LOC-PT Cronograma Valorizado
LOC-PT Cronograma Valorizado
PROYECTO INSTALACION DEL SERVICIO DE TRATAMIENTO DE AGUAS RESIDUALES EN LOCUMBA CAPITAL, DISTRITO DE LOCUMBA, PROVINCIA DE JORGE BASADRE - TACNA
PROPIETARIO MUNICIPALIDAD PROVINCIAL DE JORGE BASADRE
UBICACION DPTO:TACNA PROV:JORGE BASADRE DIST:LOCUMBA LOC:LOCUMBA
FECHA NOVIEMBRE 2020
Item Descripción Unid. Cant. Precio Parcial Sub Total MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08
1.4.2 TRANSPORTE DE MATERIALES A LA OBRA und 1.00 S/ 50,000.00 S/ 50,000.00 S/ 7,500.00 S/ 7,500.00 S/ 5,000.00 S/ 5,000.00 S/ 5,000.00 S/ 5,000.00 S/ 7,500.00 S/ 7,500.00
2 LINEA EMISOR S/ 1,896,821.30
2.1 TRABAJOS PRELIMINARES S/ 48,134.84
2.1.1 DESBROCE Y LIMPIEZA DEL TERRENO (FRANJA DE 2.50 M) m 5,035.00 S/ 4.59 S/ 23,110.65 S/ 23,110.65
2.1.2 CONTROL TOPOGRAFICO EN OBRA m 5,035.00 S/ 3.52 S/ 17,723.20 S/ 4,430.80 S/ 4,430.80 S/ 4,430.80 S/ 4,430.80
2.1.3 REPLANTEO FINAL DE LA OBRA, PARA LÍNEAS REDES CON ESTACIÓN TOTAL km 5.04 S/ 1,448.61 S/ 7,300.99 S/ 1,825.25 S/ 1,825.25 S/ 1,825.25 S/ 1,825.25
2.5.4 BUZON DE INSPECCION:TARRAJEO CON ADITIVO IMPERMEABILIZANTE m² 380.00 S/ 40.99 S/ 15,576.20 S/ 7,788.10 S/ 7,788.10
2.5.5 EMPALME A BUZON EXISTENTE und 56.00 S/ 170.41 S/ 9,542.96 S/ 4,771.48 S/ 4,771.48
2.5.6 MESON DE CONCRETO: ACERO DE REFUERZO FY = 4200 KG/CM2 kg 785.19 S/ 5.10 S/ 4,004.47 S/ 2,002.24 S/ 2,002.24
2.6 PRUEBAS S/ 9,279.00
2.6.1 PRUEBA COMPACT. DE SUELOS (PROCTOR MODIFICADO. DENSIDAD DE und 50.00 S/ 185.58 S/ 9,279.00 S/ 4,639.50 S/ 4,639.50
CAMPO)
3 PLANTA DE TRATAMIENTO DE AGUAS RESIDUALES S/ 2,926,441.90
3.1 DEMOLICIONES S/ 20,959.92
3.1.1 DEMOLICION DE CAMARA DE REJAS Y DISTRIBUIDOR DE CAUDALES m³ 14.40 S/ 42.04 S/ 605.38 S/ 605.38
3.1.2 DEMOLICION DE BIODIGESTORES und 5.00 S/ 378.35 S/ 1,891.75 S/ 1,891.75
3.1.3 DEMOLICION DE CAMARA DE LODOS m³ 18.75 S/ 42.04 S/ 788.25 S/ 788.25
3.1.4 DEMOLICION DE LAGUNA SECUNDARIA m³ 225.00 S/ 42.04 S/ 9,459.00 S/ 9,459.00
3.1.5 ACARREO DE MATERIAL EXCEDENTE A UNA DISTANCIA PROMEDIO DE 30 M m³ 263.15 S/ 12.80 S/ 3,368.32 S/ 3,368.32
3.1.6 CARGUIO E ELIMINACION DE MATERIAL EXCEDENTE DM<06 km m³ 263.15 S/ 18.42 S/ 4,847.22 S/ 4,847.22
3.2 CAMARA DE REJAS, DESARENADOR Y TRAMPA DE GRASAS S/ 25,558.81
3.2.1 TRABAJOS PRELIMINARES S/ 187.32
3.2.1.1 LIMPIEZA DE TERRENO MANUAL m² 31.64 S/ 3.44 S/ 108.84 S/ 108.84
3.2.1.2 TRAZO, NIVELACIÓN Y REPLANTEO PRELIMINAR m² 23.64 S/ 3.32 S/ 78.48 S/ 78.48
3.2.2 MOVIMIENTO DE TIERRAS S/ 13,061.25
3.2.2.1 EXCAVACION MASIVA EN TERRENO NORMAL C/MAQUINARIA m³ 4.45 S/ 6.81 S/ 30.30 S/ 15.15 S/ 15.15
3.2.2.2 PERFILADO Y NIVELACION m² 3.16 S/ 10.64 S/ 33.62 S/ 16.81 S/ 16.81
3.2.2.3 RELLENO ESTRUCTURAL CON MATERIAL PROPIO m³ 47.13 S/ 273.90 S/ 12,908.91 S/ 6,454.46 S/ 6,454.46
3.2.2.4 CARGUIO E ELIMINACION DE MATERIAL EXCEDENTE DM<06 km m³ 4.80 S/ 18.42 S/ 88.42 S/ 44.21 S/ 44.21
3.2.3 OBRAS DE CONCRETO SIMPLE S/ 1,033.61
3.2.3.1 SOLADOS DE E=4" MEZCLA 1:10 (C:H) m² 20.50 S/ 50.42 S/ 1,033.61 S/ 516.81 S/ 516.81
3.2.4 OBRAS DE CONCRETO ARMADO S/ 8,775.97
3.2.4.1 CERCO PERIMETRICO: ENCOFRADO Y DESENCOFRADO NORMAL m² 19.72 S/ 72.46 S/ 1,428.91 S/ 714.46 S/ 714.46
3.2.4.2 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 380.87 S/ 5.10 S/ 1,942.44 S/ 971.22 S/ 971.22
3.2.4.3 CONCRETO F'C=280 KG/CM2 C:A:P C/MEZCLADORA (CEMENTO PI) m³ 11.32 S/ 477.44 S/ 5,404.62 S/ 2,702.31 S/ 2,702.31
3.2.5 REVOQUES Y ENLUCIDOS S/ 2,500.66
3.2.5.1 TARRAJEO DE MUROS INTERIORES,E=1.50CM C:A 1:5 m² 17.84 S/ 23.16 S/ 413.17 S/ 206.59 S/ 206.59
3.2.5.2 TARRAJEO DE MUROS EXTERIORES,E=1.50CM C:A 1:5 m² 29.59 S/ 26.25 S/ 776.74 S/ 388.37 S/ 388.37
3.2.5.3 TARRAJEO CON IMPERMEABILIZANTE DE LOSA DE FONDO, PISO, CANALES m² 27.41 S/ 47.82 S/ 1,310.75 S/ 655.38 S/ 655.38
3.4.1.5 CARGUIO E ELIMINACION DE MATERIAL EXCEDENTE DM<06 km m³ 185.06 S/ 18.42 S/ 3,408.81 S/ 1,704.41 S/ 1,704.41
3.4.2 OBRAS DE CONCRETO SIMPLE S/ 3,030.88
3.4.2.1 CONCRETO CICLOPEO F'C=140 KG/CM2 + 30% DE P.G. P/CIMENTACION m³ 8.20 S/ 369.62 S/ 3,030.88 S/ 1,515.44 S/ 1,515.44
3.4.3 OBRAS DE CONCRETO ARMADO S/ 243,618.51
3.4.3.1 ZAPATAS S/ 62,385.15
3.4.3.1.1 CONCRETO F'C=280 KG/CM2 C:A:P C/MEZCLADORA (CEMENTO PI) m³ 46.52 S/ 477.44 S/ 22,210.51 S/ 11,105.26 S/ 11,105.26
3.4.3.1.2 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 7,877.38 S/ 5.10 S/ 40,174.64 S/ 20,087.32 S/ 20,087.32
3.4.3.2 LOSA DE FONDO S/ 70,189.69
3.4.3.2.1 CONCRETO F'C=280 KG/CM2 C:A:P C/MEZCLADORA (CEMENTO PI) m³ 22.21 S/ 477.44 S/ 10,603.94 S/ 5,301.97 S/ 5,301.97
3.4.3.2.2 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 11,683.48 S/ 5.10 S/ 59,585.75 S/ 29,792.88 S/ 29,792.88
CRONOGRAMA VALORIZADO DE OBRA
PROYECTO INSTALACION DEL SERVICIO DE TRATAMIENTO DE AGUAS RESIDUALES EN LOCUMBA CAPITAL, DISTRITO DE LOCUMBA, PROVINCIA DE JORGE BASADRE - TACNA
PROPIETARIO MUNICIPALIDAD PROVINCIAL DE JORGE BASADRE
UBICACION DPTO:TACNA PROV:JORGE BASADRE DIST:LOCUMBA LOC:LOCUMBA
FECHA NOVIEMBRE 2020
Item Descripción Unid. Cant. Precio Parcial Sub Total MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08
3.9.2.5 CARGUIO E ELIMINACION DE MATERIAL EXCEDENTE DM<06 km m³ 87.14 S/ 18.42 S/ 1,605.12 S/ 802.56 S/ 802.56
3.9.2.6 NIVELACION INTERIOR Y APISONADO m² 134.21 S/ 4.63 S/ 621.39 S/ 310.70 S/ 310.70
3.9.2.7 MATERIAL AFIRMADO DE E= 0.10m m² 133.87 S/ 12.24 S/ 1,638.57 S/ 819.29 S/ 819.29
3.9.3 OBRAS DE CONCRETO SIMPLE S/ 23,181.73
3.9.3.1 SOLADOS DE E=4" MEZCLA 1:10 (C:H) m² 30.58 S/ 50.42 S/ 1,541.84 S/ 770.92 S/ 770.92
3.9.3.2 CONCRETO CICLOPEO F'C=140 KG/CM2 + 30% DE P.G. P/CIMENTACION m³ 34.66 S/ 369.62 S/ 12,811.03 S/ 6,405.52 S/ 6,405.52
3.9.3.3 CONCRETO F'C = 175 KG/CM2 m³ 3.02 S/ 463.28 S/ 1,399.11 S/ 699.56 S/ 699.56
3.9.3.4 ENCOFRADO Y DESENCOFRADO NORMAL m² 32.22 S/ 72.46 S/ 2,334.66 S/ 1,167.33 S/ 1,167.33
3.9.3.5 FALSO PISO DE 4" DE CONCRETO MEZCLA 1:12 C:A m² 133.87 S/ 38.06 S/ 5,095.09 S/ 2,547.55 S/ 2,547.55
3.9.4 OBRAS DE CONCRETO ARMADO S/ 101,256.23
3.9.4.1 ZAPATAS: CONCRETO F'C=210 KG/CM2 m³ 12.23 S/ 298.60 S/ 3,651.88 S/ 1,825.94 S/ 1,825.94
3.9.4.2 ZAPATAS: ACERO F'Y=4200 KG/CM2 kg 456.76 S/ 5.10 S/ 2,329.48 S/ 1,164.74 S/ 1,164.74
3.9.4.3 CONCRETO F'C = 175 KG/CM2 m³ 9.90 S/ 463.28 S/ 4,586.47 S/ 2,293.24 S/ 2,293.24
3.9.4.4 SOBRECIMIENTO: ENCOFRADO Y DESENCOFRADO NORMAL m² 79.22 S/ 72.46 S/ 5,740.28 S/ 2,870.14 S/ 2,870.14
3.9.4.5 SOBRECIMIENTO ARMADO: ACERO F'Y=4200 KG/CM2 kg 1,292.88 S/ 5.10 S/ 6,593.69 S/ 3,296.85 S/ 3,296.85
3.9.4.6 COLUMNA: CONCRETO F'C=210 KG/CM2 m³ 10.41 S/ 564.70 S/ 5,878.53 S/ 2,939.27 S/ 2,939.27
3.9.4.7 ENCOFRADO Y DESENCOFRADO NORMAL m² 155.26 S/ 72.46 S/ 11,250.14 S/ 5,625.07 S/ 5,625.07
3.9.4.8 COLUMNA: ACERO F'Y=4200 KG/CM2 kg 2,091.08 S/ 5.10 S/ 10,664.51 S/ 5,332.26 S/ 5,332.26
3.9.4.9 VIGA: CONCRETO F'C=210 KG/CM2 m³ 12.49 S/ 451.80 S/ 5,642.98 S/ 2,821.49 S/ 2,821.49
3.9.4.10 VIGA: ENCOFRADO Y DESENCOFRADO NORMAL m² 89.34 S/ 72.46 S/ 6,473.58 S/ 3,236.79 S/ 3,236.79
3.9.4.11 VIGA:ACERO DE REFUERZO FY = 4200 KG/CM2 kg 2,115.85 S/ 5.10 S/ 10,790.84 S/ 5,395.42 S/ 5,395.42
CRONOGRAMA VALORIZADO DE OBRA
PROYECTO INSTALACION DEL SERVICIO DE TRATAMIENTO DE AGUAS RESIDUALES EN LOCUMBA CAPITAL, DISTRITO DE LOCUMBA, PROVINCIA DE JORGE BASADRE - TACNA
PROPIETARIO MUNICIPALIDAD PROVINCIAL DE JORGE BASADRE
UBICACION DPTO:TACNA PROV:JORGE BASADRE DIST:LOCUMBA LOC:LOCUMBA
FECHA NOVIEMBRE 2020
Item Descripción Unid. Cant. Precio Parcial Sub Total MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08
3.9.4.12 LOSA ALIGERADA: CONCRETO F'C=210 KG/CM2 m³ 12.43 S/ 451.80 S/ 5,615.87 S/ 2,807.94 S/ 2,807.94
3.9.4.13 LOSA ALIGERADA: ENCOFRADO Y DESENCOFRADO NORMAL m² 141.96 S/ 72.46 S/ 10,286.42 S/ 5,143.21 S/ 5,143.21
3.9.4.14 LOSA ALIGERADA: ACERO DE REFUERZO FY = 4200 KG/CM2 kg 966.87 S/ 5.10 S/ 4,931.04 S/ 2,465.52 S/ 2,465.52
3.9.4.15 LOSA ALIGERADA: LADRILLO HUECO DE ARCILLA DE 15X30X30 CM. und 1,183.00 S/ 3.76 S/ 4,448.08 S/ 2,224.04 S/ 2,224.04
3.9.4.16 MESON DE CONCRETO: CONCRETO F'C=175 KG/CM2 m³ 0.89 S/ 278.40 S/ 247.78 S/ 123.89 S/ 123.89
3.9.4.17 MESON DE CONCRETO: ENCOFRADO Y DESENCOFRADO NORMAL m² 13.64 S/ 72.46 S/ 988.35 S/ 494.18 S/ 494.18
3.9.4.18 MESON DE CONCRETO: ACERO DE REFUERZO FY = 4200 KG/CM2 kg 63.48 S/ 5.10 S/ 323.75 S/ 161.88 S/ 161.88
3.9.4.19 CURADO EN ESTRUCTURAS HORIZONTALES m² 176.93 S/ 2.09 S/ 369.78 S/ 184.89 S/ 184.89
3.9.4.20 CURADO EN ESTRUCTURAS VERTICALES m² 207.88 S/ 2.13 S/ 442.78 S/ 221.39 S/ 221.39
3.9.5 ALBAÑILERIA S/ 17,476.45
3.9.5.1 MURO DE LADRILLO DE SOGA C/MEZCLA 1:5 C/LADRILLO HERCULES I m² 99.56 S/ 81.76 S/ 8,140.03 S/ 4,070.02 S/ 4,070.02
3.9.5.2 MURO DE LADRILLO DE CABEZA C/MEZCLA 1:5 C/LADRILLO HERCULES I m² 72.00 S/ 127.26 S/ 9,162.72 S/ 4,581.36 S/ 4,581.36
3.9.5.3 ALAMBRE # 8 REFUERZO HORIZONTAL EN MUROS kg 42.89 S/ 4.05 S/ 173.70 S/ 86.85 S/ 86.85
3.9.6 REVOQUES Y ENLUCIDOS S/ 24,802.19
3.9.6.1 TARRAJEO PRIMARIO RAYADO CON CEMENTO - ARENA m² 51.83 S/ 23.21 S/ 1,202.97 S/ 601.49 S/ 601.49
3.9.6.2 TARRAJEO EN MUROS INTERIORES Y EXTERIORES MEZCLA 1:5 C:A m² 331.12 S/ 23.40 S/ 7,748.21 S/ 3,874.11 S/ 3,874.11
3.9.6.3 TARRAJEO DE COLUMNAS MEZCLA 1:5 C:A m² 125.94 S/ 32.16 S/ 4,050.23 S/ 2,025.12 S/ 2,025.12
3.9.6.4 TARRAJEO DE VIGAS MEZCLA 1:5 C:A m² 83.96 S/ 35.41 S/ 2,973.02 S/ 1,486.51 S/ 1,486.51
3.9.6.5 TARRAJEO DE CIELO RASO MEZCLA 1:5 C:A m² 141.96 S/ 48.72 S/ 6,916.29 S/ 3,458.15 S/ 3,458.15
3.9.6.6 VESTIDURA DE DERRAMES EN VANOS DE PUERTAS Y VENTANAS C/MEZCLA m 123.40 S/ 15.49 S/ 1,911.47 S/ 955.74 S/ 955.74
1:5 E=1.5 CM
3.9.7 PISOS S/ 6,127.65
3.9.7.1 PISOS DE CEMENTO PULIDO Y BRUÑADO m² 38.28 S/ 33.57 S/ 1,285.06 S/ 642.53 S/ 642.53
3.9.7.2 PISO CERAMICO ANTIDESLIZANTE DE ALTO TRANSITO 40 X 40 CM m² 95.59 S/ 50.66 S/ 4,842.59 S/ 2,421.30 S/ 2,421.30
3.9.8 ZOCALOS S/ 3,822.46
3.9.8.1 ZOCALO DE CERAMICO 20 X 30 CM m² 51.83 S/ 73.75 S/ 3,822.46 S/ 1,911.23 S/ 1,911.23
3.9.9 CONTRAZOCALOS S/ 6,575.41
3.9.9.1 CONTRAZOCALO DE CERAMICO h=0.10 m m 70.24 S/ 15.36 S/ 1,078.89 S/ 539.45 S/ 539.45
3.9.9.2 CONTRAZOCALO DE CEMENTO PULIDO h=0.10 m m 20.50 S/ 13.54 S/ 277.57 S/ 138.79 S/ 138.79
3.9.9.3 CONTRAZOCALO DE PIEDRA LAJA DE COLOR H=0.40M m 70.10 S/ 74.45 S/ 5,218.95 S/ 2,609.48 S/ 2,609.48
3.9.10 COBERTURAS S/ 11,195.71
3.9.10.1 IMPERMEABILIZACION DE COBERTURA DE LADRILLO PASTELERO m² 151.13 S/ 3.32 S/ 501.75 S/ 250.88 S/ 250.88
3.9.10.2 COBERTURA DE LADRILLO PASTELERO DE 20 x 20 x 3cm. CON TORTA DE m² 151.13 S/ 70.76 S/ 10,693.96 S/ 5,346.98 S/ 5,346.98
BARRO
3.9.11 CARPINTERIA DE MADERA S/ 15,091.40
3.9.11.1 PUERTA DE MADERA TIPO MACHIMBRADA SIMPLE m² 23.71 S/ 421.40 S/ 9,991.39 S/ 4,995.70 S/ 4,995.70
3.9.11.2 MARCO DE MADERA PARA VENTANAS (SEGÚN DETALLE) m 68.10 S/ 74.89 S/ 5,100.01 S/ 2,550.01 S/ 2,550.01
3.9.12 CERRAJERIA S/ 1,358.01
3.9.12.1 CERRADURA TIPO PARCHE 3 GOLPES und 6.00 S/ 125.78 S/ 754.68 S/ 377.34 S/ 377.34
3.9.12.2 CERRADURA PARA INTERIOR TIPO PERILLA und 3.00 S/ 62.23 S/ 186.69 S/ 93.35 S/ 93.35
3.9.12.3 BISAGRA ALUMINIZADA DE 4"x4''x3mm EN PUERTAS und 32.00 S/ 13.02 S/ 416.64 S/ 208.32 S/ 208.32
3.9.13 VIDRIOS S/ 2,318.12
3.9.13.1 VENTANAS TIPO SISTEMA INC. COLOCACION C/PERFILES DE ALUMINIO m² 22.38 S/ 103.58 S/ 2,318.12 S/ 1,159.06 S/ 1,159.06
3.9.14 PINTURAS S/ 10,287.10
3.9.14.1 PINTURA LATEX EN INTERIORES Y EXTERIORES m² 349.63 S/ 12.43 S/ 4,345.90 S/ 2,172.95 S/ 2,172.95
3.9.14.2 PINTURA LATEX EN COLUMNAS Y VIGAS m² 209.90 S/ 13.90 S/ 2,917.61 S/ 1,458.81 S/ 1,458.81
3.9.14.3 PINTURA LATEX EN CIELO RASO m² 141.96 S/ 13.90 S/ 1,973.24 S/ 986.62 S/ 986.62
3.9.14.4 PINTURA BARNIZ EN PUERTAS DE MADERA m² 47.42 S/ 22.15 S/ 1,050.35 S/ 525.18 S/ 525.18
3.9.15 OTROS S/ 71,202.52
3.9.15.1 JUNTA DE DILATACION CON ESPUMA PLASTICA + JEBE MICROPOROSO m 22.60 S/ 17.55 S/ 396.63 S/ 198.32 S/ 198.32
3.9.15.2 GARGOLA DE CONCRETO S/DETALLE und 6.00 S/ 199.44 S/ 1,196.64 S/ 598.32 S/ 598.32
3.9.15.3 LIMPIEZA FINAL DE OBRA m² 151.87 S/ 1.14 S/ 173.13 S/ 86.57 S/ 86.57
3.9.15.4 IMPLEMENTACION DE EQUIPAMIENTO DE ANALISIS DE AGUAS RESIDUALES und 1.00 S/ 69,436.12 S/ 69,436.12 S/ 34,718.06 S/ 34,718.06
3.9.18.6.1 SUMINISTRO E INSTALACION DE CAJAS DE PASO METALICAS 200X200X150 und 2.00 S/ 35.36 S/ 70.72 S/ 35.36 S/ 35.36
mm
3.9.18.6.2 SUMINISTRO E INSTALACION DE CAJAS DE PASO METALICAS 100X100X50 mm und 2.00 S/ 29.76 S/ 59.52 S/ 29.76 S/ 29.76
3.14.6.1 TANQUE ELEVADO und 1.00 S/ 734.34 S/ 734.34 S/ 183.59 S/ 183.59 S/ 183.59 S/ 183.59
3.14.6.2 TUBERIA GALVANIZADA 1 1/2" m 3.00 S/ 25.66 S/ 76.98 S/ 19.25 S/ 19.25 S/ 19.25 S/ 19.25
3.14.6.3 ESACLERA DE GATO und 1.00 S/ 300.00 S/ 300.00 S/ 75.00 S/ 75.00 S/ 75.00 S/ 75.00
3.14.7 CAMARA DE INGRESO TIPO A1 S/ 23,543.73 S/ - S/ - S/ - S/ -
3.14.7.1 TRAZO, NIVELACIÓN Y REPLANTEO PRELIMINAR m² 13.52 S/ 3.32 S/ 44.89 S/ 11.22 S/ 11.22 S/ 11.22 S/ 11.22
3.14.7.2 EXCAVACIÓN MANUAL EN TERRENO NORMAL m³ 9.46 S/ 55.07 S/ 520.96 S/ 130.24 S/ 130.24 S/ 130.24 S/ 130.24
3.14.7.3 SOLADOS DE E=4" MEZCLA 1:10 (C:H) m² 13.52 S/ 50.42 S/ 681.68 S/ 170.42 S/ 170.42 S/ 170.42 S/ 170.42
3.14.7.4 CONCRETO F'C = 175 KG/CM2 m³ 39.21 S/ 463.28 S/ 18,165.21 S/ 4,541.30 S/ 4,541.30 S/ 4,541.30 S/ 4,541.30
3.14.7.5 ENCOFRADO Y DESENCOFRADO NORMAL m² 13.44 S/ 72.46 S/ 973.86 S/ 243.47 S/ 243.47 S/ 243.47 S/ 243.47
3.14.7.6 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 553.60 S/ 5.10 S/ 2,823.36 S/ 705.84 S/ 705.84 S/ 705.84 S/ 705.84
3.14.7.7 TARRAJEO DE MUROS INTERIORES,E=1.50CM C:A 1:5 m² 6.16 S/ 23.16 S/ 142.67 S/ 35.67 S/ 35.67 S/ 35.67 S/ 35.67
3.14.7.8 TARRAJEO DE MUROS EXTERIORES,E=1.50CM C:A 1:5 m² 7.28 S/ 26.25 S/ 191.10 S/ 47.78 S/ 47.78 S/ 47.78 S/ 47.78
3.14.8 CAMARA DE INGRESO TIPO A2 S/ 1,882.35 S/ - S/ - S/ - S/ -
3.14.8.1 TRAZO, NIVELACIÓN Y REPLANTEO PRELIMINAR m² 1.28 S/ 3.32 S/ 4.25 S/ 1.06 S/ 1.06 S/ 1.06 S/ 1.06
3.14.8.2 EXCAVACIÓN MANUAL EN TERRENO NORMAL m³ 0.64 S/ 55.07 S/ 35.24 S/ 8.81 S/ 8.81 S/ 8.81 S/ 8.81
3.14.8.3 SOLADOS DE E=4" MEZCLA 1:10 (C:H) m² 1.28 S/ 50.42 S/ 64.54 S/ 16.14 S/ 16.14 S/ 16.14 S/ 16.14
3.14.8.4 CONCRETO F'C = 175 KG/CM2 m³ 2.69 S/ 463.28 S/ 1,246.22 S/ 311.56 S/ 311.56 S/ 311.56 S/ 311.56
3.14.8.5 ENCOFRADO Y DESENCOFRADO NORMAL m² 1.40 S/ 72.46 S/ 101.44 S/ 25.36 S/ 25.36 S/ 25.36 S/ 25.36
3.14.8.6 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 77.60 S/ 5.10 S/ 395.76 S/ 98.94 S/ 98.94 S/ 98.94 S/ 98.94
3.14.8.7 TARRAJEO DE MUROS INTERIORES,E=1.50CM C:A 1:5 m² 0.60 S/ 23.16 S/ 13.90 S/ 3.48 S/ 3.48 S/ 3.48 S/ 3.48
3.14.8.8 TARRAJEO DE MUROS EXTERIORES,E=1.50CM C:A 1:5 m² 0.80 S/ 26.25 S/ 21.00 S/ 5.25 S/ 5.25 S/ 5.25 S/ 5.25
3.14.9 CÁMARA DE REPARTO DE CAUDALES S/ 7,389.07 S/ - S/ - S/ - S/ -
3.14.9.1 TRAZO, NIVELACIÓN Y REPLANTEO PRELIMINAR m² 4.00 S/ 3.32 S/ 13.28 S/ 3.32 S/ 3.32 S/ 3.32 S/ 3.32
3.14.9.2 EXCAVACIÓN MANUAL EN TERRENO NORMAL m³ 2.80 S/ 55.07 S/ 154.20 S/ 38.55 S/ 38.55 S/ 38.55 S/ 38.55
3.14.9.3 SOLADOS DE E=4" MEZCLA 1:10 (C:H) m² 4.00 S/ 50.42 S/ 201.68 S/ 50.42 S/ 50.42 S/ 50.42 S/ 50.42
3.14.9.4 CONCRETO F'C = 175 KG/CM2 m³ 11.26 S/ 463.28 S/ 5,216.53 S/ 1,304.13 S/ 1,304.13 S/ 1,304.13 S/ 1,304.13
3.14.9.5 ENCOFRADO Y DESENCOFRADO NORMAL m² 5.04 S/ 72.46 S/ 365.20 S/ 91.30 S/ 91.30 S/ 91.30 S/ 91.30
3.14.9.6 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 4.00 S/ 5.10 S/ 20.40 S/ 5.10 S/ 5.10 S/ 5.10 S/ 5.10
3.14.9.7 TARRAJEO DE MUROS INTERIORES,E=1.50CM C:A 1:5 m² 2.24 S/ 23.16 S/ 51.88 S/ 12.97 S/ 12.97 S/ 12.97 S/ 12.97
3.14.9.8 TARRAJEO DE MUROS EXTERIORES,E=1.50CM C:A 1:5 m² 2.80 S/ 26.25 S/ 73.50 S/ 18.38 S/ 18.38 S/ 18.38 S/ 18.38
3.14.9.9 SUMINISTRO E INSTALACIÓN DE COMPUERTA DE CIERRE und 0.80 S/ 1,615.50 S/ 1,292.40 S/ 323.10 S/ 323.10 S/ 323.10 S/ 323.10
3.14.10 SUMINISTRO E INSTALACIONES DE ACCESORIOS S/ 73,218.74 S/ - S/ - S/ - S/ -
3.14.10.1 ACCESORIOS DE TUBERÍA DE CONDUCCIÓN S/ 58,648.66 S/ - S/ - S/ - S/ -
3.14.10.1.1 SUMINISTRO E INSTALACIÓN DE TUBERÍA PVC SP C-7.5 D=200MM m 112.15 S/ 92.04 S/ 10,322.29 S/ 2,580.57 S/ 2,580.57 S/ 2,580.57 S/ 2,580.57
3.14.10.1.2 SUMINISTRO E INSTALACIÓN DE TUBERÍA PVC SP C-7.5 D=300MM m 101.25 S/ 441.57 S/ 44,708.96 S/ 11,177.24 S/ 11,177.24 S/ 11,177.24 S/ 11,177.24
3.14.10.1.3 SUMINISTRO E INSTALACIÓN DE CODO F°G° DE 90° und 5.00 S/ 566.88 S/ 2,834.40 S/ 708.60 S/ 708.60 S/ 708.60 S/ 708.60
3.14.10.1.4 SUMINISTRO E INSTALACIÓN DE TEE und 1.00 S/ 783.01 S/ 783.01 S/ 195.75 S/ 195.75 S/ 195.75 S/ 195.75
3.14.10.2 ACCESORIOS DE TUBERÍA DE LIMPIA Y REBOSE S/ 14,570.08 S/ - S/ - S/ - S/ -
3.14.10.2.1 SUMINISTRO E INSTALACIÓN DE TUBERÍA PVC SP C-7.5 D=200MM m 75.00 S/ 92.04 S/ 6,903.00 S/ 1,725.75 S/ 1,725.75 S/ 1,725.75 S/ 1,725.75
3.14.10.2.2 SUMINISTRO E INSTALACIÓN DE CODO F°G° DE 90° und 8.00 S/ 566.88 S/ 4,535.04 S/ 1,133.76 S/ 1,133.76 S/ 1,133.76 S/ 1,133.76
3.14.10.2.3 SUMINISTRO E INSTALACIÓN DE TEE und 4.00 S/ 783.01 S/ 3,132.04 S/ 783.01 S/ 783.01 S/ 783.01 S/ 783.01
3.14.11 RED DE DRENAJE S/ 11,305.01 S/ - S/ - S/ - S/ -
3.14.11.1 CAPA FILTRANTE m² 228.80 S/ 49.41 S/ 11,305.01 S/ 2,826.25 S/ 2,826.25 S/ 2,826.25 S/ 2,826.25
3.15 VARIOS S/ 28,956.13
3.15.1 LIMPIEZA FINAL DE OBRA dia 10.00 S/ 275.38 S/ 2,753.80 S/ 2,753.80
3.15.2 JARDINES m² 2,382.03 S/ 11.00 S/ 26,202.33 S/ 26,202.33
3.16 DEFENSA RIBEREÑA CON MURO DE CONTENCIÓN H=5M S/ 498,275.59
3.16.1 TRABAJOS PRELIMINARES S/ 1,916.46
3.16.1.1 LIMPIEZA DE TERRENO MANUAL m² 283.50 S/ 3.44 S/ 975.24 S/ 243.81 S/ 243.81 S/ 243.81 S/ 243.81
3.16.1.2 TRAZO, NIVELACIÓN Y REPLANTEO PRELIMINAR m² 283.50 S/ 3.32 S/ 941.22 S/ 235.31 S/ 235.31 S/ 235.31 S/ 235.31
3.16.2 MOVIMIENTO DE TIERRAS S/ 71,649.56 S/ - S/ - S/ - S/ -
3.16.2.1 EXCAVACION MASIVA E/P H=2.80M (EQUIPO) m³ 1,937.24 S/ 6.81 S/ 13,192.60 S/ 3,298.15 S/ 3,298.15 S/ 3,298.15 S/ 3,298.15
3.16.2.2 PERFILADO Y NIVELACION m² 283.50 S/ 10.64 S/ 3,016.44 S/ 754.11 S/ 754.11 S/ 754.11 S/ 754.11
3.16.2.3 RELLENO COMPACTADO CON MATERIAL PROPIO m³ 1,604.15 S/ 28.26 S/ 45,333.28 S/ 11,333.32 S/ 11,333.32 S/ 11,333.32 S/ 11,333.32
3.16.2.4 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMO m³ 47.52 S/ 83.58 S/ 3,971.72 S/ 992.93 S/ 992.93 S/ 992.93 S/ 992.93
3.16.2.5 CARGUIO E ELIMINACION DE MATERIAL EXCEDENTE DM<06 km m³ 333.09 S/ 18.42 S/ 6,135.52 S/ 1,533.88 S/ 1,533.88 S/ 1,533.88 S/ 1,533.88
3.16.3 OBRAS DE CONCRETO SIMPLE S/ 1,413.78 S/ - S/ - S/ - S/ -
3.16.3.1 SOLADOS DE E=4" MEZCLA 1:10 (C:H) m² 28.04 S/ 50.42 S/ 1,413.78 S/ 353.45 S/ 353.45 S/ 353.45 S/ 353.45
3.16.4 OBRAS DE CONCRETO ARMADO S/ 349,279.18 S/ - S/ - S/ - S/ -
3.16.4.1 CONCRETO FC=210 KG/CM2 C:A:P C/MEZCLADORA (CEMENTO PI) m³ 322.17 S/ 442.20 S/ 142,463.57 S/ 35,615.89 S/ 35,615.89 S/ 35,615.89 S/ 35,615.89
3.16.4.2 ENCOFRADO Y DESENCOFRADO NORMAL m² 1,531.16 S/ 72.46 S/ 110,947.85 S/ 27,736.96 S/ 27,736.96 S/ 27,736.96 S/ 27,736.96
3.16.4.3 ACERO DE REFUERZO FY = 4200 KG/CM2 kg 18,797.60 S/ 5.10 S/ 95,867.76 S/ 23,966.94 S/ 23,966.94 S/ 23,966.94 S/ 23,966.94
3.16.5 REVOQUES Y ENLUCIDOS S/ 69,490.11 S/ - S/ - S/ - S/ -
3.16.5.1 TARRAJEO CON IMPERMEABILIZANTE DE LOSA DE FONDO, PISO, CANALES m² 1,453.16 S/ 47.82 S/ 69,490.11 S/ 17,372.53 S/ 17,372.53 S/ 17,372.53 S/ 17,372.53
Costo Directo S/ 6,123,207.97 S/ 502,698.80 S/ 1,119,250.04 S/ 1,204,711.81 S/ 652,629.40 S/ 818,678.27 S/ 781,312.29 S/ 524,202.72 S/ 519,724.65
PORCENTAJE MENSUAL 8.21% 18.28% 19.67% 10.66% 13.37% 12.76% 8.56% 8.49%
PORCENTAJE ACUMULADO 8.21% 26.49% 46.16% 56.82% 70.19% 82.95% 91.51% 100.00%