Z Parsons RISK ASSESSMENT | Lusait NOTE: THIS DOCUMENT SHOULD BE ATTACHED TO THE PROCEDURE. WHEN APPROVED IT MUST BE KEPT AT THE WORK "PLACE FOR REFERENCE PURPOSES RADESCRIPTION "TRENCH EXCAVATION, BACKFILLING AND ALL ASSOCIATED WORKS OC. {US-CPIL-VEL-RSE-CV-000 Revs Roucr c1-IXED&. CALL OFF CONTRACT FOR LUSAIL ELECTRICAL NETWORK REINFORCEMENT WORKS LocaTion [tsa “[pxres 17 apm a5 (RISK ASSESSMENT-TEAM a ‘SITE REPRESENTATION NAME | estcxation SIGNATURE NAME: DESIGNATION SIGNATURE EZHIL SAM REESANR "ENVIRONMENTAL REP lye ARLENTDHAS. cvneianeen | LS — RANKUMAR MR. | sc HS OFFICER APA | Ao 0H VIL ENGINEER — — [ists surname DESIGNATION “APPROVED SIGNATURE INO VARGHESE (CONSTRUCTION MANAGER (IV) e = ‘MOHAMMED ABDUL BARI HSEMANAGER ‘QUAMUDDEVKHATA Dy FROIECT MANAGER ARUNAGIRIA PROJECT MANAGER "TRENCH EXCAVATION, BACKFILLING AND ALL ASSOCTATED WORKS DATE: 17 APRIL 2025 Y PARSONS: RISK ASSESSMENT VOuTyAsE ENGINEERING Lusail TTL | [RESIDUAL Associa covrmots. SEE et Aegan azanos pete ee, PRECAUTIONARY tS ceoystavences) RATING MEASURES pm, 1 Sean ing Sig Tel wd | Utara e+ Posey. (2/247 Erp imps pnon oe) 2/13 Eom eupmet Dom ets Inndig eee ey | cates ‘et pope pen + Pop apparel aise eign bowed | 4 File Pr atmo ak) || ‘eprom iy | YG & Co elfen by ‘Sree Gigs | |e Blpr re a yor a iced ed wih 7 Renato Galas + Damagattandi + Peso?) 7 rer PEs dost Te vom wSTT lian mars omen tn. tvs een oy Damaging exiting |, | | g | Properindicton aod THT all cme. 7 re tpn yen me Siespeiee | | | | 3 mal ra + Bimagttac + Reso Baly 3] 36/7 Follow Paper PEW, NOC fom [37 | tls suites ta oem pri ma TET ne | | ever w+ Dangle cng suntieecny vere fried se v Bean bat pie ay live tine, Electric Shock ‘excavation area must be check if ‘cong depend! waite || evn iy ld Srey onpu pee. "TRENCH EXCAVATION, BACKFILLING AND ALL ASSOCIATED WORKS ‘DATE: 17 APRIL 2023 Gp mansons Lusait RISK ASSESSMENT vourjaca ENGINEERING 7 Avoid-uderitng of te side Sel Cope Paling of Marsa sd pense a aes “Krad wdeeting of he se | TS ‘nll of exon Ensure hata spor pase Jey baie i nll de of alps prevent flo prions nda Proger warming pes should be provid in bari wit ied Ste means of cess and eps Soul! be aranged i excel test alines trench ash or ond Ctigs| apie veil afimior oF work | $ ‘eile cident ith nce vehi. | dL Proper procaine, epoul for $ Roa eating or Woking es 10 fou om concer earn with emi. Provide Peper Caution bows ‘She bat, nfo andar ic ‘tut he ompion of wo oven ofl vile may net foceed the peed Hit All ‘oven mitbe oe so Fallon tafe mage pla fu per the ASHGAL Wert see te management guide, TRENCH ENCAVATION, BACKFILLING AND ALL ASSOCIATED WORKS ‘DATE: 17 APRIL 205, - PARSONS RISK ASSESSMENT Lusail Rosine maintnce sold te ste Following cect "by pert tating of werk. IF my eet oan, shal be repo fad egupment Jobat repair Ere oper sl apropte e ings nd Fol oxee avalible esdy Tt ny vderground wes and ding concce euting of Ieshanielexcaition the activity Should be completly stopped and Soul geting proper pet and ewan fom cone dep. ‘rv proper cleanes, Spee pe concem eure, 1 Meshal Fxcnation feecble tench > aia Uadewomd + Feral iy? 2 peewee vie Fly 2 tener CObtacks fom ober | + Propety and en prope coe dames 2 othervebices + Fal of teri, ‘ipment Prope aces wd era fr 5 ele tal ies In each ‘Wom pope PES an set el by Seger dal eee i sei te check if exiting nderzeand "TRENCH EXCAVATION, gy P parsons | RISK ASSESSMEN Lusoil | 7 Ro wise Hoa Stover ecg ark Sie "Falowng Salty ‘ere its Say ey deter te ‘Salmond ecm wd pnd Ppt inte epi | | nny eta de + Move ol bry ot eae ved ke A tremens eso. Pesoneinys | 3/3) 6) 7 Prove prope sabe sang GF S| 7 bien cals 1 alin personals edad ise ares) and green ‘peo wo ling of mae | [i Selbaling Soe ie | cya wih a= VAG moveneat |» alagafoqpnen (47 €/7 Flow emit wok pew [TS one tests rertyterect |6 neater | | ‘Srl yer meted is +) Man iting 6 Damage aes {ak for proper pps wom ue fam dine sand fling the beating si shove he | (bt in tech ty slowly and l daa "TRENCH EXCAVATION, BACKFILLING AND ALL ASSOCIATED WORKS DATE: 17 APRIL 2023 VOLT RISK ASSESSMENT ENGINEERING [7 Tan a oe ea banding cigs, rovers ‘hough TBT or START Cr 16 Wariage Na + Nawal ang + Bay pa T/¥) S| Proper penanal peeve | 7 isalnion | 2 Wie 1 yng wig ape eelpmet bl be worn ‘ame dses one or wang | | | | reson sd on ep t | ore T7 | Coapaaton > Rol log acre [> Bribes Spain —~*| 8) 2) 6 oper nspecion of aspen, | Beale 2 campus + Hhoding” Haney |» Ampatton Initio operate, wih ope Obie 2 sim ‘ld eoeumes prt a any + sie Poo Sok cetaieatieet | Spee | | See lrctpe pie Wee) seuieempoparsa | oi Cee | ere rein Sr eae coors | | | | Yo Seen mt i | ‘tre around equipment when "TRENCH EXCAVATION, BACKFILLING AND ALL ASSOCIATED WORKS ‘DATE: 17 APRIL 2025 > PARSONS RISK ASSESSMENT able small igos io work Fenced al ow ‘oper don cl es tees ie, cold oom ‘vith stondtoeed wi sabe rangement, Prope PES should be wom by Promeng to wom lng ees Shs fc covered mak 1 id et expose snl ‘Work be sepeded daring sand ‘oo ing nse ing an pero Flow heat es inde har and Insructons proving 9 follow ‘ag syste coon Inpemening be fag sytem in ‘ork stan hing ineratns ‘rough diy STARRT Coe TB. ‘hag yen ne. Proving ee fe ingee chart al ork Kept ome sand by whic wih ‘hier having eninge ‘lite rei tay inst tea competion sf wek "TRENCH EXCAVATION, BACKFILLING AND ALL ASSOCIATED WORKS ‘DATE: 17 APRIL 2023 Lusail PP PARSONS RISK ASSESSMENT ‘ae convenes! fing pe Provison of adqate PPE’ Itloder N35 mae eso gunmen ‘Compute Noe |> Lom of soe of + Nombnese 2 eng darmge Coving_ of weal andl of ‘Shing cape wi so ‘eile aber en 0 be very Giecve ih eoning vee Scone {i woven in ee of te ‘Sewn il ate tpero te works, Frowoe gloves ha mina (tron vation xpi Enpnestag ene ctl meas esoot acter imied abe ‘eduction ovo ering pate Prove of ing, and Inacion “t epens Sed vores vi Infos dese Into with COVIDID |S wii) may ret to dea Trplenent a sori roel or ae aug ih ih nen Stowe Fev Segal NDS Maks, Hand enCOVID-19 Posters inact Aes aig sot | ‘DATE: 17 APR & Lusail RISK ASSESSMENT Dilay of Additional Coch Desi (enon wh speak Ahi) Provide she sign Board wih the ei of sat aod End dates of cs [ TRENCH EXCAVATION, BACKFILLING AND ALL ASSOCIATED WORKS DATE: FT APRIL DOES

You might also like