituteccp.com.

You might also like