PROJECT "MULTI - PURPOSE TOWER" AT DARLEY ROAD, COLOMBO, SRI LANKA O6118 REV. No. DATE JOB NO. O6118 - C - TB - 01 - BQ - 0002 0 CALCULATED CHECKED DICIPLINE Structural (BOQ of Substructure)
S.No Description Unit Quantity Rate Amount
1.0 EARTHWORK EXCAVATION
1.1 General Excavation by mechanical means using excavators, JCB, Poclains etc., in all types of soil including soft / weathered rock but excluding hard rock for foundations / basement excavation; Dispose excavated material offsite by mechanical means as directed to the approval of Employer. Disposal not measured seperately. Rate to include for excavation for all leads & lift, loading, unloading & double handling where required, necessary equipments, tools & plants, dressing the excavation to proper level and grade as required, dumping the soil in the designated area approved by the Authorities, taking necessary precautions to prevent any spillages or spoiling of the premises / public roads during removal & transporting the soil, all consumables including protecting the sides of excavation as per the the nature of site soil condition and safety of excavation etc complete, as directed.
Rate shall include cost of excavation of working space as
required, slopes and berms as per site soil condition/nature of the site soil and safety of excavation. Rate shall also include for refilling such excavation of working space with approved filling material including consolidating to the required proctor density, excavation at all levels and for the following depths below average existing ground level, including shoring, strutting, protecting sides from collapses, slush removal, pumping & bailing out water, de-watering if any so as to keep foundations in dry condition at any stage of work, drain the water away from the site through sub drain and connecting into main drain, is deemed included in the rates:
Note : Excavation will be measured on the basis of the horizontal
area of open mass excavation at the base for RCC raft foundation / Retaining wall foundation or any other structures to be built.The actual depth of excavation will be arrived at as the difference between the spot levels taken at existing ground level prior to excavation at a spacing of 3m intervals in both directions and the final bottom level of founding level as per drawings. Excavation taken by the Contractor for working space as required, slopes and berms as per site soil condition / nature of site soil and safety of excavation will not be measured. Quoted rate shall be deemed to have considered the above stipulations.
a) Depth not exceeding 3.0m from existing level m3 15268
b) '-Ditto- but exceeding 3.0m and below 6.0m m3 15268 c) '-Ditto- but exceeding 6.0m and below 9.0m m3 15268 d) '-Ditto- but exceeding 9.0m and below 12.5m m3 17813 e) '-Ditto- but exceeding 12.5m upto maximum depth shown in the drawings m3 - LARSEN & TOUBRO LIMITED ECC DIVISION - EDRC
JOB No. SHEET
PROJECT "MULTI - PURPOSE TOWER" AT DARLEY ROAD, COLOMBO, SRI LANKA O6118 REV. No. DATE JOB NO. O6118 - C - TB - 01 - BQ - 0002 0 CALCULATED CHECKED DICIPLINE Structural (BOQ of Substructure)
S.No Description Unit Quantity Rate Amount
1.2 Excavation in hard rock / boulders (more than ½ Cum in size) to required level for basement excavation, foundations / footings, pile caps, under ground / water retaining structures etc.at any depth and at all levels either by manual, by chiseling / wedging or mechanical means other than blasting (which is prohibited) including conveying excavated rock at designated area and stacking for measurement as directed with all leads and lifts, including shoring, strutting, protecting sides from collapses, slush removal, etc.complete, as directed.
Rate shall include for disposing the rock by mechanical means as
detailed below including, breaking the rocks to the required size if required, for easy conveyance, etc complete, as directed. Note : .Length and breadth at bottom of foundation and depth from the top of average ground level to the bottom of foundation only should be excavated and the payment shall be made.Excavation taken by the Contractor for working space as required, slopes and berms as per site soil condition / nature of site soil and safety of excavation will not be measured. Item shall be measured from stacks of excavated hard rock, reduced by 40% for voids and such quantity arrived at shall only be paid. Quoted rate shall be deemed to have considered the above stipulation. (Provisional Quantity)
a) Depth not exceeding 3.0m from existing level m3 -
b) '-Ditto- but exceeding 3.0m and below 6.0m m3 - c) '-Ditto- but exceeding 6.0m and below 9.0m m3 - d) '-Ditto- but exceeding 9.0m and below 12.5m m3 - e) '-Ditto- but exceeding 12.5m upto maximum depth shown in the drawings m3 1527 1.3 Supplying and filling in foundations and the area wherever required below ground level with the approved filling materials either with excess excavated earth stockpiled at site and / or approved imported earth in layers not exceeding 200 mm thickness, including mixing, spreading, levelling, watering and consolidating each layer with power / hand roller of required capacity to obtain required proctor density as per relevant specification etc. all complete and as directed. Rate shall include for loading, unloading, transportation, hire and fuel charges for tools and plants employed and other incidental charges etc. complete and as directed.Rate shall also include for refilling the excavation of working space as described above.
a) With excavated earth available within site m3 200
b) With approved earth obtained from outside m3 200 6.0 Piling Works
6.1 Mobilisation of plant and equipment, installation at site as
Lumps directed and demobilisation of the same after completion of work. um LARSEN & TOUBRO LIMITED ECC DIVISION - EDRC
JOB No. SHEET
PROJECT "MULTI - PURPOSE TOWER" AT DARLEY ROAD, COLOMBO, SRI LANKA O6118 REV. No. DATE JOB NO. O6118 - C - TB - 01 - BQ - 0002 0 CALCULATED CHECKED DICIPLINE Structural (BOQ of Substructure)
S.No Description Unit Quantity Rate Amount
6.2 Boring and casting normal Bored cast-in-situ piles by DMC method of approximately 10m depth soil below basement in accordance with drawings, enclosed technical specifications and directions including setting out cardinal points, boring in over burden through all stratas upto founding layer including dewatering, chisselling through obstacles like boulders, weathering rock and keeping the bored portion intact by using Bentonite slurry (Specific gravity less than 1.08) including flushing out by using pumps of adequate capacity, clearing the same out of site, inserting the casing upto 2.0m depth and removal of temporary casing, conducting SPT and soil classification tests inside bore hole at termination depth. Concreting to be done till the cut off level.
a) 1000mm dia pile Rmt 230
b) 1200mm dia pile Rmt 1620 c) 1500mm dia pile Rmt 2400 LARSEN & TOUBRO LIMITED ECC DIVISION - EDRC
JOB No. SHEET
PROJECT "MULTI - PURPOSE TOWER" AT DARLEY ROAD, COLOMBO, SRI LANKA O6118 REV. No. DATE JOB NO. O6118 - C - TB - 01 - BQ - 0002 0 CALCULATED CHECKED DICIPLINE Structural (BOQ of Substructure)
S.No Description Unit Quantity Rate Amount
6.3 Boring and casting normal Bored cast-in-situ piles of approximately 2m depth inside hardrock below 10m deep soil in accordance with drawings, enclosed technical specifications and directions including setting out cardinal points, boring in over burden through all stratas upto founding layer including dewatering, chisselling through obstacles like boulders, weathering rock and keeping the bored portion intact by using Bentonite slurry (Specific gravity less than 1.08) including flushing out by using pumps of adequate capacity, clearing the same out of site, inserting the casing upto 2.0m depth and removal of temporary casing, conducting SPT and soil classification tests inside bore hole at termination depth. Concreting to be done till the cut off level.
a) 1000mm dia pile Rmt 46
b) 1200mm dia pile Rmt 324 c) 1500mm dia pile Rmt 480 6.4 Providing Ready mixed reinforced cement concrete of M40 grade using river sand, 20mm and down size coarse aggregates with minimum cement content of 400 kg/cum and placing into the bore by tremie method including compaction of concrete and withdrawal of casing. The rate shall include cost of approved ordinary Portland cement of specified grade, including, exposing and welding of new bars of same dia with butt weld and/or lap weld as per consultant's specifications.Design mix to be approved by the consultants, Water cement ratio to be within 0.45, the slump at pouring point to be maintained 140mm,+/-10mm. The age of concrete while pouring shoud not exceed 2Hrs.
a) 1000mm dia pile Rmt 276
b) 1200mm dia pile Rmt 1944 c) 1500mm dia pile Rmt 2880 6.5 Providing and conducting routine load tests to 2.5 times the safe load of piles as per BS 8004. a) 1000mm dia pile Nos - b) 1200mm dia pile Nos 1 c) 1500mm dia pile Nos 2 6.6 Conducting integrity tests on the piles under each cluster by using a 6 lbs nylon tipped hand held hammer, glueing sensitive accelerometer on top of the pile by petrowax or petrolium jelly after making the pile head smooth and even by disc grinder, providing stagewise and final report along with relevant conclusions etc., as per the consultants direction,enclosed technical specifications.
a) 1000mm dia pile Nos 1
b) 1200mm dia pile Nos 4 c) 1500mm dia pile Nos 5 6.7 Cutting the concrete in Piles till Cutoff level by mechanical means and finishing the top to required level with CM 1:2 and straightening the exposed reinforcement, welding the new bars of same diameter by butt or lap weld if required.Rate to include debri clearence, curing etc.,complete as per the drawings and Consultant's instructions a) 1000mm dia pile Nos 23 b) 1200mm dia pile Nos 162 c) 1500mm dia pile Nos 240 6.8 Same as item 6.2 but for Empty driving from existing ground level to cut-off level & filling the same with sand LARSEN & TOUBRO LIMITED ECC DIVISION - EDRC
JOB No. SHEET
PROJECT "MULTI - PURPOSE TOWER" AT DARLEY ROAD, COLOMBO, SRI LANKA O6118 REV. No. DATE JOB NO. O6118 - C - TB - 01 - BQ - 0002 0 CALCULATED CHECKED DICIPLINE Structural (BOQ of Substructure)
S.No Description Unit Quantity Rate Amount
a) 1000mm dia pile Rmt 276 b) 1200mm dia pile Rmt 1944 c) 1500mm dia pile Rmt 2880 Steel 6.9 Providing and fabricating reinforcement steel of high yield strength ribbed bars of various diameters and grade fe 460 conforming to BS 5950 for reinforced concrete work. The work includes cutting, bending, fabricating, welding and palcing in posiiton according to drawings. The reinforcement including supply and use of 18G black annealed binding wire double fold to tie the bars in position and providing precast cement / PVC cover blocks for main reinforcement to ensure specified cover, including welding. MT 410 Sub Total ( C/o to Summary) -----