PROCEEDINGS OF THE CHIEF EXECUTIVE OFFICER, KERALA
INFRASTRUCTURE INVESTMENT FUND BOARD, THIRUVANANTHAPURAM
(Present: Dr.K.M.Abraham, CFA)
ORDER NO: CPE/2421/2018/KIIFB dated 15/11/2019
Sub: Deviations and variations in contract agreements of KIIFB projects- Clarification- reg
Ref: 1) G. O. (Ms) No.69/2018/Fin Dated 24/02/2018
2) Order No. CPE/2421/2018/KIIFB Dated 29/10/2018
ORDER
KIIFB has accorded approval for various projects to be executed through several
Special Purpose Vehicles (SPVs) and most of those have either started or in the tendering
stages, Based on the initial scrutiny and inspections carried out on the progressing projects, it
has been observed that, in some of the cases deviations and variations in the items of work are
likely to occur. Accordingly KIIFB has examined the issue in detail and already formulated a
process for dealing with such deviations and variations vide order No. CPE/2421/2018/KIFB
dated 29.10.2018.
In continuation to the directions and procedures contained in the above order for processing
of variations / deviations in the work, following clarifications are issued herewith to remove
the ambiguity in interpreting the procedures stipulated in the above mentioned order by SPVs
while submitting deviation / RE proposals:
1. Terminology " Variation" refers to change in quantities on BOQ items with or without
extra/substituted items but without upward change in PAC
Terminology “Deviation” refers to change in quantities on BOQ items with or without
cextra/substituted items but with upward change in PAC
3. Variation: The SPVs need not to wait for the approval from KIIFB, if there is no change
in scope of work and upward change in PAC, and may continue the work after
intimation to KIIFB through PMS as per the latest guidelines issued by KIIFB. With the
concurrence of variations by TS authority, payment can be released to the contractor for
all deviated quantities & extra/substituted items as per the terms and conditions of contract.
However, this shall be subject to the examination by Inspection Authority to
avoid deliberate attempt on non-execution of low rate quoted items, execution of abnormalquantity in high rate quoted items, variation/deviation in original items without any
technical requirement at site ete,
Deviation: In the scenario of any change in scope of work and upward change in PAC,
SPV shall submit the deviation proposal with the concurrence of Technical Sanction
Authority to KIIFB. After getting an in - principle approval from KIIFB, SPV may enter
into Supplementary Agreement with contractor, if required as per contract conditions. The
deviated quantities and extra/substituted items of work shall be paid to the contractor after
executing supplementary agreement, if required, as per contract conditions.
. SPV shall submit the final revised estimate / deviation proposal against the in-principle
approval for the revised financial sanction of KIIFB strietly following the technical
serutiny note issued as per the in- principle approval. Based on this formal approval
for final revised estimate shall be issued in due course subject to the fulfilment of all
, procedural and contractual requirements.
Dr. K. M. Abraham CFA
Chief Executive Officer
‘The ACS/Principal Secretary/ Secretary
All department Heads of SPVs
‘The Chief Project Examiner, Inspection Authority, KIFB
Additional Secretary, Inspection Authority
Joint Fund Manager, KIIFB
‘The General Manager (Project Appraisal), KIIFB
‘The stock file’ Office copy.
Nave eNe
Forwarded/ By Order
at
Senior Project Examiner