Professional Documents
Culture Documents
Precio Particular in Sumo Tipov Tipo 2
Precio Particular in Sumo Tipov Tipo 2
MANO DE OBRA
0101010003 OPERARIO hh 18.8707 10.00 188.71
0101010004 OFICIAL hh 3.8735 9.00 34.86
0101010005 PEON hh 74.9813 8.00 599.85
823.42
MATERIALES
02070100010002 PIEDRA CHANCADA 1/2" m3 3.1955 140.00 447.37
02070200010002 ARENA GRUESA m3 3.1374 140.00 439.24
0207070001 AGUA PUESTA EN OBRA m3 1.0748 5.00 5.37
0213010001 CEMENTO PORTLAND TIPO I (42.5 kg) bol 48.9783 34.00 1,665.26
0240060011 PINTURA AMARILLA PARA TRAFICO gal 1.0060 75.00 75.45
0240060012 PINTURA NEGRA PARA TRAFICO gal 1.0060 75.00 75.45
02400800150001 SOLVENTE XILOL gal 2.0015 40.00 80.06
0245010004 BROCHA und 2.0015 25.00 50.04
2,838.24
EQUIPOS
0301010006 HERRAMIENTAS MANUALES %mo 25.65
0301110002 CORTADORA DE CONCRETO 14" hm 5.9322 20.00 118.64
03012200040002 CAMION VOLQUETE DE 10 m3 hm 6.9198 100.00 691.98
0301290003 MEZCLADORA DE CONCRETO hm 3.8735 15.00 58.10
894.37