LARSEN & TOUBRO LIMITED

ECC DIVISION - EDRC

JOB No.
PROJECT "MULTI - PURPOSE TOWER" AT DARLEY ROAD, COLOMBO, SRI LANKA
O6118
REV. No.
JOB NO. O6118 - C - TB - 01 - BQ - 0002
0
CALCULATED
DICIPLINE Structural (BOQ of Substructure)

S.No Description Unit Quantity Rate

1.0 EARTHWORK EXCAVATION


1.1 General Excavation by mechanical means using excavators,
JCB, Poclains etc., in all types of soil including soft / weathered
rock but excluding hard rock for foundations / basement
excavation; Dispose excavated material offsite by mechanical
means as directed to the approval of Employer. Disposal not
measured seperately. Rate to include for excavation for all leads
& lift, loading, unloading & double handling where required,
necessary equipments, tools & plants, dressing the excavation to
proper level and grade as required, dumping the soil in the
designated area approved by the Authorities, taking necessary
precautions to prevent any spillages or spoiling of the premises /
public roads during removal & transporting the soil, all
consumables including protecting the sides of excavation as per
the the nature of site soil condition and safety of excavation etc
complete, as directed.

Rate shall include cost of excavation of working space as


required, slopes and berms as per site soil condition/nature of the
site soil and safety of excavation. Rate shall also include for
refilling such excavation of working space with approved filling
material including consolidating to the required proctor density,
excavation at all levels and for the following depths below
average existing ground level, including shoring, strutting,
protecting sides from collapses, slush removal, pumping & bailing
out water, de-watering if any so as to keep foundations in dry
condition at any stage of work, drain the water away from the site
through sub drain and connecting into main drain, is deemed
included in the rates:

Note : Excavation will be measured on the basis of the horizontal


area of open mass excavation at the base for RCC raft
foundation / Retaining wall foundation or any other structures to
be built.The actual depth of excavation will be arrived at as the
difference between the spot levels taken at existing ground level
prior to excavation at a spacing of 3m intervals in both directions
and the final bottom level of founding level as per drawings.
Excavation taken by the Contractor for working space as
required, slopes and berms as per site soil condition / nature of
site soil and safety of excavation will not be measured. Quoted
rate shall be deemed to have considered the above stipulations.

a) Depth not exceeding 3.0m from existing level m3 15268


b) '-Ditto- but exceeding 3.0m and below 6.0m m3 15268
c) '-Ditto- but exceeding 6.0m and below 9.0m m3 15268
d) '-Ditto- but exceeding 9.0m and below 12.5m m3 17813
e) '-Ditto- but exceeding 12.5m upto maximum depth shown in
the drawings m3 -
1.2 Excavation in hard rock / boulders (more than ½ Cum in size) to
required level for basement excavation, foundations / footings,
pile caps, under ground / water retaining structures etc.at any
depth and at all levels either by manual, by chiseling / wedging or
mechanical means other than blasting (which is prohibited)
including conveying excavated rock at designated area and
stacking for measurement as directed with all leads and lifts,
including shoring, strutting, protecting sides from collapses, slush
removal, etc.complete, as directed.

Rate shall include for disposing the rock by mechanical means as


detailed below including, breaking the rocks to the required size if
required, for easy conveyance, etc complete, as directed.
Note : .Length and breadth at bottom of foundation and depth
from the top of average ground level to the bottom of foundation
only should be excavated and the payment shall be
made.Excavation taken by the Contractor for working space as
required, slopes and berms as per site soil condition / nature of
site soil and safety of excavation will not be measured. Item shall
be measured from stacks of excavated hard rock, reduced by
40% for voids and such quantity arrived at shall only be paid.
Quoted rate shall be deemed to have considered the above
stipulation. (Provisional Quantity)

a) Depth not exceeding 3.0m from existing level m3 -


b) '-Ditto- but exceeding 3.0m and below 6.0m m3 -
c) '-Ditto- but exceeding 6.0m and below 9.0m m3 -
d) '-Ditto- but exceeding 9.0m and below 12.5m m3 -
e) '-Ditto- but exceeding 12.5m upto maximum depth shown in
the drawings m3 1527
1.3 Supplying and filling in foundations and the area wherever
required below ground level with the approved filling materials
either with excess excavated earth stockpiled at site and / or
approved imported earth in layers not exceeding 200 mm
thickness, including mixing, spreading, levelling, watering and
consolidating each layer with power / hand roller of required
capacity to obtain required proctor density as per relevant
specification etc. all complete and as directed. Rate shall include
for loading, unloading, transportation, hire and fuel charges for
tools and plants employed and other incidental charges etc.
complete and as directed.Rate shall also include for refilling the
excavation of working space as described above.

a) With excavated earth available within site m3 200


b) With approved earth obtained from outside m3 200
2.0 CONCRETE
Plain Cement Concrete (PCC)
2.1 Providing and laying plain cement concrete using 1:3:6 coarse
graded aggregate of 20 mm down size for levelling course filling,
including laying in layers of specified thickness as directed
including form work wherever necessary and well compacted etc.
all complete, as directed. Rate to include for all necessary
formwork & supports wherever applicable
m3 319
2.2 Providing and laying plain cement concrete 1:4:8 using coarse
graded aggregate of 40 mm and down size for levelling course
under footings, steps, walls, platform etc. including in laying
layers of specified thickness as directed including form work
wherever necessary and well compacted etc. all complete, as
directed. Rate to include for all necessary formwork & supports
wherever applicable
m3 1,018
Reinforced Cement Concrete (RCC)
Note: Ready Mixed Concrete (RMC) shall be used in this project.
RMC shall be procured from approved RMC supplier (site mix
by batching plant) and shall be manufactured and supplied to
meet the strength requirements of concrete.

2.3 Providing ready mixed concrete to site, taking delivery, laying,


compacting and curing concrete course grade M60 as per
specifications using coarse graded aggregate of 20mm and down
size aggregate of approved properties for the following members
of all shapes, at all levels including all lead and lifts, tools &
plants, pumping the concrete to all levels, vibrating, curing etc.
complete. Depending on the size and location, the maximum
depth of concreting will be decided by Engineer in casting at a
time.

Corewalls/Shear Walls
i) Core Walls / Shear Walls from Raft Level - Ground Level m3 819
Columns
i) Columns from Raft Level - Ground Level m3 384
2.4 Providing ready mixed concrete to site, taking delivery, laying,
compacting and curing concrete grade M60 as per specifications
using coarse graded aggregate of 20mm and down size
aggregate of approved properties for the following members of all
shapes, at all levels including necessary formwork, centering,
shuttering, all lead and lifts, tools & plants, pumping the concrete
to all levels, vibrating, curing etc. complete but excluding cost of
reinforcement. Depending on the size and location, the maximum
depth of concreting will be decided by Engineer in casting at a
time. Rate to include for all necessary formwork

Substructure:
i) Floor Slab m3 2,211
ii) Floor Beams m3
753
2.5 Providing ready mixed concrete to site, taking delivery, laying,
compacting and curing concrete grade M40 as per specifications
using coarse graded aggregate of 20mm and down size
aggregate of approved properties for the following members of all
shapes, at all levels including necessary formwork, centering,
shuttering, all lead and lifts, tools & plants, pumping the concrete
to all levels, vibrating, curing etc. complete but excluding cost of
reinforcement. Depending on the size and location, the maximum
depth of concreting will be decided by Engineer in casting at a
time. Rate to include for all necessary formwork

Substructure:
i) Raft Slab m3 9,777
ii) Retaining Walls m3 6,092
iii) Ramp Beam m3 119
iv) Ramp Slab m3 137
v) Staircase m3
41
vi) Water Retaining Structures m3 102
vii) Lintel m3 6
3.0 FORM WORK
Form work for Reinforced Cement Concrete (RCC)
3.1 Supplying, fabricating, erecting and fixing in position centering
and shuttering to correct line and levels including
strutting,propping, wtc. With necessary bracings in all axes to
give a stable assembly with provision for making the joints in the
shuttering fully leak proof and with provision for inserts, projecting
dowels, anchor bolts or any other fixture, including staging,
access and working platforms etc all complete as specified and
directed including dismantling and removing the aforesaid
assembly after the concrete attains the sufficient strength to self-
support itself without cracking and distortion, all materials and
labour complete in all respects for the following

Corewalls/Shear Walls
i) Core Walls / Shear Walls Basement - ground floor m2 3,796
Columns
ii) Columns Basement - ground floor m2 1,175
Substructure:
i) Raft Slab m2 568
ii) Retaining Walls m2 3,146
iii) Floor Slab m2 13,628
iv) Floor Beams m2 4,318
v) Ramp Beam m2 866
vi) Ramp Slab m2 784
vii) Staircase m2 214
viii) Water Retaining Structures m2 656
ix) Lintel m2 90

4.0 REINFORCEMENT STEEL WORK

4.1 Providing fabricating and fixing reinforcement for RCC work with
high yield strength ribbed cold twisted tor steel of various
diameters and all lengths, including cutting, bending, fabricating,
welding, wastage and placing in position according to drawings
and binding the reinforcement with the use of 16 gauge
galvanised binding wire of double fold and providing precast
cement cover blocks for main reinforcements to ensure specified
cover according to relevant BS code. The measurements will be
in accordance with BS 5950.
Note : Unless noted otherwise the measurements in accordance
with BS 5950 or equivalent BS. However reinforcement shall be
measured only in lengths of bars as actually placed in position on
standard weight basis, no allowance being made in the weight for
rolling margin. Authorised laps and splices only will be measured.
Chairs of any shape & profile, Spacer bar of any shape & profile,
cover block, wastage and binding wire will not be measured and
shall be included in the quoted rates. Quoted rate shall be
deemed to have considered the above stipulations.

i) In all reinforced concrete elements MT 2,640


4.2 Providing and fixing mechanical treaded Splicing for the higher
dia. bars by a standard sleeve of specially produced steel to join
ribbed bearing bars and treatment as required for system. Cost to
include pressing of sleeve by hydraulic press on to the bar and
slipping of in-si-tu bar to the un pressed end and pressing to
complete the joint. Cost to include testing of joints before usage
of the splice as required by Consultants at intervals

i) Y32 Nos 309


ii) Y25 Nos 534
5.0 WATERPROOFING WORKS
Toilets
5.1 a) The application consists of two layer of ACRYLIC MODIFIED /
POLYMER MODIFIED CEMENTITIOUS waterproof coating either
single component or two component over a component of
crystallisation waterproofing coating (500gms/Sqm) after base
preparation of cleaning, brushing and removal of flacky materials,
grouting the porous area with cementations grout,fixing of weep
holes,Grouting of pipe outlets etc and second layer of coating
using the same coating when the first coating is still green. The
coatings shall be applied at intervals and as per the
manufacturers specifications. Cost to include the treatment along
wall up to min 300 mm and no extra measurements shall be
accounted for the wall treatment. (Only Plan area shall be
accounted) Fosroc/Polyplus or equivalent

Sqm 88
b) Waterproofing treatment protection shall be in two layers in CM
1:4 of thickness 35mm for floor, 25mm for walls till floor level and
18mm till 300mm above floor level with water proof admixture as
per Manufacturer's specification approved by consultants with a
minimum guarantee period of 10 years.Note: Plan area shall be
the mode of measurement
Sqm 88
Water Tank,Lift pits and Disel storage tank
5.2 a) The method consists of application of first layer of ACRYLIC
MODIFIED / POLYMER MODIFIED CEMENTITIOUS waterproof
coating either single component or two part one after base
preparation of cleaning, brushing and removal of flacky materials,
grouting the porous area with cementations grout,fixing of weep
holes,Grouting of pipe outlets etc and second layer of coating
after fixing theGeo fabric / Fibre glass cloth with proper over
lappings using the same coating when the coating is still green.
The coatings shall be applied at intervals and as per the
manufacturers specifications.

Sqm 1,082
b) Waterproofing treatment protection shall be in two layers in CM
1:4 of thickness 25mm for floor, 18mm for walls with water proof
admixture as per Manufacturer's specification approved by
consultants with a minimum guarantee period of 10 years.Note:
Plan area shall be the mode of measurement

i) Floors Sqm 415


ii) Walls Sqm 667
Basement Waterproofing:
5.3 Raft Slab:
Providing waterproofing for Raft Slab by following one or all
methods as per the specifications listed below with a minimum
guarantee period of 10 years and Testing of treatment as per the
requirements. (only plan area shall be accounted)

a) Provided PCC for raft shall be finished smooth to receive water


proofing membrane (only additional workman shall be
considered) Sqm 4889
b) Supplying, providing and applying water proofing treatment
with Membrane type water proofing methods using polymer
modified Bituminous membrane of approved makes of Atactic
Poly-Propylene (APP-4mm thk) based with UV resistant, ground
chemical resistant, high melting points, flexible and elastic with
high adhesive strength. The membrane shall be reinforced with
non woven polyester reinforcement of minimum of 180 g/sqm and
reinforced including coating with compatible primer of Bituminous
base and torch application with overlap of 100 mm wherever
required. The reinforcement provided shall be able to withstand
the traffic flow density and after construction and shall carry a
minimum guarantee period of 10 years. Cost to include laying by
loose and torching the prefabricated overlap at ends. Approved
makes (Polyplus/Fosroc/IWL/ Texsa or Equilent/Tristar intec)

Sqm 4889
c) Providing and laying of 50mm screed concrete of M20 as
protection layer for waterproofing membrane Sqm 4889
5.4 Ground Waterproofing:
Providing waterproofing for Ground Floor Slab by following one or
all methods as per the specifications listed below with a minimum
guarantee period of 10 years and Testing of treatment as per the
requirements. (only plan area shall be accounted)

a) First layer of cement concrete 1:3:6 over base concrete laid to


falls and slope of minimum 1:100 and finished smooth to receive
water proofing membrane. Sqm 2503
b) Supplying, providing and applying water proofing treatment
with Membrane type water proofing methods using polymer
modified Bituminous membrane of approved makes of Atactic
Poly-Propylene (APP-4mm thk) based with UV resistant, ground
chemical resistant, high melting points, flexible and elastic with
high adhesive strength. The membrane shall be reinforced with
non woven polyester reinforcement of minimum of 180 g/sqm and
reinforced including coating with compatible primer of Bituminous
base and torch application with overlap of 100 mm wherever
required. The reinforcement provided shall be able to withstand
the traffic flow density and after construction and shall carry a
minimum guarantee period of 10 years. Cost to include laying by
loose and torching the prefabricated overlap at ends. Approved
makes (Polyplus/Fosroc/IWL/ Texsa or Equilent/Tristar intec)

Sqm 2503
c) Providing and laying of 50mm screed concrete of M20 as
protection layer for waterproofing membrane Sqm 2503
5.5 Retaining Wall:
a) Providing CM as leveling course of 20-25mm thk in two layers
of plaster for receiving APP membrane.
Sqm 8126
b) Supplying, providing and applying water proofing treatment
with Membrane type water proofing methods using polymer
modified Bituminous membrane of approved makes of Atactic
Poly-Propylene (APP-4mm thk) based with UV resistant, ground
chemical resistant, high melting points, flexible and elastic with
high adhesive strength. The membrane shall be reinforced with
non woven polyester reinforcement of minimum of 180 g/sqm and
reinforced including coating with compatible primer of Bituminous
base and torch application with overlap of 100 mm wherever
required. The reinforcement provided shall be able to withstand
the traffic flow density and after construction and shall carry a
minimum guarantee period of 10 years. Cost to include laying by
loose and torching the prefabricated overlap at ends. Approved
makes (Polyplus/Fosroc/IWL/ Texsa or Equilent/Tristar intec)

Sqm 8126
c) Providing and fixing of 6mm thk bituminous board as protection
layer for waterproofing membrane for retaining walls.
Sqm 8126
6.0 Piling Works

6.1 Mobilisation of plant and equipment, installation at site as


Lumps
directed and demobilisation of the same after completion of work.
um

6.2 Boring and casting normal Bored cast-in-situ piles by DMC


method of approximately 10m depth soil below basement in
accordance with drawings, enclosed technical specifications and
directions including setting out cardinal points, boring in over
burden through all stratas upto founding layer including
dewatering, chisselling through obstacles like boulders,
weathering rock and keeping the bored portion intact by using
Bentonite slurry (Specific gravity less than 1.08) including flushing
out by using pumps of adequate capacity, clearing the same out
of site, inserting the casing upto 2.0m depth and removal of
temporary casing, conducting SPT and soil classification tests
inside bore hole at termination depth. Concreting to be done till
the cut off level.
a) 1000mm dia pile Rmt 230
b) 1200mm dia pile Rmt 1620
c) 1500mm dia pile Rmt 2400
6.3 Boring and casting normal Bored cast-in-situ piles of
approximately 2m depth inside hardrock below 10m deep soil in
accordance with drawings, enclosed technical specifications and
directions including setting out cardinal points, boring in over
burden through all stratas upto founding layer including
dewatering, chisselling through obstacles like boulders,
weathering rock and keeping the bored portion intact by using
Bentonite slurry (Specific gravity less than 1.08) including flushing
out by using pumps of adequate capacity, clearing the same out
of site, inserting the casing upto 2.0m depth and removal of
temporary casing, conducting SPT and soil classification tests
inside bore hole at termination depth. Concreting to be done till
the cut off level.

a) 1000mm dia pile Rmt 46


b) 1200mm dia pile Rmt 324
c) 1500mm dia pile Rmt 480
6.4 Providing Ready mixed reinforced cement concrete of M40 grade
using river sand, 20mm and down size coarse aggregates with
minimum cement content of 400 kg/cum and placing into the
bore by tremie method including compaction of concrete and
withdrawal of casing. The rate shall include cost of approved
ordinary Portland cement of specified grade, including, exposing
and welding of new bars of same dia with butt weld and/or lap
weld as per consultant's specifications.Design mix to be approved
by the consultants, Water cement ratio to be within 0.45, the
slump at pouring point to be maintained 140mm,+/-10mm. The
age of concrete while pouring shoud not exceed 2Hrs.

a) 1000mm dia pile Rmt 276


b) 1200mm dia pile Rmt 1944
c) 1500mm dia pile Rmt 2880
6.5 Providing and conducting routine load tests to 2.5 times the safe
load of piles as per BS 8004.
a) 1000mm dia pile Nos -
b) 1200mm dia pile Nos 1
c) 1500mm dia pile Nos 2
6.6 Conducting integrity tests on the piles under each cluster by
using a 6 lbs nylon tipped hand held hammer, glueing sensitive
accelerometer on top of the pile by petrowax or petrolium jelly
after making the pile head smooth and even by disc grinder,
providing stagewise and final report along with relevant
conclusions etc., as per the consultants direction,enclosed
technical specifications.

a) 1000mm dia pile Nos 1


b) 1200mm dia pile Nos 4
c) 1500mm dia pile Nos 5
6.7 Cutting the concrete in Piles till Cutoff level by mechanical means
and finishing the top to required level with CM 1:2 and
straightening the exposed reinforcement, welding the new bars of
same diameter by butt or lap weld if required.Rate to include
debri clearence, curing etc.,complete as per the drawings and
Consultant's instructions
a) 1000mm dia pile Nos 23
b) 1200mm dia pile Nos 162
c) 1500mm dia pile Nos 240
6.8 Same as item 6.2 but for Empty driving from existing
ground level to cut-off level & filling the same with sand

a) 1000mm dia pile Rmt 276


b) 1200mm dia pile Rmt 1944
c) 1500mm dia pile Rmt 2880
Steel
6.9 Providing and fabricating reinforcement steel of high yield
strength ribbed bars of various diameters and grade fe 460
conforming to BS 5950 for reinforced concrete work. The work
includes cutting, bending, fabricating, welding and palcing in
posiiton according to drawings. The reinforcement including
supply and use of 18G black annealed binding wire double fold to
tie the bars in position and providing precast cement / PVC cover
blocks for main reinforcement to ensure specified cover, including
welding.
MT 410
Sub Total ( C/o to Summary) -----
SHEET

DATE

CHECKED

Amount
-
LARSEN & TOUBRO LIMITED
ECC DIVISION - EDRC

JOB No. SHEET


PROJECT "MULTI - PURPOSE TOWER" AT DARLEY ROAD, COLOMBO, SRI LANKA
O6118
REV. No. DATE
JOB NO. O6118 - C - TB - 01 - BQ - 0001
0
CALCULATED CHECKED
DICIPLINE Structural (BOQ of Superstructure)

S.No Description Unit Quantity Rate Amount

1.0 CONCRETE

Reinforced Cement Concrete (RCC)


Note: Ready Mixed Concrete (RMC) shall be used in this project.
RMC shall be procured from approved RMC supplier (site mix
by batching plant) and shall be manufactured and supplied to
meet the strength requirements of concrete.
1.1 Providing ready mixed concrete to site, taking delivery, laying,
compacting and curing concrete grade M60 as per specifications
using coarse graded aggregate of 20mm and down size
aggregate of approved properties for the following members of all
shapes, at all levels including all lead and lifts, tools & plants,
pumping the concrete to all levels, vibrating, curing etc. complete.
Depending on the size and location, the maximum depth of
concreting will be decided by Engineer in casting at a time.

Corewalls/Shear Walls
i) Core Walls / Shear Walls from Ground Level - 10th Level m3 4,019
ii) Core Walls / Shear Walls from 11th Level - 20th Level m 3
4,342
iii) Local Lift from Ground Level - 6th Level m4 186
Columns
i) Columns from Ground Level - 10th Level m3 1,135
ii) Columns from 11th Level - 20th Level m 3
1,066
1.2 Providing ready mixed concrete to site, taking delivery, laying,
compacting and curing concrete grade M50 as per specifications
using coarse graded aggregate of 20mm and down size
aggregate of approved properties for the following members of all
shapes, at all levels including all lead and lifts, tools & plants,
pumping the concrete to all levels, vibrating, curing etc. complete.
Depending on the size and location, the maximum depth of
concreting will be decided by Engineer in casting at a time.

Corewalls/Shear Walls
i) Core Walls / Shear Walls from 21st Level - 30th Level m3 3,206
ii) Core Walls / Shear Walls from 31st Level - 40th Level m3 2,957
iii) Core Walls / Shear Walls from 41st Level - 50th Level m3 2,491
iv) Core Walls / Shear Walls from 51st & above Levels m3 2,225
Columns
i) Columns from 21st Level - 30th Level m3 1,167
ii) Columns from 31st Level - 40th Level m3 1,368
iii) Columns from 41st Level - 50th Level m3 1,131
iv) Columns from 51st & above Levels m3 464
1.3 Providing ready mixed concrete to site, taking delivery, laying,
compacting and curing concrete grade M60 as per specifications
using coarse graded aggregate of 20mm and down size
aggregate of approved properties for the following members of all
shapes, at all levels including necessary formwork, centering,
shuttering, all lead and lifts, tools & plants, pumping the concrete
to all levels, vibrating, curing etc. complete but excluding cost of
reinforcement. Depending on the size and location, the maximum
depth of concreting will be decided by Engineer in casting at a
time. Rate to include for all necessary formwork

Superstructure
i) Floor Slab from 1st Level - 20th Level m3 9,251
ii) Floor beams from 1st Level - 20th Level m3
2,511
1.4 Providing ready mixed concrete to site, taking delivery, laying,
compacting and curing concrete grade M50 as per specifications
using coarse graded aggregate of 20mm and down size
aggregate of approved properties for the following members of all
shapes, at all levels including necessary formwork, centering,
shuttering, all lead and lifts, tools & plants, pumping the concrete
to all levels, vibrating, curing etc. complete but excluding cost of
reinforcement. Depending on the size and location, the maximum
depth of concreting will be decided by Engineer in casting at a
time. Rate to include for all necessary formwork

Superstructure
i) Floor Slab from 21st - 51st & above Levels m3 14,643
ii) Floor beams from 21st - 51st & above Levels m3 4,172
1.5 Providing ready mixed concrete to site, taking delivery, laying,
compacting and curing concrete grade M40 as per specifications
using coarse graded aggregate of 20mm and down size
aggregate of approved properties for the following members of all
shapes, at all levels including necessary formwork, centering,
shuttering, all lead and lifts, tools & plants, pumping the concrete
to all levels, vibrating, curing etc. complete but excluding cost of
reinforcement. Depending on the size and location, the maximum
depth of concreting will be decided by Engineer in casting at a
time. Rate to include for all necessary formwork

Superstructure
i) Staircase m3 1,024
ii) Ramp Beam m3 172
iii) Ramp Slab m3
315
iv) Water Retaining Structures m3 331
v) Lintel at all heights m3
250

2.0 FORM WORK

Form work forReinforced Cement Concrete (RCC)


2.1 Supplying, fabricating, erecting and fixing in position centering
and shuttering to correct line and levels including
strutting,propping, wtc. With necessary bracings in all axes to
give a stable assembly with provision for making the joints in the
shuttering fully leak proof and with provision for inserts, projecting
dowels, anchor bolts or any other fixture, including staging,
access and working platforms etc all complete as specified and
directed including dismantling and removing the aforesaid
assembly after the concrete attains the sufficient strength to self-
support itself without cracking and distortion, all materials and
labour complete in all respects for the following

Corewalls/Shear Walls
i) Core Walls / Shear Walls from Ground Level - 10th Level m2 14,023
ii) Core Walls / Shear Walls from 11th Level - 20th Level m2 15,275
iii) Core Walls / Shear Walls from 21st Level - 30th level m2 13,670
iv) Core Walls / Shear Walls from 31st Level - 40th Level m2 13,681
v) Core Walls / Shear Walls from 41st Level - 50th Level m2 11,885
vi) Core Walls / Shear Walls from 51st & above Levels m2 10,247
Columns
i) Columns from Ground Level - 10th Level m2 3,188
ii) Columns from 11th Level - 20th Level m2 2,927
iii) Columns from 21st Level - 30th Level m2 3,789
iv) Columns from 31st Level - 40th Level m2 4,667
v) Columns from 41st Level - 50th Level m2 3,871
vi) Columns from 51st & above Levels m2 1,922
Superstructure
i) Floor Slab m2 126,831
ii) Floor beams m2 19,101
iii) Staircase m2 5,402
iv) Ramp Beam m3 1,100
v) Ramp Slab m3 1,140
vi) Water Retaining Structures m3 2,289
vii) Lintel at all heights m3 3,380

3.0 REINFORCEMENT STEEL WORK

3.1 Providing fabricating and fixing reinforcement for RCC work with
high yield strength ribbed cold twisted tor steel of various
diameters and all lengths, including cutting, bending, fabricating,
welding, wastage and placing in position according to drawings
and binding the reinforcement with the use of 16 gauge
galvanised binding wire of double fold and providing precast
cement cover blocks for main reinforcements to ensure specified
cover according to relevant BS code. The measurements will be
in accordance with BS 5950.
Note : Unless noted otherwise the measurements in accordance
with BS 5950 or equivalent BS. However reinforcement shall be
measured only in lengths of bars as actually placed in position on
standard weight basis, no allowance being made in the weight for
rolling margin. Authorised laps and splices only will be measured.
Chairs of any shape & profile, Spacer bar of any shape & profile,
cover block, wastage and binding wire will not be measured and
shall be included in the quoted rates. Quoted rate shall be
deemed to have considered the above stipulations.

i) In all reinforced concrete elements MT 11,000


3.2 Providing and fixing mechanical treaded Splicing for the higher
dia. bars by a standard sleeve of specially produced steel to join
ribbed bearing bars and treatment as required for system. Cost to
include pressing of sleeve by hydraulic press on to the bar and
slipping of in-situ bar to the un pressed end and pressing to
complete the joint. Cost to include testing of joints before usage
of the splice as required by Consultants at intervals

i) Y32 Nos 4,740


ii) Y25 Nos 3,600
iii) Y20 Nos 8,316
3.3 Providing , cutting, fixing, stressing and grouting high tensile steel
reinforcement strands including all accessories complete in all
respects for post tensioned works. (Rate includes recess formers,
spacers and grout)

a) 5 - 4 tendon units comprising 13mm diameter low relaxation


strands with a tensile strength of 1860 N/mm2 MT 900

b) Corrugated flat duct 25 mm x 80 mm Rmt 296,425

c) Stressing anchorage VSL type SO 5 - 4 or equivalent Nos 10,996

d) Dead end Anchorage VSL type H or equivalent Nos 4,212


4.0 STRUCTURAL STEEL WORKS
4.1 Providing, Fabricating, hoisting and erecting in position Mild steel
structural steel works of Grade Yst 250/320 at all elevations, levels
and heights including aligning, levelling, providing and fixing
bolts, nuts, washers, comprising MS angles, channels, joists,
rails, tees, plates, chequered plates, flats, rounds, squares etc.,
of various sizes and other structural steel sections conforming to
latest BS 449 including straightening, cutting, welding, bending
to shape, bolting and inclusive of the following finishes.

i) Sand blasting SSPC - SP10 (Sa 2-1/2)


ii) 2 Coats (each one coat 25 microns DFT) of EPOXY polyamide based
red oxide zinc phosphate primer. 1 coat of Zinc rich primer shall be
aplied after the base coat of red oxide zinc phosphate primer at the
welded joints/welded surfaces, and this application carried out prior to
second coat of Zinch rich primer

iii) 2 Coats (each one coat of 35 microns DFT) of EPOXY polyamide


based enamel finish of approved colour and make.
iv) Final Top Coat of EPOXY based polyurethene paint - Aliphatic
grade for 35 microns DFT of approved colour and make shall be
provided.
a) Entrance Canopy MT. 10
b) Steel Works for façade Supports MT. 10
c) Roof Top Architectural Elements MT. 900
d) Pergola at various levels MT. 6
4.2 Providing and Anchoring bolt or through bolt in position high
strength anchor bolts of grade 5.8 and specified dia and standard
lengths upto 1.5M, including anchoring and groughting with
necessary equipments etc., complete as per specification of
agency approved by Employer / PMC.
-
i) 32mm dia Nos 116
ii) 25mm dia Nos 100
iii) 20mm dia Nos -
5.0 WATERPROOFING WORKS
5.1 Toilets & Balconies

a) The application consists of two layer of ACRYLIC MODIFIED /


POLYMER MODIFIED CEMENTITIOUS waterproof coating either
single component or two component over a component of
crystallisation waterproofing coating (500gms/Sqm) after base
preparation of cleaning, brushing and removal of flacky materials,
grouting the porous area with cementations grout,fixing of weep
holes,Grouting of pipe outlets etc and second layer of coating
using the same coating when the first coating is still green. The
coatings shall be applied at intervals and as per the
manufacturers specifications. Cost to include the treatment along
wall up to min 300 mm and no extra measurements shall be
accounted for the wall treatment. (Only Plan area shall be
accounted) Fosroc/Polyplus or equivalent

Sqm 14,148
b) Waterproofing treatment protection shall be in two layers in CM
1:4 of thickness 35mm for floor, 25mm for walls till floor level and
18mm till 300mm above floor level with water proof admixture as
per Manufacturer's specification approved by consultants with a
minimum guarantee period of 10 years.Note: Plan area shall be
the mode of measurement
Sqm 14,148
5.2 Terrace Water Proofing

Providing waterproofing for Terraces by following one or all


methods as per the specifications listed below with a minimum
guarantee period of 10 years and Testing of treatment as per the
requirements. (only plan area shall be accounted)

a) First layer of cement concrete 1:3:6 over base concrete laid to


falls and slope of minimum 1:100 and finished smooth to receive
water proofing membrane.
Sqm 555
b) Supplying, providing and applying water proofing treatment
with Membrane type water proofing methods using polymer
modified Bituminous membrane of approved makes of Atactic
Poly-Propylene (APP-4mm thk) based with UV resistant, ground
chemical resistant, high melting points, flexible and elastic with
high adhesive strength. The membrane shall be reinforced with
non woven polyester reinforcement of minimum of 180 g/sqm and
reinforced including coating with compatible primer of Bituminous
base and torch application with overlap of 100 mm wherever
required. The reinforcement provided shall be able to withstand
the traffic flow density and after construction and shall carry a
minimum guarantee period of 10 years. Cost to include laying by
loose and torching the prefabricated overlap at ends. Approved
makes (Polyplus/Fosroc/IWL/ Texsa or Equilent/Tristar intec)

Sqm 555
c) Providing and laying of 50mm screed concrete of M20 finished
smooth to receive waterproofing membrane
Sqm 555
5.3 Water Tank and Swimming Pool
a) The method consists of application of first layer of ACRYLIC
MODIFIED / POLYMER MODIFIED CEMENTITIOUS waterproof
coating either single component or two part one after base
preparation of cleaning, brushing and removal of flacky materials,
grouting the porous area with cementations grout,fixing of weep
holes,Grouting of pipe outlets etc and second layer of coating
after fixing theGeo fabric / Fibre glass cloth with proper over
lappings using the same coating when the coating is still green.
The coatings shall be applied at intervals and as per the
manufacturers specifications.

Sqm 2,101 -
b) Waterproofing treatment protection shall be in two layers in CM
1:4 of thickness 25mm for floor, 18mm for walls with water proof
admixture as per Manufacturer's specification approved by
consultants with a minimum guarantee period of 10 years.Note:
Plan area shall be the mode of measurement

a) Floors Sqm 632


b) Walls Sqm 1,469
Sub Total ( C/o to Summary) -----