Professional Documents
Culture Documents
5.5 HRC Specificationa For Concrete and Reinforcing
5.5 HRC Specificationa For Concrete and Reinforcing
1.1 GENERAL
The drawings and specification shall be read together and the works
shall be completed in accordance with the true intent and meaning of
the same. Anything shown on the drawings and not specified or vice-
versa shall be equally binding as though included in both.
Where work is vitally necessary for the saving of life or property or for
assuring the safety of the works, such works shall be carried out by the
Contractor immediately, by day or by night. The Contractor immediately
shall advise the Engineer in writing of the full circumstances.
The Contractor must locate all services as far as is possible before work
commences. Any information shown in the drawings is given in good
faith but with no guarantee of accuracy as regards alignment,
furthermore, no guarantee is given or implied that the information
provided covers all existing services. The Contractor shall be solely
responsible for all damage done to existing services and shall make
good at his own cost all such damage without delay to the satisfaction of
the Engineer and the appropriate Controlling Authority or owner. The
Contractor shall provide all temporary support etc, necessary to allow
the continued use of all services throughout the duration of the Contract.
The whole of the work shall be carried out in such a manner as to cause
as little convenience to adjoining property owners and the public and the
Contractor will be responsible for any claims which may arise. In
particular all noisy equipment shall, where practicable, be fitted with
silencers.
The Contractor shall be responsible for seeing that all his sub-
contractors and workmen are employed on the site comply with these
requirements.
1.1.11. Dimensions
1.2.1. Preliminary
1.2.2. Scope
1.2.5. Cement
1.2.8. Additives
1.2.9. Water
Clean water from the Council water supply shall be used for making
concrete.
1.2.10. Dimensions
Check all dimensions on the site and notify the Engineer of any
inconsistencies of levels or dimensions with the plans prior to
commencing work.
1.2.11. Concrete Mixtures
The mixes shall be capable of being readily placed and well compacted
in normal placing situations without segregation. They shall result in
homogeneous concrete with the required strength, density, durability
and surface finish.
When use of any mix has been approved it shall still be the Contractor's
responsibility to ensure that the concrete satisfies the Specification at all
times.
If at any time the concrete does not satisfy the Specification, delivery
shall cease until approved corrective action has been taken.
Permission may be given only by the Engineer for higher than specified
slumps in special situations provided the water cement ratio is not
changed. Special situations shall be those where spacing between
reinforcing bars makes placement of concrete and use of a suitable
vibrator difficult.
For a ready mixed concrete plant supplying concrete for the precast
concrete the initial grading shall be either:
For the grade of concrete required, the Contractor shall submit full
details of all plant, materials, mix details and supervision, and co-
operate in conducting any tests required. Where some or all of the
details of the plant, materials and concrete proposed for the Contract
are the same as have applied on recent work, the Contractor shall
supply supporting test data from:
Plant test results obtained in the course of plant quality control, certified
by the Supervising Engineer; or, Consecutive test results from an
independent test agency with MWD Laboratory.
The interval between adding cement to the ingredients in the mixer and
discharging at the site shall not exceed 90 minutes of 300 revolutions,
whichever comes first, unless otherwise approved.
No water shall be added to the mixer after it has left the mixing plant.
Delivery dockets shall show specified strength and slump, date, time
completed, admixtures, cement content, and mix designation and time
of loading and unloading.
Vibrators shall be immersion type of frequency not less than 8000 RPM
and centrifugal force not less than 5 KN.
Vibrators shall penetrate the previous layer at about 0.5 M intervals for
periods of five to fifteen seconds and shall continue to be operated while
being slowly withdrawn. Concrete shall not be vibrated to such an extent
as to cause segregation. Sufficient reserve vibrators shall be held at the
job during concreting operations, some powered by alternative means.
Generally, however:
The area of ground floor slab poured in one pour shall be planned so
that when saw cut the area between joints shall not exceed 30 square
metres and the length of any side shall not exceed 7.5 metres.
Saw cuts, when used, shall be 6.0 mm wide and between 25% and 30%
of the slab thickness in depth and unless specifically noted otherwise
shall be washed out and filled as soon as is practicable after cutting with
Fosroc Colpor 200 or other equivalent approved product applied strictly
in accordance with the manufacturer's requirements.
If necessary, areas shall be less than those given above and shall be
poured in alternate bays, or with shrinkage gaps, with a suitable delay
before infilling is carried out.
Type A
Type B
The surface shall be kept moist for 24 hours prior to placing fresh
concrete, there shall be no separate application of grout or mortar to the
joint.
A delay until the concrete has ceased sedimentation and bleeding water
shall be allowed in walls, columns and deep beams before concreting
any member supported by them as part of the same pour. This delay will
not normally be less than half an hour or so long that penetration of the
supporting concrete by a vibrator cannot readily be accomplished. This
delay is intended to avoid a crack between supported and supporting
members caused by settlement of concrete in the latter.
1.2.17. Curing
The Contractor shall carry out all concrete testing and bear the cost for
such tests and all incidentals arising.
The frequency of testing shall be as required by Clause 9.5.2.3 of NZS
3109:1997.
Locations from which the concrete test specimens are taken shall be
recorded so that limits of the concrete sampled can be identified.
Concrete compression test sets shall consist of six specimens, three for
testing and seven days, and three for testing and 28 days.
The concrete shall be suspect if the seven day strength is less than
such value as tests have shown to be required and the Engineer may
direct that no more concrete be placed until the suspect concrete is
shown to comply with the Specification.
Traps of sufficient size for cleaning inside the formwork and/or placing
concrete shall be provided for all concrete lifts in columns and walls.
They shall not be more than 1.5m apart horizontally and 2m vertically in
walls. Wall formwork at bottom of openings over 900 mm wide shall be
removable.
Wire ties shall not be used inside the forms to tie them together.
If tie-bolts for the formwork are required, they shall be situated above
the wall. There shall be no tie-bolts passing through the concrete wall.
1.2.21. Cleaning
1.2.22. Defects
Repair of defects shall not be carried out without prior inspection and
approval.
1.2.23. Tolerances
Dry pack mortar shall be of very dry consistency such that when
squeezed in the hand to a ball it will retain its shape. The water cement
ratio shall not exceed 0.40 by weight.
1.2.26. Slabs
Unprotected slabs will not be poured if the Contractor considers that the
weather or the weather forecast is unsuitable.
The contractor shall advise the Engineer of how they will meet the
specified surface finishes and supply a 1m x 1m test panel of concrete
showing its finish for approval.
1.3.1. General
This trade is subject to all the documents of the Main Contract and to
the Preliminary and General Clauses of this Specification and is to be
read in conjunction with all other trade sections.
Read this section in conjunction with the Concrete Work Section of this
Specification.
1.3.3. Materials
Provide all supports, hangers, spacers and ties to approval where not
shown.
Plain and deformed bars shall comply with NZS 3402 and be of mild
steel and shall have a guaranteed minimum yield point of 300 MPa for
mid steel, and 430 MPa for high yield steel.
1.3.4. Designation
1.3.6. Protection
Store steel and mesh immediately upon delivery to the site, clear of the
ground and on approved racks under cover.
1.3.7. Fabrication
Rods with kinks or bends not shown on the drawings shall not be used.
All reinforcement must be kept straight between the bends shown.
Bend deformed bars once only. Any deformed bars requiring rebending
must be removed and replaced.
1.3.8. Tolerances
Tie reinforcement with not less than 1.25 mm diameter soft black iron
wire sufficiently to maintain correct relative positions.
1.3.10. Laps
Where lengths of laps are not shown, minimum lap lengths shall be as
specified for tensile splices in NZS 3109:1987.
1.3.11. Welding