MIL-HDBK-353

7.5 SOPs

7.5.1 SOP Submission. The A-E shall provide the contracting


officer a draft of the SOPs at 50 percent construction completion
and the final draft of the SOPs 30 days prior to construction
completion. At the end of the performance period, the A-E shall
also provide a site-tested, final SOP for each major component of
the treatment plant.

7.5.2 Processes Requiring SOPs. The SOPs are part of the


system O&M manuals (par. 4.8.2) and may require revision to
reflect actual operating experience. SOPs shall be prepared for
all processes including, but not limited to, those listed below:

a) Pumping stations

b) Screening removal and disposal

c) Grit removal

d) Primary treatment

e) Biological treatment

f) Advanced treatment

g) Sludge handling system

h) Tank drainage system

i) Fuel storage and distribution system

j) Potable water system

k) Plant water system

l) Power distribution system

m) Standby power system

7.5.3 Elements of SOPs. Each SOP shall contain, at a


minimum, the following elements: