Professional Documents
Culture Documents
CC-23-presentation-Concurrent Delay
CC-23-presentation-Concurrent Delay
Concurrent Delay
Presented by
Paul Gibbons
CONCURRENT DELAY
“A Period of project overrun which is caused by two or more effective causes of delay
which are of approximately equal causative potency”
• However opposing expert will nearly always raise alternative causes of delay to negate
and cast doubt over the EOT / L&E entitlement.
• Complicated by the SCL Protocol providing two alternative views on concurrency (see
para 10.7 to 10.10).
THE ORTHODOX APPROACH TO CONCURRENCY
• Malmaison, etc:
• Delaying act must cause actual delay to the progress of the works.
• Delaying act must prevent contractor from achieving an earlier completion date. If
earlier completion date would not have been met (due to contractor delay), then no
concurrency exists.
• First event problem – Will new approach prevent parties from raising issues, whilst awaiting
the other side’s delay to materialise?
• Concurrency argument often won on the factual evidence rather than from the delay analysis
itself.
QUESTIONS?
CONTACT DETAILS
TELL ME MORE