You are on page 1of 105

G.R. No. 153310.

 March 2, 2004.* Relative to the construction of a condominium project called "The Salcedo Park,"
MEGAWORLD GLOBUS ASIA, INC., petitioner, vs. DSM CONSTRUCTION located at H.V. dela Costa St., Salcedo Village, Makati City, the project owner,
AND DEVELOPMENT CORPORATION and PRUDENTIAL GUARANTEE Megaworld, entered into three separate contracts with DSM Construction, namely:
AND ASSURANCE, INC., respondents. (1) Contract for Architectural Finishing Works; (2) Contract for Interior Finishing
Remedial Law; Appeals; Construction Industry Arbitration Commission Works; and (3) Contract for Supply and Installation of Kitchen Cabinets and Closets.
(CIAC); Decisions of the CIAC may be appealed to the Court of Appeals not only on The total contract price, which was initially placed at ₱300 Million, was later
questions of law but also on questions of fact and mixed questions of law and fact.— reduced to ₱240 Million when the items for kitchen cabinets and walk-in closets
Under Section 19 of Executive Order No. 1008, the CIAC’s arbitral award “shall be were deleted.4 The contracts also contain a stipulation for Retention Money, which is
final and inappealable except on questions of law which shall be appealable to the a portion of the total contract price (usually, as in this case, 10%) set aside by the
Supreme Court.” In Metro Construction, however, this Court held that, with the project owner from all approved billings and retained for a certain period to
modification of E.O. No. 1008 by subsequent laws and issuances, decisions of the guarantee the performance by the contractor of all corrective works during the
CIAC may be appealed to the Court of Appeals not only on questions of law but also defect-liability period which, in this case, is twelve months from the issuance of
on questions of fact and mixed questions of law and fact. the Taking Over Certificate of Works.5
Same; Same; Findings of fact of administrative agencies and quasi-judicial
bodies, which have acquired expertise because their jurisdiction is confined to The Letter of Award for Architectural Finishing Works provides that the period for
specific matters, are generally accorded not only respect, but finality when affirmed commencement and completion shall be twelve months, from August 1, 1997 to July
by the Court of Appeals.—Considering that the computations, as well as the 31, 1998. However, on February 21, 2000, representatives of both Megaworld and
propriety of the awards of the Arbitral Tribunal, are unquestionably factual issues DSM Construction entered into an Interim Agreement whereby they agreed on a new
that have been discussed and ruled upon by Arbitral Tribunal and affirmed by the schedule of the turnover of units from the 26th floor to the 40th floor, which was the
Court of Appeals, we cannot depart from such findings. Findings of fact of last of the contracted works.6 The consideration agreed upon in the Interim
administrative agencies and quasi-judicial bodies, which have acquired expertise Agreement was ₱53,000,000.00. Of this amount, ₱3,000,000.00 was to be released
because their jurisdiction is confined to specific matters, are generally accorded not immediately while five (5) equal installments of ₱7,000,000.00 were to be released
only respect, but finality when affirmed by the Court of Appeals. depending on the turn-over of units from the 26th floor to the 40th floor. The
remaining amount of ₱15,000,000.00 of the ₱53,000,000.00 consisted of half of the
PETITION for review on certiorari of a decision of the Court of Appeals.
retention money.7
The facts are stated in the opinion of the Court.
     Benitez, Parlade, Africa, Herrera, Parlade & Panga Law Office for Because of the differences that arose from the billings, DSM Construction filed on
petitioner. August 21, 2002, a Complaint before the CIAC for compulsory arbitration, claiming
     Garrido & Associates Law Offices for respondent DSM Construction & Dev. payment of ₱97,743,808.33 for the outstanding balance of the three construction
Corp. contracts, variation works, labor escalation, preliminaries loss and expense, earned
     Felipe Antonio B. Remollo for respondent PGAI. retention money, interests, and attorney’s fees. 8 DSM Construction alleged that it
already commenced the finishing works on the existing 12 floors on August 1, 1997,
instead of waiting for the entire 40-floor structure to be completed. At one time,
TINGA, J.:
DSM Construction worked with other contractors whose work often depended on,
interfered or conflicted with said contractors. Delay by a trade contractor would start
Before this Court is a Petition for Review on Certiorari assailing the Decision dated a chain reaction by delaying or putting off other works.9
February 14, 2002, of the Court of Appeals in CA G.R. SP No. 67432,1 which
affirmed the Decision2 of the Construction Industry Arbitration Commission
Interposing mainly the defense of delay in the turn-over of units and the poor quality
(CIAC)3 dated September 8, 2001, in CIAC Case No. 22-2000 finding petitioner
of work of DSM Construction, Megaworld filed its Answer and made a counter-
Megaworld Globus Asia, Inc., liable to DSM Construction in the amount of
claim for loss of profits, liquidated damages, costs of take-over and rectification
₱62,760,558.49.
works, administration expenses, interests, attorney’s fees and cost of arbitration in
the total amount of ₱85,869,870.28.10
The antecedents are as follows:

1
Prudential Guarantee and Assurance, Inc. (PGAI), which issued a Performance The Court of Appeals denied the motion for reconsideration in its Resolution25 dated
Bond to guarantee Megaworld’s contractual obligation on the project, was impleaded April 25, 2002. While acknowledging that the findings of fact of the CIAC may be
by Megaworld as a third-party respondent.11 questioned in line with Metro Construction,26 the appellate court stressed that the
tribunal’s decision is not devoid of factual or evidentiary support.
On March 28, 2001, the parties signed before the members of the Arbitral Tribunal
the Terms of Reference12 (TOR) where they setforth their admitted facts,13 respective Megaworld elevated the case to this Court through the present Petition, advancing
documentary evidence,14 summary of claims15 and issues to be resolved by the the following grounds, viz:
tribunal.16 After presenting their evidence in the form of affidavits of witnesses, 17 the
parties submitted their respective memoranda/draft decisions.18 I

On October 19, 2001, the Arbitral Tribunal promulgated its Decision dated THE COURT OF APPEALS IN EFFECT REFUSED TO HEED THE RULE LAID
September 28, 2001, awarding ₱62,760,558.49 to DSM Construction and DOWN BY THIS Honorable Court in the Metro Construction, INC. vs. Chatham
₱9,473,799.46 to Megaworld.19 properties, inc. case when it dismissed mgai’s petition despite the grave questions of
both fact and law brought before it by the petitioner.
Megaworld filed a Petition for Review under Rule 43 of the Rules of Civil Procedure
before the Court of Appeals. It faulted the Arbitral Tribunal for finding that DSM II
Construction achieved a 95.56% level of accomplishment as of February 14, 2000;
for absolving DSM Corporation of the consequences of the alleged delay in the the finding of the appellate court that the decision was based on substantial evidence
performance of its work; and for ruling that DSM Construction had complied with adduced by both parties sans any review of the record or of attachments of dsm is
the contractual requirements for filing requests for extension. Megaworld likewise fatally wrong, such finding being merely an adoption of the tribunal’s decision
questioned the sufficiency of evidence to justify the awards for liquidated damages; which, as earlier pointed out, was not supported by competent, credible and
the balance of the contract price; the balance of amounts payable on account of admissible evidence.
the Interim Agreement of February 21, 2000; the amount of ₱6,596,675.55 for
variation orders; the amount of ₱29,380,902.35 as reimbursement for III
preliminaries/loss and expense; the amount of ₱413,041.52 for labor escalation costs;
and the balance of the retention money in the amount of ₱14,700,000.00 despite its
the court of appeals seriously erred in giving blanket approval of all the unfounded
award of ₱11,820,000.00 under the February 21, 2000, Interim Agreement. Finally,
claims and conclusions of the ciac arbitral tribunal’s SEPTEMBER 28, 2001
Megaworld claimed that the Arbitral Tribunal erred in denying its claim for
decision to the detriment of petitioner’s cardinal right to due process, particularly to
liquidated damages, expenses incurred for the cost of take-over work, administrative
its right to administrative due process.
expenses, and its recourse against PGAI and for limiting its recovery for rectification
work to only ₱9,197,863.55.20
IV
On February 14, 2002, the Court of Appeals promulgated its Decision21 affirming
that of the Arbitral Tribunal. The court pointed out that only questions of law may be the findings and conclusions made by a highly partisan ciac arbitral tribunal have no
raised before it on appeal from an award of the CIAC.22 That pronouncement basis on the evidence on record. hence, the exception to the rule that only questions
notwithstanding, the Court of Appeals proceeded to review the decision of the of law may be brought to the honorable court is applicable in the case AT bar. 27
Arbitral Tribunal and found the same to be amply supported by evidence. 23
Although Megaworld, at the outset,28 intimates that the case involves grave questions
Megaworld sought reconsideration of the Court of Appeals’ Decision arguing, of both fact and law, a cursory reading of the Petition reveals that, except for the
among other things, that the appellate court ignored the ruling in Metro amorphous advertence to administrative due process, the alleged errors
Construction, Inc. v. Chatham Properties24 that the review of the CIAC award may fundamentally involve only questions of fact. Megaworld’s plea for the Court to pass
involve either questions of fact, law, or both fact and law. upon the findings of facts of the Arbitral Tribunal, which were upheld by the
appellate court, must perforce fail.

2
To jumpstart its bid, Megaworld exploits the Court of Appeals’ pronouncement in the 31st floor while the 32nd to the 34th floors were only 60% completed.35 Megaworld
the assailed decision that only questions of law may be raised before it from an insisted, therefore, that the level of accomplishment was nowhere near 90%.
award of the CIAC. The appellate court did so, Megaworld continues, in evident
disregard of Metro Construction.29 DSM Construction countered that Megaworld, in claiming a level of accomplishment
of only 90%, contradicted its own Project Manager, TCGI,36 which came up with a
Under Section 19 of Executive Order No. 1008,30 the CIAC’s arbitral award "shall be different percentage of accomplishment that are notably higher than Megaworld’s
final and inappealable except on questions of law which shall be appealable to the computation.37
Supreme Court." In Metro Construction, however, this Court held that, with the
modification of E.O. No. 1008 by subsequent laws and issuances,31 decisions of the In resolving this issue, the Arbitral Tribunal relied on the computation of Davis
CIAC may be appealed to the Court of Appeals not only on questions of law but also Langdon & Seah (DLS), the project’s independent surveyor,38 which found the level
on questions of fact and mixed questions of law and fact. of accomplishment as of February 14, 2000, to be 95.56%. DLS’s computation is
recited in Exhibit "NN",39 thus:
Of such subsequent laws and issuances, only Section 1,32 Rule 43 of the 1997 Rules
of Civil Procedure expressly mentions the CIAC. While an argument may be made
that procedural rules cannot modify substantive law, adding in support thereof that Architectural Finishing :40
Section 1, Rule 43 has increased the jurisdiction of the Court of Appeals by
The 24th Progress Billing
expanding the scope of review of CIAC awards, or that it contravenes the rationale
evaluated by DLS covering the
for arbitration, extant from the record is the fact that no party raised such argument.
period November 15, 1999 to
Consequently, the matter need not be delved into. Php213,658,888.7741Php223,456,756.684
December 15, 1999 over the
Contract Price for Architectural
In any case, the attack against the merits of the Court of Appeals’ Decision must fail. Finishing Works.
Although Metro Construction may have been unbeknownst to the appellate court
when it promulgated its Decision, the fact remains that, as noted therein,33 it Kitchen Cabinets & Bedroom Closets:43
reviewed the findings of facts of the CIAC and ruled that the findings are amply
supported by the evidence. The 9th Progress Billing evaluated
by DLS covering the period
The Court of Appeals is presumed to have reviewed the case based on December 1, 1999 to December 9,
Php26,228,091.7344Php28,556,915.174
the Petition and its annexes, and weighed them against the Comment of DSM 1999 over the contract price for
Construction and the Decision of the Arbitral Tribunal to arrive at the conclusion that Kitchen Cabinet and Bedroom
the said Decision is based on substantial evidence. In administrative or quasi-judicial Closet.
bodies like the CIAC, a fact may be established if supported by substantial evidence
or that amount of relevant evidence which a reasonable mind might accept as Interior Finishing Works:46
adequate to justify a conclusion.34
The 13th Progress Billing
evaluated by DLS covering the
The tenability of the assailed Decision is clear from the following discussion of the period January 8, 2000 to February
arguments raised by Megaworld before the Court of Appeals which significantly are Php49,383,114.6747Php50,685,416.554
7, 2000 for the Interior Finishing
the same arguments it has raised before this Court. Works over the contract price for
Interior Finishing Work.
Issue of Accomplishment Level
Php213,658,888 Php26,228,091 Php49,383,114 289,270,295.17=9
Megaworld contested the finding of 95.56% level of accomplishment by the Arbitral .77 + .72 + .67 = 5.56%
Tribunal, alleging that the receipts DSM Construction issued for payments under
the Interim Agreement show that the latter only achieved 90% accomplishment up to Php223,456,756 Php Php50,685,416 302,699,097.40

3
The Arbitral Tribunal held that Section 2.01 presupposes that on the date of
.68 28,556,915.17 .55
possession by DSM Construction of the work premises, the preceding contractor had
already left the same.51 The tribunal explained that the delay incurred by other trade
Clearly, thus, CIAC’s finding that the level of accomplishment of DSM Construction contractors also resulted in the delay of the work of DSM Construction.
as of February 12, 2002, stood at 95.56% was affirmed by the Court of Appeals
because it is supported by substantial evidence. It also pointed out that under Section 5.3 (1)52 of the Interim
Agreement,53 Megaworld is required to complete and turn over to DSM Construction
The Court of Appeals also noted that the Arbitral Tribunal did not give due course to preceding works for the latter to complete their works in accordance with the
all of DSM Construction’s claims. Indeed, the Arbitral Tribunal rejected the Revised Work Schedule. Section 5.3 (1), the Arbitral Tribunal noted, even allows
construction company’s demand for payment for subsequent works done after DSM Construction to recover losses incurred on account of the standby time of
February 12, 2000, because Exhibit "OO," on which DSM Construction’s demand DSM’s personnel/manpower or workers mobilized while Megaworld is not ready to
was based, does not bear any mark that it had been received by Megaworld. Thus, turn over the preceding works. The Arbitral Tribunal further held that, in accordance
the Arbitral Tribunal concluded that subsequent works up to September 22, 2000, with Section 5.3 (2)54of the Interim Agreement, DSM Construction was entitled to an
when DSM Construction supposedly stopped working on the project, had not been extension of time corresponding to the number of days of delay reckoned from the
established.49 time the preceding work item or area should have been turned over to DSM
Construction. Consequently, such delay, which is not exclusively imputable to DSM
This Court observes that between the two contrasting claims of Megaworld and DSM Construction, negates the claim for liquidated damages by Megaworld. 55
Construction on the percentage of work accomplishment, the Arbitral Tribunal
instead accorded weight to the assessment of DLS which is the project surveyor. In affirming the Arbitral Tribunal’s disposition of the issues of delay and payment of
Apart from being reasonable, DLS’s evaluation is impartial. Thus, as correctly liquidated damages, the appellate court noted that the Arbitral Tribunal narrated the
pointed out by the Arbitral Tribunal, DLS rejected DSM Construction’s 99% claims and defenses of both DSM Construction and Megaworld before making an
accomplishment claim when it limited its evaluation to only 95.56%. evaluation thereof and arriving at its conclusion.56 Clearly, the evidence and
arguments were carefully weighed to justify the said disposition.
Issues of Delay and Liquidated Damages
The Tribunal’s finding that the project had already been delayed even before DSM
Next, Megaworld attributed the delay in the completion of the construction project Construction commenced its work is borne out by the evidence. In his letter, Exhibit
solely to DSM Construction. The latter countered that among the causes of delay was X-2,57 Project Management Consultant Eduardo C. Arrojado, conceded that the
the lack of coordination among trade contractors and the absence of a general previous contractors had delayed the project, at the same time faulting DSM
contractor.50 Although the contract purportedly contains a provision for the Construction for incurring its own delay. Furthermore, the work of DSM
coordination of trade contractors, the lack of privity among them prevented Construction pertaining as it did to the architectural and interior finishing stages as
coordination such that DSM Construction could not require compliance on the part well as the supply and installation of kitchen cabinets and closets, obviously related
of the other trade contractors. to the final details and completion stage of the project. Thus, commencement of its
task had to depend on the turn over of the complete work of the prior contractors.
Hence, the delay of the previous contractors resulted in the delay of DSM
The Arbitral Tribunal decided this question by turning to Section 2.01 of the General
Construction’s work.
Conditions of the Contract, which states:
Issues of the Contract Price Balance and Retention Money
2.01 SITE, ACCESS & WORKS

Megaworld also questioned the Arbitral Tribunal’s awards of ₱7,129,825.19


The Contractor shall accept the Site as found on the date for possession and at their
own expense clear the site of any debris which may have been left by the preceding corresponding to the balance of the contract price, and ₱11,820,000.00 pursuant to
occupants/contractors. the Interim Agreement.58 Megaworld alleged that DSM Construction was no longer
entitled to the balance of the contract price and the retention money after the latter
received payments pursuant to the Interim Agreement in the amounts of
₱5,444,553.18 for the 26th to the 28th floors, another ₱5,444,553.18 for the 29th to the
4
31st floors at a 90% completion rate, and ₱4,161,818.18 for the 32nd to the 34thfloors but, of this claim, the Arbitral Tribunal only awarded ₱6,686,675.55 in line with the
which were 60% completed. Megaworld also contended that since it spent more evaluation of DLS.
money to complete the scope of work of DSM Construction, the latter was no longer
entitled to any of the balance. Megaworld conceded that DSM Construction performed additional works to the
extent of ₱5,036,252.81. However, Megaworld claimed that since it incurred
On the other hand, DSM Construction argued that the award was justified in view of expenses when it hired another trade contractor to take over the works left
the failure of Megaworld to controvert the amount of ₱7,129,825.19 included in the uncompleted by DSM Construction, the latter lost its right to claim such amount
Account Overview of DLS. DSM Construction also emphasized that it was not especially since DSM Construction did not comply with the documentation when
claiming the entire ₱53 Million under the Interim Agreement but only the amount claiming variation works.65
corresponding to the actual work done. Even based on DLS’s computation, a total of
₱11,820,000.00 of retention money is still unpaid out of the 50% agreed to be DSM Construction asserted that the Arbitral Tribunal, in fact, should have awarded
released under the Interim Agreement (₱15,000,000.00 less ₱3,180,000.00 retention ₱26,208,639.00 instead of limiting the award to only ₱6,686,675.55 because it was
money or ₱11,820,000.00 for the paid billings).59 not even disputed that variation works were performed. It also contended that it
cannot be faulted for the lack of documentation because the fault lay on
The Arbitral Tribunal ruled that the balance claimed under the three contracts was Megaworld’s project manager who failed to forward the variation orders to DLS.66
based on what DSM Construction had actually accomplished less the payments it had
previously received. Considering that the remaining works which were performed by The Arbitral Tribunal ruled in favor of DSM Construction, holding that there was
another trade contractor, Deticio and Isabedra Builders, were paid directly by enough evidence to prove that the contractor made a request for change or variation
Megaworld, no other cost for work accomplished in the Interim Agreement is due orders. The Arbitral Tribunal also found the testimony of Engineer Eduardo C.
DSM Construction except the retention money of ₱11,820,000.00.60 Arrojado convincing, factual and balanced despite Megaworld’s attempt to discredit
him. However, while the amount claimed for variation works was ₱26,208,639.00,
The Court of Appeals affirmed the award of the Arbitral Tribunal regarding the the Arbitral Tribunal limited the awarded to only ₱6,686,675.5567 since a closer
balance of the contract price of ₱7,129,825.19 and the retention money of scrutiny of the other items indicated that some works were not performed. 68
₱11,820,000.00 to DSM Construction. The Court of Appeals noted that the Arbitral
Tribunal again narrated the claims and defenses of both DSM Construction and The appellate court upheld the award of the Arbitral Tribunal because the award was
Megaworld before arriving at its conclusion. The appellate court further stated that based not only on the documentary exhibits prepared by DLS but on the testimony of
the mere fact that the tribunal did not award the whole amount claimed by DSM Engineer Eduardo C. Arrojado, as well.69
Construction (₱12,820,000.00) and instead awarded only ₱11,820,000.00 belies
Megaworld’s allegation that the tribunal adopted "hook, line and sinker" DSM This Court is convinced that payments for variation works is due. Undoubtedly,
Construction’s claims.61 variation works were performed by DSM Construction. This was confirmed by
Engineer Eduardo C. Arrojado who testified that he recommended the payment for
This Court finds the award of the balance of the contract price of ₱7,129,825.20 substantial additional works to DSM Construction. He further stated that since time
justified in view of DLS’ explanation in Exhibit MM-362 that the amount of was of the essence in the completion of the project, there were variation orders which
₱7,129,825.20 represented the unpaid billing for architectural, interior and kitchen were performed without the prior approval of the owner. However, he explained that
billings before Megaworld and DSM Construction drafted the Interim Agreement. this was a common construction practice. Finally, he stated that he agreed with the
evaluation of DLS.70
Issue of Variation Works 
The testimony justified the Arbitral Tribunal’s reliance on the evaluation made by
Megaworld also disputed before the Court of Appeals the ₱6,686,675.55  award by
63 DLS which limited the claim for variation works to ₱6,596,675.55.
the Arbitral Tribunal for variation works. Variation works consist of the addition,
omission or alteration to the kind, quality or quantity of the works.64 DSM Issue of Preliminaries/Loss and Expense
Construction originally claimed a total of ₱26,208,639.00 for variation works done

5
Megaworld also disputed the award of ₱29,380,902.35 for preliminaries/losses and Although the Arbitral Tribunal ruled that DSM Construction was entitled to claim for
expense. preliminaries, the award was not based on the claim of DSM Construction but on the
evaluation made by DLS.
The provision for preliminaries/loss and expense in the contract assumes a direct loss
and/or expense incurred in the regular progress of work for which the contractor The foregoing disquisition adequately shows that the evidence on record supports the
would not be reimbursed under any other provision of the contract.71 DSM findings of facts of the Arbitral Tribunal on which the Court of Appeals based its
Construction’s claim for preliminaries/loss and expense in the amount of decision. In fact, although not all the exhibits in the Arbitral Tribunal were presented
₱36,603,192.82 covered the loss and expense incurred on payroll, equipment rental, before the Court of Appeals, the record of the appellate court contains the operative
materials and site clearing on account of such factors as delay in the execution of the facts and the substance of said exhibits, thus enabling the intelligent disposition of
works for causes not attributable to DSM Construction.72 the issues presented before it. This Court went over all the records, including the
exhibits, to ascertain whether the appellate court missed any crucial point. It did not.
Megaworld refused to recognize DSM Construction’s claim because the latter
allegedly failed to comply with Clause 6.16 of the Conditions of Contract, which The alleged undue favor accorded by the Arbitral Tribunal to DSM Construction is
imposes a two-month deadline for submission of claims for preliminaries reckoned belied by the fact that the Arbitral Tribunal did not grant all of DSM Construction’s
from "the happening of the event giving rise to the loss and expense."73 DSM claims. In majority of DSM Construction’s claims, the Arbitral Tribunal awarded
Construction, however, argued that the documentary evidence shows that out of the amounts lower than what DSM Construction demanded. The Arbitral Tribunal also
four claims for preliminaries, only one (Exhibit MM-5with an evaluation of granted some of Megaworld’s claims.80
₱17,552,722.47), covering the period August 1, 1998 to April 1999, was submitted
beyond the two-months requirement.74 DSM Construction also pointed out that the Neither did the Court of Appeals merely "swallow hook, line and sinker" the award
two-month requirement for this claim was waived by Megaworld through DLS when of the Arbitral Tribunal. While the appellate court affirmed the decision of the
the latter recognized the validity of claims by coming up with an evaluation of Arbitral Tribunal, it also ruled in favor of Megaworld when it limited DSM
₱17,552,722.47 for the period covered in Exhibit MM-5.75 Construction’s lien to only six units instead of all the condominium units to which
DSM was entitled under the Contract, rationalizing that the ₱62 Million award can
The Arbitral Tribunal ruled that DSM Construction was entitled to extended be covered by the value of the six units of the condominium project.81
preliminaries considering that delay was not attributable to DSM Construction. The
Arbitral Tribunal observed that Megaworld did not present evidence to refute the Considering that the computations, as well as the propriety of the awards of the
claim for extended preliminaries which were previously evaluated by DLS. Arbitral Tribunal, are unquestionably factual issues that have been discussed and
However, after assessing the two previous evaluations by DLS, the tribunal ruled that ruled upon by Arbitral Tribunal and affirmed by the Court of Appeals, we cannot
the claims for hauling and disposal and cleaning and clearing of debris should not be depart from such findings. Findings of fact of administrative agencies and quasi-
included in the extended preliminaries. Hence, the Arbitral Tribunal reduced the judicial bodies, which have acquired expertise because their jurisdiction is confined
amount of ₱44,051.62 from the claim of ₱2,655,879.89 per Exhibit "MM-7," and to specific matters, are generally accorded not only respect, but finality when
₱3,883,309.54 from the claim of ₱5,651,235.24 per Exhibit "MM-8," such amounts affirmed by the Court of Appeals.82
being unnecessary.76
Megaworld, however, adamantly contends that the present case constitutes an
The appellate court affirmed the award, stressing the fact that the Arbitral Tribunal exception to the above rule because: (1) there is grave abuse of discretion in the
denied some of the claims which it did not find valid.77 appreciation of facts; (2) the judgment is premised on misapprehension of facts; and,
(3) the findings of fact of the Court of Appeals is premised on the supposed absence
DSM Construction’s entitlement to the payment for preliminaries was explained by of evidence and is contradicted by the evidence on record.83
Engineer Eduardo C. Arrojado to be the necessary result of the extension of the
contract between DSM Construction and Megaworld.78 Notably, majority of the We disagree. None of these flaws appear in this case. Grave abuse of discretion
claims of DSM Construction was reduced by the Arbitral Tribunal on the basis means the capricious or whimsical exercise of judgment that is so patent and gross as
of Exhibit MM-479 or the Summary of Variation Order Status Report prepared by to amount to an evasion of positive duty or a virtual refusal to perform a duty
DLS. enjoined by law, or to act at all in contemplation of law, as where the power is
exercised in an arbitrary and despotic manner by reason of passion or hostility.84 No
6
abuse of discretion was established by Megaworld. On the contrary, what is apparent which shall be appealable to the Supreme Court.” In Hi-Precision Steel Center, Inc.
is Megaworld’s effort to attribute grave abuse of discretion to the Arbitral Tribunal v. Lim Kim Steel Builders, Inc., 228 SCRA 397 (1993), we explained raison d’
simply because of the unfavorable judgment against it. Megaworld’s assertion that etre for the rule on finality of the CIAC’s arbitral award in this wise: Voluntary
there was misapprehension of facts and that the evidence is insufficient to support arbitration involves the reference of a dispute to an impartial body, the members of
the decision is also untenable. The Decisions of the Arbitral Tribunal and the Court which are chosen by the parties themselves, which parties freely consent in advance
of Appeals adequately explain the reasons therefor and are supported by substantial to abide by the arbitral award issued after proceedings where both parties had the
evidence. opportunity to be heard. The basic objective is to provide a speedy and inexpensive
method of settling disputes by allowing the parties to avoid the formalities, delay,
Likewise unmeritorious is Megaworld’s assertion that it was deprived of expense and aggravation which commonly accompany ordinary litigation, especially
administrative due process. The Arbitral Tribunal considered the arguments and the litigation which goes through the entire hierarchy of courts. Executive Order No.
evidence submitted by both parties. That it accorded greater weight to DSM 1008 created an arbitration facility to which the construction industry in the
Construction’s evidence, by itself, does not constitute a denial of due process. Philippines can have recourse. The Executive Order was enacted to encourage the
early and expeditious settlement of disputes in the construction industry, a public
WHEREFORE, the Petition is DENIED. The Decision dated February 14, 2001, of policy the implementation of which is necessary and important for the realization of
the Court of Appeals is AFFIRMED. The Temporary Restraining Order issued by national development goals. Aware of the objective of voluntary arbitration in the
this Court on July 12, 2002, is hereby LIFTED. Costs against Petitioner. labor field, in the construction industry, and in any other area for that matter, the
Court will not assist one or the other or even both parties in any effort to subvert or
defeat that objective for their private purposes. The Court will not review the factual
SO ORDERED. findings of an arbitral tribunal upon the artful allegation that such body had
“misapprehended the facts” and will not pass upon issues which are, at bottom,
issues of fact, no matter how cleverly disguised they might be as “legal questions.”
The parties here had recourse to arbitration and chose the arbitrators themselves; they
G.R. No. 187521. March 14, 2012.* must have had confidence in such arbitrators. x x x.
F.F. CRUZ & CO., INC., petitioner, vs. HR CONSTRUCTION CORP., Questions of Law; A question of law arises when there is doubt as to what the
respondent. law is on a certain state of facts, while there is a question of fact when the doubt
Construction Contracts; Construction Industry Arbitration Commission arises as to the truth or falsity of the alleged facts.—A question of law arises when
(CIAC); Jurisdiction; Arbitration; Appeals; Executive Order (E.O.) No. 1008 vests there is doubt as to what the law is on a certain state of facts, while there is a
upon the Construction Industry Arbitration Commission (CIAC) original and question of fact when the doubt arises as to the truth or falsity of the alleged facts.
exclusive jurisdiction over disputes arising from, or connected with, contracts For a question to be one of law, the same must not involve an examination of the
entered into by parties involved in construction in the Philippines; The arbitral probative value of the evidence presented by the
award of Construction Industry Arbitration Commission (CIAC) shall be final and 304
inappealable except on questions of law which shall be appealable to the Supreme 304 SUPREME COURT REPORTS ANNOTATED
Court.—Executive Order (E.O.) No. 1008 vests upon the CIAC original and
F.F. Cruz & Co., Inc. vs. HR Construction Corp.
exclusive jurisdiction
litigants or any of them. The resolution of the issue must rest solely on what
_______________
the law provides on the given set of circumstances. Once it is clear that the issue
**  Designated additional member per Special Order No. 1207 dated February
invites a review of the evidence presented, the question posed is one of fact.
23, 2012.
Waivers; Waiver is defined as “a voluntary and intentional relinquishment or
* SECOND DIVISION.
abandonment of a known existing legal right, advantage, benefit, claim or privilege,
303
which except for such waiver the party would have enjoyed; the voluntary
VOL. 668, MARCH 14, 2012 303 abandonment or surrender, by a capable person, of a right known by him to exist,
F.F. Cruz & Co., Inc. vs. HR Construction Corp. with the intent that such right shall be surrendered and such person forever deprived
over disputes arising from, or connected with, contracts entered into by parties of its benefit; or such conduct as warrants an inference of the relinquishment of such
involved in construction in the Philippines. Under Section 19 of E.O. No. 1008, the right; or the intentional doing of an act inconsistent with claiming it.”—In People of
arbitral award of CIAC “shall be final and inappealable except on questions of law the Philippines v. Donato, 198 SCRA 130 (1991), this Court explained the doctrine

7
of waiver in this wise: Waiver is defined as “a voluntary and intentional PETITION for review on certiorari of the decision and resolution of the Court of
relinquishment or abandonment of a known existing legal right, advantage, benefit, Appeals.
claim or privilege, which except for such waiver the party would have enjoyed; the    The facts are stated in the opinion of the Court.
voluntary abandonment or surrender, by a capable person, of a right known by him to   Vincent S. Tagoc for petitioner.
exist, with the intent that such right shall be surrendered and such person forever   Rodolfo B. Ta-asan for respondent.
deprived of its benefit; or such conduct as warrants an inference of the REYES, J.:
relinquishment of such right; or the intentional doing of an act inconsistent with This is a petition for review on certiorari under Rule 45 of the Rules of Court
claiming it.” As to what rights and privileges may be waived, the authority is settled: filed by petitioner F.F. Cruz & Co., Inc.
x x x the doctrine of waiver extends to rights and privileges of any character, and, 306
since the word ‘waiver’ covers every conceivable right, it is the general rule that a 306 SUPREME COURT REPORTS ANNOTATED
person may waive any matter which affects his property, and any alienable
F.F. Cruz & Co., Inc. vs. HR Construction Corp.
right or privilege of which he is the owner or which belongs to him or to which
he is legally entitled, whether secured by contract, conferred with statute, or (FFCCI) assailing the Decision1 dated February 6, 2009 and Resolution2 dated April
guaranteed by constitution, provided such rights and privileges rest in the 13, 2009 issued by the Court of Appeals (CA) in CA-G.R. SP No. 91860.
individual, are intended for his sole benefit, do not infringe on the rights of
others, and further provided the waiver of the right or privilege is not forbidden The Antecedent Facts
by law, and does not contravene public policy; and the principle is recognized that
everyone has a right to waive, and agree to waive, the advantage of a law or rule Sometime in 2004, FFCCI entered into a contract with the Department of Public
made solely for the benefit and protection of the individual in his private capacity, if Works and Highways (DPWH) for the construction of the Magsaysay Viaduct,
it can be dispensed with and relinquished without infringing on any public right, and known as the Lower Agusan Development Project. On August 9, 2004, FFCCI, in
without detriment to the community at large. x x x.305 turn, entered into a Subcontract Agreement 3with HR Construction Corporation
(HRCC) for the supply of materials, labor, equipment, tools and supervision for the
VOL. 668, MARCH 14, 2012 305
construction of a portion of the said project called the East Bank Levee and Cut-Off
F.F. Cruz & Co., Inc. vs. HR Construction Corp. Channel in accordance with the specifications of the main contract.
Reciprocal Obligations; Rescission; While the right to rescind reciprocal The subcontract price agreed upon by the parties amounted to P31,293,532.72.
obligations is implied, that is, that such right need not be expressly provided in the Pursuant to the Subcontract Agreement, HRCC would submit to FFCCI a monthly
contract, nevertheless the contracting parties may waive the same.—The right of progress billing which the latter would then pay, subject to stipulated deductions,
rescission is statutorily recognized in reciprocal obligations. Article 1191 of the Civil within 30 days from receipt thereof.
Code pertinently reads: Art. 1191. The power to rescind obligations is implied in The parties agreed that the requests of HRCC for payment should include
reciprocal ones, in case one of the obligors should not comply with what is progress accomplishment of its completed works as approved by FFCCI.
incumbent upon him. The injured party may choose between the fulfillment and the Additionally, they agreed to conduct a joint measurement of the completed works of
rescission of the obligation, with the payment of damages in either case. He may also HRCC together with the representative of DPWH and consultants to arrive at a
seek rescission, even after he has chosen fulfillment, if the latter should become common quantity.
impossible. The court shall decree the rescission claimed, unless there be just cause Thereafter, HRCC commenced the construction of the works pursuant to the
authorizing the fixing of a period. This is understood to be without prejudice to the Subcontract Agreement.
rights of third persons who have acquired the thing, in accordance with Articles 1385 _______________
and 1388 and the Mortgage Law. The rescission referred to in this article, more 1 Penned by Associate Justice Romeo F. Barza, with Associate Justices Josefina
appropriately referred to as resolution is on the breach of faith by the defendant Guevara-Salonga and Arcangelita M. Romilla-Lontok, concurring; Rollo, pp. 47-69.
which is violative of the reciprocity between the parties. The right to rescind, 2 Id., at p. 78.
however, may be waived, expressly or impliedly. While the right to rescind 3 Id., at pp. 85-92.
reciprocal obligations is implied, that is, that such right need not be expressly 307
provided in the contract, nevertheless the contracting parties may waive the same. VOL. 668, MARCH 14, 2012 307
Contrary to the respective dispositions of the CIAC and the CA, we find that HRCC
had no right to rescind the Subcontract Agreement in the guise of a work stoppage, F.F. Cruz & Co., Inc. vs. HR Construction Corp.
the latter having waived such right. On September 17, 2004, HRCC submitted to FFCCI its first progress billing in
the amount of P2,029,081.59 covering the construction works it completed from
8
August 16 to September 15, 2004.4 However, FFCCI asserted that the DPWH was halted the construction of the subcontracted project after taking its Christmas break
then able to evaluate the completed works of HRCC only until July 25, 2004. Thus, on December 18, 2004.
FFCCI only approved the gross amount of P423,502.88 for payment. Pursuant to the On March 7, 2005, HRCC, pursuant to the arbitration clause in the Subcontract
Subcontract Agreement, FFCCI deducted from the said gross amount P42,350.29 for Agreement, filed with the Construction Industry Arbitration Commission (CIAC) a
retention and P7,700.05 for expanded withholding tax leaving a net payment in the Complaint11 against FFCCI praying for the payment of the following: (1) overdue
amount of P373,452.54. This amount was paid by FFCCI to HRCC on December 3, obligation in the reduced amount of P4,096,656.53 as of December 15, 2004 plus
2004.5 legal interest; (2) P1,500,000.00 as attorney’s fees; (3) P80,000.00 as acceptance fee
FFCCI and the DPWH then jointly evaluated the completed works of HRCC for and representation expenses; and (4) costs of litigation.
the period of July 26 to September 25, 2004. FFCCI claimed that the gross amount In its Answer,12 FFCCI claimed that it no longer has any liability on the
due for the completed works during the said period was P2,008,837.52. From the Subcontract Agreement as the three payments
said gross amount due, FFCCI deducted therefrom P200,883.75 for retention and _______________
P36,524.07 for expanded withholding tax leaving amount of P1,771,429.45 as the 9  Id., at p. 113.
approved net payment for the said period. FFCCI paid this amount on December 21, 10 Id., at p. 96.
2004.6 11 Id., at pp. 79-84.
On October 29, 2004, HRCC submitted to FFCCI its second progress billing in 12 Id., at pp. 97-105.
the amount of P1,587,760.23 covering its completed works from September 18 to 25, 309
2004.7 FFCCI did not pay the amount stated in the second progress billing, claiming VOL. 668, MARCH 14, 2012 309
that it had already paid HRCC for the completed works for the period stated therein.
F.F. Cruz & Co., Inc. vs. HR Construction Corp.
On even date, HRCC submitted its third progress billing in the amount of
P2,569,543.57 for its completed works from September 26 to October 25, it made to HRCC, which amounted to P3,472,521.86, already represented the amount
2004.8 FFCCI did not immedi- due to the latter in view of the works actually completed by HRCC as shown by the
_______________ survey it conducted jointly with the DPWH. FFCCI further asserted that the delay in
4 Id., at p. 93. the payment processing was primarily attributable to HRCC inasmuch as it presented
5 Id., at p. 109. unverified work accomplishments contrary to the stipulation in the Subcontract
6 Id., at p. 111. Agreement regarding requests for payment.
7 Id., at p. 94. Likewise, FFCCI maintained that HRCC failed to comply with the condition
8 Id., at p. 95. stated under the Subcontract Agreement for the payment of the latter’s progress
308 billings, i.e. joint measurement of the completed works, and, hence, it was justified
in not paying the amount stated in HRCC’s progress billings.
308 SUPREME COURT REPORTS ANNOTATED On June 16, 2005, an Arbitral Tribunal was created composed of Engineer
F.F. Cruz & Co., Inc. vs. HR Construction Corp. Ricardo B. San Juan, Joven B. Joaquin and Attorney Alfredo F. Tadiar, with the
ately pay the amount stated in the third progress billing, claiming that it still had to latter being appointed as the Chairman.
evaluate the works accomplished by HRCC. In a Preliminary Conference held on July 5, 2005, the parties defined the issues
On November 25, 2004, HRCC submitted to FFCCI its fourth progress billing in to be resolved in the proceedings before the CIAC as follows:
the amount of P1,527,112.95 for the works it had completed from October 26 to 1. What is the correct amount of [HRCC’s] unpaid progress billing?
November 25, 2004. 2. Did [HRCC] comply with the conditions set forth in subparagraph 4.3 of
Subsequently, FFCCI, after it had evaluated the completed works of HRCC from the Subcontract Agreement for the submission, evaluation/processing
September 26 to November 25, 2004, approved the payment of the gross amount of and release of payment of its progress billings?
P1,505,570.99 to HRCC. FFCCI deducted therefrom P150,557.10 for retention and 3. Did [HRCC] stop work on the project?
P27,374.02 for expanded withholding tax leaving a net payment of P1,327,639.87, 3.1 If so, is the work stoppage justified?
which amount was paid to HRCC on March 11, 2005.9 3.2 If so, what was the percentage and value of [HRCC’s] work
Meanwhile, HRCC sent FFCCI a letter10 dated December 13, 2004 demanding accomplishment at the time it stopped work on the project?310
the payment of its progress billings in the total amount of P7,340,046.09, plus 310 SUPREME COURT REPORTS ANNOTATED
interests, within three days from receipt thereof. Subsequently, HRCC completely
F.F. Cruz & Co., Inc. vs. HR Construction Corp.

9
4. Who between the parties should bear the cost of arbitration or in what On clarificatory questioning by the Tribunal, [FFCCI] admitted that there is no
proportion should it be shared by the parties?13 “back-to-back” provision in the sub-contract as basis for this sequential payment
Likewise, during the said Preliminary Conference, HRCC further reduced the arrangement and, therefore, [FFCCI’s] imposition thereof by withholding payment
amount of overdue obligation it claimed from FFCCI to P2,768,916.66. During the to [HRCC] until it is first paid by the project owner on the Main Contract, clearly
course of the proceedings before the CIAC, HRCC further reduced the said amount violates said sub-contract. It [is] this unauthorized implementation of a back-to-back
to P2,635,397.77 – the exact difference between the total amount of HRCC’s payment scheme that is seen to be the reason for [FFCCI’s] non-payment of the third
progress billings (P6,107,919.63) and FFCCI’s total payments in favor of the latter progress billings.
(P3,472,521.86). It is accordingly the holding of this Arbitral Tribunal that [FFCCI] is not
justified in withholding payment of [HRCC’s] third progress billing for this scheme
The CIAC Decision that [HRCC] has not agreed to in the sub-contract agreement x x x.
xxx
On September 6, 2005, after due proceedings, the CIAC rendered a Decision 14 in The total retention money deducted by [FFCCI] from [HRCC’s] three progress
favor of HRCC, the decretal portion of which reads: billings, amounts to [P]395,945.14 x x x. The retention money is part of [HRCC’s]
“WHEREFORE, judgment is hereby rendered in favor of the Claimant HR progress billings and must, therefore, be credited to this account. The two amounts
CONSTRUCTION CORPORATION and AWARDmade on its monetary claim (deductions and net payments) total [P]3,868,467.00 x x x. This represents the total
against Respondent F.F. CRUZ & CO., INC., as follows: gross payments that should be credited and deducted from the total gross billings to
[P]2,239,452.63    as the balance of its unpaid billings and arrive at what has not been paid to the [HRCC]. This
     101,161.57     as reimbursement of the arbitration  312
                                  costs. 312 SUPREME COURT REPORTS ANNOTATED
[P]2,340,614.20    Total due the Claimant
F.F. Cruz & Co., Inc. vs. HR Construction Corp.
Interest on the foregoing amount [P]2,239,452.63 shall be paid at the rate of
results in the amount of [P]2,239,452.63 ([P]6,107,919.63 - [P]3,868,467.00) as the
6% per annum from the date of this Decision. After finality of this Decision, interest
correct balance of [HRCC’s] unpaid billings.”16
at the rate of 12% per annum shall be paid thereon until full payment of the awarded
Further, the CIAC ruled that FFCCI had already waived its right under the
amount shall have been made x x x.
Subcontract Agreement to require a joint measurement of HRCC’s completed works
SO ORDERED.”15
as a condition precedent to the payment of the latter’s progress billings. Hence:
_______________
“[FFCCI] admits that in all three instances where it paid [HRCC] for its progress
13 Id., at p. 124.
billings, it never required compliance with the aforequoted contractual provision of a
14 Id., at pp. 116-135.
prior joint quantification. Such repeated omission may reasonably be construed as
15 Id., at p. 134.
a waiver by [FFCCI] of its contractual right to require compliance of said condition
311
and it is now too late in the day to so impose it. Article 6 of the Civil Code expressly
VOL. 668, MARCH 14, 2012 311 provides that “rights may be waived unless the waiver is contrary to law, public
F.F. Cruz & Co., Inc. vs. HR Construction Corp. order, public policy, morals or good customs.” The tribunal cannot see any such
The CIAC held that the payment method adopted by FFCCI is actually what is violation in this case.
known as the “back-to-back payment scheme” which was not agreed upon under the xxx
Subcontract Agreement. As such, the CIAC ruled that FFCCI could not impose upon [FFCCI’s] omission to enforce the contractually required condition of payment,
HRCC its valuation of the works completed by the latter. The CIAC gave credence has led [HRCC] to believe it to be true that indeed [FFCCI] has waived the condition
to HRCC’s valuation of its completed works as stated in its progress billings. Thus: of joint quantification and, therefore, [FFCCI] may not be permitted to falsify such
“During the trial, [FFCCI’s] Aganon admitted that [HRCC’s] accomplishments resulting position.”17
are included in its own billings to the DPWH together with a substantial mark-up to Likewise, the CIAC held that FFCCI’s non-payment of the progress billings
cover overhead costs and profit. He further admitted that it is only when DPWH submitted by HRCC gave the latter the right to rescind the Subcontract Agreement
approves its (Respondent’s) billings covering [HRCC’s] scope of work and pays for and, accordingly, HRCC’s work stoppage was justified. It further opined that, in
them, that [FFCCI] will in turn pay [HRCC] for its billings on the sub-contracted effect, FFCCI had ratified the right of HRCC to stop the construction works as it did
works. not file any counterclaim against HRCC for liquidated damages arising therefrom.

10
FFCCI then filed a petition for review with CA assailing the foregoing x x x Second, [d]oes the payment of [FFCCI] to [HRCC] based on the results of the
disposition by the CIAC. above mentioned verification survey result in the former being obliged to accept
_______________ whatever accomplishment was reported by the latter?
16 Id., at pp. 127-128. [III.]
17 Id., at pp. 130-131. x x x Third, [d]oes the mere comparison of the payments made by [FFCCI] with the
   313 contested progress billings of [HRCC] amount to an adjudication of the controversy
VOL. 668, MARCH 14, 2012 313 between the parties?
[IV.]
F.F. Cruz & Co., Inc. vs. HR Construction Corp.
x x x Fourth, [d]oes the failure of [FFCCI] to interpose a counterclaim against
[HRCC] for liquidated damages due to the latter’s work stoppage, amount to a
The CA Decision ratification of such work stoppage?
[V.]
On February 6, 2009, the CA rendered the herein assailed Decision 18 denying the x x x Fifth, [d]id the [CA] disregard or overlook significant and material facts which
petition for review filed by FFCCI. The CA agreed with the CIAC that FFCCI had would affect the result of the litigation?21
waived its right under the Subcontract Agreement to require a joint quantification of In sum, the crucial issues for this Court’s resolution are: first, what is the effect
HRCC’s completed works. of FFCCI’s non-compliance with the stipulation in the Subcontract Agreement
The CA further held that the amount due to HRCC as claimed by FFCCI could requiring a joint quantification of the works completed by HRCC on the payment of
not be given credence since the same was based on a survey of the completed works the progress billings submitted by the latter; and second, whether there was a valid
conducted without the participation of HRCC. Likewise, being the main contractor, it rescission of the Subcontract Agreement by HRCC.
ruled that it was the responsibility of FFCCI to include HRCC in the joint The Court’s Ruling
measurement of the completed works. Furthermore, the CA held that HRCC was The petition is not meritorious.
justified in stopping its construction works on the project as the failure of FFCCI to Procedural Issue:
pay its progress billings gave the former the right to rescind the Subcontract Finality and Conclusiveness of the CIAC’s
Agreement. Factual Findings
FFCCI sought a reconsideration 19 of the said February 6, 2009 Decision but it Before we delve into the substantial issues raised by FFCCI, we shall first
was denied by the CA in its Resolution20 dated April 13, 2009. address the procedural issue raised by
_______________
Issues 21 Rollo, pp. 21-22.
315
In the instant petition, FFCCI submits the following issues for this Court’s
VOL. 668, MARCH 14, 2012 315
resolution:
[I.] F.F. Cruz & Co., Inc. vs. HR Construction Corp.
x x x First, [d]oes the act of [FFCCI] in conducting a verification survey of HRCC. According to HRCC, the instant petition merely assails the factual findings
[HRCC’s] billings in the latter’s presence amount to a waiver of the right of [FFCCI] of the CIAC as affirmed by the CA and, accordingly, not proper subjects of an
to verify and approve said billings? What, if any, is the legal significance of said act? appeal under Rule 45 of the Rules of Court. It likewise pointed out that factual
_______________ findings of the CIAC, when affirmed by the CA, are final and conclusive upon this
18 Supra note 1. Court.
19 Rollo, pp. 70-77. Generally, the arbitral award of
20 Supra note 2. CIAC is final and may not be ap-
314 pealed except on questions of law.
314 SUPREME COURT REPORTS ANNOTATED Executive Order (E.O.) No. 100822 vests upon the CIAC original and exclusive
jurisdiction over disputes arising from, or connected with, contracts entered into by
F.F. Cruz & Co., Inc. vs. HR Construction Corp. parties involved in construction in the Philippines. Under Section 19 of E.O. No.
[II.] 1008, the arbitral award of CIAC “shall be final and inappealable except on
questions of law which shall be appealable to the Supreme Court.”23

11
In Hi-Precision Steel Center, Inc. v. Lim Kim Steel Builders, Inc.,24 we undue means; (2) there was evident partiality or corruption of the arbitrators or of
explained raison d’ etre for the rule on finality of the CIAC’s arbitral award in this any of them; (3) the arbitrators were guilty of misconduct in refusing to postpone the
wise: hearing upon sufficient cause shown, or in refusing to
“Voluntary arbitration involves the reference of a dispute to an impartial body, _______________
the members of which are chosen by the parties themselves, which parties freely 25 Id., at p. 405.
consent in advance to abide by the arbitral award issued after proceedings where 26 479 Phil. 578; 435 SCRA 654 (2004).
both parties had the opportunity to be heard. The basic objective is to provide a 317
speedy and inexpensive method of settling disputes by allowing the parties to avoid VOL. 668, MARCH 14, 2012 317
the formalities, delay, expense and aggravation which com-
F.F. Cruz & Co., Inc. vs. HR Construction Corp.
_______________
22 Creating an Arbitration Machinery in the Construction Industry of the hear evidence pertinent and material to the controversy; (4) one or more of the
Philippines, otherwise known as the “Construction Industry Arbitration Law.” arbitrators were disqualified to act as such under section nine of Republic Act No.
23 SC Circular No. 1-91 and Revised Administrative Circular No. 1-95 provides 876 and willfully refrained from disclosing such disqualifications or of any other
that appeal from the arbitral award of the CIAC must first be brought to the CA on misbehavior by which the rights of any party have been materially prejudiced; or (5)
questions of fact, law or mixed questions of fact and law. the arbitrators exceeded their powers, or so imperfectly executed them, that a mutual,
24 G.R. No. 110434, December 13, 1993, 228 SCRA 397. final and definite award upon the subject matter submitted to them was not made. x x
316 x”27 (Citation omitted)
Issues on the proper interpretation
316 SUPREME COURT REPORTS ANNOTATED of the terms of the Subcontract
F.F. Cruz & Co., Inc. vs. HR Construction Corp. Agreement involve questions of law.
monly accompany ordinary litigation, especially litigation which goes through the A question of law arises when there is doubt as to what the law is on a certain
entire hierarchy of courts. Executive Order No. 1008 created an arbitration facility to state of facts, while there is a question of fact when the doubt arises as to the truth or
which the construction industry in the Philippines can have recourse. The Executive falsity of the alleged facts. For a question to be one of law, the same must not
Order was enacted to encourage the early and expeditious settlement of disputes in involve an examination of the probative value of the evidence presented by the
the construction industry, a public policy the implementation of which is necessary litigants or any of them. The resolution of the issue must rest solely on what the law
and important for the realization of national development goals. provides on the given set of circumstances. Once it is clear that the issue invites a
Aware of the objective of voluntary arbitration in the labor field, in the review of the evidence presented, the question posed is one of fact.28
construction industry, and in any other area for that matter, the Court will not assist On the surface, the instant petition appears to merely raise factual questions as it
one or the other or even both parties in any effort to subvert or defeat that objective mainly puts in issue the appropriate amount that is due to HRCC. However, a more
for their private purposes. The Court will not review the factual findings of an thorough analysis of the issues raised by FFCCI would show that it actually asserts
arbitral tribunal upon the artful allegation that such body had “misapprehended the questions of law.
facts” and will not pass upon issues which are, at bottom, issues of fact, no matter FFCCI primarily seeks from this Court a determination of whether amount
how cleverly disguised they might be as “legal questions.” The parties here had claimed by HRCC in its progress billing may be enforced against it in the absence of
recourse to arbitration and chose the arbitrators themselves; they must have had a joint measurement of the former’s completed works. Otherwise stated, the main
confidence in such arbitrators. x x x”25 (Citation omitted) question advanced by FFCCI is this: in the absence of the joint measurement agreed
Thus, in cases assailing the arbitral award rendered by the CIAC, this Court may upon in the Subcontract Agree-
only pass upon questions of law. Factual findings of construction arbitrators are final _______________
and conclusive and not reviewable by this Court on appeal. This rule, however, 27 Id., at pp. 590-591; p. 666.
admits of certain exceptions. 28 Vda. De Formoso v. Philippine National Bank, G.R. No. 154704, June 1,
In Spouses David v. Construction Industry and Arbitration Commission,26 we 2011, 650 SCRA 35.
laid down the instances when this Court may pass upon the factual findings of the 318
CIAC, thus: 318 SUPREME COURT REPORTS ANNOTATED
“We reiterate the rule that factual findings of construction arbitrators are final and
F.F. Cruz & Co., Inc. vs. HR Construction Corp.
conclusive and not reviewable by this Court on appeal, except when the petitioner
proves affirmatively that: (1) the award was procured by corruption, fraud or other ment, how will the completed works of HRCC be verified and the amount due
thereon be computed?
12
The determination of the foregoing question entails an interpretation of the terms ambiguity in the light of the intrinsic evidence.” 32 (Emphasis supplied and citation
of the Subcontract Agreement vis-à-vis the respective rights of the parties herein. On omitted)
this point, it should be stressed that where an interpretation of the true agreement Article 4 of the Subcontract Agreement, in part, contained the following
between the parties is involved in an appeal, the appeal is in effect an inquiry of the stipulations:
law between the parties, its interpretation necessarily involves a question of law.29 ARTICLE 4
Moreover, we are not called upon to examine the probative value of the evidence SUBCONTRACT PRICE
presented before the CIAC. Rather, what is actually sought from this Court is an 4.1 The total SUBCONTRACT Price shall be THIRTY ONE MILLION TWO
interpretation of the terms of the Subcontract Agreement as it relates to the dispute HUNDRED NINETY THREE THOUSAND FIVE HUNDRED THIRTY
between the parties. TWO PESOS & 72/100 ONLY ([P]31,293,532.72) inclusive of Value Added
Tax
First Substantive Issue: Effect of Non-compliance x x x.
with the Joint Quantification Requirement on xxx
the Progress Billings of HRCC 4.3 Terms of Payment
  FFCCI shall pay [HRCC] within thirty (30) days upon receipt of the
Basically, the instant issue calls for a determination as to which of the parties’ [HRCC’s] Monthly Progress Billings subject to deductions due to ten
respective valuation of accomplished works should be given credence. FFCCI claims percent (10%) 
that its valuation should be upheld since the same was the result of a measurement of _______________
the completed works conducted by it and the DPWH. On the other hand, HRCC 30 Civil Code of the Philippines, Article 1370.
maintains that its valuation should be upheld on account of FFCCI’s failure to 31 G.R. No. 168108, April 13, 2007, 521 SCRA 131.
observe the joint measurement requirement in ascertaining the extent of its 32 Id., at p. 144.
completed works. 320
The terms of the Subcontract 320 SUPREME COURT REPORTS ANNOTATED
Agreement should prevail.
F.F. Cruz & Co., Inc. vs. HR Construction Corp.
In resolving the dispute as to the proper valuation of the works accomplished by
retention, and any other sums that may be due and recoverable by FFCCI from
HRCC, the primordial consideration
[HRCC] under this SUBCONTRACT. In all cases, however, two percent (2%)
_______________
expanded withholding tax on the [HRCC’s] income will be deducted from the
29 See Philippine National Construction Corporation v. Court of Appeals, G.R.
monthly payments.
No. 159417, January 25, 2007, 512 SCRA 684, 695.
  Requests for the payment by the [HRCC] shall include progress
319
accomplishment of completed works (unit of work accomplished x unit
VOL. 668, MARCH 14, 2012 319 cost) as approved by [FFCCI]. Cut-off date of monthly billings shall be
F.F. Cruz & Co., Inc. vs. HR Construction Corp. every 25th of the month and joint measurement shall be conducted with
should be the terms of the Subcontract Agreement. It is basic that if the terms of a the DPWH’s representative, Consultants, FFCCI and [HRCC] to arrive
contract are clear and leave no doubt upon the intention of the contracting parties, the at a common/agreed quantity.”33 (Emphasis supplied)
literal meaning of its stipulations shall control.30 Pursuant to the terms of payment agreed upon by the parties, FFCCI obliged
In Abad v. Goldloop Properties, Inc.,31 we stressed that: itself to pay the monthly progress billings of HRCC within 30 days from receipt of
“A court’s purpose in examining a contract is to interpret the intent of the the same. Additionally, the monthly progress billings of HRCC should indicate the
contracting parties, as objectively manifested by them. The process of extent of the works completed by it, the same being essential to the valuation of the
interpreting a contract requires the court to make a preliminary inquiry as to whether amount that FFCCI would pay to HRCC.
the contract before it is ambiguous. A contract provision is ambiguous if it is The parties further agreed that the extent of HRCC’s completed works that would
susceptible of two reasonable alternative interpretations. Where the written terms be indicated in the monthly progress billings should be determined through a joint
of the contract are not ambiguous and can only be read one way, the court will measurement conducted by FFCCI and HRCC together with the representative of
interpret the contract as a matter of law. If the contract is determined to be DPWH and the consultants.
ambiguous, then the interpretation of the contract is left to the court, to resolve the

13
It is the responsibility of FFCCI  The CIAC held that FFCCI, on account of its failure to demand the joint
to call for the joint measurement measurement of HRCC’s completed works, had effectively waived its right to ask for
of HRCC’s completed works. the conduct of the same as a condition sine qua non to HRCC’s submission of its
It bears stressing that the joint measurement contemplated under the Subcontract monthly progress billings.
Agreement should be conducted by the parties herein together with the representative We agree.
of the DPWH and the consultants. Indubitably, FFCCI, being the main In People of the Philippines v. Donato,35 this Court explained the doctrine of
_______________ waiver in this wise:
33 Rollo, p. 87. “Waiver is defined as “a voluntary and intentional relinquishment or
321 abandonment of a known existing legal right, advantage, benefit, claim or privilege,
VOL. 668, MARCH 14, 2012 321 which except for such waiver the party would have enjoyed; the voluntary
abandonment or surrender, by a capable person, of a right known by him to exist,
F.F. Cruz & Co., Inc. vs. HR Construction Corp.
with the intent that such right shall be surrendered and such person forever deprived
contractor of DPWH, has the responsibility to request the representative of DPWH to of its benefit; or such conduct as warrants an inference of the relinquishment of
conduct the said joint measurement. such right; or the intentional doing of an act inconsistent with claiming it.”
On this score, the testimony of Engineer Antonio M. Aganon, Jr., project As to what rights and privileges may be waived, the authority is settled:
manager of FFCCI, during the reception of evidence before the CIAC is telling, thus: x x x the doctrine of waiver extends to rights and privileges of any character,
MR. J. B. JOAQUIN: and, since the word ‘waiver’ covers every conceivable right, it is the general
Engr. Aganon, earlier there was a stipulation that in all the four billings, there never rule that a person may waive any matter which affects his property, and
was a joint quantification. any alienable right or privilege of which he is the owner or which belongs
PROF. A. F. TADIAR: to him or to which he is legally entitled, whether secured by contract,
  He admitted that earlier. Pinabasa ko sa kanya. conferred with statute, or guaranteed by constitution, provided such rights
ENGR. R. B. SAN JUAN: and privileges rest in the individual, are intended for his sole benefit, do
The joint quantification was done only between them and DPWH. not infringe on the rights of others, and further provided the waiver of
xxxx the right or privilege is not forbidden by law, and does not contravene
ENGR. AGANON: public policy; and the principle is recognized that everyone has a right
Puwede ko po bang i-explain sandali lang po regarding lang po doon sa _______________
quantification na iyon? Basically po as main contractor of DPWH, we are the 35 G.R. No. 79269, June 5, 1991, 198 SCRA 130.
ones who [are] requesting for joint survey quantification with the owner, 323
DPWH. Ngayon po, although wala sa papel na nag-witness and [HRCC] still the
same po, nandoon din po sila during that time, kaya lang ho . . . VOL. 668, MARCH 14, 2012 323
MR. J. B. JOAQUIN: F.F. Cruz & Co., Inc. vs. HR Construction Corp.
Hindi pumirma? to waive, and agree to waive, the advantage of a law or rule made solely for
ENGR. AGANON: the benefit and protection of the individual in his private capacity, if it can be
Hindi sila puwede pumirma kasi ho kami po ang contractor ng DPWH hindi dispensed with and relinquished without infringing on any public right, and
sila.34 (Emphasis supplied) without detriment to the community at large. x x x”36(Emphasis supplied and
FFCCI had waived its right to citations omitted)
demand for a joint measurement  Here, it is undisputed that the joint measurement of HRCC’s completed works
_______________ contemplated by the parties in the Subcontract Agreement never materialized.
34 Id., at pp. 330-331. Indeed, HRCC, on separate occasions, submitted its monthly progress billings
322 indicating the extent of the works it had completed sans prior joint measurement.
322 SUPREME COURT REPORTS ANNOTATED Thus:
F.F. Cruz & Co., Inc. vs. HR Construction Corp. Progress Billing Period Covered Amount
of HRCC’s completed works under  1st Progress Billing dated September August 16 to P2,029,081.59
the Subcontract Agreement. 17, 200437 September 15,

14
2004 In view of FFCCI’s waiver of the joint measurement requirement, the CA,
essentially echoing the CIAC’s disposition, found that FFCCI is obliged to pay the
2nd Progress Billing dated October September 18 to P1,587,760.23
amount claimed by HRCC in its monthly progress billings. The CA reasoned thus:
29, 200438 25, 2004 “Verily, the joint measurement that [FFCCI] claims it conducted without the
3rd Progress Billing dated October 29, September 26 to P2,569,543.57 participation of [HRCC], to which [FFCCI] an-
200439 October 25, 2004 _______________
40 Supra note 5.
4th Progress Billing dated November October 26 to P1,527,112.95
41 Supra note 6.
25, 2004 November 25, 42 Supra note 9.
2004 325
FFCCI did not contest the said progress billings submitted by HRCC despite the VOL. 668, MARCH 14, 2012 325
lack of a joint measurement of the latter’s completed works as required under the
F.F. Cruz & Co., Inc. vs. HR Construction Corp.
Subcontract Agreement. Instead, FFCCI proceeded to conduct its own verification of
the works actually completed by HRCC and, on separate dates, made the following chors its claim of full payment of its obligations to [HRCC], cannot be applied, nor
payments to HRCC: imposed, on [HRCC]. In other words, [HRCC] cannot be made to accept a
_______________ quantification of its works when the said quantification was made without its
36 Id., at p. 154. participation. As a consequence, [FFCCI’s] claim of full payment cannot be upheld
37 Supra note 4. as this is a result of a quantification that was made contrary to the express provisions
38 Supra note 7. of the Subcontract Agreement.
39 Supra note 8. The Court is aware that by ruling so, [FFCCI] would seem to be placed at a
324 disadvantage because it would result in [FFCCI] having to pay exactly what [HRCC]
was billing the former. If, on the other hand, the Court were to rule otherwise[,] then
324 SUPREME COURT REPORTS ANNOTATED [HRCC] would be the one at a disadvantage because it would be made to accept
F.F. Cruz & Co., Inc. vs. HR Construction Corp. payment that is less than what it was billing.
Date of Payment Period Covered Amount Circumstances considered, however, the Court deems it proper to rule in favor of
[HRCC] because of the explicit provision of the Subcontract Agreement that requires
December 3, 2004 40
April 2 to July 25, 2004 P373,452.24 the participation of the latter in the joint measurement. If the Court were to rule
December 21, 200441 July 26 to September 25, 2004 P1,771,429.45 otherwise, then the Court would, in effect, be disregarding the explicit agreement of
March 11, 2005 42
September 26 to November 25, P1,327,639.87 the parties in their contract.”43
Essentially, the question that should be resolved is this: In view of FFCCI’s
2004
waiver of its right to demand a joint measurement of HRCC’s completed works, is
FFCCI’s voluntary payment in favor of HRCC, albeit in amounts substantially
FFCCI now barred from disputing the claim of HRCC in its monthly progress
different from those claimed by the latter, is a glaring indication that it had
billings?
effectively waived its right to demand for the joint measurement of the completed
We rule in the affirmative.
works. FFCCI’s failure to demand a joint measurement of HRCC’s completed works
As intimated earlier, the joint measurement requirement is a mechanism
reasonably justified the inference that it had already relinquished its right to do so.
essentially granting FFCCI the opportunity to verify and, if necessary, contest
Indeed, not once did FFCCI insist on the conduct of a joint measurement to verify
HRCC’s valuation of its completed works prior to the submission of the latter’s
the extent of HRCC’s completed works despite its receipt of the four monthly
monthly progress billings.
progress billings submitted by the latter.
In the final analysis, the joint measurement requirement seeks to limit the dispute
FFCCI is already barred from 
between the parties with regard to the valuation of HRCC’s completed works.
contesting HRCC’s valuation of
Accordingly, any issue which FFCCI may have with regard to HRCC’s valua-
the completed works having 
_______________
waived its right to demand the
43 Rollo, pp. 65-66.
joint measurement require-
326
ment.
326 SUPREME COURT REPORTS ANNOTATED

15
F.F. Cruz & Co., Inc. vs. HR Construction Corp. reciprocity between the parties.44 The right to rescind, however, may be waived,
tion of the works it had completed should be raised and resolved during the said joint expressly or impliedly.45
measurement instead of raising the same after HRCC had submitted its monthly While the right to rescind reciprocal obligations is implied, that is, that such right
progress billings. Thus, having relinquished its right to ask for a joint measurement need not be expressly provided in the contract, nevertheless the contracting parties
of HRCC’s completed works, FFCCI had necessarily waived its right to dispute may waive the same.46
HRCC’s valuation of the works it had accomplished. Contrary to the respective dispositions of the CIAC and the CA, we find that
HRCC had no right to rescind the Subcontract Agreement in the guise of a work
Second Substantive Issue: stoppage, the latter having waived such right. Apropos is Article 11.2 of the
Validity of HRCC’s Rescission of the  Subcontract Agreement, which reads:
Subcontract Agreement _______________
44 Pryce Corp. v. Phil. Amusement and Gaming Corp., 497 Phil. 490, 505; 458
SCRA 164, 177 (2005), citing the Concurring Opinion of Mr. Justice J.B. L. Reyes
Both the CA and the CIAC held that the work stoppage of HRCC was justified as
in Universal Food Corp. v. Court of Appeals, 144 Phil. 1, 21; 33 SCRA 1, 22-23
the same is but an exercise of its right to rescind the Subcontract Agreement in view
(1970).
of FFCCI’s failure to pay the former’s monthly progress billings. Further, the CIAC
45 Francisco v. DEAC Construction, Inc., G.R. No. 171312, February 4, 2008,
stated that FFCCI could no longer assail the work stoppage of HRCC as it failed to
543 SCRA 644, 655.
file any counterclaim against HRCC pursuant to the terms of the Subcontract
46 Tolentino, Commentaries and Jurisprudence on the Civil Code of the
Agreement.
Philippines, Vol. IV (1991).
For its part, FFCCI asserted that the work stoppage of HRCC was not justified
328
and, in any case, its failure to raise a counterclaim against HRCC for liquidated
damages before the CIAC does not amount to a ratification of the latter’s work 328 SUPREME COURT REPORTS ANNOTATED
stoppage. F.F. Cruz & Co., Inc. vs. HR Construction Corp.
The determination of the validity of HRCC’s work stoppage depends on a 11.2 Effects of Disputes and Continuing Obligations
determination of the following: first,whether HRCC has the right to extrajudicially   Notwithstanding any dispute, controversy, differences or arbitration
rescind the Subcontract Agreement; and second, whether FFCCI is already barred proceedings relating directly or indirectly to this SUBCONTRACT
from disputing the work stoppage of HRCC. Agreement and without prejudice to the eventual outcome
HRCC had waived its right to re- thereof, [HRCC] shall at all times proceed with the prompt
scind the Subcontract Agreement. performance of the Works in accordance with the directives of
The right of rescission is statutorily recognized in reciprocal obligations. Article FFCCI and this SUBCONTRACT Agreement.47 (Emphasis
1191 of the Civil Code pertinently reads:327 supplied)
VOL. 668, MARCH 14, 2012 327 Hence, in spite of the existence of dispute or controversy between the parties
F.F. Cruz & Co., Inc. vs. HR Construction Corp. during the course of the Subcontract Agreement, HRCC had agreed to continue the
performance of its obligations pursuant to the Subcontract Agreement. In view of the
“Art. 1191. The power to rescind obligations is implied in reciprocal ones, in
provision of the Subcontract Agreement quoted above, HRCC is deemed to have
case one of the obligors should not comply with what is incumbent upon him.
effectively waived its right to effect extrajudicial rescission of its contract with
The injured party may choose between the fulfillment and the rescission of the
FFCCI. Accordingly, HRCC, in the guise of rescinding the Subcontract Agreement,
obligation, with the payment of damages in either case. He may also seek rescission,
was not justified in implementing a work stoppage.
even after he has chosen fulfillment, if the latter should become impossible.
The costs of arbitration should be
The court shall decree the rescission claimed, unless there be just cause
shared by the parties equally.
authorizing the fixing of a period.
Section 1, Rule 142 of the Rules of Court provides:
This is understood to be without prejudice to the rights of third persons who have
“Section 1. Costs ordinarily follow results of suit.—Unless otherwise provided
acquired the thing, in accordance with Articles 1385 and 1388 and the Mortgage
in these rules, costs shall be allowed to the prevailing party as a matter of course, but
Law.”
the court shall have power, for special reasons, to adjudge that either party shall pay
The rescission referred to in this article, more appropriately referred to as
the costs of an action, or that the same be divided, as may be equitable. No costs
resolution is on the breach of faith by the defendant which is violative of the

16
shall be allowed against the Republic of the Philippines unless otherwise provided by
law.” (Emphasis supplied)
Although, generally, costs are adjudged against the losing party, courts
nevertheless have discretion, for special reasons, to decree otherwise.
_______________
47 Rollo, p. 91.
329
VOL. 668, MARCH 14, 2012 329
F.F. Cruz & Co., Inc. vs. HR Construction Corp.
Here, considering that the work stoppage of HRCC is not justified, it is only
fitting that both parties should share in the burden of the cost of arbitration equally.
HRCC had a valid reason to institute the complaint against FFCCI in view of the
latter’s failure to pay the full amount of its monthly progress billings. However, we
disagree with the CIAC and the CA that only FFCCI should shoulder the arbitration
costs. The arbitration costs should be shared equally by FFCCI and HRCC in view of
the latter’s unjustified work stoppage.
WHEREFORE, in consideration of the foregoing disquisitions, the Decision
dated February 6, 2009 and Resolution dated April 13, 2009 of the Court of Appeals
in CA-G.R. SP No. 91860 are hereby AFFIRMED with MODIFICATION that the
arbitration costs shall be shared equally by the parties herein.
SO ORDERED.
Carpio (Chairperson), Brion, Perez and Sereno, JJ., concur. 
Judgment and resolution affirmed with modification.
Notes.—A waiver or quitclaim is a valid and binding agreement between the
parties, provided that it constitutes a credible and reasonable settlement, and that the
one accomplishing it has done so voluntarily and with a full understanding of its
import. (Plastimer Industrial Corporation vs. Gopo, 643 SCRA 502 [2011])
Factual findings of construction arbitrators are final and conclusive and not
reviewable by this Court on appeal. (De Guzman vs. Tumolva, 659 SCRA 725
[2011])
——o0o—— 

G.R. No. 211588, September 09, 2015


17
WORLD'S BEST GAS, INC., Petitioner, v. HENRY VITAL, JOINED BY HIS For its part, WBGI averred that the Labor Arbiter (LA) had no jurisdiction over the
WIFE FLOSERFINA VITAL, Respondents. complaint because Vital is not an employee, but a mere incorporator and stockholder
of WBGI, hence, no employer-employee relationship exists between them.12
DECISION
The LA Ruling
PERLAS-BERNABE, J.:
In a Decision13 dated May 3, 2006, the LA found that the issues between Vital and
WBGI are intra-corporate in nature as they arose between the relations of a
Before the Court is a petition for review on certiorari1 filed by petitioner World's stockholder and the corporation, and not from an employee and employer
Best Gas, Inc. (WBGI) assailing the Decision2 dated September 30, 2013 and the relationship.14 Thus, the LA dismissed the case for lack of jurisdiction,15 prompting
Resolution3 dated March 4, 2014 of the Court of Appeals (CA) in CA-G.R. SP No. Vital to file his complaint16 for payment of unpaid salaries, separation and retirement
123497, which affirmed the Decision4dated December 12, 2011 of the Regional Trial benefits, and damages on July 19, 2007 before the RTC, docketed as Civil Case No.
Court of Bataan, Branch 2 (RTC) in Civil Case No. 8694 finding WBGI liable to 8694.17
respondent Henry Vital (Vital) for his unpaid salaries and separation pay.
The RTC Ruling
The Facts
In a Decision18 dated December 12, 2011, the RTC, acting as a special commercial
Vital was one of the incorporators of WBGI, holding P500,000.00 worth of shares of court, oppositely found that Vital was an employee of WBGI and thereby, upheld his
stocks therein.5 As a separate business venture, Vital and his wife, respondent claim of P845,000.00 and P250,000.00 in unpaid salaries and separation pay.
Floserfina Vital (respondents), sourced Liquefied Petroleum Gas (LPG) from WBGI However, the RTC offset these amounts, including the P500,000.00 due from
and distributed the same through ERJ Enterprises owned by them.6 As of WBGFs acquisition of Vital's shares of stocks, against the P923,843.59 payable to
respondents' last statement of account, their outstanding balance with WBGI for WBGI from ERJ Enterprises, thus, awarding Vital the net amount of P671,156.41,
unpaid LPG amounted to P923,843.59.7 with legal interest from date of demand until full payment, P50,000.00 as attorney's
fees and costs of suit plus litigation expenses.19
On January 6, 1999, Vital was appointed as Internal Auditor and Personnel Manager
by WBGI's President/CEO and continued to serve as such until his mandatory The RTC ratiocinated that since the positions of Internal Auditor and Personnel
retirement on September 25, 2003.8 Upon his retirement, WBGI's Board of Directors Manager were not provided for in WBGI's By-Laws, Vital was not a corporate
computed Vital's retirement benefits at P82,500.00 by multiplying his P15,000.00 officer but an employee entitled to employment benefits. It also maintained that it
monthly pay by 5.5 years, which was the number of years he served as Internal had jurisdiction to rule on the main intra-corporate controversy, together with the
Auditor and Personnel Manager. WBGI also agreed to acquire Vital's P500,000.00 question of damages and employment benefits.20
shares of stocks at par value.9  
Aggrieved, WBGI elevated the case to the CA on appeal.21
After offsetting the P500,000.00 due from WBGI's acquisition of his shares of stocks  
against ERJ Enterprises' P923,843.59 outstanding balance to WBGI, Vital claimed The CA Ruling
that the unpaid salaries and separation pay due him amounted to P845,000.00
and P250,000.00, respectively, leaving a net amount of P671,156.41 payable to him. In a Decision22 dated September 30, 2013, the CA dismissed the appeal, agreeing
WBGI rejected Vital's claim and contended that after offsetting, Vital actually owed with the RTC's finding that Vital was an employee of WGBI. While the CA observed
it P369,156.19.10 that the RTC's award of employment benefits to Vital was improper, as the same was
under the exclusive jurisdiction of the labor arbiters, it still ruled on said claim,
On January 4, 2006, Vital filed a complaint before the National Labor Relations reasoning that it has the eventual authority to review the labor courts' decision on the
Commission (NLRC) — Regional Arbitration Branch III (RAB), docketed as NLRC matter.23
Case No. RAB-III-01-9671-06, for non-payment of separation and retirement
benefits, underpayment of salaries/wages and 13th month pay, illegal reduction WBGI filed a motion for reconsideration24 which was, however, denied in a
of salary and benefits, and damages.11 Resolution25 dated March 4, 2014; hence, the present petition.

18
The Issue Before the Court including those of persons in domestic or household service, involving an
amount exceeding five thousand pesos (P5,000.00) regardless of whether
The main issue to be resolved is whether or not the CA erred in ruling upon Vital's accompanied with a claim for reinstatement.
claim of P845,000.00 and P250,000.00 in unpaid salaries and separation pay.  
 x x x x
The Court's Ruling Having no subject matter jurisdiction to resolve claims arising from employer-
employee relations, the RTC's ruling on Vital's claim of P845,000.00 and
The petition is partly meritorious. P250,000.00 in unpaid salaries and separation pay is, thus, null and void, and
therefore, cannot perpetuate even if affirmed on appeal,26 rendering the CA's
At the outset, it should be pointed out that the instant case actually involves three (3) ratiocination that it "has the eventual authority to review the labor courts' decision on
distinct causes of action, namely, (1) Vital's claim for P845,000.00 and P250,000.00 the matter"27 direly infirm. As a result, WBGI's petition is meritorious on this score.
in unpaid salaries and separation pay; (2) the P923,843.59 in arrearages payable to However, since the dismissal is grounded on lack of jurisdiction, then the same
WBGI from ERJ Enterprises, which was admitted by Vital but not claimed by should be considered as a dismissal without prejudice.28As such, Vital may re-
WBGI; and (3) Vital's claim of P500,000.00 due from WBGI's acquisition of Vital's file29the same claim, including those related thereto (e.g., moral and exemplary
shares of stocks. All of the foregoing were threshed out by the RTC in its December damages, and attorney's fees) before the proper labor tribunal.
12, 2011 Decision, and effectively upheld by the CA on appeal.
Contrary to its lack of jurisdiction over claims arising from employer-employee
However, the RTC's adjudication of the first cause of action was improper since the relations, the RTC has: (a) general jurisdiction to adjudicate on the P923,843.59 in
same is one which arose from Vital and WBGI's employer-employee relations, arrearages payable to WBGI from ERJ Enterprises, which was admitted by
involving an amount exceeding P5,000.00, hence, belonging to the jurisdiction of the Vital but not claimed by WBGI;30and (b) special jurisdiction, as a special
labor arbiters pursuant to Article 217 of the Labor Code: commercial court, to adjudicate on Vital's claim of P500,000.00 from WBGI's
Art. 217. Jurisdiction of the Labor Arbiters and the Commission. acquisition of his shares of stocks.31 Indeed, even acting as a special commercial
court, the RTC's general jurisdiction to adjudicate on the first-mentioned claim is
(a) Except as otherwise provided under this Code, the Labor Arbiters shall have retained.
original and exclusive jurisdiction to hear and decide, within thirty (30) calendar
days after the submission of the case by the parties for decision without extension, With the RTC's jurisdiction established over the above-mentioned causes of action,
even in the absence of stenographic notes, the following cases involving all workers, Vital's claim of P500,000.00 due from WBGI's acquisition of his shares of stocks
whether agricultural or non-agricultural:chanRoblesvirtualLawlibrary should therefore be offsetagainst the P923,843.59 in arrearages payable to WBGI by
ERJ Enterprises owned by respondents, as prayed for by him. Hence, no amount can
 1. Unfair labor practice cases;ChanRoblesVirtualawlibrary be adjudicated in Vital's favor, since it is the respondents who, after due
computation, would be left liable to WBGI in the net amount of P423,843.59. This
 2. Termination disputes;ChanRoblesVirtualawlibrary notwithstanding, WBGI cannot recover this latter amount in this casesince it never
interposed a permissive counterclaim therefor in its answer. 32 It is well-settled that
 3. If accompanied with a claim for reinstatement, those cases that workers may file courts cannot grant a relief not prayed for in the pleadings or in excess of what is
involving wages, rates of pay, hours of work and other terms and conditions of being sought by the party.33WBGI may, however, opt to file a separate collection
employment;ChanRoblesVirtualawlibrary suit, including those related thereto (e.g., moral and exemplary damages, and
attorney's fees), to recover such sum.
 4. Claims for actual, moral, exemplary and other forms of damages arising from the
employer-employee relations; WHEREFORE, the petition is PARTLY GRANTED. The Decision dated
  September 30, 2013 and the Resolution dated March 4, 2014 of the Court of Appeals
 5. Cases arising from any violation of Article 264 of this Code, including questions in CA-G.R. SP No. 123497 are hereby SET ASIDE. A new one is
involving the legality of strikes and lockouts; and entered:chanRoblesvirtualLawlibrary
 
 6. Except claims for Employees' Compensation, Social Security, Medicare and (a) DISMISSING respondent Henry Vital's (Vital) labor claims of P845,000.00 and
maternity benefits, all other claims arising from employer-employee relations, P250,000.00 in unpaid salaries and separation pay against petitioner World's Best

19
Gas, Inc.'s (WBGI), WITHOUT PREJUDICE as stated in this Decision; and

(b) RECOGNIZING WBGI's liability to Vital in the amount of P500,000.00 due


from the acquisition of his shares of stocks. This amount is,
however, OFFSET against the P923,843.59 in arrearages payable to WBGI by ERJ
Enterprises owned by Vital and his wife, respondent Floserfma Vital, leaving a net
amount of P423,843.59, which WBGI may claim in a separate case as stated in this
Decision.

SO ORDERED.chanroblesvirtuallawlibra

G.R. No. 203355. August 18, 2015.*


 
LEO R. ROSALES, EDGAR SOLIS, JONATHAN G. RANIOLA, LITO
FELICIANO, RAYMUNDO DIDAL, JR., NESTOR SALIN, ARNULFO S.
ABRIL, RUBEN FLORES, DANTE FERMA and MELCHOR SELGA,
petitioners, vs.NEW A.N.J.H. ENTERPRISES & N.H. OIL MILL
CORPORATION, NOEL AWAYAN, MA. FE AWAYAN, BYRON ILAGAN,
HEIDI A. ILAGAN and AVELINO AWAYAN, respondents.
Remedial Law; Civil Procedure; Appeals; On the issue of perfecting the
appeal, the Court of Appeals (CA) was correct when it pointed out that Rule VI of
the New Rules of Procedure of the National Labor Relations Commission (NLRC)
provides that a motion to reduce bond shall be entertained “upon the posting of a
bond in a reasonable amount in relation to the monetary award.”—On the issue of
perfecting the appeal, the CA was correct when it pointed out that Rule VI of the
New Rules of Procedure of the NLRC provides that a motion to reduce bond shall be
entertained “upon the posting of a bond in a reasonable amount in relation to the
monetary award.” As to what the “reasonable amount” is, the NLRC has wide
discretion in determining the reasonableness of the bond for purposes of perfecting
an appeal.
Same; Same; Res Judicata; Requisites of Res Judicata.—On the matter of the
application of the doctrine of res judicata, however, this Court is loath to sustain the
finding of the appellate court and the NLRC. For res judicata to apply, the
concurrence of the following requisites must be verified: (1) the former judgment is
final; (2) it is rendered by a court having jurisdiction over the subject matter and the
parties; (3) it is a judgment or an order on the merits; (4) there is — between the first
and the second actions — identity of parties, of subject matter, and of causes of
action.
_______________

*  EN BANC.
 
 
150
20
150 SUPREME COURT REPORTS ANNOTATED of the employees to the corporation’s act of considering them as terminated and their
subsequent acceptance of separation pay does not remove the taint of illegal
Rosales vs. vs. New A.N.J.H. Enterprises
dismissal. Acceptance of separation pay does not bar the employees from
Labor Law; Labor Disputes; Words and Phrases; Article 219 (previously subsequently contesting the legality of their dismissal, nor does it estop them from
Article 212) of the Labor Code defines a “labor dispute” as “any controversy or challenging the legality of their separation from the service.
matter concerning terms and conditions of employment or the association or Corporations; Piercing the Veil of Corporate Fiction; The application of the
representation of persons in negotiating, fixing, maintaining, changing or arranging doctrine of piercing the veil of corporate fiction is frowned upon.—The application
the terms and conditions of employment, regardless of whether the disputants stand of the doctrine of piercing the veil of corporate fiction is frowned upon. However,
in the proximate relation of employer and employee.”—Article 219 (previously this Court will not hesitate to disregard the corporate fiction if it is used to such an
Article 212) of the Labor Code defines a “labor dispute” as “any controversy extent that injustice, fraud, or crime is committed against another in disregard of his
or matter concerning terms and conditions of employment or the association or rights. In this case, petitioners advance the application of the doctrine because they
representation of persons in negotiating, fixing, maintaining, changing or arranging were terminated from employment on the pretext that there will be an impending
the terms and conditions of employment, regardless of whether the disputants stand permanent closure of the business as a result of an intended sale of its assets to an
in the proximate relation of employer and employee.” As separation pay concerns a undisclosed corporation, and that there will be a change in the management.
term and condition of employment, Noel’s request to be guided in the payment Same; Same; Mere ownership by a single stockholder of all or nearly all of the
thereof is clearly a labor dispute under the Labor Code. capital stock of the corporation does not by itself justify piercing the corporate veil.
Same; Separation Pay; Labor Arbiters; Jurisdiction; The proper payment of —Subsequent events revealed that the buyer of the assets of their employer was a
separation pay falls under the jurisdiction of the labor arbiter (LA) pursuant to Art. corporation owned by the same employer and members of his family. Furthermore,
224 (previously Art. 217) of the Labor Code, as it is mandated as a necessary the business reopened in less than a month under the same management. Admittedly,
condition for the termination of employees.—The proper payment of separation pay mere ownership by a single stockholder of all or nearly all of the capital stock of the
further falls under the jurisdiction of the labor arbiter pursuant to Art. 224 corporation does not by itself justify piercing the corporate veil. Nonetheless, in this
(previously Art. 217) of the Labor Code, as it is mandated as a necessary condition case, other circumstances show that the buyer of the assets of petitioners’ employer
for the termination of employees, viz.: Art. 224. Jurisdiction of the Labor Arbiters is none other than his alter ego.
and the Commission. (a) Except as otherwise provided under this Code, the Labor PETITION for review on certiorari of a decision of the Court of Appeals.
Arbiters shall have original and exclusive jurisdiction to hear and decide, within  
thirty (30) calendar days after the submission of the case by the parties for decision  
without extension, even in the absence of stenographic notes, the following cases 152
involving all workers, whether agricultural or nonagricultural: 1. Unfair labor
practice cases; 2. Termination disputes; x x x x 6. Except claims for employees 152 SUPREME COURT REPORTS ANNOTATED
compensation, social security, medicare and maternity benefits, all other claims Rosales vs. vs. New A.N.J.H. Enterprises
arising from employer-employee relations, including those of persons in domestic The facts are stated in the opinion of the Court.
or household service, involving an amount exceeding five thousand pesos   Florencio C. Lameyra for petitioners.
(P5,000.00) regardless of whether accompanied with a claim for reinstatement.   Maria Christine C. Cabrera-Anonuevo for respondents.
Same; Same; Res Judicata; In SME Bank, Inc. v. De Guzman, 707 SCRA 35  
(2013), the Supreme Court (SC) held that the accep- VELASCO, JR., J.:
   
  This is a Petition for Review on Certiorari under Rule 45 of the Rules of Court
151 assailing the September 5, 2012 Decision 1 of the Court of Appeals (CA) in C.A.-
VOL. 767, AUGUST 18, 2015 151 G.R. S.P. No. 124395, which, in turn, affirmed the Resolutions of the National Labor
Relations Commission (NLRC) dated December 28, 2011 2 and February 28, 20123 in
Rosales vs. vs. New A.N.J.H. Enterprises
NLRC-LAC Case No. 07-001796-11.
tance of separation pay is an issue distinct from the legality of the dismissal of Respondent New ANJH Enterprises (New ANJH) is a sole proprietorship owned
the employees.—While there may be substantial identity of the parties, there is no by respondent Noel Awayan (Noel). Petitioners are its former employees who
identity of subject matter or cause of action. In SME Bank, Inc. v. De Guzman, 707 worked as machine operators, drivers, helpers, lead and boiler men.
SCRA 35 (2013), this Court held that the acceptance of separation pay is an issue
distinct from the legality of the dismissal of the employees. We held: The conformity
21
Allegedly due to dwindling capital, on February 11, 2010, Noel wrote the 8  Id., at pp. 141-146. The following are the incorporators of NH Oil Mill
Director of the Department of Labor and Employment (DOLE) Region IV-A a letter
regarding New ANJH’s impending cessation of operations and the sale of its assets Name No. of Shares Subscribed Paid-Up
to respondent NH Oil Mill Corporation (NH Oil), as well as the termination of thirty-
three (33) employees by reason thereof. 4 On February 13, 2010, Noel met with the 33 1. Noel D. Awayan 7,900 P790,000.00 P237,000.00
affected employees, which included petitioners, to inform them of his plan. 5 On even
date, he gave the employees uni- 2. Heide A. Ilagan 1,900 P190,000.00 P57,000.00
_______________
3. Marife D. Awayan 100 P10,000.00 P3,000.00
1  Rollo, pp. 44-67. Penned by Associate Justice Vicente S.E. Veloso, with 4. Jay Byron S. Ilagan 50 P5,000.00 P1,500.00
Associate Justices Jane Aurora C. Lantion and Eduardo B. Peralta, Jr., concurring.
2  Id., at pp. 100-110. Penned by NLRC Presiding Commissioner Herminio V. 5. Imelda S. Awayan 50 P5,000.00 P1,500.00
Suelo, with Commissioners Angelo Ang Palana and Numeriano D. Villena,
TOTAL   P1,000,000.00 P300,000.00
concurring, Fourth Division.
3  Id., at pp. 111-115. Corporation with their respective subscribed and paid-up shares:
4  Id., at pp. 192-194.
5  Id., at pp. 195-196. 9  Id.
   
   
153 154
VOL. 767, AUGUST 18, 2015 153 154 SUPREME COURT REPORTS ANNOTATED
Rosales vs. vs. New A.N.J.H. Enterprises Rosales vs. vs. New A.N.J.H. Enterprises
formly-worded Notices dated February 12, 20106  informing them of the cessation of Please be informed that the business operations of the New ANJH Enterprises, a
operations of New ANJH effective March 15, 2010 and the sale of its assets to a single Proprietorship engaged in oil extraction situated in San Pablo City, will
corporation. Noel also offered the employees, including petitioners, their separation be permanently closed effective 15 March 2010 due to lack of capital caused by
pay. enormous uncollected receivables/debts and the necessity for the plant to undergo
On March 5, 2010, Noel signed a Deed of Sale selling the equipment, machines, general repairs and maintenance.
tools and/or other devices being used by New ANJH Enterprises for the x x x x
manufacturing and/or extraction of coconut oil for P950,000 to NH Oil, as In this connection, we respectfully request that we be allowed to effect the payment
represented by respondent Heidi A. Ilagan (Heidi), Noel’s sister.7 of the separation benefits to our employees before your Office and with your kind
6  Id., at pp. 435-444. intervention to ensure that we are properly guided by the provisions of law in this
7  Id., at pp. 190-191. undertaking.10 (emphasis supplied)
   
Parenthetically, the Articles of Incorporation of NH Oil were prepared on On March 16, 2010, petitioners Lito Feliciano (Feliciano), Edgar Solis (Solis),
January 27, 2010 with Noel appearing to have more than two-thirds (2/3) of the and Nestor Salin (Salin) received their respective separation pays, signed the
subscribed capital stock of the corporation. 8 The remaining shares had been corresponding check vouchers and executed Quitclaims and Release before Labor
subscribed by Heidi and other members of the Awayan family.9 Arbiter Melchisedek A. Guan (LA Guan) of NLRC-SRAB-IV San Pablo Office. 11
On March 8, 2010, respondents New ANJH and Noel filed before the NLRC On March 27, 2010, petitioner Leo Rosales (Rosales) similarly received his
Sub-Regional Arbitration Branch No. IV (NLRC-SRAB-IV), San Pablo City a separation pay from Noel and signed a Quitclaims and Release.12 On March 29,
“Letter Request for Intervention,” which was docketed as SRAB-IV-03-5066-10-L. 2010, the other petitioners, Arnulfo Abril (Abril), Raymundo Didal (Didal), Ruben
The letter request reads: Flores (Flores), Melchor Selga (Selga), Jonathan Ranola (Ranola), and Dante Ferma
_______________ (Ferma) also received their separation benefits and signed their
respective Quitclaims and Release and check vouchers.13

22
Following the payments thus made to petitioners and their execution 19  Id., at pp. 254-274.
of Quitclaims and Release, LA Guan issued four (4) Orders, to wit: three Orders all  
dated March 22, 2010 for  
_______________ 156
156 SUPREME COURT REPORTS ANNOTATED
10  Id., at p. 307.
Rosales vs. vs. New A.N.J.H. Enterprises
11  Id., at pp. 447-448, 451-452, 455-456.
12  Id., at pp. 445-446. with the NLRC. They also posted 60% of the award ordered by the LA, or Six
13  Id., at pp. 449-450, 453-454, 457-464. Hundred Three Thousand Six Hundred Twenty-Seven and 52/100 Pesos
  (P603,627.52), as their appeal bond.21
  Meanwhile, petitioners also filed a Memorandum of Partial Appeal contending
155 that ELA Santos erred in failing to award them moral and exemplary damages.22
On September 24, 2011, the NLRC issued a Decision 23denying respondents’
VOL. 767, AUGUST 18, 2015 155 Verified Motion to Reduce Bond for lack of merit and so dismissing their appeal for
Rosales vs. vs. New A.N.J.H. Enterprises non-perfection. In the same Decision, the NLRC also granted petitioners’ partial
petitioners Feliciano, Solis, and Salin; 14 and one Order dated April 8, 2010 for appeal by modifying ELA Santos’ Decision to include the award of P20,000.00 to
petitioners Abril, Flores, Didal, Ferma, Rosales, Selga and Ranola.15 In the said each petitioner as moral and exemplary damages.24
Orders, LA Guan declared the “labor dispute” between New ANJH and petitioners as Respondents filed their Motion for Reconsideration with Motion to Admit
“dismissed with prejudice on ground of settlement.”16 Additional Appeal Cash Bond25 with corresponding payment of additional cash
Petitioners, however, filed a complaint for illegal dismissal, docketed as NLRC bond.26
Case No. RAB-IV-04-00649-10-L, with NLRC Regional Arbitration Branch IV While the motion was opposed by petitioners, 27 the NLRC, in its Resolution
(NLRC-RAB-IV) in Calamba City. They alleged in their complaint that while New dated December 28, 2011,28reversed its earlier Decision and ordered the dismissal of
ANJH stopped its operations on March 15, 2010, it resumed its operations as NH Oil petitioners’ complaint on the ground that it was barred by the Orders issued by LA
using the same machineries and with the same owners and management. 17Petitioners Guan under the doctrine of res judicata. Further, the NLRC pointed out that the sale
thus claimed that the sale of the assets of New ANJH to NH Oil was a circumvention of New ANJH’s assets to NH Oil Mill was in the exercise of sound management
of their security of tenure. prerogative and there was no proof that it was made to defeat petitioners’ security of
In a Decision dated April 29, 2011,18 Executive Labor Arbiter Generoso V. tenure.
Santos (ELA Santos) found that petitioners had been illegally dismissed and ordered _______________
their reinstatement and the payment of One Million Six Thousand Forty-Five and
87/100 Pesos (P1,006,045.87) corresponding to the petitioners’ full backwages less 20  Id., at pp. 275-277.
the amount paid to them as their respective “separation pay.” In ruling for the 21  Id.
petitioners, ELA Santos ratiocinated that the buyer “in the ‘impending sale’ 22  Id., at pp. 286-288.
undisclosed in the notices of [petitioners] is divulged by subsequent development to 23  Id., at pp. 290-297.
be practically the same as the seller.” Hence, for ELA Santos, it was extremely 24  Id., at p. 296.
difficult to conclude that the sale was genuine and can validly justify the termination 25  Id., at pp. 298-331.
of the petitioners. 26  Id., at p. 331.
Respondents filed their Notice of Appeal with Appeal Memorandum 19 along with 27  Id., at pp. 340-346.  
a Verified Motion to Reduce Bond20 28  Supra note 2.
_______________  
 
14  Id., at pp. 184-189. 157
15  Id., at pp. 182-183. VOL. 767, AUGUST 18, 2015 157
16  Id., at pp. 183, 185, 187, and 189.
Rosales vs. vs. New A.N.J.H. Enterprises
17  Id., at pp. 116-121.
18  Id., at pp. 238-251.

23
In its Resolution dated February 28, 2012, 29 the NLRC denied petitioners’ appellant’s motion is indeed based on “meritorious ground” and whether the bond he
Motion for Reconsideration. Hence, petitioners filed a petition for certiorari with the or she posted is of a “reasonable amount.” Thus, the appellant always runs the risk of
CA. failing to perfect an appeal.
In the assailed Decision,30 the appellate court denied the petition for certiorari, x x x In order to give full effect to the provisions on motion to reduce bond, the
thereby affirming the NLRC’s Resolutions dated December 28, 2011 and February appellant must be allowed to wait for the ruling of the NLRC on the motion
28, 2012. even beyond the 10-day period to perfect an appeal. If the NLRC grants the
In its Decision, the appellate court held that private respondents had substantially motion and rules that there is indeed meritorious ground and that the amount of the
complied with the rule requiring the posting of an appeal bond equivalent to the total bond posted is reasonable, then the appeal is perfected. If the NLRC denies the
award given to the employees. More importantly, so the CA held, the Orders motion, the appellant may still file a motion for reconsideration as provided
rendered by LA Guan in NLRC Case No. SRAB-IV-03-5066-10-L were considered under Section 15, Rule VII of the Rules. If the NLRC grants the motion for
final and binding upon the parties and had the force and effect of a judgment reconsideration and rules that there is indeed meritorious ground and that the
rendered by the labor arbiter. Thus, the appellate court declared that the petitioners’ amount of the bond posted is reasonable, then the appeal is perfected. If the
complaint for illegal dismissal was already barred by res judicata. NLRC denies the motion, then the decision of the labor arbiter becomes final and
Aggrieved by the CA’s Decision, petitioners are now before this Court on a executory.
petition for review on certiorari. x x x
We find the petition to be with merit. In any case, the rule that the filing of a motion to reduce bond shall not stop the
  running of the period to perfect an appeal is not absolute. The Court may relax the
The suspension of the period to rule.
perfect the appeal upon the filing  _______________
of a motion to reduce bond 
  31  G.R. No. 196830, February 29, 2012, 667 SCRA 396.
On the issue of perfecting the appeal, the CA was correct when it pointed out that  
Rule VI of the New Rules of Procedure of the NLRC provides that a motion to  
reduce bond shall be entertained “upon the posting of a bond in a reasonable amount 159
in relation to the monetary award.” As to what the “reasonable amount” is, the VOL. 767, AUGUST 18, 2015 159
NLRC has wide discretion in determining the reasonableness of the bond for
purposes of Rosales vs. vs. New A.N.J.H. Enterprises
_______________ In Intertranz Container Lines, Inc. v. Bautista, the Court held:
        “Jurisprudence tells us that in labor
29  Supra note 3. cases, an appeal from a decision involving a
30  Supra note 1. monetary award may be perfected only upon
  the posting of cash or surety bond. The Court,
  however, has relaxed this requirement under
158 certain exceptional circumstances in order to
resolve controversies on their merits. These
158 SUPREME COURT REPORTS ANNOTATED circumstances include: (1) fundamental con-
Rosales vs. vs. New A.N.J.H. Enterprises sideration of substantial justice; (2) preven-
perfecting an appeal. In Garcia v. KJ Commercial,31 this Court explained: tion of miscarriage of justice or of unjust en-
The filing of a motion to reduce bond and compliance with the two conditions richment; and (3) special circumstances of the
stop the running of the period to perfect an appeal. x x x case combined with its legal merits, and the
x x x x amount and the issue involved.”32 (emphasis
The NLRC has full discretion to grant or deny the motion to reduce bond, and underscoring supplied)
and it may rule on the motion beyond the 10-day period within which to perfect  
an appeal. Obviously, at the time of the filing of the motion to reduce bond and In this case, the NLRC had reconsidered its original position and declared that
posting of a bond in a reasonable amount, there is no assurance whether the the 60% bond was reasonable given the merits of the justification provided by

24
respondents in their Motion to Reduce Bond, as supplemented by their Motion for discretion on the part of the NLRC and the affirmation of the CA of the
Reconsideration with Motion to Admit Additional Appeal Cash Bond. The CA reasonableness of the motions and the amount of bond posted, there is
affirmed the merits of the grounds cited by respondents in their motions and the _______________
reasonableness of the bond originally posted by respondents. This is in accord with
the guidelines established in McBurnie v. Ganzon,33 where this Court declared that 34  Id., at pp. 693-694.
the posting of a provisional cash or surety bond equivalent to ten percent (10%) of  
the monetary award subject of the appeal is sufficient provided that there is  
meritorious ground therefor, viz.: 161
[O]n the matter of the filing and acceptance of motions to reduce appeal bond, as VOL. 767, AUGUST 18, 2015 161
provided in Section 6, Rule VI of the 2011 NLRC Rules of Procedure, the Court
hereby Rosales vs. vs. New A.N.J.H. Enterprises
_______________ no ground for this Court to reverse the CA’s finding that the appeal had been
perfected.  
32  Id., at pp. 409-411.  
33  G.R. Nos. 178034 & 178117, G.R. Nos. 186984-85, October 17, 2013, 707 Res Judicata does not bar the 
SCRA 646. filing of the complaints for 
  illegal dismissal
   
160 On the matter of the application of the doctrine of res judicata, however, this
Court is loath to sustain the finding of the appellate court and the NLRC. For res
160 SUPREME COURT REPORTS ANNOTATED judicata to apply, the concurrence of the following requisites must be verified: (1)
Rosales vs. vs. New A.N.J.H. Enterprises the former judgment is final; (2) it is rendered by a court having jurisdiction over the
RESOLVES that henceforth, the following guidelines shall be observed: subject matter and the parties; (3) it is a judgment or an order on the merits; (4) there
(a) The filing of a motion to reduce appeal bond shall be entertained by is —between the first and the second actions — identity of parties, of subject matter,
the NLRC subject to the following conditions: (1) there is meritorious and of causes of action.35
ground; and (2) a bond in a reasonable amount is posted; The petitioners dispute the existence of all of the foregoing requisites. First,
(b) For purposes of compliance with condition no. (2), a motion shall be petitioners contend that LA Guan does not have jurisdiction to issue the Orders in
accompanied by the posting of a provisional cash or surety bond equivalent SRAB-IV-03-5066-10-L since, in the first place, Noel’s letter-request for guidance in
to ten percent (10%) of the monetary award subject of the appeal, the payment of separation pay is allegedly not a “labor dispute.”
exclusive of damages and attorney’s fees; Article 219 (previously Article 212) of the Labor Code defines a “labor dispute”
(c) Compliance with the foregoing conditions shall suffice to suspend as “any controversy or matter concerning terms and conditions of employment or
the running of the 10-day reglementary period to perfect an appeal from the the association or representation of persons in negotiating, fixing, maintaining,
labor arbiter’s decision to the NLRC; changing or arranging the terms and conditions of employment, regardless of
(d) The NLRC retains its authority and duty to resolve the motion to whether the disputants stand in the proximate relation of employer and employee.”
reduce bond and determine the final amount of bond that shall be posted by As separation pay concerns a term and condition of employment, Noel’s request to
the appellant, still in accordance with the standards of meritorious grounds be guided in the payment thereof is clearly a labor dispute under the Labor Code.
and reasonable amount; and _______________
(e) In the event that the NLRC denies the motion to reduce bond, or
requires a bond that exceeds the amount of the provisional bond, the 35  Luzon Development Bank v. Conquilla, G.R. No. 163338, September 21,
appellant shall be given a fresh period of ten (10) days from notice of the 2005, 470 SCRA 533, 545.
NLRC order within which to perfect the appeal by posting the required  
appeal bond.34 (emphasis and underscoring added)  
  162
It is noted that the respondents have eventually posted the full amount of the 162 SUPREME COURT REPORTS ANNOTATED
award ordered by the labor arbiter. Thus, given the absence of grave abuse of
Rosales vs. vs. New A.N.J.H. Enterprises
25
The proper payment of separation pay further falls under the jurisdiction of the In the absence of the third and fourth requisites, the appellate court should have
labor arbiter pursuant to Art. 224 (previously Art. 217) of the Labor Code, as it is proceeded to rule on the validity of petitioners’ termination.
mandated as a necessary condition for the termination of employees, viz.:  
Art. 224. Jurisdiction of the Labor Arbiters and the Commission. Piercing the veil of corporate 
(a) Except as otherwise provided under this Code, the Labor Arbiters shall have existence is justified in the 
original and exclusive jurisdiction to hear and decide, within thirty (30) calendar present case 
days after the submission of the case by the parties for decision without extension,  
even in the absence of stenographic notes, the following cases involving all workers, The application of the doctrine of piercing the veil of corporate fiction is frowned
whether agricultural or nonagricultural:   upon. However, this Court will not hesitate to disregard the corporate fiction if it is
1. Unfair labor practice cases; used to such
2. Termination disputes; _______________
x x x x
6. Except claims for employees compensation, social security, medicare and 36  A judgment is “on the merits” when it amounts to a legal declaration of the
maternity benefits, all other claims arising from employer-employee relations, respective rights and duties of the parties, based upon the disclosed facts.
including those of persons in domestic or household service, involving an amount See Manalo v. Court of Appeals, G.R. No. 124204, April 20, 2001, 357 SCRA 112,
exceeding five thousand pesos (P5,000.00) regardless of whether accompanied with 121; Mendiola v. Court of Appeals, G.R. No. 122807, July 5, 1996, 258 SCRA 492,
a claim for reinstatement. (emphasis supplied) 500-501.
  37  G.R. No. 184517, October 8, 2013, 707 SCRA 35.
The invocation of the labor arbiter’s jurisdiction by way of a letter-request 38  Id., at p. 57.
instead of a complaint is of no moment, as it is well-settled that the application of  
technical rules of procedure is relaxed in labor cases.    
The third requisite, however, is not present. The Orders rendered by LA Guan 164
cannot be considered as constituting a judgment on the merits. The Orders simply 164 SUPREME COURT REPORTS ANNOTATED
manifest that petitioners “are amenable to the computations made by the company
respecting their separation pay.” Nothing more. Rosales vs. vs. New A.N.J.H. Enterprises
  an extent that injustice, fraud, or crime is committed against another in disregard of
  his rights.39
163 In this case, petitioners advance the application of the doctrine because they were
terminated from employment on the pretext that there will be an impending
VOL. 767, AUGUST 18, 2015 163 permanent closure of the business as a result of an intended sale of its assets to an
Rosales vs. vs. New A.N.J.H. Enterprises undisclosed corporation, and that there will be a change in the management. The
They do not clearly state the petitioners’ right or New ANJH’s corresponding duty as termination notices received by petitioners identically read:
a result of the termination.36 Nais po naming ipaabot sa inyo na ang New ANJH Enterprises ay ihihinto na
Similarly, the fourth requisite is also absent. While there may be substantial ang operasyon dahil sa nagpasya ako bilang may-ari na ipagbili na ang ari-arian
identity of the parties, there is no identity of subject matter or cause of action. nito sa iba kung kayat magkakaroon ng pagpapalit sa pamumunuan nito.
In SME Bank, Inc. v. De Guzman,37 this Court held that the acceptance of separation Kaugnay po nito at ayon sa itinatadhana ng batas ay nais kong ipaabot sa inyo
pay is an issue distinct from the legality of the dismissal of the employees. We held: na 30 araw matapos ninyong matanggap ang pasabing ito o simula sa Marso 15,
The conformity of the employees to the corporation’s act of considering them as 2010 ay ititigil na ang operasyon ng New ANJH Enterprises at sa nasabi ring petsa
terminated and their subsequent acceptance of separation pay does not remove the ay matatapos na rin ang pagtratrabaho o “employment” ninyo sa New ANJH
taint of illegal dismissal. Acceptance of separation pay does not bar the Enterprises.40
employees from subsequently contesting the legality of their dismissal, nor does  
it estop them from challenging the legality of their separation from the Subsequent events, however, revealed that the buyer of the assets of their
service.38 (emphasis supplied) employer was a corporation owned by the same employer and members of his
  family. Furthermore, the business reopened in less than a month under the same
management.

26
Admittedly, mere ownership by a single stockholder of all or nearly all of the  
capital stock of the corporation does not by itself justify piercing the corporate veil.  
Nonetheless, in this case, other circumstances show that the buyer of the assets of 166
  166 SUPREME COURT REPORTS ANNOTATED
_______________
Rosales vs. vs. New A.N.J.H. Enterprises
39  Kukan International Corporation v. Reyes, G.R. No. 182729, September 29, and/or extraction of coconut oil. This Office cannot simply accept it as sufficient
2010, 631 SCRA 596, 617. proof of sale by the seller to a distinct and separate entity.
40  Rollo, pp. 435-444. x x x x
  The subscribed capital stock of Noel and Heidi [in NH Oil] are worth
  Php790,000.00 and Php190,000.00, respectively, or the total of
165 Php980,000.00. Respondents claim that Noel was managing ANJH and Heidi
was its Secretary. The Deed of Sale is signed by Noel and Heidi, Noel as [seller],
VOL. 767, AUGUST 18, 2015 165 and Heidi as representative of NH Oil Mill. Respondents did not enumerate what
Rosales vs. vs. New A.N.J.H. Enterprises [were] the equipment etc. subject of the “sale,” and how they were depreciated, and
petitioners’ employer is none other than his alter ego. 41 We quote with approval the what [were] the equipment/machines owned by Avelino and rented by NH Oil Mill
observations of ELA Santos: and for how much? Therefrom, it is extremely difficult to conclude by quantum of
Respondents did not allege that they informed complainants neither did they state evidence acceptable to [a] reasonable mind, [that] the “sale to a distinct entity” is
in the notices of termination that the buyer in the “impending sale” is NH Oil Mill. genuine. And while the notices of termination state that there would be [a] change in
Pondering on these observations, this Office finds it too difficult to surmise that management, this Office notes that respondents do not deny that Noel and Heidi
respondents’ omission was not deliberate, and so this Office holds that Noel was not continue to manage NH Oil Mill. Therefore, as far as complainants’ employment is
in good faith in dealing with complainants. The information disclosed by the concerned, this Office pierces the veil of corporate fiction of NH Oil Mill and finds
Certificate of Registration and Articles of Incorporation of NH Oil Mill explains that the purported sale thereto of the assets of ANJH is insufficient to validly
respondents’ motive. Its stockholders are members of [Noel’s] family known to terminate such employment. This Office cannot rule otherwise without running afoul
complainants, and Noel is the controlling stockholder and director. The to the mandate of the Constitution securing to the workingman his employment, and
immediate resumption of operation after cessation of operation on March 15, 2010 guaranteeing to him full protection. So this Office declares that complainants were
further explains it. While complainants failed to prove that the stockholders in NH illegally dismissed.42 (emphasis and underscoring supplied)
Oil Mill were those who managed ANJH, respondents did not dispute that there  
was no change in the management people, premises, tools, devices, equipment, Clearly, the milieu of the present case compels this Court to remove NH Oil’s
and machinery under NH Oil Mill. The buyer in the “impending sale” corporate mask as it had become, and was used as, a shield for fraud, illegality and
undisclosed in the notices to complainants is divulged by subsequent inequity against the petitioners.
development to be practically the same as the seller. These things are inconsistent _______________
with good faith.
x x x x 42  Rollo, pp. 246-248.
Here, complainants’ employment was terminated for the alleged sale of assets of  
ANJH to NH Oil Mill that would allegedly entail [a] change of management. The  
Deed of Sale dated March 5, 2010 [that] respondents presented (Annex “20,” 167
respondents position paper) to prove the “sale,” states that [for] the consideration of VOL. 767, AUGUST 18, 2015 167
Nine Hundred Fifty Thousand Pesos (Php950,000.00), Noel sold to NH Oil Mill the
Rosales vs. vs. New A.N.J.H. Enterprises
equipment, machines, tool and/or other devises being used by ANJH for
manufacturing WHEREFORE, the instant petition is GRANTED and the Decision dated
_______________ September 5, 2012 of the Court of Appeals in C.A.-G.R. S.P. No. 124395, affirming
the Resolutions of the National Labor Relations Commission (NLRC) dated
41  Prince Transport, Inc. v. Garcia, G.R. No. 167291, January 12, 2011, 639 December 28, 2011 and February 28, 2012 in NLRC-LAC Case No. 07-001796-11,
SCRA 312. is hereby REVERSEDand SET ASIDE. The Decision of Executive Labor Arbiter

27
Generoso Santos in NLRC Case No. RAB-IV-04-00649-10-L to the effect that
petitioners were illegally dismissed is REINSTATED.
SO ORDERED.
Sereno (CJ.), Carpio, Leonardo-De Castro, Brion, Peralta, Bersamin, Del
Castillo, Perez, Mendoza, Perlas-Bernabe, Leonen and Jardeleza, JJ., concur.
Villarama, Jr., J., On Official Leave.
Reyes, J., On Leave.
Petition granted, judgment reversed and set aside.
Notes.—Under a variation of the doctrine of piercing the veil of corporate
fiction, when two business enterprises are owned, conducted and controlled by the
same parties, both law and equity will, when necessary to protect the rights of third
parties, disregard the legal fiction that two corporations are distinct entities and treat
them as identical or one and the same. (Heirs of Fe Tan Uy vs. International
Exchange Bank, 690 SCRA 519 [2013])
No motion to reduce bond shall be entertained except on meritorious grounds and
upon the posting of a bond in a reasonable amount in relation to the monetary award.
(McBurnie vs. Ganzon, 707 SCRA 646 [2013])
 
 
——o0o——

G.R. No. 168612. December 10, 2014.*


 
PHILIPPINE ELECTRIC CORPORATION (PHILEC), petitioner, vs. COURT
OF APPEALS, NATIONAL CONCILIATION AND MEDIATION BOARD
(NCMB), Department of Labor and Employment, RAMON T. JIMENEZ, in his
capacity as Voluntary Arbitrator, PHILEC WORKERS’ UNION (PWU),
ELEODORO V. LIPIO, and EMERLITO C. IGNACIO, respondents.
Labor Law; Voluntary Arbitrators; Appeals; The proper remedy to reverse or
modify a Voluntary Arbitrator’s or a panel of Voluntary Arbitrators’ decision or
award is to appeal the award or decision before the Court of Appeals (CA).—The
proper remedy to reverse or modify a Voluntary Arbitrator’s or a panel of Voluntary
Arbitrators’ decision or award is to appeal the award or decision before the Court of
Appeals.
Same; Same; Jurisdiction; A Voluntary Arbitrator or a panel of Voluntary

28
Arbitrators has the exclusive original jurisdiction over grievances arising from the
interpretation or implementation of collective bargaining agreements.—A Voluntary VOL. 744, DECEMBER 10, 2014
Arbitrator or a panel of Voluntary Arbitrators has the exclusive original jurisdiction Philippine Electric Corporation (PHILEC) vs. Court of Appeals
over grievances arising from the interpretation or implementation of collective
bargaining agreements.  Should the parties agree, a Volun-
_______________ Same; Same; Same; Perfection of an appeal within the reglementary period is
*  SECOND DIVISION. not only mandatory but also jurisdictional so that failure to do so rendered the
362 decision final and executory, and deprives the appellate court of jurisdiction to alter
the final judgment much less to entertain the appeal.—Appeal is a “statutory
362 SUPREME COURT REPORTS ANNOTATED privilege,” which may be exercised “only in the manner and in accordance with the
Philippine Electric Corporation (PHILEC) vs. Court of Appeals provisions of the law.” “Perfection of an appeal within the reglementary period is not
only mandatory but also jurisdictional so that failure to do so rendered the decision
final and executory, and deprives the appellate court of jurisdiction to alter the final
tary Arbitrator or a panel of Voluntary Arbitrators shall also resolve the parties’ other judgment much less to entertain the appeal.”
labor disputes, including unfair labor practices and bargaining deadlocks. Labor Law; Voluntary Arbitrators; Judgments; Statute provides that the
Same; Same; Appeals; Since the office of a Voluntary Arbitrator or a panel of Voluntary Arbitrator’s decision “shall be final and executory after ten (10) calendar
Voluntary Arbitrators is considered a quasi-judicial agency, the Supreme Court (SC) days from receipt of the copy of the award or decision by the parties.”—We ruled
concluded that a decision or award rendered by a Voluntary Arbitrator is that Article 262-A of the Labor Code allows the appeal of decisions rendered by
appealable before the Court of Appeals (CA).—Since the office of a Voluntary Voluntary Arbitrators. Statute provides that the Voluntary Arbitrator’s decision
Arbitrator or a panel of Voluntary Arbitrators is considered a quasi-judicial agency, “shall be final and executory after ten (10) calendar days from receipt of the copy of
this court concluded that a decision or award rendered by a Voluntary Arbitrator is the award or decision by the parties.” Being provided in the statute, this 10-day
appealable before the Court of Appeals. Under Section 9 of the Judiciary period must be complied with; otherwise, no appellate court will have jurisdiction
Reorganization Act of 1980, the Court of Appeals has the exclusive original over the appeal. This absurd situation occurs when the decision is appealed on the
jurisdiction over decisions or awards of quasi-judicial agencies and instrumentalities. 11th to 15th day from receipt as allowed under the Rules, but which decision, under
Same; Same; Judgments; Article 262-A of the Labor Code provides that the the law, has already become final and executory.
award or decision of the Voluntary Arbitrator “shall be final and executory after ten Same; Same; Appeals; The ten (10)-day period to appeal under the Labor
(10) calendar days from receipt of the copy of the award or decision by the Code being a substantive right, this period cannot be diminished, increased, or
parties.”—Article 262-A of the Labor Code provides that the award or decision of modified through the Rules of Court.—Under Article VIII, Section 5(5) of the
the Voluntary Arbitrator “shall be final and executory after ten (10) calendar days Constitution, this court “shall not diminish, increase, or modify substantive rights” in
from receipt of the copy of the award or decision by the parties.” promulgating rules of procedure in courts. The 10-day period to appeal under the
Remedial Law; Civil Procedure; Appeals; It is true that Rule 43, Section 4 of Labor Code being a substantive right, this period cannot be diminished, increased, or
the Rules of Court provides for a fifteen (15)-day reglementary period for filing an modified through the Rules of Court.
appeal.—It is true that Rule 43, Section 4 of the Rules of Court provides for a 15-day Same; Same; Same; The rule is that a Voluntary Arbitrator’s award or
reglementary period for filing an appeal: Section 4. Period of appeal.—The appeal decision shall be appealed before the Court of Appeals (CA) within ten (10) days
shall be taken within fifteen (15) days from notice of the award, judgment, final from receipt of the award or decision.—The rule, therefore, is that a Voluntary
order or resolution, or from the date of its last publication, if publication is required Arbitrator’s award or decision shall be appealed before the Court of Appeals within
by law for its effectivity, or of the denial of petitioner’s motion for new trial or 10 days from receipt of the award or decision. Should the aggrieved party choose to
reconsideration duly filed in accordance with the governing law of the court or file a
agency a quo. Only one (1) motion for reconsideration shall be allowed. Upon proper 364
motion and the payment of the full amount of the docket fee before the expiration of
the reglementary period, the Court of Appeals may grant an additional period of 364 SUPREME COURT REPORTS ANNOTATED
fifteen (15) days only within which to file the petition for review. No further Philippine Electric Corporation (PHILEC) vs. Court of Appeals
extension shall be granted except for the most compelling reason and in no case to
exceed fifteen (15) days.
363 motion for reconsideration with the Voluntary Arbitrator, the motion must be filed

29
within the same 10-day period since a motion for reconsideration is filed “within the May 25, 2004, dismissing the Philippine Electric Corporation’s petition for
period for taking an appeal.” certiorari for lack of merit.
Remedial Law; Special Civil Actions; Certiorari; An extraordinary remedy, a  Philippine Electric Corporation (PHILEC) is a domestic corporation “engaged in the
petition for certiorari may be filed only if appeal is not available. If appeal is manufacture and repairs of high voltage transformers.” 3 Among its rank-and-file
available, an appeal must be taken even if the ground relied upon is grave abuse of employees were Eleodoro V. Lipio (Lipio) and Emerlito C. Ignacio, Sr. (Ignacio,
discretion.—A petition for certiorari is a special civil action “adopted to correct Sr.), former members of the PHILEC Workers’ Union (PWU). 4 PWU is a legitimate
errors of jurisdiction committed by the lower court or quasi-judicial agency, or when labor organization and the exclusive bargaining representative of PHILEC’s rank-
there is grave abuse of discretion on the part of such court or agency amounting to and-file employees.5
lack or excess of jurisdiction.” An extraordinary remedy, a petition for certiorari From June 1, 1989 to May 31, 1997, PHILEC and its rank-and-file employees were
may be filed only if appeal is not available. If appeal is available, an appeal must be governed by collective bargaining agreements providing for the following step
taken even if the ground relied upon is grave abuse of discretion. As an exception to increases in an employee’s basic salary in case of promotion:6
the rule, this court has allowed petitions for certiorari to be filed in lieu of an appeal _______________
“(a) when the public welfare and the advancement of public policy dictate; (b) when 1  Rollo, pp. 9-29.
the broader interests of justice so require; (c) when the writs issued are null; and (d) 2  Id., at pp. 32-40. The decision docketed as C.A.-G.R. S.P. No. 60457 was
when the questioned order amounts to an oppressive exercise of judicial authority.” penned by Associate Justice Aurora Santiago-Lagman and concurred in by Associate
Labor Law; Collective Bargaining Agreements; Words and Phrases; A Justices Romeo A. Brawner and Juan Q. Enriquez, Jr. of the Twelfth Division.
collective bargaining agreement (CBA) is “a contract executed upon the request of 3  Id., at p. 84.
either the employer or the exclusive bargaining representative of the employees 4  Id.
incorporating the agreement reached after negotiations with respect to wages, hours 5  Id.
of work and all other terms and conditions of employment, including proposals for 6  Id., at pp. 84 and 91.
adjusting any grievances or questions arising under such agreement.”—A collective 366
bargaining agreement is “a contract executed upon the request of either the employer
or the exclusive bargaining representative of the employees incorporating the 366 SUPREME COURT REPORTS ANNOTATED
agreement reached after negotiations with respect to wages, hours of work and all Philippine Electric Corporation (PHILEC) vs. Court of Appeals
other terms and conditions of employment, including proposals for adjusting any
grievances or questions arising under such agreement.” A collective bargaining
agreement being a contract, its provisions “constitute the law between the parties”  
and must be complied with in good faith.
PETITION for review on certiorari of a decision of the Court of Appeals.
The facts are stated in the opinion of the Court.
365
VOL. 744, DECEMBER 10, 2014
Philippine Electric Corporation (PHILEC) vs. Court of Appeals

  Sanidad, Abaya, Te, Viterbo, Enriquez & Tan for petitioner.


  Potenciano A. Flores, Jr. for respondents.
 
LEONEN, J.:
 
An appeal to reverse or modify a Voluntary Arbitrator’s award or decision must be
filed before the Court of Appeals within 10 calendar days from receipt of the award
or decision.
This is a petition1 for review on certiorari of the Court of Appeals’ decision 2 dated  

30
On August 18, 1997 and with the previous collective bargaining agreements already agreement, effective retroactively
expired, PHILEC selected Lipio for promotion from Machinist under Pay Grade _______________
VIII7 to Foreman I under Pay Grade B. 8 PHILEC served Lipio a memorandum,9 10  Id.
instructing him to undergo training for the position of Foreman I beginning on 11  Id., at p. 76.
August 25, 1997.  PHILEC undertook to pay Lipio training allowance as provided in 12  Id., at p. 135.
the memorandum: 13  Id.
This will confirm your selection and that you will undergo training for the position of 14  Id.
Foreman I (PG B) of the Tank Finishing Section, Distribution Transformer 368
Manufacturing and Repair effective August 25, 1997.
You will be trained as a Foreman I, and shall receive the following training 368 SUPREME COURT REPORTS ANNOTATED
allowance until you have completed Philippine Electric Corporation (PHILEC) vs. Court of Appeals
_______________
7  Id., at p. 76.
8  Id., at p. 134. on June 1, 1997 and expiring on May 31, 1999. 15 Under Article X, Section 4 of the
9  Id. June 1, 1997 collective bargaining agreement, a rank-and-file employee promoted
367 shall be entitled to the following step increases in his or her basic salary:16
Section 4. STEP INCREASES.—[Philippine Electric Corporation] shall adopt the
VOL. 744, DECEMBER 10, 2014 following step increases on the basic salary in case of promotion effective June 1,
Philippine Electric Corporation (PHILEC) vs. Court of Appeals 1997. Such increases shall be based on the scale below or upon the minimum of the
new pay grade to which the employee is promoted, whichever is higher:
 
the training/observation period which shall not exceed four (4) months.
First Month - - - - - P350.00
Second Month - - - - - P815.00
Third Month - - - - - P815.00
Fourth Month - - - - - P815.00
Please be guided accordingly.10
 
Ignacio, Sr., then DT-Assembler with Pay Grade VII, 11 was likewise selected for
training for the position of Foreman I.12 On August 21, 1997, PHILEC served
Ignacio, Sr. a memorandum,13 instructing him to undergo training with the following
schedule of allowance:    
This will confirm your selection and that you will undergo training for the position of To be promoted, a rank-and-file employee shall undergo training or observation and
Foreman I (PG B) of the Assembly Section, Distribution Transformer Manufacturing shall receive training allowance as provided in Article IX, Section 1(f) of the June 1,
and Repair effective August 25, 1997. 1997 collective bargaining agreement:17
You will be trained as a Foreman I, and shall receive the following training Section 1. JOB POSTING AND BIDDING:
allowance until you have completed the training/observation period which shall not ....
exceed four (4) months. (f) Allowance for employees under Training or Observation shall be on a graduated
First Month - - - - - P255.00 basis as follows:
Second Month - - - - - P605.00 For the first month of training, the allowance should be equivalent to one step
Third Month - - - - - P1,070.00 increase of the next
Fourth Month - - - - - P1,070.00 _______________
Please be guided accordingly.14 15  Id., at pp. 64 and 113.
  16  Id., at pp. 86-87 and 113-114.
On September 17, 1997, PHILEC and PWU entered into a new collective bargaining 17  Id., at pp. 113-114.
31
369 In their submission agreement, PWU and PHILEC designated Hon. Ramon T.
Jimenez as Voluntary Arbitrator (Voluntary Arbitrator Jimenez). 22
VOL. 744, DECEMBER 10, 2014 Voluntary Arbitrator Jimenez, in the order23 dated January 4, 1999, directed the
Philippine Electric Corporation (PHILEC) vs. Court of Appeals parties to file their respective position papers.
In its position paper,24 PWU maintained that PHILEC failed to follow the schedule of
step increases under Article X, Section 4 of the June 1, 1997 collective bargaining
higher grade. Every month thereafter the corresponding increase shall be equivalent agreement.  Machinist I, Lipio’s position before he underwent training for Foreman
to the next higher grade until the allowance for the grade applied for is attained. I, fell under Pay Grade VIII, while Foreman I fell under Pay Grade X. Following the
As an example, if a Grade I employee qualifies for a Grade III position, he will schedule under Article X, Section 4 of the June 1, 1997 collective bargaining
receive the training allowance for Grade I to Grade II for the first month. On the agreement and the formula under Article IX, Section 1(f), Lipio should be paid
second month, he will receive the training allowance for Grade I to Grade II plus the training allowance equal to the step increase for pay grade bracket VIII-IX for the
allowance for Grade II to Grade III. He will then continue to receive this amount first month of training. For the succeeding months, Lipio should be paid an
until he finishes his training or observation period.18 allowance equal to the step increase for pay grade bracket VIII-IX plus the step
  increase for pay grade bracket IX-X, thus:25
Claiming that the schedule of training allowance stated in the memoranda served on
Lipio and Ignacio, Sr. did not conform to Article X, Section 4 of the June 1, 1997 First month - - - - - P456.00
collective bargaining agreement, PWU submitted the grievance to the grievance Second month - - - - - P1,031.00
machinery.19 Third month - - - - - P1,031.00
PWU and PHILEC failed to amicably settle their grievance.  Thus, on December 21, Fourth month - - - - - P1,031.00.
1998, the parties filed a submission agreement 20 with the National Conciliation and _______________
Mediation Board, submitting the following issues to voluntary arbitration: 21  Id., at p. 73.
I 22  Id.
WHETHER OR NOT PHILEC VIOLATED SECTION 4 (Step Increases) 23  Id., at p. 82.
ARTICLE X (Wage and Position Standardization) OF THE EXISTING 24  Id., at pp. 111-133.
COLLECTIVE BARGAINING AGREEMENT (CBA) IN IMPLEMENTING THE 25  Id., at pp. 123-125.
STEP INCREASES RELATIVE TO THE PROMOTION OF INDIVIDUAL 371
COMPLAINANTS.
  VOL. 744, DECEMBER 10, 2014
II Philippine Electric Corporation (PHILEC) vs. Court of Appeals
WHETHER OR NOT PHILEC’s MANNER OF IMPLEMENTING THE STEP
INCREASES IN CONNECTION
_______________ With respect to Ignacio, Sr., he was holding the position of DT-Assembler under Pay
18  Id., at p. 65. Grade VII when he was selected to train for the position of Foreman I under Pay
19  Id., at pp. 85-86 and 115. Grade X. Thus, for his first month of training, Ignacio, Sr. should be paid training
20  Id., at pp. 73-74. allowance equal to the step increase under pay grade bracket VII-VIII. For the
370 second month, he should be paid an allowance equal to the step increase under pay
grade bracket VII-VIII plus the step increase under pay grade bracket VIII-IX. For
370 SUPREME COURT REPORTS ANNOTATED the third and fourth months, Ignacio, Sr. should receive an allowance equal to the
Philippine Electric Corporation (PHILEC) vs. Court of Appeals amount he received for the second month plus the amount equal to the step increase
under pay grade bracket IX-X, thus:26
First month - - - - - P361.00
WITH THE PROMOTION OF INDIVIDUAL COMPLAINANTS IN RELATION Second month - - - - - P817.00
TO THE PROVISIONS OF SECTION 4, ARTICLE X OF THE CBA Third month - - - - - P1,392.00
CONSTITUTES UNFAIR LABOR PRACTICE.21 Fourth month - - - - - P1,392.00.
   

32
For PHILEC’s failure to apply the schedule of step increases under Article X of the 30  Id., at pp. 86-87.
June 1, 1997 collective bargaining agreement, PWU argued that PHILEC committed 31  Id., at p. 85.
an unfair labor practice under Article 24827 of the Labor Code.28 32  Id., at p. 87.
In its position paper,29 PHILEC emphasized that it promoted Lipio and Ignacio, Sr. 33  Id., at p. 67.
while it was still negotiating a new collective bargaining agreement with PWU. 34  Id.
Since PHILEC and PWU had not yet negotiated a new collective bargaining 373
agreement when PHILEC selected Lipio and Ignacio,
_______________ VOL. 744, DECEMBER 10, 2014
26  Id. Philippine Electric Corporation (PHILEC) vs. Court of Appeals
27  Labor Code, Art. 248 provides:
Art. 248. Unfair labor practices of employers.—It shall be unlawful for an
employer to commit any of the following unfair labor practice:  
....
(i) To violate a collective bargaining agreement.
28  Rollo, p. 129.
29  Id., at pp. 83-90.
372
372 SUPREME COURT REPORTS ANNOTATED
Philippine Electric Corporation (PHILEC) vs. Court of Appeals

Sr. for training, PHILEC applied the “Modified SGV” pay grade scale in computing
Lipio’s and Ignacio, Sr.’s training allowance.30
This “Modified SGV” pay grade scale, which PHILEC and PWU allegedly agreed to
implement beginning on May 9, 1997, covered both rank-and-file and supervisory
employees.31 According to PHILEC, its past collective bargaining agreements with  
the rank-and-file and supervisory unions resulted in an overlap of union membership Pay grade bracket I-IX covered rank-and-file employees, while pay grade bracket A-
in Pay Grade IX of the rank-and-file employees and Pay Grade A of the supervisory F covered supervisory employees.35
employees.32 Worse, past collective bargaining agreements resulted in rank-and-file Under the “Modified SGV” pay grade scale, the position of Foreman I fell under Pay
employees under Pay Grades IX and X enjoying higher step increases than Grade B. PHILEC then computed Lipio’s and Ignacio, Sr.’s training allowance
supervisory employees under Pay Grades A and B:33 accordingly.36
  PHILEC disputed PWU’s claim of unfair labor practice. According to PHILEC, it
did not violate its collective bargaining agreement with PWU when it implemented
the “Modified SGV” scale. Even assuming that it violated the collective bargaining
agreement, PHILEC argued that its violation was not “gross” or a “flagrant and/or
malicious refusal to comply with the economic provisions of [the collective
bargaining agreement].”37 PHILEC, therefore, was not guilty of unfair labor
practice.38
_______________
  35  Id.
To preserve the hierarchical wage structure within PHILEC’s enterprise, PHILEC 36  Id., at p. 54.
and PWU allegedly agreed to implement the uniform pay grade scale under the 37  Labor Code, Art. 261 provides:
“Modified SGV” pay grade system, thus:34 Art. 261. Jurisdiction of Voluntary Arbitrators or panel of Voluntary
_______________ Arbitrators.—The Voluntary Arbitrator or panel of Voluntary Arbitrators shall have
33
original and exclusive jurisdiction to hear and decide all unresolved grievances ing agreement] nor . . . [a] flagrant and/or malicious refusal to comply with the
arising from the interpretation or implementation of the Collective Bargaining economic provisions of the [agreement].”45
Agreement and those arising from the interpreta- Thus, Voluntary Arbitrator Jimenez ordered PHILEC to pay Lipio and Ignacio, Sr.
374 training allowance based on Article X, Section 4 and Article IX, Section 1 of the
June 1, 1997 collective bargaining agreement.46
374 SUPREME COURT REPORTS ANNOTATED PHILEC received a copy of Voluntary Arbitrator Jimenez’s decision on August 16,
Philippine Electric Corporation (PHILEC) vs. Court of Appeals 1999.47 On August 26, 1999, PHILEC filed a motion for partial reconsideration 48 of
Voluntary Arbitrator Jimenez’s decision.
In the resolution49 dated July 7, 2000, Voluntary Arbitrator Jimenez denied
Voluntary Arbitrator Jimenez held in the decision 39 dated August 13, 1999, that PHILEC’s motion for partial reconsideration for lack of merit. PHILEC received a
PHILEC violated its collective bargaining agreement with PWU. 40 According to copy of the July 7, 2000 resolution on August 11, 2000.50
Voluntary Arbitrator Jimenez, the June 1, 1997 collective bargaining agreement On August 29, 2000, PHILEC filed a petition51 for certiorari before the Court of
governed when PHILEC selected Lipio and Ignacio, Sr. for promotion on August 18 Appeals, alleging that Voluntary Arbitrator Jimenez gravely abused his discretion in
and 21, 1997.41 The provisions of the collective bargaining agreement being the law rendering his decision.52 PHILEC maintained that it did not violate the June 1, 1997
between the parties, PHILEC should have computed Lipio’s and Ignacio, Sr.’s collective bargaining agreement.53 It applied the “Modified SGV” pay grade rates to
training allowance based on Article X, Section 4 of the June 1, 1997 collective avoid salary distortion within its enterprise. 54
bargaining agreement.42 In addition, PHILEC argued that Article X, Section 4 of the collective bargaining
As to PHILEC’s claim that applying Article X, Section 4 would result in salary agreement did not apply to Lipio and Ignacio, Sr. Considering that Lipio and Ignacio,
distortion within PHILEC’s enterprise, Voluntary Arbitrator Jimenez ruled that this Sr. were promoted to a supervisory position, their training allowance
was “a concern that PHILEC could have anticipated and could have taken corrective _______________
action”43 before signing the collective bargaining agreement. 45  Id., at pp. 70-71.
Voluntary Arbitrator Jimenez dismissed PWU’s claim of unfair labor practice. 44 46  Id., at p. 70.
According to him, PHILEC’s acts “cannot be considered a gross violation of the 47  Id., at p. 180.
[collective bargain- 48  Id., at pp. 179-185.
_______________ 49  Id., at p. 72.
tion or enforcement of company personnel policies referred to in the immediately 50  Id., at p. 46.
preceding article. Accordingly, violations of a Collective Bargaining Agreement, 51  Id., at pp. 45-59.
except those which are gross in character, shall no longer be treated as unfair labor 52  Id., at p. 52.
practice and shall be resolved as grievances under the Collective Bargaining 53  Id., at p. 57.
Agreement. For purposes of this article, gross violations of Collective Bargaining 54  Id., at p. 53.
Agreement shall mean flagrant and/or malicious refusal to comply with the economic 376
provisions of such agreement.
38  Rollo, p. 88. 376 SUPREME COURT REPORTS ANNOTATED
39  Id., at pp. 63-71. Philippine Electric Corporation (PHILEC) vs. Court of Appeals
40  Id., at p. 70.
41  Id., at pp. 68-69.
42  Id. should be computed based on the provisions of PHILEC’s collective bargaining
43  Id., at pp. 69-70. agreement with ASSET, the exclusive bargaining representative of PHILEC’s
44  Id., at p. 71. supervisory employees.55
375 The Court of Appeals affirmed Voluntary Arbitrator Jimenez’s decision. 56 It agreed
that PHILEC was bound to apply Article X, Section 4 of its June 1, 1997 collective
VOL. 744, DECEMBER 10, 2014 bargaining agreement with PWU in computing Lipio’s and Ignacio, Sr.’s training
Philippine Electric Corporation (PHILEC) vs. Court of Appeals allowance.57 In its decision, the Court of Appeals denied due course and dismissed
PHILEC’s petition for certiorari for lack of merit.58
PHILEC filed a motion for reconsideration, which the Court of Appeals denied in the

34
resolution59 dated June 23, 2005. We note that PHILEC filed before the Court of Appeals a petition for certiorari
On August 3, 2005, PHILEC filed its petition for review on certiorari before this under Rule 65 of the Rules of Court against Voluntary Arbitrator Jimenez’s
court,60 insisting that it did not violate its collective bargaining agreement with decision.69
PWU.61 PHILEC maintains that Lipio and Ignacio, Sr. were promoted to a position This was not the proper remedy.
covered by the pay grade scale for supervisory employees. 62 Consequently, the _______________
provisions of PHILEC’s collective bargaining agreement with its supervisory 65  Id., at p. 335.
employees should apply, not its collective bargaining agreement with PWU. 63 To 66  Id., at pp. 350-387. The May 7, 2006 comment was entitled
insist on applying the pay grade scale in Article X, Section 4, PHILEC argues, would “MEMORANDUM.”
result in a salary distortion within PHILEC.64 67  Id., at p. 351.
_______________ 68  Id., at pp. 398-408.
55  Id. 69  Id., at p. 45.
56  Id., at p. 40. 378
57  Id., at p. 38.
58  Id., at p. 40. 378 SUPREME COURT REPORTS ANNOTATED
59  Id., at pp. 42-43. Philippine Electric Corporation (PHILEC) vs. Court of Appeals
60  Id., at p. 9.
61  Id., at p. 19.
62  Id., at p. 23. Instead, the proper remedy to reverse or modify a Voluntary Arbitrator’s or a panel
63  Id. of Voluntary Arbitrators’ decision or award is to appeal the award or decision before
64  Id., at p. 24. the Court of Appeals. Rule 43, Sections 1 and 3 of the Rules of Court provide:
377 Section 1. Scope.—
This Rule shall apply to appeals from judgments or final orders of the Court of Tax
VOL. 744, DECEMBER 10, 2014 Appeals and from awards, judgments, final orders or resolutions of or authorized by
Philippine Electric Corporation (PHILEC) vs. Court of Appeals any quasi-judicial agency in the exercise of its quasi-judicial functions. Among these
agencies are the Civil Service Commission, Central Board of Assessment Appeals,
Securities and Exchange Commission, Office of the President, Land Registration
In the resolution65 dated September 21, 2005, this court ordered PWU to comment on Authority, Social Security Commission, Civil Aeronautics Board, Bureau of Patents,
PHILEC’s petition for review on certiorari. Trademarks and Technology Transfer, National Electrification Administration,
In its comment,66 PWU argues that Voluntary Arbitrator Jimenez did not gravely Energy Regulatory Board, National Telecommunications Commission, Department
abuse his discretion in rendering his decision. He correctly applied the provisions of of Agrarian Reform under Republic Act No. 6657, Government Service Insurance
the PWU collective bargaining agreement, the law between PHILEC and its rank- System, Employees’ Compensation Commission, Agricultural Inventions Board,
and-file employees, in computing Lipio’s and Ignacio, Sr.’s training allowance. 67 Insurance Commission, Philippine Atomic Energy Commission, Board of
On September 27, 2006, PHILEC filed its reply, 68 reiterating its arguments in its Investments, Construction Industry Arbitration Commission, and voluntary
petition for review on certiorari. arbitrators authorized by law.
The issue for our resolution is whether Voluntary Arbitrator Jimenez gravely abused ....
his discretion in directing PHILEC to pay Lipio’s and Ignacio, Sr.’s training Sec. 3. Where to appeal.—
allowance based on Article X, Section 4 of the June 1, 1997 rank-and-file collective An appeal under this Rule may be taken to the Court of Appeals within the period
bargaining agreement. and in the manner herein provided, whether the appeal involves questions of fact, of
This petition should be denied. law, or mixed questions of fact and law. (Emphasis supplied)
   
I A Voluntary Arbitrator or a panel of Voluntary Arbitrators has the exclusive original
  jurisdiction over grievances arising from the interpretation or implementation of
The Voluntary Arbitrator’s decision dated August 13, 1999 is already final and collective bargaining agreements. Should the parties agree, a Voluntary
executory 379
 

35
rights of parties; hence, their decisions have the same legal effect as judgments of a
VOL. 744, DECEMBER 10, 2014 court. In Oceanic Bic Division (FFW), et al. v. Romero, et al., this Court ruled that “a
Philippine Electric Corporation (PHILEC) vs. Court of Appeals voluntary arbitrator by the nature of her functions acts in a quasi-judicial capacity.”
Under these rulings, it follows that the voluntary arbitrator, whether acting solely or
in a panel, enjoys in law the status of a quasi-judicial agency but independent of, and
Arbitrator or a panel of Voluntary Arbitrators shall also resolve the parties’ other apart from, the NLRC since his decisions are not appealable to the latter. 73 (Citations
labor disputes, including unfair labor practices and bargaining deadlocks. Articles omitted)
261 and 262 of the Labor Code provide:    
ART. 261. JURISDICTION OF VOLUNTARY ARBITRATORS OR PANEL OF This court then stated that the office of a Voluntary Arbitrator or a panel of
VOLUNTARY ARBITRATORS.— Voluntary Arbitrators, even assuming that the office is not strictly a quasi-judicial
The Voluntary Arbitrator or panel of Voluntary Arbitrators shall have original and agency, may be considered an instrumentality, thus:
exclusive jurisdiction to hear and decide all unresolved grievances arising from the Assuming arguendo that the voluntary arbitrator or the panel of voluntary arbitrators
interpretation or implementation of the Collective Bargaining Agreement and those may not strictly be
arising from the interpretation or enforcement of company personnel policies _______________
referred to in the immediately preceding article. Accordingly, violations of a 70  319 Phil. 262; 249 SCRA 162 (1995) [Per J. Romero, En Banc].
Collective Bargaining Agreement, except those which are gross in character, shall no 71  187 Phil. 202; 98 SCRA 314 (1980) [Per J. De Castro, First Division].
longer be treated as unfair labor practice and shall be resolved as grievances under 72  215 Phil. 340; 130 SCRA 392 (1984) [Per J. Gutierrez, Jr., Second Division].
the Collective Bargaining Agreement. For purposes of this article, gross violations of 73  Luzon Development Bank v. Association of Luzon Development Bank
Collective Bargaining Agreement shall mean flagrant and/or malicious refusal to Employees, supra at p. 269; pp. 168-169.
comply with the economic provisions of such agreement. 381
The Commission, its Regional Offices and the Regional Directors of the Department
of Labor and Employment shall not entertain disputes, grievances, or matters under VOL. 744, DECEMBER 10, 2014
the exclusive and original jurisdiction of the Voluntary Arbitrator or panel of Philippine Electric Corporation (PHILEC) vs. Court of Appeals
Voluntary Arbitrators and shall immediately dispose and refer the same to the
Grievance Machinery or Voluntary Arbitration provided in the Collective Bargaining
Agreement. considered as a quasi-judicial agency, board or commission, still both he and the
 ART. 262. JURISDICTION OVER OTHER LABOR DISPUTES.— panel are comprehended within the concept of a “quasi-judicial instrumentality.” It
The Voluntary Arbitrator or panel of Voluntary Arbitrators, upon agreement of the may even be stated that it was to meet the very situation presented by the quasi-
parties, shall also hear and decide all other labor disputes including unfair labor judicial functions of the voluntary arbitrators here, as well as the subsequent
practices and bargaining deadlocks. arbitrator/arbitral tribunal operating under the Construction Industry Arbitration
380 Commission, that the broader term “instrumentalities” was purposely included in the
above quoted provision.
380 SUPREME COURT REPORTS ANNOTATED An “instrumentality” is anything used as a means or agency. Thus, the terms
Philippine Electric Corporation (PHILEC) vs. Court of Appeals governmental “agency” or “instrumentality” are synonymous in the sense that either
of them is a means by which a government acts, or by which a certain government
act or function is performed. The word “instrumentality,” with respect to a state,
In Luzon Development Bank v. Association of Luzon Development Bank Employees,70 contemplates an authority to which the state delegates governmental power for the
this court ruled that the proper remedy against the award or decision of the Voluntary performance of a state function. An individual person, like an administrator or
Arbitrator is an appeal before the Court of Appeals. This court first characterized the executor, is a judicial instrumentality in the settling of an estate, in the same manner
office of a Voluntary Arbitrator or a panel of Voluntary Arbitrators as a quasi- that a sub-agent appointed by a bankruptcy court is an instrumentality of the court,
judicial agency, citing Volkschel Labor Union, et al. v. NLRC 71 and Oceanic Bic and a trustee in bankruptcy of a defunct corporation is an instrumentality of the state.
Division (FFW) v. Romero:72 The voluntary arbitrator no less performs a state function pursuant to a governmental
In Volkschel Labor Union, et al. v. NLRC, et al., on the settled premise that the power delegated to him under the provisions therefor in the Labor Code and he falls,
judgments of courts and awards of quasi-judicial agencies must become final at some therefore, within the contemplation of the term “instrumentality” in the aforequoted
definite time, this Court ruled that the awards of voluntary arbitrators determine the Sec. 9 of B.P. 129.74 (Citations omitted)

36
 
Since the office of a Voluntary Arbitrator or a panel of Voluntary Arbitrators is The provisions may be new to the Rules of Court but it is far from being a new law.
considered a quasi-judicial agency, this court concluded that a decision or award Section 2, Rule 42 of the 1997 Rules of Civil Procedure, as presently worded, is
rendered by a Voluntary Arbitrator is appealable before the Court of Appeals. Under nothing more but a reiteration of the exception to the exclusive appellate jurisdiction
Section 9 of the Judiciary Reorganization Act of 1980, the Court of Appeals has the of the Court of Appeals, as provided for in Section 9, Batas Pambansa Blg. 129, as
exclusive original jurisdiction amended by Republic Act No. 7902:
_______________ (3) Exclusive appellate jurisdiction over all final judgments, decisions, resolutions,
74  Id., at pp. 270-271; pp. 169-170. orders or awards of Regional Trial Courts and quasi-judicial agencies,
382 instrumentalities, boards or commissions, including  the Securities and Exchange
Commission, the Employees’ Compensation Commission and the Civil Service
382 SUPREME COURT REPORTS ANNOTATED Commission, except those falling within the appellate jurisdiction of the Supreme
Philippine Electric Corporation (PHILEC) vs. Court of Appeals Court in accordance with the Constitution, the Labor Code of the Philippines under
Presidential Decree No. 442, as amended, the provisions of this Act and of
subparagraph (1) of the third paragraph and subparagraph (4) of the fourth paragraph
over decisions or awards of quasi-judicial agencies and instrumentalities: of Section 17 of the Judiciary Act of 1948.
Section 9. Jurisdiction.—The Court of Appeals shall exercise: The Court took into account this exception in Luzon Development Bank but,
.... nevertheless, held that the decisions of voluntary arbitrators issued pursuant to the
3. Exclusive appellate jurisdiction over all final judgements, resolutions, orders or Labor Code do not come within its ambit:
awards of Regional Trial Courts and quasi-judicial agencies, instrumentalities, x x x. The fact that [the voluntary arbitrator’s] functions and powers are provided for
boards or commission, including the Securities and Exchange Commission, the in the Labor Code does not place him within the exceptions to said Sec. 9 since he is
Social Security Commission, the Employees’ Compensation Commission and the a quasi-judicial instrumentality as contemplated therein. It will be noted that,
Civil Service Commission, except those falling within the appellate jurisdiction of although the Employees’ Compensation Commission is also provided for in the
the Supreme Court in accordance with the Constitution, the Labor Code of the Labor Code, Circular No. 1-91, which is the forerunner of the present Revised
Philippines under Presidential Decree No. 442, as amended, the provisions of this Administrative Circular No. 1-95, laid down the procedure for the appealability of its
Act, and of subparagraph (1) of the third paragraph and subparagraph 4 of the fourth decisions to the Court of Appeals under the foregoing rationalization, and this was
paragraph of Section 17 of the Judiciary Act of 1948. (Emphasis supplied) later
  384
Luzon Development Bank was decided in 1995 but remains “good law.” 75 In the
2002 case of Alcantara, Jr. v. Court of Appeals,76 this court rejected petitioner 384 SUPREME COURT REPORTS ANNOTATED
Santiago Alcantara, Jr.’s argument that the Rules of Court, specifically Rule 43, Philippine Electric Corporation (PHILEC) vs. Court of Appeals
Section 2, superseded the Luzon Development Bank ruling:
Petitioner argues, however, that Luzon Development Bank is no longer good law
because of Section 2, Rule 43 of the Rules of Court, a new provision introduced by adopted by Republic Act No. 7902 in amending Sec. 9 of B.P. 129.
the 1997 revision. The provision reads: A fortiori, the decision or award of the voluntary arbitrator or panel of arbitrators
SEC. 2. Cases not covered.—This Rule shall not apply to judgments or final should likewise be appealable to the Court of Appeals, in line with the procedure
orders issued under the Labor Code of the Philippines. outlined in Revised Administrative Circular No. 1-95, just like those of the quasi-
_______________ judicial agencies, boards and commissions enumerated therein. 77 (Emphases in the
75  Alcantara, Jr. v. Court of Appeals, 435 Phil. 395, 404; 386 SCRA 370, 379 original)
(2002) [Per J. Kapunan, First Division].  
76  Id. This court has since reiterated the Luzon Development Bank ruling in its decisions.78
383 _______________
77  Id., at pp. 404-406; pp. 379-380.
VOL. 744, DECEMBER 10, 2014 78  Royal Plant Workers Union v. Coca-Cola Bottlers Philippines, Inc.-Cebu
Philippine Electric Corporation (PHILEC) vs. Court of Appeals Plant, G.R. No. 198783, April 15, 2013, 696 SCRA 357 [Per J. Mendoza, Third
Division]; Samahan ng mga Manggagawa sa Hyatt (SAMASAH-NUWHRAIN) v.

37
Magsalin, G.R. No. 164939, June 6, 2011, 650 SCRA 445 [Per J. Villarama, Jr., Arbitrators, for any reason, may issue a writ of execution requiring either the sheriff
Third Division]; Teng v. Pahagac, G.R. No. 169704, November 17, 2010, 635 SCRA of the Commission or regular courts or any public official whom the parties may
173 [Per J. Brion, Third Division]; Samahan ng mga Manggagawa sa Hyatt- designate in the submission agreement to execute the final decision, order or award.
NUWHRAIN-APL v. Bacungan, 601 Phil. 365; 582 SCRA 369 (2009) [Per J. Tinga, (Emphasis supplied)
Second Division]; Mora v. Avesco Marketing Corporation, 591 Phil. 827; 571 SCRA 386
226 (2008) [Per J. Carpio-Morales, Second Division]; AMA Computer College-
Santiago City, Inc. v. Nacino, 568 Phil. 465; 544 SCRA 502 (2008) [Per J. Nachura, 386 SUPREME COURT REPORTS ANNOTATED
Third Division]; Centro Escolar University Faculty and Allied Workers Union- Philippine Electric Corporation (PHILEC) vs. Court of Appeals
Independent v. Court of Appeals, 523 Phil. 427; 490 SCRA 61 (2006) [Per J. Puno,
Second Division]; Coca-Cola Bottlers Philippines, Inc. Sales Force Union-PTGWO-
BALAIS v. Coca-Cola Bottlers Philippines, Inc., 502 Phil. 748; 464 SCRA 507 Thus, in Coca-Cola Bottlers Philippines, Inc. Sales Force Union-PTGWO-BALAIS
(2005) [Per J. Chico-Nazario, Second Division]; Nippon Paint Employees Union- v. Coca Cola-Bottlers Philippines, Inc.,79 this court declared that the decision of the
OLALIA v. Court of Appeals, 485 Phil. 675; 443 SCRA 286 (2004) [Per J. Puno, Voluntary Arbitrator had become final and executory because it was appealed
Second Division]; Manila Midtown Hotel v. Borromeo, 482 Phil. 137; 438 SCRA beyond the 10-day reglementary period under Article 262-A of the Labor Code.
653 (2004) [Per J. Sandoval-Gutierrez, Third Division]; Sevilla Trading Company v. It is true that Rule 43, Section 4 of the Rules of Court provides for a 15-day
Semana, G.R. No. 152456, April 28, 2004, 428 SCRA 239 [Per J. Puno, Second reglementary period for filing an appeal:
Division]. Section 4. Period of appeal.—The appeal shall be taken within fifteen (15) days
385 from notice of the award, judgment, final order or resolution, or from the date of its
last publication, if publication is required by law for its effectivity, or of the denial of
VOL. 744, DECEMBER 10, 2014 petitioner’s motion for new trial or reconsideration duly filed in accordance with the
Philippine Electric Corporation (PHILEC) vs. Court of Appeals governing law of the court or agency a quo. Only one (1) motion for reconsideration
shall be allowed. Upon proper motion and the payment of the full amount of the
docket fee before the expiration of the reglementary period, the Court of Appeals
Article 262-A of the Labor Code provides that the award or decision of the may grant an additional period of fifteen (15) days only within which to file the
Voluntary Arbitrator “shall be final and executory after ten (10) calendar days from petition for review. No further extension shall be granted except for the most
receipt of the copy of the award or decision by the parties”: compelling reason and in no case to exceed fifteen (15) days. (Emphasis supplied)
   
Art. 262-A. PROCEDURES.—The Voluntary Arbitrator or panel of Voluntary The 15-day reglementary period has been upheld by this court in a long line of
Arbitrators shall have the power to hold hearings, receive evidences and take cases.80 In AMA Computer College-
whatever action is necessary to resolve the issue or issues subject of the dispute, _______________
including efforts to effect a voluntary settlement between parties. 79  Coca-Cola Bottlers Philippines, Inc. Sales Force Union-PTGWO-BALAIS v.
All parties to the dispute shall be entitled to attend the arbitration proceedings. The Coca-Cola Bottlers Philippines, Inc., id.
attendance of any third party or the exclusion of any witness from the proceedings 80  Royal Plant Workers Union v. Coca-Cola Bottlers Philippines, Inc.-Cebu
shall be determined by the Voluntary Arbitrator or panel of Voluntary Arbitrators. Plant, supra note 78 at pp. 371-372; Samahan ng mga Manggagawa sa Hyatt
Hearing may be adjourned for cause or upon agreement by the parties. (SAMASAH-NUWHRAIN) v. Magsalin, supra note 78 at p. 456; Mora v. Avesco
Unless the parties agree otherwise, it shall be mandatory for the Voluntary Arbitrator Marketing Corporation, supra note 78 at p. 836; p. 274; AMA Computer College-
or panel of Voluntary Arbitrators to render an award or decision within twenty (20) Santiago City, Inc. v. Nacino, supra note 78 at p. 471; p. 510; Nippon Paint
calendar days from the date of submission of the dispute to voluntary arbitration. Employees Union-OLALIA v. Court of Appeals, supra note 78 at p. 682; p. 292;
The award or decision of the Voluntary Arbitrator or panel of Voluntary Manila Midtown Hotel v. Borromeo, supra note 78 at p. 142; p. 657; Sevilla Trading
Arbitrators shall contain the facts and the law on which it is based. It shall be final Company v. Semana, supra note 78 at p. 244.
and executory after ten (10) calendar days from receipt of the copy of the award or 387
decision by the parties.
Upon motion of any interested party, the Voluntary Arbitrator or panel of VOL. 744, DECEMBER 10, 2014
Voluntary Arbitrators or the Labor Arbiter in the region where the movant resides, in Philippine Electric Corporation (PHILEC) vs. Court of Appeals
case of the absence or incapacity of the Voluntary Arbitrator or panel of Voluntary

38
procedure in courts.89 The 10-day period to appeal under the Labor Code being a
Santiago City, Inc. v. Nacino, Nippon Paint Employees Union-OLALIA v.
81
substantive right, this period cannot be diminished, increased, or modified through
Court of Appeals,82 Manila Midtown Hotel v. Borromeo,83 and Sevilla Trading the Rules of Court.90
Company v. Semana,84 this court denied petitioners’ petitions for review on  In Shioji v. Harvey,91 this court held that the “rules of court, promulgated by
certiorari since petitioners failed to appeal the Voluntary Arbitrator’s decision within authority of law, have the force and effect of law, if not in conflict with positive
the 15-day reglementary period under Rule 43.  In these cases, the Court of Appeals law.”92 Rules of
had no jurisdiction to entertain the appeal assailing the Voluntary Arbitrator’s _______________
decision. 89  Const., Art. VIII, Sec. 5, par. (5) provides:
Despite Rule 43 providing for a 15-day period to appeal, we rule that the Section 5. The Supreme Court shall have the following powers:
Voluntary Arbitrator’s decision must be appealed before the Court of Appeals within ....
10 calendar days from receipt of the decision as provided in the Labor Code. 5. Promulgate rules concerning the protection and enforcement of constitutional
Appeal is a “statutory privilege,” 85 which may be exercised “only in the manner rights, pleading, practice, and procedure in all courts, the admission to the practice of
and in accordance with the provisions of the law.” 86 “Perfection of an appeal within law, the integrated bar, and legal assistance to the under-privileged. Such rules shall
the reglementary period is not only mandatory but also jurisdictional so that failure provide a simplified and inexpensive procedure for the speedy disposition of cases,
to do so rendered the decision final and executory, and deprives the appellate court shall be uniform for all courts of the same grade, and shall not diminish, increase, or
of jurisdiction to alter the final judgment much less to entertain the appeal.” 87 modify substantive rights. Rules of procedure of special courts and quasi-judicial
We ruled that Article 262-A of the Labor Code allows the appeal of decisions bodies shall remain effective unless disapproved by the Supreme Court.
rendered by Voluntary Arbitrators.88 Stat- 90  Habaluyas Enterprises, Inc. v. Japson, 226 Phil. 145; 142 SCRA 208 (1986)
_______________ [Per J. Feria, En Banc].
81  AMA Computer College-Santiago City, Inc. v. Nacino, supra note 78. 91  43 Phil. 333 (1922) [Per J. Malcolm, En Banc].
82  Nippon Paint Employees Union-OLALIA v. Court of Appeals, supra note 78. 92  Id., at p. 342.
83  Manila Midtown Hotel v. Borromeo, supra note 78. 389
84  Sevilla Trading Company v. Semana, supra note 78.
85  Fenequito v. Vergara, Jr., G.R. No. 172829, July 18, 2012, 677 SCRA 113, VOL. 744, DECEMBER 10, 2014
117 [Per J. Peralta, Third Division]. Philippine Electric Corporation (PHILEC) vs. Court of Appeals
86  Id.
87  Pedrosa v. Hill, 327 Phil. 153; 257 SCRA 373 (1996) [Per J. Bellosillo, First
Division]. Court are “subordinate to the statute.”93 In case of conflict between the law and the
88  Coca-Cola Bottlers Philippines, Inc. Sales Force Union-PTGWO-BALAIS v. Rules of Court, “the statute will prevail.”94
Coca Cola-Bottlers Philippines, Inc., supra note 78. The rule, therefore, is that a Voluntary Arbitrator’s award or decision shall be
388 appealed before the Court of Appeals within 10 days from receipt of the award or
decision. Should the aggrieved party choose to file a motion for reconsideration with
388 SUPREME COURT REPORTS ANNOTATED the Voluntary Arbitrator,95 the motion must be filed within the same 10-day period
Philippine Electric Corporation (PHILEC) vs. Court of Appeals since a motion for reconsideration is filed “within the period for taking an appeal.” 96
A petition for certiorari is a special civil action “adopted to correct errors of
jurisdiction committed by the lower court or quasi-judicial agency, or when there is
ute provides that the Voluntary Arbitrator’s decision “shall be final and executory grave abuse of discretion on the part of such court or agency amounting to lack or
after ten (10) calendar days from receipt of the copy of the award or decision by the excess of jurisdiction.”97 An extraordinary remedy,98 a petition for certiorari may be
parties.” Being provided in the statute, this 10-day period must be complied with; filed only if appeal is not available. 99 If appeal is available, an appeal must be taken
otherwise, no appellate court will have jurisdiction over the appeal. This absurd even if the ground relied upon is grave abuse of discretion.100
situation occurs when the decision is appealed on the 11th to 15th day from receipt As an exception to the rule, this court has allowed petitions for certiorari to be filed
as allowed under the Rules, but which decision, under the law, has already become in lieu of an appeal “(a) when the public welfare and the advancement of public
final and executory. policy dictate; (b) when the broader interests of justice so require; (c) when
Furthermore, under Article VIII, Section 5(5) of the Constitution, this court “shall _______________
not diminish, increase, or modify substantive rights” in promulgating rules of 93  Id.

39
94  Id. 104  Id., at p. 756; p. 166.
95  Teng v. Pahagac, supra note 78 at p. 184. 105  Mora v. Avesco Marketing Corporation, supra note 78.
96  Rules of Court, Rule 37, Sec. 1. 106  Id., at p. 836; p. 235.
97  Centro Escolar University Faculty and Allied Workers Union-Independent v. 391
Court of Appeals, supra note 78 at pp. 437-438; p. 70.
98  Id., at p. 437; p 70. VOL. 744, DECEMBER 10, 2014
99  Rules of Court, Rule 65, Sec. 1. Supra note 78 at p. 437; p. 70. Philippine Electric Corporation (PHILEC) vs. Court of Appeals
100  Bugarin v. Palisoc, 513 Phil. 59, 66; 476 SCRA 587, 595 (2005) [Per J.
Quisumbing, First Division]; Association of Integrated Security Force of Bislig
(AISFB)-ALU v. Court of Appeals, 505 Phil. 10, 18; 467 SCRA 483, 493 (2005) [Per None of the circumstances similar to Unicraft Leyte IV Electric Cooperative, and
J. Chico-Nazario, Second Division]. Mora are present in this case. PHILEC received Voluntary Arbitrator Jimenez’s
390 resolution denying its motion for partial reconsideration on August 11, 2000. 107
PHILEC filed its petition for certiorari before the Court of Appeals on August 29,
390 SUPREME COURT REPORTS ANNOTATED 2000,108 which was 18 days after its receipt of Voluntary Arbitrator Jimenez’s
Philippine Electric Corporation (PHILEC) vs. Court of Appeals resolution.  The petition for certiorari was filed beyond the 10-day reglementary
period for filing an appeal. We cannot consider PHILEC’s petition for certiorari as
an appeal.
the writs issued are null; and (d) when the questioned order amounts to an oppressive There being no appeal seasonably filed in this case, Voluntary Arbitrator Jimenez’s
exercise of judicial authority.”101 decision became final and executory after 10 calendar days from PHILEC’s receipt
 In Unicraft Industries International Corporation, et al. v. The Hon. Court of of the resolution denying its motion for partial reconsideration. 109 Voluntary
Appeals,102 petitioners filed a petition for certiorari against the Voluntary Arbitrator Jimenez’s decision is already “beyond the purview of this Court to act
Arbitrator’s decision. Finding that the Voluntary Arbitrator rendered an award upon.”110
without giving petitioners an opportunity to present evidence, this court allowed  
petitioners’ petition for certiorari despite being the wrong remedy. The Voluntary II
Arbitrator’s award, this court said, was null and void for violation of petitioners’  
right to due process.  This court decided the case on the merits. PHILEC must pay training allowance based on the step increases provided in the
In Leyte IV Electric Cooperative, Inc. v. LEYECO IV Employees Union-ALU,103 June 1, 1997 collective bargaining agreement
petitioner likewise filed a petition for certiorari against the Voluntary Arbitrator’s  
decision, alleging that the decision lacked basis in fact and in law. Ruling that the The insurmountable procedural issue notwithstanding, the case will also fail on its
petition for certiorari was filed within the reglementary period for filing an appeal, merits. Voluntary Arbitrator Jimenez correctly awarded both Lipio and Ignacio, Sr.
this court allowed petitioner’s petition for certiorari in “the broader interests of training allowances based on the amounts and formula provided in the June 1, 1997
justice.”104 collective bargaining agreement.
 In Mora v. Avesco Marketing Corporation,105 this court held that petitioner Noel E. _______________
Mora erred in filing a petition for certiorari against the Voluntary Arbitrator’s 107  Rollo, p. 46.
decision. Nevertheless, this court decided the case on the merits “in the interest of 108  Id., at p. 45.
substantial justice to arrive at the proper conclusion that is conformable to the 109  See Manila Midtown Hotel v. Borromeo, supra note 78 at
evidentiary facts.”106 p. 143; p. 656.
_______________ 110  AMA Computer College-Santiago City, Inc. v. Nacino, supra note 78 at p.
101  Leyte IV Electric Cooperative, Inc. v. LEYECO IV Employees Union-ALU, 471; p. 510.
562 Phil. 743, 755; 537 SCRA 154, 166 (2007) [Per J. Austria-Martinez, Third 392
Division]. (Emphases omitted)
102  407 Phil. 527; 355 SCRA 233 (2001) [Per J. Ynares-Santiago, First 392 SUPREME COURT REPORTS ANNOTATED
Division]. Philippine Electric Corporation (PHILEC) vs. Court of Appeals
103  Leyte IV Electric Cooperative, Inc. v. LEYECO IV Employees Union-ALU,
supra.

40
A collective bargaining agreement is “a contract executed upon the request of either 114  Rollo, p. 114. Collective Bargaining Agreement, Art. IX, Sec. 1(e)
the employer or the exclusive bargaining representative of the employees provides:
incorporating the agreement reached after negotiations with respect to wages, hours ....
of work and all other terms and conditions of employment, including proposals for (e)  An employee whose application for a posted job is accepted shall hold that
adjusting any grievances or questions arising under such agreement.” 111 A collective job on a trial or observation basis and during that period shall receive a monthly
bargaining agreement being a contract, its provisions “constitute the law between the allowance of an amount in accordance with Section (f) of this Article. During the
parties”112 and must be complied with in good faith.113 trial or observation period which shall not exceed four (4) months of actual training
PHILEC, as employer, and PWU, as the exclusive bargaining representative of if the employee isunable [sic] to demonstrate his ability to perform the work, he shall
PHILEC’s rank-and-file employees, entered into a collective bargaining agreement, be reverted to his previous assignment and the last preceding rate of pay but shall
which the parties agreed to make effective from June 1, 1997 to May 31, 1999. not, for a period of three (3) months, be permitted to apply for any posted job in the
Being the law between the parties, the June 1, 1997 collective bargaining agreement same higher classification. On the other hand, should the employee be considered
must govern PHILEC and its rank-and-file employees within the agreed period. capable of holding the job, he shall, subject to prior approval of the authorized
Lipio and Ignacio, Sr. were rank-and-file employees when PHILEC selected them management official, be appointed to the position in a regular capacity. Positions
for training for the position of Foreman I beginning August 25, 1997.  Lipio and vacated during the trial or observation period shall be filled up by temporary
Ignacio, Sr. were selected for training during the effectivity of the June 1, 1997 rank- employees hired for this purpose only, if necessary.
and-file collective bargaining agreement. Therefore, Lipio’s and Ignacio, Sr.’s 115  Id.
training allowance must be computed based on Article X, Section 4 and Article IX, 116  Id.
Section 1(f) of the June 1, 1997 collective bargaining agreement.   117  Id.
Contrary to PHILEC’s claim, Lipio and Ignacio, Sr. were not transferred out of the 394
bargaining unit when they were selected for training. Lipio and Ignacio, Sr. remained
rank-and-file employees while they trained for the position of 394 SUPREME COURT REPORTS ANNOTATED
_______________ Philippine Electric Corporation (PHILEC) vs. Court of Appeals
111  Davao Integrated Port Stevedoring Services v. Abarquez, G.R. No. 102132,
March 19, 1993, 220 SCRA 197, 204 [Per J. Romero, Third Division].
112  Roche (Philippines) v. NLRC, 258-A Phil. 160, 171; 178 SCRA 386, 395 Since Lipio and Ignacio, Sr. were rank-and-file employees when they applied for
(1989) [Per J. Gancayco, First Division]. training for the position of Foreman I, Lipio’s and Ignacio, Sr.’s training allowance
113  Civil Code, Art. 1159. must be computed based on Article IX, Section 1(f) of the June 1, 1997 rank-and-file
393 collective bargaining agreement.
PHILEC allegedly applied the “Modified SGV” pay grade scale to prevent any salary
VOL. 744, DECEMBER 10, 2014 distortion within PHILEC’s enterprise.  This, however, does not justify PHILEC’s
Philippine Electric Corporation (PHILEC) vs. Court of Appeals noncompliance with the June 1, 1997 collective bargaining agreement. This pay
grade scale is not provided in the collective bargaining agreement. In Samahang
Manggagawa sa Top Form Manufacturing United Workers of the Philippines
Foreman I.  Under Article IX, Section 1(e) of the June 1, 1997 collective bargaining (SMTFM-UWP) v. NLRC,118 this court ruled that “only provisions embodied in the
agreement,114 a trainee who is “unable to demonstrate his ability to perform the [collective bargaining agreement] should be so interpreted and complied with. Where
work . . . shall be reverted to his previous assignment. . . .” 115 According to the same a proposal raised by a contracting party does not find print in the [collective
provision, the trainee “shall hold that job on a trial or observation basis and . . . bargaining agreement], it is not part thereof and the proponent has no claim
subject to prior approval of the authorized management official, be appointed to the whatsoever to its implementation.”119
position in a regular capacity.”116 Had PHILEC wanted the “Modified SGV” pay grade scale applied within its
Thus, training is a condition precedent for promotion.  Selection for training does not enterprise, “it could have requested or demanded that [the ‘Modified SGV’ scale] be
mean automatic transfer out of the bargaining unit of rank-and-file employees. incorporated in the [collective bargaining agreement].” 120 PHILEC had “the means
Moreover, the June 1, 1997 collective bargaining agreement states that the training under the law to compel [PWU] to incorporate this specific economic proposal in the
allowance of a rank-and-file employee “whose application for a posted job is [collective bargaining agreement].”121 It “could have invoked Article 252 of the
accepted shall [be computed] in accordance with Section (f) of [Article IX].”117 Labor Code”122 to
_______________ _______________

41
118  356 Phil. 480; 295 SCRA 171 (1998) [Per J. Romero, Third Division]. Philippine Electric Corporation (PHILEC) vs. Court of Appeals
119  Id., at p. 491; p. 183.
120  Id., at p. 490; p. 182.
121  Id. Given the foregoing, Lipio’s and Ignacio, Sr.’s training allowance should be
122  Labor Code, Art. 252 provides: computed based on Article X, Section 4 in relation to Article IX, Section 1(f) of the
Art. 252. Meaning of duty to bargain collectively.—The duty to bargain June 1, 1997 rank-and-file collective bargaining agreement. Lipio, who held the
collectively means the performance of a mutual obligation to meet and convene position of Machinist before selection for training as Foreman I, should receive
promptly and expeditiously in good faith for the purpose of negotiating an agreement training allowance based on the following schedule:
with respect to wages, hours of work and all other terms and condi- First month - - - - - P456.00
395 Second month - - - - - P1,031.00
Third month - - - - - P1,031.00
VOL. 744, DECEMBER 10, 2014
Fourth month - - - - - P1,031.00
Philippine Electric Corporation (PHILEC) vs. Court of Appeals  
Ignacio, Sr., who held the position of DT-Assembler before selection for training as
Foreman I, should receive training allowance based on the following schedule:
incorporate the “Modified SGV” pay grade scale in its collective bargaining First month - - - - - P361.00
agreement with PWU. But it did not. Since this “Modified SGV” pay grade scale Second month - - - - - P817.00
does not appear in PHILEC’s collective bargaining agreement with PWU, PHILEC Third month - - - - - P1,392.00
cannot insist on the “Modified SGV” pay grade scale’s application. We reiterate Fourth month - - - - - P1,392.00
Voluntary Arbitrator Jimenez’s decision dated August 13, 1999 where he said that:  
. . . since the signing of the current CBA took place on September 27, 1997, Considering that Voluntary Arbitrator Jimenez’s decision awarded sums of money,
PHILEC, by oversight, may have overlooked the possibility of a wage distortion Lipio and Ignacio, Sr. are entitled to legal interest on their training allowances.
occurring among ASSET-occupied positions. It is surmised that this matter could Voluntary Arbitrator Jimenez’s decision having become final and executory on
have been negotiated and settled with PWU before the actual signing of the CBA on August 22, 2000, PHILEC is liable for legal interest equal to 12% per annum from
September 27. Instead, PHILEC, again, allowed the provisions of Art. X, Sec. 4 of finality of the decision until full payment as this court ruled in Eastern Shipping
the CBA to remain the way it is and is now suffering the consequences of its Lines, Inc. v. Court of Appeals:125
laches.123 (Emphasis in the original) When the judgment of the court awarding a sum of money becomes final and
  executory, the rate of legal interest . . .  shall be 12% per annum from such finality
We note that PHILEC did not dispute PWU’s contention that it selected several rank- un-
and-file employees for training and paid them training allowance based on the _______________
schedule provided in the collective bargaining agreement effective at the time of the 125  G.R. No. 97412, July 12, 1994, 234 SCRA 78 [Per J. Vitug, En Banc].
trainees’ selection.124 PHILEC cannot choose when and to whom to apply the 397
provisions of its collective bargaining agreement. The provisions of a collective
bargaining agreement must be applied uniformly and complied with in good faith. VOL. 744, DECEMBER 10, 2014
_______________ Philippine Electric Corporation (PHILEC) vs. Court of Appeals
tions of employment including proposals for adjusting any grievances or questions
arising under such agreements if requested by either party but such duty does not
compel any party to agree to a proposal or to make any concession. Id. til its satisfaction, this interim period being deemed to be by then as equivalent to a
123  Rollo, p. 70. forbearance of credit.126
124  Id., at p. 65. PHILEC selected rank-and-file employees Rodolfo Montepio,  
Rodel Unidad, Feliciano de los Santos, Berlin Diaz, and Melencio Rodriguez for The 6% legal interest under Circular No. 799, Series of 2013, of the Bangko Sentral
training for higher positions. ng Pilipinas Monetary Board shall not apply, Voluntary Arbitrator Jimenez’s
396 decision having become final and executory prior to the effectivity of the circular on
July 1, 2013. In Nacar v. Gallery Frames,127 we held that:
396 SUPREME COURT REPORTS ANNOTATED
. . . with regard to those judgments that have become final and executory prior to
42
July 1, 2013, said judgments shall not be disturbed and shall continue to be BENSON INDUSTRIES EMPLOYEES UNION-ALU-TUCP and/or VILMA
implemented applying the rate of interest fixed therein.128 GENON, EDISA HORTELANO, LOURDES ARANAS, TONY
  FORMENTERA, RENEBOY LEYSON, MA. ALONA ACALDO, MA.
WHEREFORE, the petition for review on certiorari is DENIED. The Court of CONCEPCION ABAO, TERESITA CALINAWAN, NICIFORO CABANSAG,
Appeals’ decision dated May 25, 2004 is AFFIRMED. STELLA BARONGO, MARILYN POTOT, WELMER ABANID, LORENZO
Petitioner Philippine Electric Corporation is ORDERED to PAY respondent ALIA, LINO PARADERO, DIOSDADO ANDALES, LUCENA ABESIA, and
Eleodoro V. Lipio a total of P3,549.00 for a four (4)-month training for the position ARMANDO YBAÑEZ, petitioners, vs. BENSON INDUSTRIES, INC.,
of Foreman I with legal interest of 12% per annum from August 22, 2000 until the respondent.
amount’s full satisfaction. Labor Law; Termination of Employment; Closure of Business; Closure of
For respondent Emerlito C. Ignacio, Sr., Philippine Electric Corporation is business may be considered as a reversal of an employer’s fortune whereby there is
ORDERED to PAY a total of P3,962.00 for a four (4)-month training for the position a complete cessation of business operations
of Foreman I with legal interest of 12% per annum from August 22, 2000 until the _______________
amount’s full satisfaction. * SECOND DIVISION.
SO ORDERED. 319and/or an actual locking-up of the doors of the establishment, usually due
_______________ to financial losses.—Closure of business may be considered as a reversal of an
126  Id., at p. 97. employer’s fortune whereby there is a complete cessation of business operations
127  G.R. No. 189871, August 13, 2013, 703 SCRA 439 [Per J. Peralta, En and/or an actual locking-up of the doors of the establishment, usually due to financial
Banc]. losses. Under the Labor Code, it is treated as an authorized cause for termination,
128  Id., at p. 457. aimed at preventing further financial drain upon an employer who cannot anymore
398 pay its employees since business has already stopped. As a form of recompense, the
employer is required to pay its employees separation benefits, except when the
398 SUPREME COURT REPORTS ANNOTATED closure is due to serious business losses.
Philippine Electric Corporation (PHILEC) vs. Court of Appeals Same; Same; Same; Separation Pay; It is only in instances of retrenchment to
prevent losses and in cases of closures or cessation of operations of establishment or
undertaking not due to serious business losses or financial reverses that employees
Carpio (Chairperson), Del Castillo, Villarama, Jr.** and Mendoza, JJ., whose employment has been terminated as a result are entitled to separation pay.—
concur. While serious business losses generally exempt the employer from paying separation
Petition denied, judgment affirmed. benefits, it must be pointed that the exemption only pertains to the obligation of the
Notes.—The proper mode of appeal from a Voluntary Arbitrator’s decision is employer under Article 297 of the Labor Code. This is because of the law’s express
review under Rule 43 of the 1997 Rules of Civil Procedure, not a petition for parameter that mandates payment of separation benefits “in case of closures or
certiorari; While Sec. 2 of the same Rule 43 provides that said Rule shall not apply cessation of operations of establishment or undertaking not due to serious business
to judgments or final orders issued under the Labor Code, the same refers only to losses or financial reverses.” The policy distinction underlying Article 297 — that
cases decided by labor arbiters which are appealable to the National Labor Relations is, the distinction between closures due to serious business losses and those which
Commission. (Mora vs. Avesco Marketing Corporation, 571 SCRA 226 [2008]) are not — was deftly discussed by the Court in the case of Cama v. Joni’s Food
When the provision of the Collective Bargaining Agreement is clear, leaving no Services, Inc., 425 SCRA 259 (2004), as follows: The Constitution, while affording
doubt on the intention of the parties, the literal meaning of the stipulation shall full protection to labor, nonetheless, recognizes “the right of enterprises to
govern. (Wesleyan University-Philippines vs. Wesleyan University-Philippines reasonable returns on investments, and to expansion and growth.” In line with this
Faculty and Staff Association, 718 SCRA 601 [2014]) protection afforded to business by the fundamental law, Article 283 [(now, Article
——o0o—— 297)] of the Labor Code clearly makes a policy distinction. It is only in instances of
“retrenchment to prevent losses and in cases of closures or cessation of
operations of establishment or undertaking not due to serious business losses or
financial reverses” that employees whose employment has been terminated as a
result are entitled to separation pay. In other words, Article 283 [(now, Article 297)]
G.R. No. 200746. August 6, 2014.* of the Labor Code does not obligate an employer to pay separation benefits when the

43
closure is due to serious losses. To require an employer to be generous when it is no Calinawan, Niciforo Cabansag, Stella Barongo, Marilyn Potot, Welmer Abanid,
longer in a position to do so, in Lorenzo Alia, Lino Paradero, Diosdado Andales, Lucena Abesia, and Armando
320our view, would be unduly oppressive, unjust, and unfair to the employer. Ybañez (petitioners) of additional separation pay equivalent to four (4) days of work
Ours is a system of laws, and the law in protecting the rights of the working man, for every year of service.
authorizes neither the oppression nor the self-destruction of the employer. The Facts
Same; Same; Same; Same; When the obligation to pay separation benefits, Respondent Benson Industries, Inc. (Benson) is a domestic corporation engaged
however, is not sourced from law (particularly, Article 297 of the Labor Code), but in the manufacturing of green coils with the brand name Lion-Tiger Mosquito Killer.
from contract, such as an existing collective bargaining agreement (CBA) between On February 12, 2008, Benson sent its employees, including herein petitioners, a
the employer and its employees, an examination of the latter’s provisions becomes notice5 informing them of their intended termination from
necessary in order to determine the governing parameters for the said obligation.— _______________
When the obligation to pay separation benefits, however, is not sourced from law 1 Rollo, pp. 5-26.
(particularly, Article 297 of the Labor Code), but from contract, such as an existing 2 Id., at pp. 31-39. Penned by Associate Justice Gabriel T. Ingles, with Associate
collective bargaining agreement between the employer and its employees, an Justices Pampio A. Abarintos and Eduardo B. Peralta, Jr., concurring.
examination of the latter’s provisions becomes necessary in order to determine the 3 Id., at pp. 41-42.
governing parameters for the said obligation. To reiterate, an employer which closes 4 Id., at pp. 253-260. Penned by Voluntary Arbitrator Manuel P. Legaspi.
shop due to serious business losses is exempt from paying separation benefits under 5 Id., at pp. 60-62.
Article 297 of the Labor Code for the reason that the said provision explicitly 322employment, to be effected on March 15, 2008 on the ground of closure and/or
requires the same only when the closure is not due to serious business losses; cessation of business operations. In consequence, the majority of Benson’s
conversely, the obligation is maintained when the employer’s closure is not due to employees resigned.6 Meanwhile, petitioners, through Benson Industries Employees
serious business losses. For a similar exemption to obtain against a contract, such as Union-ALU-TUCP (Union), filed a notice of strike, claiming that the company’s
a CBA, the tenor of the parties’ agreement ought to be similar to the law’s tenor. supposed closure was merely a ploy to replace the union members with lower paid
When the parties, however, agree to deviate therefrom, and unqualifiedly covenant workers, and, as a result, increase its profit at their expense. 7 The strike did not,
the payment of separation benefits irrespective of the employer’s financial position, however, push through due to the parties’ amicable settlement during the conciliation
then the obligatory force of that contract prevails and its terms should be carried out proceedings before the NCMB, whereby petitioners accepted Benson’s payment of
to its full effect. Verily, it is fundamental that obligations arising from contracts have separation pay, computed at 15 days for every year of service, as per the parties’
the force of law between the contracting parties and thus should be complied with in Memorandum of Agreement8 dated April 9, 2008.9
good faith; and parties are bound by the stipulations, clauses, terms and conditions This notwithstanding, petitioners proffered a claim for the payment of additional
they have agreed to, the only limitation being that these stipulations, clauses, terms separation pay at the rate of four (4) days for every year of service. As basis,
and conditions are not contrary to law, morals, public order or public policy. Hence, petitioners invoked Section 1, Article VIII of the existing collective bargaining
if the terms of a CBA are clear and there is no doubt as to the intention of the agreement (CBA) executed by and between the Union and Benson which states that
contracting parties, the literal meaning of its stipulations shall prevail. “[Benson] shall pay to any employee/laborer who is terminated from the service
PETITION for review on certiorari of the decision and resolution of the Court of without any fault attributable to him, a ‘Separation Pay’ equivalent to not less than
Appeals. nineteen (19) days’ pay for every year of service based upon the latest rate of pay of
321 the employee/laborer concerned.”10 Benson opposed petitioners’ claim, averring that
The facts are stated in the opinion of the Court. the separation pay already paid to them was already more than what the law requires.
  Seno, Mendoza and Associates for petitioners. Reaching an impasse on the conflict, the parties referred the issue to voluntary
  Vicente A. Espina, Jr. for respondent. arbitration, wherein the validity of Benson’s closure was brought up as well.11
 PERLAS-BERNABE,  J.: _______________
Before the Court is a petition for review on certiorari1assailing the 6  Id., at pp. 43-44.
Decision2 dated September 27, 2011 and the Resolution3 dated January 31, 2012 of 7   Id., at pp. 33 and 52.
the Court of Appeals (CA) in C.A.-G.R. S.P. No. 03842 which reversed and set aside 8  Id., at p. 63.
the Decision4 dated October 24, 2008 of the Voluntary Arbitrator (VA) of the 9  Id., at p. 44.
National Conciliation and Mediation Board (NCMB), and accordingly deleted the 10 Id., at p. 255.
award to petitioners Vilma Genon, Edisa Hortelano, Lourdes Aranas, Tony 11 Id., at pp. 254-255.
Formentera, Reneboy Leyson, Ma. Alona Acaldo, Ma. Concepcion Abao, Teresita 323The VA’s Ruling

44
In a Decision12 dated October 24, 2008 (October 24, 2008 VA Decision), the VA preventing further financial drain upon an employer who cannot anymore pay its
ruled in favor of petitioners, and, thus, ordered Benson to pay each of them employees since
separation benefits in “an amount equivalent to four (4) days for every year of _______________
service based on the latest rate of pay of the [individual petitioner] concerned subject 16 Id., at pp. 31-39.
to whatever legally valid deductions chargeable against [said individual petitioner] 17 Id., at pp. 35-38.
whenever applicable.”13 18 Id., at pp. 41-42.
The VA ratiocinated that in computing the amount of separation benefits due to 325business has already stopped. As a form of recompense, the employer is required
petitioners, the basis should be the provision of the existing CBA between Benson to pay its employees separation benefits, except when the closure is due to serious
and the Union which explicitly states that should the employees be terminated business losses.19 Article 297 (formerly Article 283)20 of the Labor Code, as
through no fault of their own, they should be awarded separation benefits at the rate amended, states this rule:
of 19 days for every year of service. In this regard, the VA opined that the provisions Art. 297. Closure of Establishment and Reduction of Personnel.—The employer
of the CBA should be given effect because it expresses the latest agreement of the may also terminate the employment of any employee due to the installation of labor-
union and the company, not to mention the fact that it gives more benefits to the saving devices, redundancy, retrenchment to prevent losses or the closing or
employees.14 cessation of operation of the establishment or undertaking unless the closing is for
Separately, the VA found adequate proof to support Benson’s position that it was the purpose of circumventing the provisions of this Title, x x x. In case of
indeed in a state of insolvency, which, therefore, justified its closure and/or cessation retrenchment to prevent losses and in cases of closures or cessation of operations
of business operations on the ground of serious business losses and/or financial of establishment or undertaking not due to serious business losses or financial
reverses.15 reverses, the separation pay shall be equivalent to one (1) month pay or at least
Dissatisfied, Benson elevated the matter on appeal before the CA. one-half (1/2) month pay for every year of service, whichever is higher. A
_______________ fraction of at least six (6) months shall be considered one (1) whole year. (Emphasis
12 Id., at pp. 253-260. and underscoring supplied)
13 Id., at p. 50.     While serious business losses generally exempt the employer from paying
14 Id., at p. 255. separation benefits, it must be pointed that the exemption only pertains to the
15 Id., at pp. 255-260. obligation of the employer under Article 297 of the Labor Code. This is because of
324 the law’ s express parameter that mandates payment of separation benefits “in case
The CA’s Ruling of closures or cessation of operations of establishment or undertaking not due to
In a Decision16 dated September 27, 2011, the CA reversed and set aside the serious busi-
VA’s ruling, and accordingly deleted the award of additional separation benefits _______________
equivalent to four (4) days of work for every year of service. It held that despite the 19 See Sangwoo Philippines, Inc. v. Sangwoo Philippines, Inc. Employees
express provision in the CBA stating that Benson should pay its employees who Union-Olalia, G.R. No. 173154 and G.R. No. 173229, December 9, 2013; citations
were terminated without their fault separation benefits equivalent to at least 19 days’ omitted.
pay for every year of service, Benson cannot be compelled to do so considering its 20 As amended and renumbered by Republic Act No. 10151, entitled “An Act
current financial status.17 Allowing the Employment of Night Workers, Thereby Repealing Articles 130 and
Aggrieved, petitioners moved for reconsideration, which was, however, denied 131 of Presidential Decree Number Four Hundred Forty-Two, as Amended,
by the CA in a Resolution18 dated January 31, 2012, hence, this petition. Otherwise Known as the Labor Code of the Philippines.”
The Issue Before the Court 326ness losses or financial reverses.” The policy distinction underlying Article
The sole issue for the Court’s resolution is whether or not the CA correctly 297 — that is, the distinction between closures due to serious business losses and
deleted the award to petitioners of additional separation benefits equivalent to four those which are not — was deftly discussed by the Court in the case of Cama v.
(4) days of work for every year of service. Joni’s Food Services, Inc.,21 as follows:
The Court’s Ruling The Constitution, while affording full protection to labor, nonetheless, recognizes
The petition is impressed with merit. “the right of enterprises to reasonable returns on investments, and to expansion and
Closure of business may be considered as a reversal of an employer’s fortune growth.” In line with this protection afforded to business by the fundamental law,
whereby there is a complete cessation of business operations and/or an actual Article 283 [(now, Article 297)] of the Labor Code clearly makes a policy
locking-up of the doors of the establishment, usually due to financial losses. Under distinction. It is only in instances of “retrenchment to prevent losses and in cases
the Labor Code, it is treated as an authorized cause for termination, aimed at of closures or cessation of operations of establishment or undertaking not due to

45
serious business losses or financial reverses” that employees whose employment 26 Supreme Steel Corporation v. Nagkakaisang Manggagawa Ng Supreme
has been terminated as a result are entitled to separation pay. In other words, Article Independent Union (NMSIND-APL), G.R. No. 185556, March 28, 2011, 646 SCRA
283 [(now, Article 297)] of the Labor Code does not obligate an employer to pay 501, 521.
separation benefits when the closure is due to serious losses. To require an employer 27 G.R. No. 145561, June 15, 2005, 460 SCRA 186.
to be generous when it is no longer in a position to do so, in our view, would be 328
unduly oppressive, unjust, and unfair to the employer. Ours is a system of laws, and A collective bargaining agreement refers to the negotiated contract between a
the law in protecting the rights of the working man, authorizes neither the oppression legitimate labor organization and the employer concerning wages, hours of work and
nor the self-destruction of the employer. x x x.22 (Emphasis supplied) all other terms and conditions of employment in a bargaining unit. As in all
    When the obligation to pay separation benefits, however, is not sourced from contracts, the parties in a CBA may establish such stipulations, clauses, terms and
law (particularly, Article 297 of the Labor Code), but from contract, 23 such as an conditions as they may deem convenient provided these are not contrary to law,
existing collective bar- morals, good customs, public order or public policy. Thus, where the CBA is clear
_______________ and unambiguous, it becomes the law between the parties and compliance therewith
21 469 Phil. 223; 425 SCRA 259 (2004). is mandated by the express policy of the law.28
22 Id., at pp. 235-236; p. 269.     In this case, it is undisputed that a CBA was forged by the employer, Benson,
23 Article 1157 of the Civil Code provides: and its employees, through the Union, to govern their relations effective July 1, 2005
Art. 1157. Obligations arise from: to June 30, 2010. It is equally undisputed that Benson agreed to and was thus
(1) Law; obligated under the CBA to pay its employees who had been terminated without any
(2) Contracts; fault attributable to them separation benefits at the rate of 19 days for every year of
(3) Quasi-contracts; service. This is particularly found in Section 1, Article VIII of the same contract, to
327gaining agreement between the employer and its employees, an examination of wit:
the latter’s provisions becomes necessary in order to determine the governing Section 1. Separation Pay.—The Company shall pay to any employee/laborer who
parameters for the said obligation. To reiterate, an employer which closes shop due is terminated from the service without any fault attributable to him, a “Separation
to serious business losses is exempt from paying separation benefits under Article Pay” equivalent to not less than nineteen (19) days’ pay for every year of service
297 of the Labor Code for the reason that the said provision explicitly requires the based upon the latest rate of pay of the employee/laborer concerned.29
same only when the closure is not due to serious business losses; conversely, the    As may be gleaned from the following whereas clauses in a Memorandum of
obligation is maintained when the employer’s closure is not due to serious business Agreement30 dated November 20, 2003 between the parties, Benson had been fully
losses. For a similar exemption to obtain against a contract, such as a CBA, the tenor aware of its distressed financial condition even at the time of the previous CBA
of the parties’ agreement ought to be similar to the law’s tenor. When the parties, (effective from July 1, 2000 to June 30, 2005):
however, agree to deviate therefrom, and unqualifiedly covenant the payment of _______________
separation benefits irrespective of the employer’s financial position, then the 28 Id., at pp. 190-191.
obligatory force of that contract prevails and its terms should be carried out to its full 29 Rollo, p. 255.
effect. Verily, it is fundamental that obligations arising from contracts have the force 30 Id., at pp. 415-418.
of law between the contracting parties and thus should be complied with in good 329
faith;24 and parties are bound by the stipulations, clauses, terms and conditions they WHEREAS, on February 01, 2001 the Company and the Union entered into a
have agreed to, the only limitation being that these stipulations, clauses, terms and Collective Bargaining Agreement (CBA) with effectivity from July 01, 2000 to June
conditions are not contrary to law, morals, public order or public policy. 25 Hence, if 30, 2005;
the terms of a CBA are clear and there is no doubt as to the intention of the xxxx
contracting parties, the literal meaning of its stipulations shall prevail. 26 As WHEREAS, the Company and the Union recognize that the Philippines is at
enunciated in Honda Phils., Inc. v. Samahan ng Malayang Manggagawa sa Honda:27 present in grave economic crisis;
_______________ WHEREAS, the Union recognizes and acknowledges that the Company in
(4) Acts or omissions punished by law; and particular is in grave financial difficulties and that the Company is hard up to
(5) Quasi-delicts. (Emphases supplied) meet its financial obligations to creditor banks that said creditor banks have even
24 Prisma Construction & Development Corporation v. Menchavez, G.R. No. threatened to foreclose the mortgages on and to seize the Company’s factory,
160545, March 9, 2010, 614 SCRA 590, 597. realties, machineries and assets and in fact, the Bank of the Philippine Islands, one of
25 Id., at p. 601. the creditor banks scheduled on November 17, 1998 a foreclosure sale of the

46
Company’s factory, realties, machineries and assets in Extrajudicial Foreclosure clear during the CBA negotiations that the bonus was dependent on any
Case No. EJF-2773-CEB; condition. Indeed, if the petitioner and respondent Association intended that the
x x x x (Emphases supplied) P3,000.00 bonus would be dependent on the company earnings, such intention
    Benson even admits in its Comment that it was already saddled with loan from should have been expressed in the CBA.
banks as early as 199731and that it had been unable to service its loan It is noteworthy that in petitioner’s 1998 and 1999 financial Statements, it took
obligations.32And yet, nothing appears on record to discount the fact that it still note that “the 1997 financial crisis in the Asian region adversely affected the
unqualifiedly and freely agreed to the separation pay provision in the July 1, 2005 to Philippine economy.”
June 30, 2010 CBA, its distressed financial condition notwithstanding. From the foregoing, petitioner cannot insist on business losses as a basis for
Thus, in view of the foregoing, the Court disagrees with the CA in negating disregarding its undertaking. It is manifestly clear that petitioner was very much
Benson’s obligation to pay petitioners their full separation benefits under the said aware of the imminence and possibility of business losses owing to the 1997
agreement. The postulation that Benson had closed its establishment and ceased financial crisis. In 1998, petitioner suffered a net loss of P14,347,548.00. Yet it gave
_______________ a P3,000.00 bonus to the members of the Association. In 1999, when petitioner’s
31 Id., at p. 455. very own financial statement reflected that “the positive developments in the
32 Id. economy have yet to favorably affect the operations of the company,” and reported a
330operations due to serious business losses cannot be accepted as an excuse to clear loss of P346,025,733.00, it entered into the CBA with the respondent Association
itself of any liability since the ground of serious business losses is not, unlike Article whereby it contracted to grant a Christmas gift package/bonus to the
297 of the Labor Code, considered as an exculpatory parameter under the latter. Petitioner supposedly continued to incur losses on the years 2000 and
aforementioned CBA. Clearly, Benson, with full knowledge of its financial situation, 2001. Still and all, this did not deter it from honoring the CBA provision on
freely and voluntarily entered into such agreement with petitioners. Hence, having Christmas bonus as it continued to give P3,000.00 each to the members of the
failed to show that the subject CBA provision on separation benefits is contrary to respondent Association in the years 1999, 2000 and 2001.
law, morals, public order or public policy, or that the same can be interpreted as one All given, business losses are a feeble ground for petitioner to repudiate its
with a condition — for instance, that the parties actually contemplated nonpayment obligation under the CBA. The rule is settled that any benefit and supplement being
of separation benefits in the event of closure due to serious business losses — the enjoyed by the employees cannot be reduced,
Court is constrained to reinstate the October 24, 2008 VA Decision ordering Benson 332diminished, discontinued or eliminated by the employer. The principle of non-
to pay each of the petitioners separation benefits in “an amount equivalent to four (4) diminution of benefits is founded on the constitutional mandate to protect the rights
days for every year of service based on the latest rate of pay of the [individual of workers and to promote their welfare and to afford labor full protection.
petitioner] concerned, subject to whatever legally valid deductions chargeable Hence, absent any proof that petitioner’s consent was vitiated by fraud, mistake
against [said individual petitioner], whenever applicable.”33 or duress, it is presumed that it entered into the CBA voluntarily and had full
Analogous to the foregoing is the Court’s disquisition in Lepanto Ceramics, Inc. knowledge of the contents thereof and was aware of its commitments under the
v. Lepanto Ceramics Employees Association,34 whereby the employer therein was contract.35 (Emphases and underscoring supplied; citations omitted)
held liable for the payment of Christmas bonus benefits, considering that the grant      A similar disposition was also made in the case of Eastern
thereof was voluntarily and unqualifiedly agreed upon by the parties under the CBA Telecommunications Philippines, Inc. v. Eastern Telecoms Employees
despite the employer’s full awareness of its distressed financial position (as Benson Union,36 wherein the Court held as follows:
in this case), viz.: The parties to the contract must be presumed to have assumed the risks of
It is a familiar and fundamental doctrine in labor law that the CBA is the law unfavorable developments. It is, therefore, only in absolutely exceptional changes of
between the parties and they are obliged to comply with its provisions. This principle circumstances that equity demands assistance for the debtor. In the case at bench, the
stands strong and true in the case at bar. Court determines that ETPI’s claimed depressed financial state will not release it
A reading of the provision of the CBA reveals that the same provides for the from the binding effect of the 2001-2004 CBA Side Agreement.
giving of a “Christmas gift ETPI appears to be well aware of its deteriorating financial condition when it
_______________ entered into the 2001-2004 CBA Side Agreement with ETEU and obliged itself to
33 Id., at p. 260. pay bonuses to the members of ETEU. Considering that ETPI had been continuously
34 G.R. No. 180866, March 2, 2010, 614 SCRA 63. suffering huge losses from 2000 to 2002, its business losses in the year 2003 were
331package/bonus” without qualification. Terse and clear, the said provision did not not exactly unforeseen or unexpected. Consequently, it cannot be said that the
state that the Christmas package shall be made to depend on the petitioner’s financial difficulty in complying with its obligation under the Side Agreement was
standing. The records are also bereft of any showing that the petitioner made it “manifestly beyond the contemplation of the parties.” Besides, as held in Central

47
Bank of the Philippines v. Court of Appeals, mere pecuniary inability to fulfill an the doors of the establishment, usually due to financial losses — as an authorized
engagement cause for termination of employment, it aims to prevent further financial drain upon
_______________ an employer who can no longer pay his employees since business has already
35 Id., at pp. 73-74. stopped. (Peñafrancia Tours and Travel Transport, Inc. vs. Sarmiento, 634 SCRA
36 G.R. No. 185665, February 8, 2012, 665 SCRA 516. 279 [2010])
333does not discharge a contractual obligation. Contracts, once perfected, are Closure or cessation of business is the complete or partial cessation of the
binding between the contracting parties. Obligations arising therefrom have the force operations and/or shut-down of the establishment of the employer; It is carried out to
of law and should be complied with in good faith. ETPI cannot renege from the either stave off the financial ruin or promote the business interest of the employee.
obligation it has freely assumed when it signed the 2001-2004 CBA Side (Sy vs. Fairland Knitcraft Co., Inc., 662 SCRA 67 [2011])
Agreement.37 (Emphases and underscoring supplied; citations omitted)
    To quell any doubts, it bears pointing out that the CA’s reliance on Galaxie ——o0o——
Steel Workers Union (GSWU-NAFLU-KMU) v. NLRC 38 and Cama v. Joni’s Food
Services, Inc.39 was actually misplaced since no CBA was involved in those cases.
As such, consistent with the parameters of Article 297 of the Labor Code as above
discussed, the payment of separation benefits in view of the employer’s serious
business losses in those cases was not in order. In the same light, North Davao
Mining Corporation v. NLRC40 was speciously applied by the CA given that the
payment of separation benefits in that case was not sourced from a contractual CBA G.R. No. 161006. October 14, 2015.*
obligation but merely from a unilateral company practice which was deemed as an  
act of generosity on the part of the employer. It was in this context that the Court ROGELIO BARONDA, petitioner, vs. HON. COURT OF APPEALS, and
held that “to require [the company] to continue being generous when it is no longer HIDECO SUGAR MILLING CO., INC., respondents.
in a position to do so would certainly be unduly oppressive, unfair and most Labor Law; Voluntary Arbitrators; Appeals; Article 262-A of the Labor Code
revolting to the conscience.” 41 The factual dissimilarity of these cases to Benson and expressly states that the award or decision of the Voluntary Arbitrator shall be final
petitioners’ situation therefore precludes the application ofthe same ruling. and executory after ten (10) calendar days from receipt of the copy of the award or
Accordingly, finding no cogent reason for Benson not to comply with its decision by the parties.—The period of appeal was 10 days from receipt of the copy
obligations under the July 1, 2005 to June 30, 2010 CBA, and considering further of the order of July 25, 2001 by the parties. It is true that Section 4 of Rule 43
that the interpretation of any law or provision affecting labor should be interpreted in stipulates that the appeal shall be taken within 15 days from notice of the award,
_______________ judgment, final order or resolution, or from the date of its last publication, if
37 Id., at pp. 531-532. publication is required by law for its effectivity, or of the denial of the petitioner’s
38 535 Phil. 675; 504 SCRA 692 (2006). motion for new trial or reconsideration duly filed in accordance with the governing
39 Supra note 21. law of the court or agency a quo. However, Article 262-A of the Labor Code, the
40 G.R. No. 112546, March 13, 1996, 254 SCRA 721. relevant portion of which follows, expressly states that the award or decision of the
41 Id., at p. 730. Voluntary Arbitrator shall be final and executory after 10 calendar days from receipt
334favor of labor,42 the Court hereby reverses the CA Decision and reinstates the of the copy of the award or decision by the parties, viz.: Art. 262-A. Procedures.—
October 24, 2008 VA Decision. x x x x The award or decision of the Voluntary Arbitrator or panel of Voluntary
WHEREFORE, the petition is GRANTED. The Decision dated September 27, Arbitrators shall contain the facts and the law on which it is based. It shall be final
2011 and the Resolution dated January 31, 2012 of the Court of Appeals in C.A.- and executory after ten (10) calendar days from receipt of the copy of the award
G.R. S.P. No. 03842 are hereby REVERSED and SET ASIDE. The Decision dated or decision by the parties. Upon motion of any interested party, the Voluntary
October 24, 2008 of the Voluntary Arbitrator of the National Conciliation and Arbitrator or panel of Voluntary Arbitrators or the Labor Arbiter in the region where
Mediation Board is REINSTATED. the movant resides, in case of the absence or incapacity of the Voluntary Arbitrator
SO ORDERED. or panel of Voluntary Arbitrators for any reason, may issue a writ of execution
Carpio (Chairperson), Brion, Del Castillo and Perez, JJ., concur. requiring either the sheriff of the Commission or regular courts or any public official
Petition granted, judgment and resolution reversed and set aside. whom the parties may designate in the submission agreement to execute the final
Notes.—Closure of business is the reversal of fortune of the employer whereby decision, order or award.
there is a complete cessation of business operations and/or an actual locking-up of

48
Same; Same; Same; Even if the error sought to be reviewed concerned grave  
abuse of discretion on the part of the Voluntary Arbitrator, the remedy was an  
appeal in due course by filing the petition for  278
_______________ 278 SUPREME COURT REPORTS ANNOTATED
Baronda vs. Court of Appeals
*  FIRST DIVISION.
  Same; Reinstatement Pending Appeal; The immediate reinstatement of the
  employee pending the appeal has been introduced by Section 12 of Republic Act
277 (RA) No. 6715, which amended Article 223 of the Labor Code.—The immediate
reinstatement of the employee pending the appeal has been introduced by Section 12
VOL. 772, OCTOBER 14, 2015 277 of Republic Act No. 6715, which amended Article 223 of the Labor Code, to wit:
Baronda vs. Court of Appeals SEC. 12. Article 223 of the same code is amended to read as follows: Art.
review within ten (10) days from notice of the award or decision.—To begin 223. Appeal.—x x x x In any event, the decision of the Labor Arbiter reinstating
with, even if the error sought to be reviewed concerned grave abuse of discretion on a dismissed or separated employee, insofar as the reinstatement aspect is
the part of the Voluntary Arbitrator, the remedy was an appeal in due course by filing concerned, shall immediately be executory, even pending appeal. The employee
the petition for review within 10 days from notice of the award or decision. This was shall either be admitted back to work under the same terms and conditions prevailing
because certiorari, as an extraordinary remedy, was available only when there was prior to his dismissal or separation or, at the option of the employer, merely
no appeal, or any plain, speedy and adequate remedy in the ordinary course of law. reinstated in the payroll. The posting of a bond by the employer shall not stay the
In other words, the justification for HIDECO’s resort to the extraordinary equitable execution for reinstatement provided herein.
remedy of certiorari did not exist due to the availability of appeal, or other ordinary Same; Same; Reinstatement pending appeal thus affirms the constitutional
remedies in law to which HIDECO as the aggrieved party could resort. mandate to protect labor and to enhance social justice.—The normal consequences
Same; Same; Same; Certiorari; Although it is true that certiorari cannot be a of a finding that an employee was illegally dismissed are, firstly, that the employee
substitute for a lost appeal, and that either remedy was not an alternative of the becomes entitled to reinstatement to his former position without loss of seniority
other, the Supreme Court (SC) has at times permitted the resort to certiorari despite rights; and secondly, the payment of wages corresponding to the period from his
the availability of appeal, or of any plain speedy and adequate remedy in the illegal dismissal up to the time of actual reinstatement. These two consequences give
ordinary course of law in exceptional situations.—Although it is true meaning and substance to the constitutional right of labor to security of tenure.
that certiorari cannot be a substitute for a lost appeal, and that either remedy was not Reinstatement pending appeal thus affirms the constitutional mandate to protect
an alternative of the other, we have at times permitted the resort to certiorari despite labor and to enhance social justice.
the availability of appeal, or of any plain speedy and adequate remedy in the ordinary PETITION for review on certiorari of a decision of the Court of Appeals.
course of law in exceptional situations, such as: (1) when the remedy of certiorari is The facts are stated in the opinion of the Court.
necessary to prevent irreparable damages and injury to a party; (2) where the trial   Santo Law Office for petitioner.
judge capriciously and whimsically exercised his judgment; (3) where there may be   Flor Amor A. Opon for respondent.
danger of a failure of justice; (4) where appeal would be slow, inadequate and  
insufficient; (5) where the issue raised is one purely of law; (6) where public interest  
is involved; and (7) in case of urgency. Verily, as pointed out in Jaca v. Davao 279
Lumber Company, 113 SCRA 107 (1982), the availability of the ordinary course of VOL. 772, OCTOBER 14, 2015 279
appeal does not constitute sufficient ground to prevent a party from making use
Baronda vs. Court of Appeals
of certiorari where the appeal is not an adequate remedy or equally beneficial,
speedy and sufficient; for it is inadequacy, not the mere absence of all other legal BERSAMIN, J.:
remedies and the danger of failure of justice without the writ that must usually  
determine the propriety of certiorari. It is nonetheless necessary in such exceptional The reinstatement aspect of the Voluntary Arbitrator’s award or decision is
situations for the petitioner to make a strong showing in such situations that the immediately executory from its receipt by the parties.
respondent judicial or quasi-judicial official or tribunal lacked or exceeded its  
jurisdiction, or gravely abused its discretion amounting to lack or excess of The Case 
jurisdiction.  

49
The petitioner assails the decision 1 promulgated on August 21, 2003 in C.A.- Wherefore, insofar as the case of ROGELIO BARONDA is concerned, this
G.R. S.P. No. 67059, whereby the Court of Appeals (CA) annulled and set aside the Office finds his dismissal illegal and reinstatement is therefore ordered. His
order issued by the Voluntary Arbitrator 2 granting his motion for the issuance of the separation on June 16, 1998 up to January 15, 1999 is deemed suspension without
writ of execution.3 pay for his negligent acts, and is further ordered to pay respondent employer the sum
  of P26,484.41 for actual damages at P1,500.00 every month deductible from his
Antecedents  salary until complete payment is made.
   
Respondent Hideco Sugar Milling Co., Inc. (HIDECO) employed the petitioner HIDECO filed a motion for reconsideration, 8 but the Voluntary Arbitrator denied
as a mud press truck driver with a daily salary of P281.00. On May 1, 1998, he hit the motion on August 11, 2000.9 Accepting the outcome, HIDECO reinstated the
HIDECO’s transmission lines while operating a dump truck, causing a total factory petitioner on September 29, 2000.10
blackout from 9:00 p.m. until 2:00 a.m. of the next day. Power was eventually _______________
restored but the restoration cost HIDECO damages totaling P26,481.11. Following
the incident, HIDECO served a notice of offense requiring him to explain the 5   Id., at pp. 24-25.
incident within three days from notice. He complied. Thereafter, the management 6   Id., at pp. 25-26.
conducted its investigation, and, finding him guilty of negligence, recommended his 7   Id., at p. 48.
dismissal.4 On June 15, 1998, the resident manager served a termination letter and 8   Id., at pp. 138-141.
informed him of the decision to termi- 9   Id., at p. 142.
_______________ 10  Id., at p. 27.
 
1  Rollo, pp. 23-38; penned by Associate Justice Cancio C. Garcia (later  
Presiding Justice, and a member of the Court/retired/ 281
deceased) with concurrence of Associate Justices Martin S. Villarama, Jr. (now a VOL. 772, OCTOBER 14, 2015 281
member of the Court) and Mario L. Guariña III (retired).
Baronda vs. Court of Appeals
2  Id., at pp. 50-51.
3  Id., at pp. 159-161. Thereafter, on October 9, 2000, the petitioner filed his manifestation with motion
4  Id., at p. 24. for the issuance of the writ of execution in the Office of the Voluntary
  Arbitrator,11praying for the execution of the decision, and insisting on being entitled
  to backwages and other benefits corresponding to the period from January 16, 1999
280 up to September 28, 2000 totaling P192,268.66 based on Article 279 of the Labor
Code (“An employee who is unjustly dismissed from work shall be entitled to
280 SUPREME COURT REPORTS ANNOTATED reinstatement without loss of seniority rights and other privileges and to his full
Baronda vs. Court of Appeals backwages, inclusive of allowances, and to his other benefits or their monetary
nate his employment effective at the close of office hours of that day. Hence, equivalent computed from the time his compensation was withheld from him up to
HIDECO no longer allowed him to report to work on the next day.5 the time of his actual reinstatement”).
In August 1998, the petitioner, along with another employee also dismissed by HIDECO opposed the petitioner’s motion for execution, 12and simultaneously
HIDECO, filed in the Office of the Voluntary Arbitrator of the National Conciliation presented its own motion for execution to enforce the decision of the Voluntary
and Mediation Board in Tacloban City a complaint for illegal dismissal against Arbitrator directing the petitioner to pay the actual damages totaling P26,484.41 at
HIDECO.   the rate of P1,500.00/month deductible from his salary starting in January 2001 until
Voluntary Arbitrator Antonio C. Lopez, Jr. handled the case and eventually complete payment was made.13
rendered his decision on January 13, 1999 by finding the petitioner’s dismissal In his order dated March 20, 2001, 14 the Voluntary Arbitrator denied the
illegal, and ordering his reinstatement. Voluntary Arbitrator Lopez, Jr. deemed the petitioner’s motion for execution on the ground that the decision did not award any
petitioner’s separation from the service from June 16, 1998 to January 15, 1999 as a backwages; and granted HIDECO’s motion for execution by directing the petitioner
suspension from work without pay, and commanded him to pay on installment basis to pay HIDECO P26,484.41 at the rate of P1,500.00/month.
the damages sustained by HIDECO from the May 1, 1998 incident he had caused, 6 to On May 17, 2001, the petitioner filed another motion for execution praying that a
wit:7 writ of execution requiring HIDECO to pay to him unpaid wages, 13th month pay

50
and bonuses from January 16, 2001, the date when his reinstatement was effected, 17  Id., at pp. 50-51.
until his actual reinstatement.15 HIDECO opposed the petitioner’s second motion for  
execution because “the items  
_______________ 283
VOL. 772, OCTOBER 14, 2015 283
11  Id., at pp. 144-145.
Baronda vs. Court of Appeals
12  Id., at pp. 152-155.
13  Id., at pp. 156-157. Having received a copy of the order of July 25, 2001 on August 7,
14  Id., at p. 158. 2001,18 HIDECO instituted a special civil action for certiorari in the Court of
15  Id., at pp. 159-162. Appeals (CA) on October 2, 2001.19
   
  Decision of the CA 
282  
HIDECO’s petition for certiorari averred that the Voluntary Arbitrator had acted
282 SUPREME COURT REPORTS ANNOTATED with grave abuse of discretion amounting to lack or excess of jurisdiction in issuing
Baronda vs. Court of Appeals the July 25, 2001 order. It listed the following issues, namely:
prayed for by the complainant in his Motion for Issuance of Writ of Execution are I. The voluntary arbitrator, in rendering the assailed order actually granted an
not included in the dispository portion of the decision of the voluntary arbitrator, award without giving due process to the herein petitioner.20
neither are the said items mentioned in any part of the same decision.”16 II. The voluntary arbitrator resolved the (second) motion by applying Art. 223
On July 25, 2001, however, the Voluntary Arbitrator granted the petitioner’s of the Labor Code. Was this the correct law to apply under the circumstances? Did
second motion for execution,17 to wit: he have jurisdiction to apply this law?21
Wherefore, for failure of complainant to readmit complainant nor reinstate him in III. The decision dated January 13, 1999 clearly stated the relief that had been
the payroll for the period from January 21, [1999] up to September 28, 2000, let an granted to the complainant Baronda, which was reinstatement. Baronda was
order or execution issue for the satisfaction of his reinstatement wages in the amount reinstated on September 29, 2000, thus [HIDECO] had complied with the decision.
of P155,647.00 (554 days at P281.00 per day), 13th month pay in the amount of The questions therefore: Could a relief that is not written in the decision be
P7,200.00, bonus in the amount of P8,000.00 for 1999, and P8,000.00 for his signing executed? Since the voluntary arbitrator clearly did this in this case, is it not correct
bonus. to say that he committed grave abuse of discretion?22
The sheriff of the National Labor Relations Commission, Regional Arbitration IV. In the assailed Order dated July 25, 2001 the Voluntary Arbitrator said,
Branch No. VIII is directed to implement the writ. among others, that it treated a second motion for the issuance of a writ of execution,
So ordered. and that a first motion had already been denied on the ground that no backwages had
  been awarded to the com-
The Voluntary Arbitrator cited as basis Article 223 of the Labor Code, which _______________
pertinently provides:
Art. 223. Appeal.— 18  Id., at p. 54.
x x x x 19  CA Rollo, p. 2.
In any event, the decision of the Labor Arbiter reinstating a dismissed or 20  Id., at p. 10.
separated employee, insofar as the reinstatement aspect is concerned, shall 21  Id.
immediately be executory, even pending appeal. The employee shall either be 22  Id., at p. 11.
admitted back to work under the same terms and conditions prevailing prior to his  
dismissal or separation or, at the option of the employer, merely reinstated in the  
payroll. The posting of a bond by the employer shall not stay the execution for 284
reinstatement provided herein. 284 SUPREME COURT REPORTS ANNOTATED
_______________
Baronda vs. Court of Appeals
16  Id., at p. 164. plainant Baronda. Did he have any legal basis then to issue two different and
contradictory orders for what are essentially similar motions?23
51
In his comment,24 the petitioner countered that the petition for certiorari should THE SAKE OF ARGUMENT THAT SAID PETITION COULD BE
be dismissed considering that HIDECO should have appealed the decision of the CONSIDERED AS FILED UNDER RULE 43 OF THE RULES OF COURT, THE
Voluntary Arbitrator under Rule 43 of the Rules of Courtbecause certiorari was not a HONORABLE COURT OF APPEALS COMMITTED AN ERROR OF LAW IN
substitute for a lost appeal; that HIDECO did not file a motion for reconsideration of NOT CONSIDERING THAT IT WAS FILED OUT OF TIME.
the questioned order, which would have been an adequate remedy at law; that the II.
petition for certiorari did not raise any jurisdictional error on the part of the THE HONORABLE COURT OF APPEALS COMMITTED AN ERROR OF
Voluntary Arbitrator but only factual and legal issues not proper in certiorari; and LAW WHEN IT DID NOT DISMISS THE PETITION FILED BY THE PRIVATE
that the Voluntary Arbitrator did not commit any error, much less grave abuse of RESPONDENT FOR NOT HAVING PREVIOUSLY FILED A MOTION FOR
discretion amounting to lack or excess of jurisdiction in rendering the questioned RECONSIDERATION BEFORE RESORTING TO THE PETITION
order. FOR CERTIORARI.
In the decision promulgated on August 21, 2003, 25 the CA treated HIDECO’s _______________
petition for certiorari as a petition for review brought under Rule 43, and brushed
aside the matters raised by the petitioner. It observed that the petition 26  Id., at p. 37.
for certiorari included the contents required by Section 6, Rule 43 for the petition for 27  Id., at pp. 8-9.
review; that the writ of execution was proper only when the decision to be executed  
carried an award in favor of the movant; that the Voluntary Arbitrator had issued the  
writ of execution for backwages despite his decision lacking such award for 286
backwages; and that the reliance by the Voluntary Arbitrator on Article 223 of 286 SUPREME COURT REPORTS ANNOTATED
the Labor Code was misplaced because said provision referred to decisions, awards
or orders of the Labor Arbiter, not the Voluntary Arbitrator. It disposed as follows: Baronda vs. Court of Appeals
_______________ III.
THE HONORABLE COURT OF APPEALS COMMITTED AN ERROR OF
23  Id., at p. 14. LAW WHEN IT CONSIDERED THE WRIT OF EXECUTION AS ISSUED FOR
24  Id., at pp. 128-143. THE SATISFACTION OF BACKWAGES INSTEAD OF FOR REINSTATEMENT
25  Supra note 1. WAGES.
  IV.
  THE HONORABLE COURT OF APPEALS COMMITTED AN ERROR OF
285 LAW AND SANCTIONED A VIOLATION OF THE EQUAL PROTECTION OF
THE LAWS WHEN IT RULED THAT THE REINSTATEMENT ASPECT OF
VOL. 772, OCTOBER 14, 2015 285 THE DECISION OF THE VOLUNTARY ARBITRATOR IS NOT
Baronda vs. Court of Appeals IMMEDIATELY EXECUTORY.
WHEREFORE, the instant petition is hereby GRANTED and the V.
questioned Order dated July 25, 2001 of the public THE HONORABLE COURT OF APPEALS COMMITTED AN ERROR OF
respondent ANNULLED and SET ASIDE. LAW WHEN IT DECLARED THAT PRIVATE RESPONDENT WAS DENIED
SO ORDERED.26 DUE PROCESS OF LAW.
  In other words, the decisive issues for consideration and resolution are: (a)
Issues  whether or not the CA erred in granting HIDECO’s petition for certiorari despite its
  procedural flaws; and (b) whether or not the reinstatement aspect of the Voluntary
In this appeal, the petitioner submits the following issues,27 namely: Arbitrator’s decision was executory pending appeal.
I.  
THE HONORABLE COURT OF APPEALS COMMITTED AN ERROR OF Ruling 
LAW WHEN IT CONSIDERED THE PETITION FOR CERTIORARI FILED BY  
PRIVATE RESPONDENT AS ONE FILED UNDER RULE 43 OF THE RULES The appeal is meritorious.
OF COURT WHEN SAID PETITION EXPRESSLY DECLARED THAT IT WAS  
FILED UNDER RULE 65 OF THE RULES OF COURT. EVEN GRANTING FOR I

52
HIDECO’s proper recourse was to appeal The proper remedy from such order was to appeal to the CA by petition for
by petition for review; hence, the CA erred review under Rule 43 of the Rules of Court, whose Section 1 specifically provides:
in granting HIDECO’s petition for certiorari Section 1. Scope.—This Rule shall apply to appeals from judgments or final
  orders of the Court of Tax Appeals and from awards, judgments, final orders or
  resolutions of or authorized by any quasi-judicial agency in the exercise of its quasi-
287 judicial functions. Among these agencies are the Civil Service Commission, Central
VOL. 772, OCTOBER 14, 2015 287 Boards of Assessment Appeals, Securities and Exchange Commission, Office of the
President, Land Registration Authority, Social Security Commission, Civil
Baronda vs. Court of Appeals
Aeronautics Board, Bureau of Patents, Trademarks and Technology Transfer,
The order issued on July 25, 2001 by the Voluntary Arbitrator, albeit directing National Electrification Administration, Energy Regulation Board, National
the execution of the award or decision of January 13, 1999, was a final order, as Telecommunications Commission, Department of Agrarian Reform under Republic
contrasted from a merely interlocutory order, because its issuance left nothing more Act No. 6657, Government Service Insurance System, Employees’ Compensation
to be done or taken by the Voluntary Arbitrator in the case. 28 It thus completely Commission, Agricultural Inventions Board, Insurance Commission, Philippine
disposed of what the reinstatement Atomic Energy Commission, Board of Investments, Construction Industry
_______________ Arbitration Commission, and voluntary arbitrators authorized by law.
 
28  United Overseas Bank v. Ros, G.R. No. 171532, August 7, 2007, 529 SCRA The period of appeal was 10 days from receipt of the copy of the order of July
334, quoting from Investments, Inc. v. Court of Appeals, No. L-60036, January 27, 25, 2001 by the parties. It is true that Section 4 of Rule 43 stipulates that the appeal
1987, 147 SCRA 334, 339-341, the following distinctions between a final judgment shall be taken within 15 days from notice of the award, judgment, final order
or order, on one hand, and an interlocutory order, on the other, to wit: _______________
x x x A “final” judgment or order is one that finally disposes of a case, leaving
nothing more to be done by the Court in respect thereto, e.g., an adjudication on the tension of time to file a pleading, or authorizing amendment thereof, or granting or
merits which, on the basis of the evidence presented on the trial, declares denying applications for postponement, or production or inspection of documents or
categorically what the rights and obligations of the parties are and which party is in things, etc. Unlike a “final” judgment or order, which is appealable, as above pointed
the right; or a judgment or order that dismisses an action on the ground, for instance, out, an “interlocutory” order may not be questioned on appeal except only as part of
of res judicata or prescription. Once rendered, the task of the Court is ended, as far an appeal that may eventually be taken from the final judgment rendered in the case.
as deciding the controversy or determining the rights and liabilities of the litigants is  
concerned. Nothing more remains to be done by the Court except to await the  
parties’ next move (which among others, may consist of the filing of a motion for 289
new trial or reconsideration, or the taking of an appeal) and ultimately, of course, to
cause the execution of the judgment once it becomes “final” or, to use the established VOL. 772, OCTOBER 14, 2015 289
and more distinctive term, “final and executory.” Baronda vs. Court of Appeals
x x x x or resolution, or from the date of its last publication, if publication is required by law
Conversely, an order that does not finally dispose of the case, and does not end for its effectivity, or of the denial of the petitioner’s motion for new trial or
the Court’s task of adjudicating the parties’ contentions and determining their rights reconsideration duly filed in accordance with the governing law of the court or
and liabilities as regards each other, but obviously indicates that other things remain agency a quo. However, Article 262-A of the Labor Code, the relevant portion of
to be done by the Court, is “interlocutory” e.g., an order denying motion to dismiss which follows, expressly states that the award or decision of the Voluntary Arbitrator
under Rule 16 of the Rules, or granting of motion on ex- shall be final and executory after 10 calendar days from receipt of the copy of the
  award or decision by the parties, viz.:
  Art. 262-A. Procedures.—
288 x x x x
288 SUPREME COURT REPORTS ANNOTATED The award or decision of the Voluntary Arbitrator or panel of Voluntary
Arbitrators shall contain the facts and the law on which it is based. It shall be final
Baronda vs. Court of Appeals
and executory after ten (10) calendar days from receipt of the copy of the award
of the petitioner as ordered by the Voluntary Arbitrator in the award or decision of or decision by the parties.
January 13, 1999 signified.
53
Upon motion of any interested party, the Voluntary Arbitrator or panel of 29  Philippine Electric Corporation v. Court of Appeals, G.R. No. 168612,
Voluntary Arbitrators or the Labor Arbiter in the region where the movant resides, in December 10, 2014, 744 SCRA 361.
case of the absence or incapacity of the Voluntary Arbitrator or panel of Voluntary 30  Section 1, Rule 65 of the Rules of Court.
Arbitrators for any reason, may issue a writ of execution requiring either the sheriff 31  Francisco Motors Corporation v. Court of Appeals, G.R. Nos. 117622-23,
of the Commission or regular courts or any public official whom the parties may October 23, 2006, 505 SCRA 8, 20; Republic v. Sandiganbayan (Third Division),
designate in the submission agreement to execute the final decision, order or award. G.R. No. 113420, March 7, 1997, 269 SCRA 316, 325.
(Emphasis supplied) 32  No. L-25771, March 29, 1982, 113 SCRA 107, 129.
   
On account of Article 262-A of the Labor Code, the period to appeal was  
necessarily 10 days from receipt of the copy of the award or decision of the 291
Voluntary Arbitrator or panel of Voluntary Arbitrators; otherwise, the order of July VOL. 772, OCTOBER 14, 2015 291
25, 2001 would become final and immutable, because only a timely appeal or motion
Baronda vs. Court of Appeals
for reconsideration could prevent the award or decision from attaining finality and
immutability. does not constitute sufficient ground to prevent a party from making use
Yet, HIDECO filed the petition for certiorari, not a petition for review under of certiorari where the appeal is not an adequate remedy or equally beneficial,
Rule 43, and the CA liberally treated the petition for certiorari as a petition for speedy and sufficient; for it is inadequacy, not the mere absence of all other legal
review under Rule 43. remedies and the danger of failure of justice without the writ that must usually
  determine the propriety of certiorari. It is nonetheless necessary in such exceptional
  situations for the petitioner to make a strong showing in such situations that the
290 respondent judicial or quasi-judicial official or tribunal lacked or exceeded its
jurisdiction, or gravely abused its discretion amounting to lack or excess of
290 SUPREME COURT REPORTS ANNOTATED jurisdiction.
Baronda vs. Court of Appeals HIDECO did not establish that its case came within any of the aforestated
We hold that such treatment by the CA was procedurally unwarranted.   exceptional situations.
To begin with, even if the error sought to be reviewed concerned grave abuse of And secondly, HIDECO filed the petition for certiorarion October 2, 2001. Even
discretion on the part of the Voluntary Arbitrator, 29 the remedy was an appeal in due assuming, as the CA held, that the petition for certiorari contained the matters
course by filing the petition for review within 10 days from notice of the award or required by Rule 43, such filing was not timely because 56 days had already lapsed
decision. This was because certiorari, as an extraordinary remedy, was available from HIDECO’s receipt of the denial by the Voluntary Arbitrator of the motion for
only when there was no appeal, or any plain, speedy and adequate remedy in the reconsideration. In short, HIDECO had thereby forfeited its right to appeal. We have
ordinary course of law.30 In other words, the justification for HIDECO’s resort to the always emphasized the nature of appeal as a merely statutory right for the aggrieved
extraordinary equitable remedy of certiorari did not exist due to the availability of litigant, and such nature requires the strict observance of all the rules and regulations
appeal, or other ordinary remedies in law to which HIDECO as the aggrieved party as to the manner of its perfection and as to the time of its taking. Whenever appeal is
could resort. belatedly resorted to, therefore, the litigant forfeits the right to appeal, and the higher
Although it is true that certiorari cannot be a substitute for a lost appeal, and that court ipso facto loses the authority to review, reverse, modify or otherwise alter the
either remedy was not an alternative of the other, we have at times permitted the judgment. The loss of such authority is jurisdictional, and renders the adverse
resort to certiorari despite the availability of appeal, or of any plain speedy and judgment both final and immutable.  
adequate remedy in the ordinary course of law in exceptional situations, such as: (1)  
when the remedy of certiorari is necessary to prevent irreparable damages and injury II
to a party; (2) where the trial judge capriciously and whimsically exercised his Voluntary Arbitrator’s order of reinstatement
judgment; (3) where there may be danger of a failure of justice; (4) where appeal of the petitioner was immediately executory 
would be slow, inadequate and insufficient; (5) where the issue raised is one purely  
of law; (6) where public interest is involved; and (7) in case of urgency. 31 Verily, as  
pointed out in Jaca v. Davao Lumber Company,32 the availability of the ordinary 292
course of appeal 292 SUPREME COURT REPORTS ANNOTATED
_______________
Baronda vs. Court of Appeals
54
The next query is whether the order of reinstatement of the petitioner by the These duties and responsibilities of the State are imposed not so much to express
Voluntary Arbitrator was immediately executory or not. sympathy for the workingman as to forcefully and meaningfully underscore labor as
We answer the query in the affirmative. Although the timely filing of a motion a primary social and economic force, which the Constitution also expressly affirms
for reconsideration or of an appeal forestalls the finality of the decision or award of with equal intensity. Labor is an indispensable partner for the nation’s progress and
the Voluntary Arbitrator,33 the reinstatement aspect of the Voluntary Arbitrator’s stability.
decision or award remains executory regardless of the filing of such motion for If in ordinary civil actions execution of judgment pending appeal is authorized
reconsideration or appeal. for reasons the determination of which is merely left to the discretion of the judge,
The immediate reinstatement of the employee pending the appeal has been We find no plausible reason to withhold it in cases of decisions reinstating dismissed
introduced by Section 12 of Republic Act No. 6715, which amended Article 223 of or separated employees. In such cases, the poor employees had been deprived of
the Labor Code, to wit: their only source of livelihood, their only means of support for their family their
SEC. 12. Article 223 of the same code is amended to read as follows: lifeblood. To Us, this special circumstance is far better than any other which a judge,
Art. 223. Appeal.— in his sound discretion, may determine. In short, with respect to decisions reinstating
x x x x employees, the law itself has determined sufficiently overwhelming reason for its
In any event, the decision of the Labor Arbiter reinstating a dismissed or execution pending appeal.
separated employee, insofar as the reinstatement aspect is concerned, shall _______________
immediately be executory, even pending appeal. The employee shall either be
admitted back to work under the same terms and conditions prevailing prior to his 34  Santos v. National Labor Relations Commission, No. L-76721, September
dismissal or separation or, at the option of the employer, merely reinstated in the 21, 1987, 154 SCRA 166, 171-172.
payroll. The posting of a bond by the employer shall not stay the execution for 35  G.R. No. 90501, August 5, 1991, 200 SCRA 246.
reinstatement provided herein. (bold underscoring supplied for emphasis)  
   
The normal consequences of a finding that an employee was illegally dismissed 294
are, firstly, that the employee becomes entitled to reinstatement to his former position 294 SUPREME COURT REPORTS ANNOTATED
without loss of seniority rights; and secondly, the payment of wages corresponding to
the period from his illegal dismissal up to the Baronda vs. Court of Appeals
_______________ x x x Then, by and pursuant to the same power (police power), the State may
authorize an immediate implementation, pending appeal, of a decision reinstating a
33  Teng v. Pahagac, G.R. No. 169704, November 17, 2010, 635 SCRA 173, dismissed or separated employee since that saving act is designed to stop, although
182. temporarily since the appeal may be decided in favor of the appellant, a continuing
  threat or danger to the survival or even the life of the dismissed or separated
  employee and its family.36
293  
We also see no reason to obstruct the reinstatement decreed by the Voluntary
VOL. 772, OCTOBER 14, 2015 293 Arbitrator, or to treat it any less than the reinstatement that is ordered by the Labor
Baronda vs. Court of Appeals Arbiter. Voluntary arbitration really takes precedence over other dispute settlement
time of actual reinstatement. These two consequences give meaning and substance to devices. Such primacy of voluntary arbitration is mandated by no less than the
the constitutional right of labor to security of tenure. 34 Reinstatement pending appeal Philippine Constitution,37 and is ingrained as a policy objective of our labor relations
thus affirms the constitutional mandate to protect labor and to enhance social justice, law.38 The
for, as the Court has said in Aris (Phil.), Inc. v. National Labor Relations _______________
Commission:35
In authorizing execution pending appeal of the reinstatement aspect of a decision 36  Id., at pp. 254-255.
of a Labor Arbiter reinstating a dismissed or separated employee, the law itself has 37  Constitution, Art. XIII, Sec. 3, viz.:
laid down a compassionate policy which, once more, vivifies and enhances the Sec. 3. The State shall afford full protection to labor, local and overseas,
provisions of the 1987 Constitution on labor and the workingman. organized and unorganized, and promote full employment and equality of
x x x x employment opportunities for all.

55
It shall guarantee the rights of all workers to self-organization, collective Sec. 6. Effect of Filing of Petition for Certiorari on Execution.—The filing of
bargaining and negotiations, and peaceful concerted activities, including the right to a petition for certiorari with the Court of Appeals or the Supreme Court shall not
strike in accordance with law. They shall be entitled to security of tenure, humane stay 
conditions of work, and a living wage. They shall also participate in policy and _______________
decision-making processes affecting their rights and benefits as may be provided by
law. (a) To promote and emphasize the primacy of free collective bargaining and
The State shall promote the principle of shared responsibility between workers negotiations, including voluntary arbitration, mediation and conciliation, as modes of
and employers and the preferential use of voluntary modes in settling disputes, settling labor or industrial disputes.
including conciliation, and shall enforce their mutual compliance therewith to foster x x x x
industrial peace.  
The State shall regulate the relations between workers and employers,  
recognizing the right of labor to its just share in the fruits of production and the right 296
of enterprises to reasonable returns to investments, and to expansion and growth. 296 SUPREME COURT REPORTS ANNOTATED
38  Labor Code (1974), Art. 211, pertinently states:
Art. 211. Declaration of Policy.—A. It is the policy of the State: Baronda vs. Court of Appeals
  the execution of the assailed decision unless a temporary restraining order or
  injunction is issued by the Court of Appeals or the Supreme Court pending resolution
295 of such petition. (Emphasis ours)
 
VOL. 772, OCTOBER 14, 2015 295 We declare, therefore, that the reinstatement decreed by the Voluntary Arbitrator
Baronda vs. Court of Appeals was immediately executory upon the receipt of the award or decision by the parties.
reinstatement order by the Voluntary Arbitrator should have the same authority, WHEREFORE, the Court GRANTS the petition for review
force and effect as that of the reinstatement order by the Labor Arbiter not only to on certiorari; REINSTATES the order dated July 25, 2001 of the Voluntary
encourage parties to settle their disputes through this mode, but also, and more Arbitrator; and ORDERS respondent Hideco Sugar Milling Co., Inc. to pay the costs
importantly, to enforce the constitutional mandate to protect labor, to provide of suit.
security of tenure, and to enhance social justice. SO ORDERED.
The 2001 Procedural Guidelines in the Execution of Voluntary Arbitration Sereno (CJ., Chairperson), Leonardo-De Castro, Perezand Perlas-Bernabe,
Awards/Decisions (Guidelines), albeit not explicitly discussing the executory nature JJ., concur.
of the reinstatement order, seems to align with the Court’s stance by punishing the Petition granted.
noncompliance by a party of the decision or order for reinstatement. Section 2, Rule Notes.—After the Labor Arbiter’s decision is reversed by a higher tribunal, the
III of the Guidelines states: employee may be barred from collecting the accrued wages, if it is shown that the
Sec. 2. Issuance, Form and Contents of a Writ of Execution.— delay in enforcing the reinstatement pending appeal was without fault on the part of
x x x x the employer. (Islriz Trading vs. Capada, 641 SCRA 9 [2011])
b) If the execution be for the reinstatement of any person to any position, office A decision or award of a voluntary arbitrator is appealable to the CA via a
or employment, such writ shall be served by the sheriff upon the losing party or in petition for review under Rule 43. (Royal Plant Workers Union vs. Coca-Cola
case of death of the losing party upon his successor-in-interest, executor or Bottlers Philippines, Inc.-Cebu Plant, 696 SCRA 357 [2013])
administrator and such party or person may be punished for contempt if he  
disobeys such decision or order for reinstatement. (bold underscoring supplied for G.R. No. 211145. October 14, 2015.*
emphasis)  
  SAMAHAN NG MANGGAGAWA SA HANJIN SHIPYARD, rep. by its
The 2005 NCMB Revised Procedural Guidelines in the Conduct of Voluntary President, ALFIE ALIPIO, petitioner, vs. BUREAU OF LABOR RELATIONS,
Arbitration Proceedings also supports this Court’s position, for Section 6 of its Rule HANJIN HEAVY INDUSTRIES AND CONSTRUCTION CO., LTD. (HHIC-
VIII reads: PHIL.), respondents.
Labor Law; Labor Unions; Right to Self-organization; Workers can also form
and join a workers’ association as well as labor-management councils (LMC).—

56
More often than not, the right to self-organization connotes unionism. Workers,  
however, can also form and join a workers’ association as well as labor-management  
councils (LMC). Expressed in the highest law of the land is the right of all workers to 615
self-organization. Section 3, Article XIII of the 1987 Con- VOL. 772, OCTOBER 14, 2015 615
_______________
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
*  SECOND DIVISION. formation of labor organizations.—In view of the revered right of every
  worker to self-organization, the law expressly allows and even encourages the
  formation of labor organizations. A labor organization is defined as “any union or
614 association or employees which exists in whole or in part for the purpose of
collective bargaining or of dealing with employers concerning terms and conditions
614 SUPREME COURT REPORTS ANNOTATED of employment.” A labor organization has two broad rights: (1) to bargain
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations collectively and (2) to deal with the employer concerning terms and conditions of
stitution states: Section 3. The State shall afford full protection to labor, local employment. To bargain collectively is a right given to a union once it registers itself
and overseas, organized and unorganized, and promote full employment and equality with the DOLE. Dealing with the employer, on the other hand, is a generic
of employment opportunities for all. It shall guarantee the rights of all workers to description of interaction between employer and employees concerning grievances,
self-organization, collective bargaining and negotiations, and peaceful concerted wages, work hours and other terms and conditions of employment, even if the
activities, including the right to strike in accordance with law. x x x [Emphasis employees’ group is not registered with the DOLE.
supplied] And Section 8, Article III of the 1987 Constitution also states: Section 8. Same; Same; Same; “Union” and “Workers’ Association,” Distinguished.—A
The right of the people, including those employed in the public and private sectors, union refers to any labor organization in the private sector organized for collective
to form unions, associations, or societies for purposes not contrary to law shall not be bargaining and for other legitimate purpose, while a workers’ association is an
abridged. In relation thereto, Article 3 of the Labor Code provides: Article  organization of workers formed for the mutual aid and protection of its members or
3. Declaration of basic policy.—The State shall afford protection to labor, promote for any legitimate purpose other than collective bargaining. Many associations or
full employment, ensure equal work opportunities regardless of sex, race or creed groups of employees, or even combinations of only several persons, may qualify as a
and regulate the relations between workers and employers. The State shall assure labor organization yet fall short of constituting a labor union. While every labor
the rights of workers to self-organization, collective bargaining, security of union is a labor organization, not every labor organization is a labor union. The
tenure, and just and humane conditions of work. difference is one of organization, composition and operation.
Same; Same; Same; As Article 246 (now 252) of the Labor Code provides, the Same; Same; Same; It is incorrect to say that it is the device and no other,
right to self-organization includes the right to form, join or assist labor which secures industrial democracy.—Collective bargaining is just one of the forms
organizations for the purpose of collective bargaining through representatives of of employee participation. Despite so much interest in and the promotion of
their own choosing and to engage in lawful concerted activities for the same purpose collective bargaining, it is incorrect to say that it is the device and no other, which
for their mutual aid and protection.—As Article 246 (now 252) of the Labor Code secures industrial democracy. It is equally misleading to say that collective
provides, the right to self-organization includes the right to form, join or assist labor bargaining is the end-goal of employee representation. Rather, the real aim
organizations for the purpose of collective bargaining through representatives of their is employee participation in whatever form it may appear, bargaining or no
own choosing and to engage in lawful concerted activities for the same purpose for bargaining, union or no union. Any labor organization which may or may not be a
their mutual aid and protection. This is in line with the policy of the State to foster union may deal with the employer. This explains why a workers’ association or
the free and voluntary organization of a strong and united labor movement as well as organization does not always have to be a labor union and why employer-employee
to make sure that workers participate in policy and decision-making processes collective interactions are not always collective bargaining.
affecting their rights, duties and welfare. The right to form a union or association or  
to self-organization comprehends two notions, to wit: (a) the liberty or freedom, that  
is, the absence of restraint which guarantees that the employee may act for himself 616
without being prevented by law; and (b) the power, by virtue of which an employee 616 SUPREME COURT REPORTS ANNOTATED
may, as he pleases, join or refrain from joining an association.
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
Same; Same; Same; In view of the revered right of every worker to self-
organization, the law expressly allows and even encourages the  Same; Same; Same; The right to form or join a labor organization necessarily
includes the right to refuse or refrain from exercising the said right.—The right to
57
form or join a labor organization necessarily includes the right to refuse or refrain Resolution3 of the Bureau of Labor Relations (BLR) and reinstated the April 20, 2010
from exercising the said right. It is self-evident that just as no one should be denied Decision4 of the Department of Labor and Employment (DOLE) Regional Director,
the exercise of a right granted by law, so also, no one should be compelled to cancelling the registration of Samahan ng Manggagawa sa Hanjin Shipyard
exercise such a conferred right. Also inherent in the right to self-organization is the (Samahan) as a worker’s association under Article 243 (now Article 249) of the
right to choose whether to form a union for purposes of collective bargaining or a Labor Code.
workers’ association for purposes of providing mutual aid and protection. The right  
to self-organization, however, is subject to certain limitations as provided by law. The Facts 
For instance, the Labor Code specifically disallows managerial employees from  
joining, assisting or forming any labor union. Meanwhile, supervisory employees, On February 16, 2010, Samahan, through its authorized representative, Alfie F.
while eligible for membership in labor organizations, are proscribed from joining the Alipio, filed an application for registration 5 of its name “Samahan ng Mga
collective bargaining unit of the rank-and-file employees. Even government Manggagawa sa Hanjin Shipyard” with the DOLE. Attached to the application were
employees have the right to self-organization. It is not, however, regarded as existing the list of names of the association’s officers and members, signatures of the
or available for purposes of collective bargaining, but simply for the furtherance and attendees of the February 7, 2010
protection of their interests. _______________
Same; Same; Same; Misrepresentation; Misrepresentation, as a ground for
the cancellation of registration of a labor organization, is committed in connection 1  Rollo, pp. 22-30; penned by Associate Justice Hakim S. Abdulwahid, with
with the adoption, or ratification of the constitution and bylaws or amendments Associate Justices Marlene Gonzales-Sison and Edwin D. Sorongon, concurring.
thereto, the minutes of ratification, the list of members who took part in the 2  Id., at p. 32.
ratification of the constitution and bylaws or amendments thereto, and those in 3  CA Rollo, pp. 118-123.
connection with the election of officers, minutes of the election of officers, and the 4  Id., at pp. 86-91.
list of voters.—Misrepresentation, as a ground for the cancellation of registration of a 5  Id., at p. 31.
labor organization, is committed “in connection with the adoption, or ratification of  
the constitution and bylaws or amendments thereto, the minutes of ratification, the  
list of members who took part in the ratification of the constitution and bylaws or 618
amendments thereto, and those in connection with the election of officers, minutes of 618 SUPREME COURT REPORTS ANNOTATED
the election of officers, and the list of voters, x x x.”
PETITION for review on certiorari of the decision and resolution of the Court of Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
Appeals. meeting, copies of their Constitution and By-Laws. The application stated that
The facts are stated in the opinion of the Court. the association had a total of 120 members.
   
  On February 26, 2010, the DOLE Regional Office No. 3, City of San Fernando,
617 Pampanga (DOLE-Pampanga),issued the corresponding certificate of registration 6 in
favor of Samahan.
VOL. 772, OCTOBER 14, 2015 617 On March 15, 2010, respondent Hanjin Heavy Industries and Construction Co.,
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations Ltd. Philippines (Hanjin), with offices at Greenbeach 1, Renondo
  Virginia Lacsa Suarez for petitioner. Peninsula, SitioAgustin, Barangay Cawag, Subic Bay Freeport Zone, filed a
  Christian Abello for respondents. petition7 with DOLE-Pampanga praying for the cancellation of registration of
  Samahan’s association on the ground that its members did not fall under any of the
MENDOZA, J.: types of workers enumerated in the second sentence of Article 243 (now 249).
  Hanjin opined that only ambulant, intermittent, itinerant, rural workers, self-
The right to self-organization is not limited to unionism. Workers may also form employed, and those without definite employers may form a workers’ association. It
or join an association for mutual aid and protection and for other legitimate purposes. further posited that one-third (1/3) of the members of the association had definite
This is a petition for review on certiorari seeking to reverse and set aside the employers and the continued existence and registration of the association would
July 4, 2013 Decision1 and the January 28, 2014 Resolution2 of the Court of Appeals prejudice the company’s goodwill.
(CA)in C.A.-G.R. S.P. No. 123397, which reversed the November 28, 2011

58
On March 18, 2010, Hanjin filed a supplemental petition,8 adding the alternative members should have formed a labor union for collective bargaining. 11 The
ground that Samahan committed a misrepresentation in connection with the list of dispositive portion of the decision of the Dole Regional Director, reads:
members and/or voters who took part in the ratification of their constitution and _______________
bylaws in its application for registration. Hanjin claimed that Samahan made it
appear that its members were all qualified to become members of the workers’ 9   Id., at p. 87.
association. 10  Id., at p. 53.
11  Id., at pp. 86-91.
 
On March 26, 2010, DOLE-Pampanga called for a conference, wherein Samahan  
requested for a 10-day period to file a 620
_______________ 620 SUPREME COURT REPORTS ANNOTATED
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
6  Id., at p. 61. WHEREFORE, premises considered, the petition is hereby GRANTED.
7  Id., at pp. 62-68. Consequently, the Certificate of Registration as Legitimate Workers Association
8  Id., at pp. 69-75. (LWA) issued to the SAMAHAN NG MGA MANGGAGAWA SA HANJIN
  SHIPYARD (SAMAHAN) with Registration Numbers RO300-1002-WA-009 dated
  February 26, 2010 is hereby CANCELLED, and said association is dropped from the
619 roster of labor organizations of this Office.
VOL. 772, OCTOBER 14, 2015 619 SO DECIDED.12
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations  
responsive pleading. No pleading, however, was submitted. Instead, Samahan The Ruling of the Bureau
filed a motion to dismiss on April 14, 2010.9 of Labor Relations 
   
The Ruling of the DOLE Aggrieved, Samahan filed an appeal 13 before the BLR, arguing that Hanjin had
Regional Director  no right to petition for the cancellation of its registration. Samahan pointed out that
  the words “Hanjin Shipyard,” as used in its application for registration, referred to a
On April 20, 2010, DOLE Regional Director Ernesto Bihis ruled in favor of workplace and not as employer or company. It explained that when a shipyard was
Hanjin. He found that the preamble, as stated in the Constitution and By-Laws of put up in Subic, Zambales, it became known as Hanjin Shipyard. Further, the
Samahan, was an admission on its part that all of its members were employees of remaining 63 members signed the Sama-Samang Pagpapatunay which stated that
Hanjin, to wit: they were either working or had worked at Hanjin. Thus, the alleged
KAMI, ang mga Manggagawa sa HANJIN Shipyard (SAMAHAN) ay misrepresentation committed by Samahan had no leg to stand on.14
naglalayong isulong ang pagpapabuti ng kondisyon sa paggawa at katiyakan sa In its Comment to the Appeal,15 Hanjin averred that it was a party-in-interest. It
hanapbuhay sa pamamagitan ng patuloy na pagpapaunlad ng kasanayan ng para sa reiterated that Samahan committed misrepresentation in its application for
mga kasapi nito. Naniniwala na sa pamamagitan ng aming mga angking lakas, registration before DOLE Pampanga. While Samahan insisted that the remaining 63
kaalaman at kasanayan ay aming maitataguyod at makapag-aambag sa kaunlaran members were either working, or had at least worked in Hanjin, only 10 attested to
ng isang lipunan. Na mararating at makakamit ang antas ng pagkilala, pagdakila at such fact, thus, leaving its 53 members without any workplace to claim.
pagpapahalaga sa mga tulad naming mga manggagawa. _______________
x x x10
  12  Id., at p. 91.
The same claim was made by Samahan in its motion to dismiss, but it failed to 13  Id., at pp. 92-100.
adduce evidence that the remaining 63 members were also employees of Hanjin. Its 14  Id., at p. 97.
admission bolstered Hanjin’s claim that Samahan committed misrepresentation in its 15  Id., at pp. 101-114.
application for registration as it made an express representation that all of its  
members were employees of the former. Having a definite employer, these 57  

59
621 that would strike a balance between the contending interests of Samahan and Hanjin
VOL. 772, OCTOBER 14, 2015 621 was to direct Samahan to drop the name “Hanjin Shipyard” without delisting it from
the roster of legitimate labor organizations. The fallo reads:
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
On September 6, 2010, the BLR granted Samahan’s appeal and reversed the WHEREFORE, premises considered, our Decision dated 6 September 2010 is
ruling of the Regional Director. It stated that the law clearly afforded the right to hereby AFFIRMED with a DIRECTIVE for SAMAHAN to remove “HANJIN
self-organization to all workers including those without definite employers. 16 As an SHIPYARD” from its name.
expression of the right to self-organization, industrial, commercial and self-employed SO RESOLVED.24
workers could form a workers’ association if they so desired but subject to the  
limitation that it was only for mutual aid and protection. 17 Nowhere could it be found Unsatisfied, Samahan filed a petition for certiorari25under Rule 65 before the
that to form a workers’ association was prohibited or that the exercise of a workers’ CA, docketed as C.A.-G.R. S.P. No. 123397.
right to self-organization was limited to collective bargaining.18 In its March 21, 2012 Resolution,26 the CA dismissed the petition because of
The BLR was of the opinion that there was no misrepresentation on the part of Samahan’s failure to file a motion for reconsideration of the assailed November 28,
Samahan. The phrase, “KAMI, ang mga Manggagawa sa Hanjin Shipyard,” if 2011 Resolution.
translated, would be: “We, the workers at Hanjin Shipyard.” The use of the On April 17, 2012, Samahan filed its motion for reconsideration 27 and on July 18,
preposition “at” instead of “of” would indicate that “Hanjin Shipyard” was intended 2012, Hanjin filed its comment28 to oppose the same. On October 22, 2012, the CA
to describe a place.19 Should Hanjin feel that the use of its name had affected the issued a resolution granting Samahan’s motion for reconsideration and
goodwill of the company, the remedy was not to seek the cancellation of the _______________
association’s registration. At most, the use by Samahan of the name “Hanjin
Shipyard” would only warrant a change in the name of the association. 20 Thus, the 22  Id., at pp. 124-140.
dispositive portion of the BLR decision reads: 23  Id., at pp. 29-30.
24  Id., at p. 30.
WHEREFORE, the appeal is hereby GRANTED. The Order of DOLE Region III 25  Id., at pp. 3-21.
Director Ernesto C. Bihis dated 20 April 2010 is REVERSED and SET ASIDE. 26  Id., at pp. 144-145.
Accordingly, Samahan ng mga Manggagawa sa Hanjin Shipyard shall remain in 27  Id., at pp. 148-151.
the roster of legitimate workers’ association.21 28  Id., at pp. 159-163.
_______________  
 
16  Id., at p. 121. 623
17  Id., at p. 122.
18  Id., at p. 121. VOL. 772, OCTOBER 14, 2015 623
19  Id. Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
20  Id., at p. 123. reinstating the petition. Hanjin was directed to file a comment five (5) days from
21  Id. receipt of notice.29
  On December 12, 2012, Hanjin filed its comment on the petition, 30 arguing that
  to require Samahan to change its name was not tantamount to interfering with the
622 workers’ right to self-organization.31 Thus, it prayed, among others, for the dismissal
622 SUPREME COURT REPORTS ANNOTATED of the petition for Samahan’s failure to file the required motion for reconsideration. 32
On January 17, 2013, Samahan filed its reply.33
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
On March 22, 2013, Hanjin filed its memorandum.34
On October 14, 2010, Hanjin filed its motion for reconsideration.22  
In its Resolution,23 dated November 28, 2011, the BLR affirmed its September 6, The Ruling of the Court of Appeals 
2010 Decision, but directed Samahan to remove the words “Hanjin Shipyard” from  
its name. The BLR explained that the Labor Code had no provision on the use of On July 4, 2013, the CA rendered its decision, holding that the registration of
trade or business name in the naming of a worker’s association, such matters being Samahan as a legitimate workers’ association was contrary to the provisions of
governed by the Corporation Code. According to the BLR, the most equitable relief
60
Article 243 of the Labor Code.35 It stressed that only 57 out of the 120 members were UNION, HENCE THEIR REGISTRATION AS A WORKERS’
actually working in Hanjin while the phrase in the preamble of Samahan’s ASSOCIATION SHOULD BE CANCELLED. 
Constitution and By-Laws, “KAMI, ang mga Manggagawa sa Hanjin Shipyard,” II. THE COURT OF APPEALS SERIOUSLY ERRED IN ORDERING
created an impression that all its members were employees of HHIC. Such THE REMOVAL/
unqualified manifestation which was used in its application for registration, was a DELETION OF THE WORD “HANJIN” IN THE NAME OF THE UNION BY
clear proof of misrepresentation which warranted the cancellation of Samahan’s REASON OF THE COMPANY’S PROPERTY RIGHT OVER THE
registration. COMPANY NAME “HANJIN.”38
It also stated that the members of Samahan could not register it as a legitimate _______________
worker’s association because the place where Hanjin’s industry was located was not
a rural area. Neither was there any evidence to show that the members of 36  Id., at p. 278.
_______________ 37  Rollo, pp. 29-30.
38  Id., at p. 12.
29  Id., at pp. 167-168.  
30  Id., at pp. 183-222.  
31  Id., at p. 192. 625
32  Id., at p. 220. VOL. 772, OCTOBER 14, 2015 625
33  Id., at pp. 238-242.
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
34  Id., at pp. 246-267.
35  Id., at p. 279. Samahan argues that the right to form a workers’ association is not exclusive to
  intermittent, ambulant and itinerant workers. While the Labor Code allows the
  workers “to form, join or assist labor organizations of their own choosing” for the
624 purpose of collective bargaining, it does not prohibit them from forming a labor
organization simply for purposes of mutual aid and protection. All members of
624 SUPREME COURT REPORTS ANNOTATED Samahan have one common place of work, Hanjin Shipyard. Thus, there is no reason
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations why they cannot use “Hanjin Shipyard” in their name.39
the association were ambulant, intermittent or itinerant workers. 36 Hanjin counters that Samahan failed to adduce sufficient basis that all its
At any rate, the CA was of the view that dropping the words “Hanjin Shipyard” members were employees of Hanjin or its legitimate contractors, and that the use of
from the association name would not prejudice or impair its right to self-organization the name “Hanjin Shipyard” would create an impression that all its members were
because it could adopt other appropriate names. The dispositive portion reads: employees of HHIC.40
WHEREFORE, the petition is DISMISSED and the BLR’s directive, ordering Samahan reiterates its stand that workers with a definite employer can organize
that the words “Hanjin Shipyard” be removed from petitioner association’s name, is any association for purposes of mutual aid and protection. Inherent in the workers’
AFFIRMED. The Decision dated April 20, 2010 of the DOLE Regional Director in right to self-organization is its right to name its own organization. Samahan referred
Case No. RO300-1003-CP-001, which ordered the cancellation of petitioner “Hanjin Shipyard” as their common place of work. Therefore, they may adopt the
association’s registration is REINSTATED. same in their association’s name.41
SO ORDERED.37

The Court’s Ruling 


Hence, this petition, raising the following:  
  The petition is partly meritorious.
Issues   
  Right to self-organization
I. THE COURT OF APPEALS SERIOUSLY ERRED IN FINDING THAT includes right to form a un-
SAMAHAN CANNOT FORM A WORKERS’ ASSOCIATION OF ion, workers’ association and
EMPLOYEES IN HANJIN AND INSTEAD SHOULD HAVE FORMED A labor management councils 
_______________

61
39  Id., at p. 15. movement as well as to make sure that workers participate in policy and decision-
40  Comment, id., at pp. 50-73. making processes affecting their rights, duties and welfare.42
41  Reply, id., at pp. 96-102. The right to form a union or association or to self-organization comprehends two
  notions, to wit: (a) the liberty or freedom, that is, the absence of restraint which
  guarantees that the employee may act for himself without being prevented by law;
626 and (b) the power, by virtue of which an employee may, as he pleases, join or refrain
626 SUPREME COURT REPORTS ANNOTATED from joining an association.43
In view of the revered right of every worker to self-organization, the law
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
expressly allows and even encourages the formation of labor organizations. A labor
More often than not, the right to self-organization connotes unionism. Workers, organization is defined as “any union or association or employees which exists in
however, can also form and join a workers’ association as well as labor-management whole or in part for the purpose of collective bargaining or of dealing with employers
councils (LMC). Expressed in the highest law of the land is the right of all workers to concerning terms and conditions of employment.” 44 A labor organization has two
self-organization. Section 3, Article XIII of the 1987 Constitution states: broad rights: (1) to bargain collectively and (2) to deal with the employer concerning
Section 3. The State shall afford full protection to labor, local and overseas, terms and conditions of employment. To bargain collectively is a right given to a
organized and unorganized, and promote full employment and equality of union once it registers itself with the DOLE. Dealing with the employer, on the other
employment opportunities for all. It shall guarantee the rights of all workers to hand, is a generic description of interaction between employer and employees
self-organization, collective bargaining and negotiations, and peaceful concerted concerning grievances, wages, work hours and other terms and conditions of
activities, including the right to strike in accordance with law. x x x employment, even if the employees’ group is not registered with the DOLE. 45
[Emphasis supplied] _______________
 
And Section 8, Article III of the 1987 Constitution also states: 42  Article 211 (now 217), Labor Code of the Philippines.
Section 8. The right of the people, including those employed in the 43  Knitjoy Mfg., Inc. v. Ferrer-Calleja, G.R. No. 81883, September 23, 1992,
public and private sectors, to form unions, associations, or societies for 214 SCRA 174.
purposes not contrary to law shall not be abridged. 44  Article 218(g), Labor Code of the Philippines.
In relation thereto, Article 3 of the Labor Code provides: 45  Azucena, The Labor Code with Comments and Cases, Volume II, p. 127
Article 3. Declaration of basic policy.—The State shall afford (1996); Pascual, Labor Relations Law, pp. 35-36.
protection to labor, promote full employment, ensure equal work  
opportunities regardless of sex, race or creed and regulate the relations  
between workers and employers. The State shall assure the rights of 628
workers to self-organization, collective bargaining, security of tenure,
and just and humane conditions of work. 628 SUPREME COURT REPORTS ANNOTATED
[Emphasis supplied] Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
  A union refers to any labor organization in the private sector organized for
As Article 246 (now 252) of the Labor Code provides, the right to self- collective bargaining and for other legitimate purpose, 46 while a workers’ association
organization includes the right to form, join or is an organization of workers formed for the mutual aid and protection of its
  members or for any legitimate purpose other than collective bargaining. 47
  Many associations or groups of employees, or even combinations of only several
627 persons, may qualify as a labor organization yet fall short of constituting a labor
VOL. 772, OCTOBER 14, 2015 627 union. While every labor union is a labor organization, not every labor organization
is a labor union. The difference is one of organization, composition and operation.48
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
Collective bargaining is just one of the forms of employee participation. Despite
assist labor organizations for the purpose of collective bargaining through so much interest in and the promotion of collective bargaining, it is incorrect to say
representatives of their own choosing and to engage in lawful concerted activities for that it is the device and no other, which secures industrial democracy. It is equally
the same purpose for their mutual aid and protection. This is in line with the policy misleading to say that collective bargaining is the end-goal of employee
of the State to foster the free and voluntary organization of a strong and united labor representation. Rather, the real aim is employee participation in whatever form it

62
may appear, bargaining or no bargaining, union or no union.49 Any labor individual employee or group of employees shall have the right at any time to present
organization which may or may not be a union may deal with the employer. This grievances to their employer.
explains why a workers’ association or organization does not always have to be a Any provision of law to the contrary notwithstanding, workers shall have the
labor union and why employer-employee collective interactions are not always right, subject to such rules and regulations as the Secretary of Labor and
collective bargaining.50 Employment may promulgate, to participate in policy and decision-making processes
To further strengthen employee participation, Article 255 (now 261) 51 of the of the establishment where they are employed insofar as said processes will directly
Labor Code mandates that workers shall affect their rights, benefits and welfare. For this purpose, workers and employers
_______________ may form labor-management councils: Provided, That the representatives of the
workers in such labor-management councils shall be elected by at least the majority
46  Section 1(zz), Omnibus Rules Implementing the Labor Code. of all employees in said establishment.
47  Section 1(ccc), Omnibus Rules Implementing the Labor Code. 52  Allied Free Workers Union v. Compañia Maritima, 19 SCRA 258, 278-279
48  Azucena, The Labor Code with Comments and Cases, Volume II, p. 13, (1967). (Azucena, p. 351)
7th edition, 2010.  
49  Id., at p. 417.  
50  Supra note 45. 630
51  Article 255. Exclusive bargaining representation and workers’ 630 SUPREME COURT REPORTS ANNOTATED
participation in policy and decision-making.—The labor organization designated or
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
selected by the majority of the employees in an
  Right to choose whether to form or
  join a union or workers’ associa-
629 tion belongs to workers themselves 
 
VOL. 772, OCTOBER 14, 2015 629 In the case at bench, the Court cannot sanction the opinion of the CA that
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations Samahan should have formed a union for purposes of collective bargaining instead of
have the right to participate in policy and decision-making processes of the a workers’ association because the choice belonged to it. The right to form or join a
establishment where they are employed insofar as said processes will directly affect labor organization necessarily includes the right to refuse or refrain from exercising
their rights, benefits and welfare. For this purpose, workers and employers may form the said right. It is self-evident that just as no one should be denied the exercise of a
LMCs. right granted by law, so also, no one should be compelled to exercise such a
A cursory reading of the law demonstrates that a common element between conferred right.53 Also inherent in the right to self-organization is the right to choose
unionism and the formation of LMCs is the existence of an employer-employee whether to form a union for purposes of collective bargaining or a workers’
relationship. Where neither party is an employer nor an employee of the other, no association for purposes of providing mutual aid and protection.
duty to bargain collectively would exist.52 In the same manner, expressed in Article The right to self-organization, however, is subject to certain limitations as
255 (now 261) is the requirement that such workers be employed in the provided by law. For instance, the Labor Code specifically disallows managerial
establishment before they can participate in policy and decision making processes. employees from joining, assisting or forming any labor union. Meanwhile,
In contrast, the existence of employer-employee relationship is not mandatory in supervisory employees, while eligible for membership in labor organizations, are
the formation of workers’ association. What the law simply requires is that the proscribed from joining the collective bargaining unit of the rank-and-file
members of the workers’ association, at the very least, share the same interest. The employees.54 Even government employees have the right to self-organization. It is
very definition of a workers’ association speaks of “mutual aid and protection. not, however, regarded as existing or available for purposes of collective bargaining,
but simply for the furtherance and protection of their interests. 55
Hanjin posits that the members of Samahan have definite employers, hence, they
_______________ should have formed a union instead of a workers’ association. The Court disagrees.
There is no pro-
appropriate collective bargaining unit shall be the exclusive representative of the _______________
employees in such unit for the purpose of collective bargaining. However, an
53  Reyes v. Trajano, 209 SCRA 484, 489 (1992).

63
54  Section 2, Rule 2, Department Order No. 40-03, Series of 2003. Section 2. Who may join labor unions and workers’ associations.—All
55  Arizala v. Court of Appeals, 267 Phil. 615, 629; 189 SCRA 584, 597 (1990). persons employed in commercial, industrial and agricultural enterprises, including
  employees of government-owned or -controlled corporations without original
  charters established under the Corporation Code, as well as employees of religious,
631 charitable, medical or educational institutions whether operating for profit or not,
VOL. 772, OCTOBER 14, 2015 631 shall have the right to self-organization and to form, join or assist labor unions for
purposes of collective bargaining: provided, however, that supervisory employees
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
shall not be eligible for membership in a labor union of the rank-and-file employees
vision in the Labor Code that states that employees with definite employers may but may form, join or assist separate labor unions of their own. Managerial
form, join or assist unions only. employees shall not be eligible to form, join or assist any labor unions for purposes
The Court cannot subscribe either to Hanjin’s position that Samahan’s members of collective bargaining. Alien employees with valid working permits issued by the
cannot form the association because they are not covered by the second sentence of Department may exercise the right to self-organization and join or assist labor unions
Article 243 (now 249), to wit: for purposes of collective bargaining if they are nationals of a country which grants
Article 243. Coverage and employees’ right to self-organization.—All the same or similar rights to Filipino workers, as certified by the Department of
persons employed in commercial, industrial and agricultural enterprises and in Foreign Affairs.
religious, charitable, medical, or educational institutions, whether operating for profit For purposes of this section, any employee, whether employed for a definite
or not, shall have the right to self-organization and to form, join, or assist labor period or not, shall beginning on the first day of his/her service, be eligible for
organizations of their own choosing for purposes of collective membership in any labor organization.
bargaining. Ambulant, intermittent and itinerant workers, self-employed people, All other workers, including ambulant, intermittent and other workers, the self-
rural workers and those without any definite employers may form labor employed, rural workers and those without any definite employers may form labor
organizations for their mutual aid and protection. (As amended by Batas organizations for their mutual aid and protection and other legitimate
Pambansa Bilang 70, May 1, 1980) purposes except collective bargaining.
[Emphasis supplied] [Emphases supplied]
   
Further, Article 243 should be read together with Rule 2 of Department Order Clearly, there is nothing in the foregoing implementing rules which provides that
(D.O.) No. 40-03, Series of 2003, which provides: workers, with definite employers, cannot form or join a workers’ association for
  mutual aid and
RULE II   
   
COVERAGE OF THE RIGHT TO SELF-ORGANIZATION 633
Section 1. Policy.—It is the policy of the State to promote the free and
responsible exercise of the right to self-organization through the establishment of a VOL. 772, OCTOBER 14, 2015 633
simplified mechanism for the speedy registration of labor unions and workers Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
associations, determination of representation status and resolution of inter/intra- protection. Section 2 thereof even broadens the coverage of workers who can
union and other related labor relations disputes. Only legitimate or registered labor form or join a workers’ association. Thus, the Court agrees with Samahan’s
unions shall have the right to represent their members for collective bargaining and argument that the right to form a workers’ association is not exclusive to ambulant,
other pur- intermittent and itinerant workers. The option to form or join a union or a workers’
  association lies with the workers themselves, and whether they have definite
  employers or not.
632  
632 SUPREME COURT REPORTS ANNOTATED No misrepresentation on the
part of Samahan to warrant
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
cancellation of registration 
poses. Workers’ associations shall have the right to represent their members for  
purposes other than collective bargaining.

64
In this case, Samahan’s registration was cancelled not because its members were established is that the specific act or omission of the union deprived the complaining
prohibited from forming a workers’ association but because they allegedly employees-members of their right to choose.
committed misrepresentation for using the phrase, “KAMI, ang mga Manggagawa sa [Emphases supplied]
HANJIN Shipyard.”  
Misrepresentation, as a ground for the cancellation of registration of a labor Based on the foregoing, the Court concludes that misrepresentation, to be a
organization, is committed “in connection with the adoption, or ratification of the ground for the cancellation of the certificate of registration, must be done
constitution and by-laws or amendments thereto, the minutes of ratification, the list maliciously and deliberately. Further, the mistakes appearing in the application or at-
of members who took part in the ratification of the constitution and bylaws or _______________
amendments thereto, and those in connection with the election of officers, minutes of
the election of officers, and the list of voters, x x x.”56 58  581 Phil. 405; 559 SCRA 435 (2008).
In Takata Corporation v. Bureau of Relations,57 the DOLE Regional Director  
granted the petition for the cancellation of certificate of registration of Samahang  
Lakas Manggagawa sa Takata (Salamat) after finding that the employees who 635
attended the organizational meeting fell short of the 20% union registration VOL. 772, OCTOBER 14, 2015 635
requirement. The BLR, however, reversed the ruling of the DOLE Regional Director,
stating that petitioner Takata Corporation (Takata) failed to prove deliberate Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
_______________ tachments must be grave or refer to significant matters. The details as to how the
alleged fraud was committed must also be indubitably shown.
56  Section 3, Rule XIV, Department Order No. 40-03, Series of 2003. The records of this case reveal no deliberate or malicious intent to commit
57  G.R. No. 196276, June 4, 2014, 725 SCRA 61, 76. misrepresentation on the part of Samahan. The use of such words “KAMI, ang mga
  Manggagawa sa HANJIN Shipyard” in the preamble of the constitution and bylaws
  did not constitute misrepresentation so as to warrant the cancellation of Samahan’s
634 certificate of registration. Hanjin failed to indicate how this phrase constitutes a
malicious and deliberate misrepresentation. Neither was there any showing that the
634 SUPREME COURT REPORTS ANNOTATED alleged misrepresentation was serious in character. Misrepresentation is a devious
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations charge that cannot simply be entertained by mere surmises and conjectures.
and malicious misrepresentation on the part of respondent Salamat. Although Even granting arguendo that Samahan’s members misrepresented themselves as
Takata claimed that in the list of members, there was an employee whose name employees or workers of Hanjin, said misrepresentation does not relate to the
appeared twice and another was merely a project employee, such facts were not adoption or ratification of its constitution and bylaws or to the election of its officers.
considered misrepresentations in the absence of showing that the respondent  
deliberately did so for the purpose of increasing their union membership. The Court Removal of the word “Hanjin
ruled in favor of Salamat. Shipyard” from the associa-
In S.S. Ventures International v. S.S. Ventures Labor Union,58 the petition for tion’s name, however, does not
cancellation of certificate of registration was denied. The Court wrote: infringe on Samahan’s right
If the union’s application is infected by falsification and like serious to self-organization 
irregularities, especially those appearing on the face of the application and its  
attachments, a union should be denied recognition as a legitimate labor Nevertheless, the Court agrees with the BLR that “Hanjin Shipyard” must be
organization. Prescinding from these considerations, the issuance to the Union of removed in the name of the association. A legitimate workers’ association refers to
Certificate of Registration No. RO300-00-02-UR-0003 necessarily implies that its an association of workers organized for mutual aid and protection of its members or
application for registration and the supporting documents thereof are prima facie free for any legitimate purpose other than collective bargaining registered with the
from any vitiating irregularities. Another factor which militates against the veracity DOLE.59 Having been granted a certificate of registration, Samahan’s association is
of the allegations in the Sinumpaang Petisyon is the lack of particularities on how, now recognized by law as a legitimate workers’ association.
when and where respondent union perpetrated the alleged fraud on each _______________
member. Such details are crucial for in the proceedings for cancellation of union
registration on the ground of fraud or misrepresentation, what needs to be 59  Section 1(ff), Rule I, Department Order No. 40-03, Series of 2003.

65
   
  Thus, in the directive of the BLR removing the words “Hanjin Shipyard,” no
636 abridgement of Samahan’s right to self-organization was committed.
636 SUPREME COURT REPORTS ANNOTATED WHEREFORE, the petition is PARTIALLY GRANTED. The July 4, 2013
Decision and the January 28, 2014 Resolution of the Court of Appeals are
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
hereby REVERSED and SET ASIDE. The September 6, 2010 Resolution of the
According to Samahan, inherent in the workers’ right to self-organization is its Bureau of Labor Relations, as modified by its November 28, 2011 Resolution,
right to name its own organization. It seems to equate the dropping of words “Hanjin is REINSTATED.
Shipyard” from its name as a restraint in its exercise of the right to self-organization. SO ORDERED.
Hanjin, on the other hand, invokes that “Hanjin Shipyard” is a registered trade name Brion** (Acting Chairperson), Peralta,*** Del Castilloand Leonen, JJ., concur.
and, thus, it is within their right to prohibit its use. Petition partially granted, judgment and resolution reversed and set aside.
As there is no provision under our labor laws which speak of the use of name by Notes.—After the issuance of the certificate of registration, the labor
a workers’ association, the Court refers to the Corporation Code, which governs the organization’s registration could be assailed directly through cancellation of
names of juridical persons. Section 18 thereof provides: registration proceedings in accordance with Articles 238 and 239 of the Labor Code.
No corporate name may be allowed by the Securities and Exchange Commission (Takata [Philippines] Corporation vs. Bureau of Labor Relations, 725 SCRA 61
if the proposed name is identical or deceptively or confusingly similar to that of [2014])
any existing corporation or to any other name already protected by law or is patently _______________
deceptive, confusing or contrary to existing laws. When a change in the corporate
name is approved, the Commission shall issue an amended certificate of **  Per Special Order No. 2222 dated September 29, 2015.
incorporation under the amended name. ***  Designated acting member per Special Order No. 2223 dated September 29,
[Emphases supplied] 2015.
   
The policy underlying the prohibition in Section 18 against the registration of a  
corporate name which is “identical or deceptively or confusingly similar” to that of 638
any existing corporation or which is “patently deceptive” or “patently confusing” or
“contrary to existing laws,” is the avoidance of fraud upon the public which would 638 SUPREME COURT REPORTS ANNOTATED
have occasion to deal with the entity concerned, the evasion of legal obligations and Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
duties, and the reduction of difficulties of administration and supervision over A petition for cancellation of union registration shall not suspend the proceedings
corporations.60 for certification election nor shall it prevent the filing of a petition for certification
For the same reason, it would be misleading for the members of Samahan to use election.(Heritage Hotel Manila vs. Secretary of Labor and Employment, 730
“Hanjin Shipyard” in its name as it SCRA 400 [2014])
_______________  
 
60  Lyceum of the Philippines, Inc. v. Court of Appeals, G.R. No. 101897, March ——o0o——
5, 1993, 219 SCRA 610, 615.
 
 
637
VOL. 772, OCTOBER 14, 2015 637
Samahan ng Manggagawa sa Hanjin Shipyard vs. Bureau of Labor Relations
could give the wrong impression that all of its members are employed by Hanjin.
Further, Section 9, Rule IV of D.O. No. 40-03, Series of 2003 explicitly states:
The change of name of a labor organization shall not affect its legal personality.
All the rights and obligations of a labor organization under its old name shall
continue to be exercised by the labor organization under its new name.
66
Labor Law; Collective Bargaining Agreements; No Strike, No Lockout
Provision; It is settled that a “no strike, no lockout” provision in the Collective
Bargaining Agreement (CBA) “may [only] be invoked by [an] employer when the
strike is economic in nature or one which is conducted to force wage or other
agreements from the employer that are not mandated to be granted by law. It [is not
applicable when the strike] is grounded on unfair labor practice.”—Indeed, the
parties through their CBA, agreed to a “no strike, no lockout” policy and to resolve
their disputes through grievance machinery and voluntary arbitration. Despite these,
respondents were justified in filing a
_______________

*  SECOND DIVISION.
 
 
610
610 SUPREME COURT REPORTS ANNOTATED
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
notice of strike in light of the facts of this case. It is settled that a “no strike, no
lockout” provision in the CBA “may [only] be invoked by [an] employer when the
strike is economic in nature or one which is conducted to force wage or other
agreements from the employer that are not mandated to be granted by law. It [is not
applicable when the strike] is grounded on unfair labor practice.” Here, while
respondents enumerated four grounds in their notice of strike, the facts of the case
reveal that what primarily impelled them to file said notice was their perception of
bad faith bargaining and violation of the duty to bargain collectively by GNC —
charges which constitute unfair labor practice under Article 248(g) of the Labor
Code.
Same; Voluntary Arbitration; It is the declared policy of the State to promote
and emphasize the primacy of voluntary arbitration as a mode of settling labor or
industrial disputes.—It must be noted that under the facts of University of San
Agustin Employees’ Union-FFW v. Court of Appeals, 485 SCRA 526 (2006), the
dispute between the parties primarily involved the formula in computing the TIP
share of the employees — one which clearly arose from the interpretation or
implementation of the CBA. Pursuant to Article 261 of the Labor Code, such a
grievance falls under the original and exclusive jurisdiction of the voluntary
arbitrator or panel of voluntary arbitrators. Even if otherwise, the dispute would still
fall under the said jurisdiction pursuant to Article 262 of the same Code since the
parties agreed in their CBA that practically all disputes, including bargaining
G.R. No. 204693. July 13, 2016.* deadlock, shall be referred to grievance machinery that ends in voluntary arbitration.
  It can safely be concluded, therefore, that the clear showing of the voluntary
GUAGUA NATIONAL COLLEGES, petitioner, vs.GUAGUA NATIONAL arbitrator’s jurisdiction over the parties’ dispute in University of San Agustin is the
COLLEGES FACULTY LABOR UNION and GUAGUA NATIONAL underlying reason why the Court upheld the CA’s directive for the parties to proceed
COLLEGES NON-TEACHING AND MAINTENANCE LABOR UNION, to voluntary arbitration in accordance with their CBA. After all, it is the declared
respondents.

67
policy of the State to promote and emphasize the primacy of voluntary arbitration as a special class of disputes that are generally within the exclusive original jurisdiction
a mode of settling labor or industrial disputes. of the Labor Arbiter by express provision of the law. “Absent such express stipu-
Same; Voluntary Arbitrators; Jurisdiction; Since the parties allegedly agreed  
to submit a dispute of this kind to their Collective Bargaining Agreement’s (CBA’s)  
grievance resolution procedure which ends in voluntary arbitration, it is the 612
voluntary arbitrator which has jurisdiction in view of Article 262 of the Labor Code. 612 SUPREME COURT REPORTS ANNOTATED
—Unlike in University of San Agustin Employees’ Union-FFW v. Court of Appeals,
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
485
  lation, the phrase ‘all disputes’ [or ‘any other matter or dispute’ for that matter]
  should be construed as limited to the areas of conflict traditionally within the
611 jurisdiction of Voluntary Arbitrators, i.e., disputes relating to contract-interpretation,
contract-implementation, or interpretation or enforcement of company personnel
VOL. 796, JULY 13, 2016 611 policies. [Unfair labor practices cases] — not falling within any of these categories
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union — should then be considered as a special area of interest governed by a specific
SCRA 526 (2006), the main cause of the dispute between the parties in this provision of law.”
case, i.e., GNC’s alleged commission of unfair labor practice, did not arise from the Same; Compulsory Arbitration; The Secretary of Labor and Employment’s
interpretation or implementation of the parties’ CBA, or neither from the certification for compulsory arbitration of a dispute over which he/she has assumed
interpretation or enforcement of company personnel policies. Hence, it does not fall jurisdiction is but an exercise of the powers granted to him/her by Article 263(g) of
under the original and exclusive jurisdiction of the voluntary arbitrator or panel of the Labor Code as amended.—As expounded by both the NLRC and the CA, the
voluntary arbitrators under the aforementioned Article 261. Be that as it may, GNC Secretary of Labor and Employment’s certification for compulsory arbitration of a
argues that since the grounds cited by respondents in their notice of strike come dispute over which he/she has assumed jurisdiction is but an exercise of the powers
within the scope of “grievance” under the grievance resolution and voluntary granted to him/her by Article 263(g) of the Labor Code as amended. “[These] powers
arbitration provision of the parties’ CBA, the same is cognizable by the voluntary x x x have been characterized as an exercise of the police power of the State, aimed
arbitrator. Otherwise stated, since the parties allegedly agreed to submit a dispute of at promoting the public good. When the Secretary exercises these powers, he[/she] is
this kind to their CBA’s grievance resolution procedure which ends in voluntary granted ‘great breadth of discretion’ to find a solution to a labor dispute.” The Court
arbitration, it is the voluntary arbitrator which has jurisdiction in view of Article 262 therefore cannot subscribe to GNC’s contention since to say that compulsory
of the Labor Code. arbitration may only be resorted to in instances agreed upon by the parties would
Same; Same; Same; Unfair Labor Practices; There is a need for an express limit the power of the Secretary of Labor and Employment to certify cases that are
stipulation in the Collective Bargaining Agreement (CBA) that unfair labor practices proper subject of compulsory arbitration. The great breadth of discretion granted to
should be resolved in the ultimate by the voluntary arbitrator or panel of voluntary the Secretary of Labor and Employment for him/her to find an immediate solution to
arbitrators since the same fall within a special class of disputes that are generally a labor dispute would unnecessarily be diminished if such would be the case.
within the exclusive original jurisdiction of the Labor Arbiter (LA) by express Same; Duty to Bargain Collectively; The effect of an employer’s or a union’s
provision of the law.—Plainly, a charge of unfair labor practice does not fall under actions individually is not the test of good faith bargaining, but the impact of all
the first three definition of grievance as above quoted. Neither can it be considered as such occasions or actions, considered as a whole.—The duty to bargain collectively
embraced by the fourth which at first blush, appears to be a “catch-all” definition of is defined under Article 252 of the Labor Code to, viz.: ARTICLE 252. Meaning of
grievance because of the phrase “[a]ny other matter or dispute.” It has been held that duty to bargain collectively.—The duty to bargain collectively means the
while the phrase “all other labor dispute” or its variant “any other matter or dispute” performance of a mutual obligation to meet and convene promptly and
may include unfair labor practices, it is imperative, however, that the agreement expeditiously in good faith for the purpose of negotiating an agreement with respect
between the union and the company states in unequivocal language that the parties to wages, hours of work and all other terms and conditions of employment including
conform to the submission of unfair labor practices to voluntary arbitration. It is not proposals for adjusting any grievances or questions arising under such agreements
sufficient to merely say that parties to the CBA agree on principle that “all disputes” and execut-
or as in this case, “any other matter or dispute,” should be submitted to the grievance  
machinery and eventually to the voluntary arbitrator. There is a need for an express 613
stipulation in the CBA that unfair labor practices should be resolved in the ultimate VOL. 796, JULY 13, 2016 613
by the voluntary arbitrator or panel of voluntary arbitrators since the same fall within
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
68
ing a contract incorporating such agreements if requested by either party but required by law; (2) while it later manifested through a letter dated May 27, 2009
such duty does not compel any party to agree to a proposal or to make any that it is not inclined to grant the economic provisions in respondents’ proposal, it
agreement. (Emphasis supplied) “It has been held that the crucial question whether did not fully discuss or explain to respondents its claimed opposition; (3) Atty.
or not a party has met his statutory duty to bargain in good faith typically turns on Sampang did not make good on the promise he made in the meeting of June 16, 2009
the facts of the individual case. There is no per se test of good faith in bargaining. that GNC would submit its counterproposal to respondents’ economic provisions
Good faith or bad faith is an inference to be drawn from the facts.” “The effect of an with the corresponding explanation; and (4) as shown by the minutes of the
employer’s or a union’s actions individually is not the test of good faith bargaining, meetings, the members of the management panel simply made general statements
but the impact of all such occasions or actions, considered as a whole. x x x” Here, that GNC was having financial difficulties but failed to elaborate on the same. As it
the collective conduct of GNC is indicative of its failure to meet its duty to bargain in is, GNC allowed itself to go through the process of negotiating with respondents
good faith. Badges of bad faith attended its actuations both at the plant and NCMB without fully discussing its financial status and despite this, knowingly entered into
levels. At the plant level, GNC failed to comply with the mandatory requirement of an agreement with them. It cannot, therefore, be allowed to later interpose an
serving a reply/counterproposal within 10 calendar days from receipt of a proposal, a opposition to the terms of the CBA based on financial incapacity by belatedly
fact which by itself is already an indication of lack of genuine interest to bargain. submitting a counterproposal, which from the circumstances, is an obvious attempt
Then, it led respondents to believe that it was doing away with the to stall what would have been the last step of the process — the execution of the
reply/counterproposal when it proceeded to just orally discuss the economic terms. CBA. The Court cannot be expected to affix its imprimatur to such a dubious
After a series of negotiation meetings, the parties finally agreed on the economic maneuver.
terms which based on the records was the only contentious issue between them. In Same; Same; In the cases of Kiok Loy v. National Labor Relations
fact, in their meeting of August 24, 2009, Rodriguez, in her capacity as member of Commission, 141 SCRA 179 (1986), Divine Word University of Tacloban v.
the management panel, already announced the benefits included under the CBA for Secretary of Labor and Employment, 213 SCRA 759 (1992), and General Milling
2009-2014. She then stated that the signing thereof would be underway. In the days Corporation v. Court of Appeals, 422 SCRA 514 (2004), the Supreme Court (SC)
that followed, however, GNC ignored the follow-ups made by respondents regarding unilaterally imposed upon the employers the Collective Bargaining Agreements
the signing. It then suddenly capitalized on the fact that it had not yet submitted a (CBAs) proposed by the unions after the employers were found to have violated their
reply/counterproposal and thereupon served one upon respondents despite the parties duty to bargain collectively.—In the cases of Kiok Loy v. National Labor Relations
already having reached an agreement. Commission, 141 SCRA 179 (1986), Divine Word University of Tacloban v.
Same; Same; The employer’s duty to negotiate in good faith with its employees Secretary of Labor and Employment, 213 SCRA 759 (1992), and General Milling
consists of matching the latter’s proposals, if unacceptable, with counterproposals, Corporation v. Court of Appeals, 422 SCRA 514 (2004), the Court unilaterally
and of making every reasonable effort to reach an agreement.—Anent GNC’s claim imposed upon the employers the CBAs proposed by the unions after the employers
that it was suffering from financial difficulties which according to it was one of the were found to have violated their duty to bargain collectively. This is
reasons why it saw the need to submit a counterproposal, suffice it to say that GNC  
should have squarely raised this early on in the negotiations. After all, the  
employer’s duty to negotiate in good faith with its employees consists of matching 615
the latter’s proposals, if unacceptable, with counterproposals, and of making every VOL. 796, JULY 13, 2016 615
reasonable effort to reach an agreement. There must be common willingness
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
 
  on the premise that the said employers, by their acts which bespeak of
614 insincerity, had lost their statutory right to negotiate or renegotiate the terms and
conditions contained in the unions’ proposed CBAs. Here, the Court finds nothing
614 SUPREME COURT REPORTS ANNOTATED wrong in the pronouncement of the NLRC that the final CBA draft submitted by
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union respondents to the NCMB should serve as the parties’ CBA for the period June 1,
among the parties to discuss freely and fully their respective claims and 2009 to May 31, 2014. More than the fact that GNC is the erring party in this case,
demands and, when these are opposed, to justify them on reason. However, instead records show that the said draft is actually the final CBA draft of the parties which
of laying all its card on the table, GNC for reasons only known to it, chose to forego incorporates their agreements. Indeed and as held by the NLRC, fairness, equity and
the opportunity of discussing its claimed financial predicament with respondents as social justice are best served if the said final CBA draft shall govern their industrial
shown by the following: (1) GNC did not submit a reply/counterproposal within 10 relationship.
calendar days from its receipt of respondents’ proposed CBA on April 3, 2009 as

69
PETITION for review on certiorari of the decision and resolution of the Court of  
Appeals. _______________
The facts are stated in the opinion of the Court.
   Padilla Law Office for petitioner. 3  Records, pp. 76-88.
   Emmanuel Noel A. Cruz for respondents. 4  Id., at p. 91.
  5  Id., at pp. 92-95.
DEL CASTILLO, J.: 6  Id., at pp. 96-97.
  7  Id., at pp. 98-102.
This Petition for Review on Certiorari assails the September 26, 2012 8  This is in view of the following clauses in the parties’ subsequent CBAs, to
Decision1 and December 3, 2012 Resolution2 of the Court of Appeals (CA) in C.A.- wit: (1) In the CBA for 1999-2004, “[Terms of the p]revious CBA — June 1, 1994-
G.R. S.P. No. 120669, which respectively denied for lack of merit the Petition May 31, 1999 which were not touched or covered by the current CBA — 1999-2004
for Certiorari filed therewith by petitioner Guagua National Colleges (GNC) and the is still honored and become part and parcel of the latter,” id., at p. 94; and (2) In the
motion for reconsideration thereto. CBA for 2004-2009, “Matters contained in the previous CBA, which
   
   
_______________ 617
VOL. 796, JULY 13, 2016 617
1  CA Rollo, pp. 683-709; penned by Associate Justice Fernanda Lampas-Peralta
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
and concurred in by Associate Justices Francisco P. Acosta and Angelita A. Gacutan.
2  Id., at p. 741. On April 3, 2009, the Presidents of both GNCFLU and GNCNTMLU, wrote the
  President of GNC, Atty. Ricardo V. Puno (Atty. Puno), to inform him of the former’s
  intention to open the negotiation for the renewal of the then existing CBA which
616 would expire on May 31, 2009.9 Attached to the said letter was respondents’
proposal for the next CBA10which was received by GNC on even date.11
616 SUPREME COURT REPORTS ANNOTATED Instead of serving upon respondents a reply/counterproposal within 10 days from
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union its receipt of respondents’ proposal, GNC wrote respondents on May 11, 2009
Factual Antecedents calling for a meeting at 10:00 a.m. of May 15, 2009 regarding CBA negotiations.
  While the said meeting took place and was attended by panel members from GNC,
GNC is an educational institution located in Sta. Filomena, Guagua, Pampanga. GNCFLU and GNCNTMLU, no agreement was reached except that GNC would
On the other hand, respondents Guagua National Colleges Faculty Labor Union notify respondents of the next negotiation meeting. However, what respondents later
(GNCFLU) and Guagua National Colleges Non-Teaching and Maintenance Labor received from GNC’s Corporate Secretary, Atty. Ricardo M. Sampang (Atty.
Union (GNCNTMLU) were the bargaining agents for GNC’s faculty members and Sampang) was not a notice of meeting but a letter dated May 27, 2009 which, among
nonteaching and maintenance personnel, respectively. others, stated that the “management is not inclined to grant the economic/monetary-
Beginning 1994 until their present dispute, the parties concluded their Collective related proposals in [respondents’] letter of April 3, 2009.”12
Bargaining Agreements (CBAs) without issue as follows: (1) CBA effective June 1, Still, respondents on June 1, 2009, requested for a conference with GNC to
1994 to May 31, 1999 (1994-1999 CBA),3 the economic provisions of which were discuss the ground rules.13 GNC granted respondents’ request and scheduled a
renegotiated on November 3, 1997 for years 1997-1999; 4 (2) CBA effective June 1, meeting at 1:00 p.m. of June 11, 2009 at the GNC boardroom. 14Although
1999 to May 31, 2004,5 the economic provisions of which were renegotiated on July respondents described GNC as “noncommittal” during the meeting, they nevertheless
4, 2002 for years 2002-2004;6 and (3) CBA effective June 1, 2004 to May 31, reckoned thereon the start of the negotiation proper between the parties.
2009.7 The aforementioned CBAs applied to both GNCFLU and GNCNTMLU  
without distinction. _______________
Significantly, the 1994-1999 CBA has a “no strike, no lockout” clause under
Section 17 thereof which likewise provides for mechanism for grievance resolution were not touched or covered by the current CBA are still honored and become part
and voluntary arbitration. This provision was considered carried over in the and parcel of the latter,” id., at p. 102.
subsequent CBAs.8 9   Id., at p. 103.

70
10  Id., at pp. 104-106. taining all the benefits agreed upon. GNC requested that some revisions be made
11  Id., at p. 103. thereon; (8) Atty. Sampang called for a meeting on October 9, 2009. In the said
12  Id., at p. 107. meeting, the parties reviewed all the benefits agreed on. Rodriguez then stated that
13  Id., at p. 108. the signing of the next CBA may take place the following meeting; (9) on October
14  Id., at p. 109. 15, 2009, respondents submitted to Atty. Sampang the agreed terms of the CBA
  which already contained the revisions requested by GNC and the P100,000.00
  signing bonus for each union. The document according to them was by then ready
618 for signing; (10) respondents made several follow-ups with both Atty. Sampang and
618 SUPREME COURT REPORTS ANNOTATED Rodriguez regarding the signing of the CBA but to no avail; (11) respondents
received from Atty. Sampang, through a letter17 dated December 21, 2009, GNC’s
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
counterproposal.18 Respondents were surprised since they thought all along that all
As to the events that transpired thereafter, the parties have conflicting claims. matters, except for some details on the signing bonus, were already settled. Besides,
While GNC asserted in general terms that the parties exchanged proposals and the three-week period previously requested by GNC within which to submit its
counterproposals in the months that followed,15 respondents, on the other hand, counterproposal had long lapsed; (12) Atty. Sampang requested respondents to
detailed the negotiations that allegedly ensued between the parties, 16 to wit: (1) attend a meeting with Atty. Puno on January 5, 2010. Despite Atty. Puno’s presence
another meeting was held on June 16, 2009 but since GNC at that time still did not in the school premises, he did not, however, face respondents’ representatives who
have any reply/counterproposal to respondents’ proposal, it asked for three weeks to waited for him for a considerable length of time; (13) in view of the foregoing,
submit the same; (2) in their July 10, 2009 meeting, GNC failed to submit its respondents were constrained to write Atty. Puno on January 8, 2010. 19 They stressed
purported counterproposal; (3) in the meeting of July 31, 2009, Cita Rodriguez that while they have been bargaining in good faith, it was otherwise on the part of
(Rodriguez), the school treasurer and a member of the management panel, discussed GNC. Respondents thus expressed their belief that the parties have already reached
with respondents some of the economic items in respondents’ proposal, particularly an impasse. They therefore asked GNC to respond to their letter and therein state its
those relating to longevity pay, birthday gift, family assistance, medical checkup and stand as to whether a third party is needed to assist them in threshing out their
clothing allowance; (4) the parties discussed further on longevity pay and family differences. As respondents did not get any reply from GNC, they
assistance benefit in the August 11, 2009 meeting. They also talked about an increase  
in rice subsidy; (5) in the August 17, 2009 meeting, Rodriguez stated that based on  
GNC’s Faculty Manual of 2008, longevity pay shall be given according to the _______________
number of years of service and shall be deemed as loyalty pay. The parties then
agreed to an increase of P5.00 in the longevity pay previously being given; (6) in the 17  Id., at p. 112.
following meeting of August 24, 2009, Rodriguez announced the increased benefits 18  Id., at pp. 113-119.
included in the new CBA, to wit: loyalty pay, cash gift, rice subsidy, birthday gift 19  Id., at pp. 121-123.
and clothing allowance. Rodriguez likewise confirmed the grant of a Union Office at  
the 3rd floor of Goseco Building in GNC. However, respondents’ demand for an  
increased signing bonus of P100,000.00 for each union (previously given at 620
P50,000.00 each union) remained unsettled. Nevertheless, the parties agreed to
further discuss the matter; (7) on September 23, 2009, respondents submitted to GNC 620 SUPREME COURT REPORTS ANNOTATED
a draft of the CBA con- Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
_______________ filed on February 3, 2010 a preventive mediation case with the National Conciliation
and Mediation Board (NCMB).20
15  Position Paper for Guagua National Colleges, id., at pp. 140-160.  
16  [Respondents’] Position Paper, id., at pp. 49-74. Proceedings before the National
  Conciliation and Mediation Board
   
619 Again, the parties differ in their account of what transpired before the NCMB.
VOL. 796, JULY 13, 2016 619 Respondents alleged that after several mediation meetings, the parties finally
agreed on the details regarding the grant of signing bonus. Hence, they undertook to
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
71
compose the final draft of the 2009-2014 CBA which it submitted to the NCMB on CBA and the CBAs subsequent thereto. According to it, the four grounds cited by
May 14, 2010 and copy furnished GNC on May 21, 2010. 21 Respondents likewise respondents in their notice of strike, i.e., bad faith bargaining, violation of the duty to
averred that the parties already agreed to schedule the signing of the said CBA on bargain, gross violation of the provisions of the CBA, and gross and blatant
May 28, 2010. To their dismay, however, no signing of the CBA took place. Instead, diminution of benefits, all come within the definition of “grievance” under their
Atty. Sabino Jose M. Padilla III (Atty. Padilla) appeared before the NCMB on behalf CBA, hence, not strikeable.
of GNC and requested for 10 days or until June 7, 2010 within which to submit In the afternoon of the same day, respondents conducted their respective Strike
GNC’s Comment/Counterproposal to the “Union[s’] CBA draft.” Although Votes wherein majority voted in favor
disappointed that Atty. Padilla merely referred to the supposed “final draft” of the  
parties as the “Union[s’] CBA draft,” respondents agreed to the period requested by _______________
GNC to give the latter time to go over it. Respondents, however, manifested that they
would want the parties to meet again on June 1, 2010. Come the said date, no one 23  Id., at pp. 208-224.
appeared on behalf of GNC. Thus, respondents filed on the same day a Notice of 24  Id., at p. 207.
Strike22 charging GNC with bad faith bargaining, violation of its duty to bargain, 25  Id., at pp. 227-223.
gross violations of the provisions of the CBA, and gross and blatant diminution of 26  Id., at pp. 11-16.
benefits. Subsequent to this, GNC allegedly stopped the grant of certain benefits to  
its employees.  
  622
_______________ 622 SUPREME COURT REPORTS ANNOTATED
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
20  Id., at pp. 124-125.
21  [Respondents’] Position Paper, id., at pp. 49-74, 64. of a strike.27 They then informed the NCMB of the strike vote results on June 21,
22  Id., at pp. 169-170. 2010.28
  Since the NCMB had not yet acted upon GNC’s Motion to Strike Out Notice of
  Strike and to Refer Dispute to Grievance Machinery and Voluntary Arbitration
621 Pursuant to the Collective Bargaining Agreement despite the looming strike of
respondents, GNC urged the Secretary of Labor and Employment to assume
VOL. 796, JULY 13, 2016 621 jurisdiction over the dispute.29 It specifically prayed in its letter of June 24, 2010 that
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union the Secretary of Labor and Employment, pursuant to Article 263(g)30 of the Labor
GNC, on the other hand, contended that during mediation meetings with the _______________
NCMB, respondents submitted several CBA drafts for its consideration. Upon its
receipt on May 21, 2010 of another draft CBA23 from respondents under cover letter 27  Id., at pp. 8-10.
dated May 20, 2010,24 it decided to secure the services of Atty. Padilla to assist it in 28  Id., at pp. 6-7.
its negotiations with respondents. Hence, on May 28, 2010, Atty. Padilla appeared 29  Id., at pp. 167-168.
before the NCMB and asked for 10 days to submit GNC’s comment/counterproposal 30  Article 263. Strikes, picketing and lockouts.—
to the purported draft CBA of respondents. However, on June 1, 2010, respondents x x x x
filed a notice of strike.            (g) When, in his opinion, there exists a labor dispute causing or likely to
In view of the notice of strike, the NCMB called for a conciliation conference on cause a strike or lockout in an industry indispensable to the national interest, the
June 4, 2010 which was later set for continuation on June 9, 2010. Meanwhile on Secretary of Labor and Employment may assume jurisdiction over the dispute and
June 7, 2010, GNC filed with the NCMB its counterproposal 25 to respondents’ decide it or certify the same to the Commission for compulsory arbitration. Such
purported final CBA draft. assumption or certification shall have the effect of automatically enjoining the
Subsequently during the June 9, 2010 conference, GNC filed a Motion to Strike intended or impending strike or lockout as specified in the assumption or
Out Notice of Strike and to Refer Dispute to Grievance Machinery and Voluntary certification order. If one has already taken place at the time of assumption or
Arbitration Pursuant to the Collective Bargaining Agreement. 26 It invoked the “no certification, all striking or locked out employees shall immediately return to work
strike, no lockout” clause and the grievance machinery and voluntary arbitration and the employer shall immediately resume operations and readmit all workers under
provision of the parties’ existing CBA which was carried over from their 1994-1999 the same terms and conditions prevailing before the strike or lockout. The Secretary

72
of Labor and Employment or the Commission may seek the assistance of law the national interest, and from intervening at any time and assuming jurisdiction over
enforcement agencies to ensure compliance with this provision as well as with such any such labor dispute in order to settle or terminate the same.
orders as he may issue to enforce the same. 31  Records, p. 168.
        In line with the national concern for and the highest respect accorded to the 32  Id., at pp. 35-38.
right of patients to life and health, strikes and lockouts in hospitals, clinics and  
similar medical institutions shall, to every extent possible, be avoided, and all serious  
efforts, not only by labor and management but government as well, be exhausted to 624
substantially minimize, if not prevent, their adverse effects on such life and health, 624 SUPREME COURT REPORTS ANNOTATED
through the exercise, however legitimate, by labor of
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
 
  Proceedings before the National
623 Labor Relations Commission
 
VOL. 796, JULY 13, 2016 623 In their Position Paper,33 respondents recounted that GNC at the plant level had
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union already failed to reply or furnish them a timely counterproposal. While GNC asked
Code “assume jurisdiction over the labor dispute between GNC and the Unions, i.e., for three weeks to submit its counterproposal in the meeting of June 16, 2009, no
GNCFLU and GNCNTMLU[,] in order to enjoin the intended strike x x x and such counterproposal was submitted. Instead, GNC opted to orally discuss with
thereafter direct the parties to submit the dispute to the grievance machinery and respondents the terms of the CBA. Yet, after the conduct of a series of
voluntary arbitration provisions of the CBA.”31 meetings/negotiations and at a time when the parties had already substantially agreed
In an Order32 dated June 28, 2010, the Secretary of Labor and Employment, after on the terms of the new CBA, respondents received from Atty. Sampang on
finding the subject labor dispute as one affecting national interest, assumed December 21, 2009 GNC’s counterproposal to respondents’ purported “latest
jurisdiction over the case; certified the same to the National Labor Relations proposal.” Respondents denied the existence of any “latest proposal” which requires
Commission (NLRC) for immediate compulsory arbitration; and accordingly a “counterproposal” from GNC. And even assuming that said counterproposal is
enjoined the intended strike. GNC’s answer to the proposal they furnished it at very outset, the same was already
  belatedly submitted not only because the period to serve a reply/counterproposal had
_______________ long lapsed, but also since all matters were already substantially agreed upon by the
parties. This explains why at that point, respondents were already following up the
its right to strike and by management to lockout. In labor disputes adversely affecting signing of the CBA.
the continued operation of such hospitals, clinics or medical institutions, it shall be The same goes true in the NCMB level. Respondents averred that the parties had
the duty of the striking union or locking-out employer to provide and maintain an already come into agreement regarding the signing bonus after several
effective skeletal workforce of medical and other health personnel, whose movement mediation/conciliation meetings held therein. But when they undertook to draft the
and services shall be unhampered and unrestricted, as are necessary to insure the CBA containing the terms agreed upon by the parties and submitted the same to the
proper and adequate protection of the life and health of its patients, most especially NCMB, Atty. Padilla suddenly entered the picture and submitted a counterproposal
emergency cases, for the duration of the strike or lockout. In such cases, therefore, to what he referred to as the “Union[s’] CBA draft” when in fact, the same was
the Secretary of Labor and Employment may immediately assume, within twenty- actually the parties’ final draft. Respondents thus argued that GNC clearly committed
four (24) hours from knowledge of the occurrence of such a strike or lockout, an unfair labor practice by bad faith bargaining. In addition, respondents averred that
jurisdiction over the same or certify it to the Commission for compulsory arbitration. GNC, without notice, stopped the release of benefits to its employees.
For this purpose, the contending parties are strictly enjoined to comply with such _______________
orders, prohibitions and/or injunctions as are issued by the Secretary of Labor and
Employment or the Commission, under pain of immediate disciplinary action, 33  Id., at pp. 49-74.
including dismissal or loss of employment status or payment by the locking-out  
employer of backwages, damages and other affirmative relief, even criminal  
prosecution against either or both of them. 625
         The foregoing notwithstanding, the President of the Philippines shall not be VOL. 796, JULY 13, 2016 625
precluded from determining the industries that, in his opinion, are indispensable to
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
73
For its part, GNC called attention to the fact that when it requested the Secretary GNC prays that [w]e dismiss the labor dispute for lack of jurisdiction and direct
of Labor and Employment to assume jurisdiction over the dispute, it also prayed that the parties to resolve their differences through the grievance machinery provided for
the same be ordered submitted to the grievance machinery and voluntary arbitration by their CBA and eventually, resolve it under voluntary arbitration. They aver that
provided for under the parties’ CBA. It stressed that its participation in the x x x the failure or refusal of the NCMB and thereafter, the Secretary of Labor and
compulsory arbitration proceeding should therefore not be construed as a waiver of Employment to enforce the grievance machinery and voluntary arbitration x x x
its position that jurisdiction over the dispute rests with the voluntary arbitrator in [allowed] the unions to circumvent the CBA and their agreement to resolve conflicts
view of the parties’ agreement in the CBA, the pertinent provisions of the Labor through voluntary arbitration by the simple [expedient] of filing a notice of strike.
Code, and of the Court’s ruling in University of San Agustin Employees’ Union-FFW We completely disagree.
(USAEU-FFW) v. Court of Appeals.34 When GNC filed their petition for assumption of jurisdiction[,] they prayed that:
As to the charge of unfair labor practice on account of its alleged bad faith “x x x. . .the Honorable Secretary of Labor and Employment, pursuant to
bargaining and violation of duty to bargain, GNC argued that the same is belied by Article 263(g) of the Labor Code, assume jurisdiction over the labor dispute
the fact that since the very beginning, the parties were negotiating. This continued between GNC and the Unions, i.e., GNCFLU and GNCNTMLU[,] in order to
during the mediation and conciliation proceedings before the NCMB. And had not enjoin the intended strike, or to order the immediate return to work of strikers
for respondents’ impatience which caused them to file a notice of strike, such _______________
negotiations would have progressed. To GNC, respondents’ move of filing a notice
of strike was uncalled for and was only intended to compel GNC to hastily concede 36  Records, pp. 319-343; penned by Commissioner Nieves E. Vivar-De Castro
to their proposals. What respondents refused to see, however, was GNC’s critical and concurred in by Presiding Commissioner Benedicto R. Palacol and
financial status that hindered it from readily agreeing with their economic proposals. Commissioner Isabel G. Panganiban-Ortiguerra.
GNC likewise denied the allegation that it stopped the release of benefits to its  
employees. It explained that its Protégé Program 35 was only subjected to stricter  
implementation guidelines but not stopped; that its employees received their 627
uniforms; and that it could not have stopped the grant of pilgrimage or excursion VOL. 796, JULY 13, 2016 627
benefits since no such benefit was provided for in their previous CBAs. What was
actually provided therein was the conduct of an annual retreat which was Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
_______________ if a strike has taken place, and thereafter direct the parties to submit to the
grievance machinery and voluntary arbitration provisions of the CBA.”
34  520 Phil. 400; 485 SCRA 526 (2006). The June 28, 2010 Order of the Secretary granted the assumption of jurisdiction
35  Otherwise known as Child or Dependent Scholarship Privilege. of the labor dispute and certified the same to this Commission for compulsory
  arbitration. In effect, the Order denied GNC’s plea to submit the dispute to the
  parties’ grievance machinery and voluntary arbitration. Article 263(g) does not
626 encompass referral of the labor dispute in an industry imbibed with national interest
to grievance machinery or voluntary arbitration. In the absence of a timely
626 SUPREME COURT REPORTS ANNOTATED reconsideration or proof that GNC had exercised any available remedy in law, the
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union Order now stands beyond reproach. In Union of Filipro Employees v. NLRCx x x, the
already held in December 2009 at the GNC campus; that as to rice subsidy, the same Supreme Court ruled:
is granted on a best effort basis and only when savings are generated; and that it had “When sitting in a compulsory arbitration certified to by the Secretary of
always endeavored to provide, to the best of its ability, the rice subsidy benefits to its Labor, the NLRC is not sitting as a judicial court but as an administrative
employees. In fact, rice subsidy was last given in December 2009; and that since the body charged with the duty to implement the order of the Secretary. Its
management was not generating savings from its operations, no rice subsidy has function only is to formulate the terms and conditions of the CBA and cannot
been released thereafter. GNC asserted that it had been explaining these to the go beyond the scope of the order. Moreover, the Commission is further
respondents but the latter would just not listen. tasked to act within the earliest time possible and with the end in view that its
The NLRC rendered a Decision36 on March 31, 2011. action would not only serve the interests of the parties alone, but would also
As to GNC’s contention that jurisdiction over the dispute rests on the voluntary have favorable implications to the community and to the economy as a whole.
arbitrator, the NLRC had this to say: This is the clear intention of the legislative body in enacting Art. 263,

74
paragraph (g) of the Labor Code, as amended by Section 27 of RA 6175.” Plaintly, [o]ur jurisdiction in this certified case extends to all other issues
x x x between the parties so long as they are relevant and germane in the resolution of the
Corollary thereto, as an implementing body, [o]ur authority does not include the main labor dispute. Our rules, under pain of contempt, require consolidation of all
power to amend the Secretary’s Order. To accede to a referral of the labor dispute cases pending with [o]ur Regional Arbitration Branches or with any Voluntary
  Arbitrator and consider them included or absorbed in the certified case to be able to
  completely and finally settle it. The intention of the law is an immediate and
628 complete resolution of a labor dispute in an industry indispensable to the national
628 SUPREME COURT REPORTS ANNOTATED interest. In this certified case, We are called to exercise [o]ur judgment and
adjudicate the labor dispute in accordance with the Order of the Secretary of Labor
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
and Employment. This Commission will not recuse from this responsibility for want
to the grievance machinery and ultimately to voluntary arbitration is equivalent to of jurisdiction.38
amending said Order. x x x37  
  Anent the merits of the case, the NLRC held that based on the totality of conduct
The NLRC thus upheld its jurisdiction over the case, viz.: of GNC, it was guilty of bad faith bargaining and therefore committed an unfair
The Secretary is explicitly granted by Article 263(g) of the Labor Code the labor practice. This was on account of GNC’s submission of a counterproposal
authority to assume jurisdiction over a labor dispute causing or likely to cause a despite the parties already having reached an agreement regarding the terms of the
strike or lockout in an industry indispensable to the national interest, and decide the CBA. To the NLRC, the belated submission of GNC’s counterproposal was intended
same accordingly. Inevitably, this authority to assume jurisdiction over a labor to evade the execution of the CBA. With respect to GNC’s alleged withdrawal of
dispute must include and extend to all questions and controversies arising therefrom, employees’ benefits, the NLRC ruled that pursuant to Article 253 of the Labor Code,
including cases over which the Labor Arbiter has exclusive jurisdiction x x x. It is the parties have the duty to keep the status quo and to continue in full force and
the declared policy of this Commission that in certified labor disputes for effect the terms and conditions of their existing agreement within 60 days prior to the
compulsory arbitration, We must ensure and maintain industrial peace based on expiration thereof and/or until a new agreement is reached by the parties. The NLRC,
social justice and national interest by having a full, complete and immediate thus, held that GNC failed to abide by this duty when it discontinued the release of
settlement or adjudication of all labor disputes between the parties, as well as issues benefits pending the conclusion of a new CBA. Finally, pursuant to General Milling
that are relevant to or incidents of the certified issues. Under Section 3, par. (b), Rule Corporation v. Court of
VIII of our 2005 Revised Rules of Procedure: _______________
“(b) All cases between the same parties, except where the certification
order specifies otherwise, the issues submitted for arbitration which are 38  Id., at pp. 330-332; italics and underscoring in the original.
already filed or may be filed, and are relevant to or are proper incidents of  
the certified case, shall be considered subsumed or absorbed by the certified  
case, and shall be decided by the appropriate Division of the Commission. 630
Subject to the second paragraph of Section 4 of Rule IV, the parties to a
certified case, under pain of contempt, shall inform their counsels and the 630 SUPREME COURT REPORTS ANNOTATED
Division concerned of all cases pending with the Regional Arbitra- Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
_______________ Appeals,39 the NLRC deemed it proper to declare the final draft submitted by
respondents to the NCMB as the parties’ CBA for the period June 1, 2009 to May 31,
37  Id., at pp. 332-334; italics and underscoring in the original; citations omitted. 2014.
  The NLRC ultimately ruled as follows:
  WHEFORE, considering [o]ur foregoing disquisitions, [w]e find Guagua
629 National Colleges (GNC) to have committed an unfair labor practice by violating the
VOL. 796, JULY 13, 2016 629 statutory duty to bargain collectively in good faith. We [o]rder that the final CBA
draft submitted by the unions to GNC and NCMB x x x be the Collective Bargaining
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
Agreement between the parties for the period June 1, 2009 to May 31, 2014 with the
tion Branches and the Voluntary Arbitrators relative or incident to the parties free to renegotiate the economic provisions not later than May 31, 2012 in
certified case before it.” accordance with Article 253-A of the Labor Code. Lastly, We further [o]rder that the

75
benefits agreed on by the parties as of August 24, 2009 be given retroactive effect to 1. Whether the subject labor dispute should have been ordered submitted to
June 1, 2009. voluntary arbitration by the Secretary of Labor and Employment pursuant
SO ORDERED.40 to the parties’ CBA and not certified to the NLRC for compulsory
  arbitration;          
Since GNC’s Motion for Reconsideration41 thereto was denied for lack of merit 2. Whether GNC is guilty of bad faith bargaining and thus violated its duty to
in the NLRC Resolution42 dated May 25, 2011, it sought recourse from the CA bargain;           
through a Petition for Certiorari.43 3. Whether the final CBA draft submitted by respondents to the NCMB was
  correctly declared to be the parties’ CBA for the period June 1, 2009 to
Ruling of the Court May 31, 2014.
of Appeals
  _______________
In a Decision44 dated September 26, 2012, the CA did not find any grave abuse of
discretion on the part of NLRC in issuing its assailed orders. Hence, it denied the 45  Id., at pp. 711-727.
Petition for lack of 46  Id., at p. 741.
_______________ 47  Rollo, p. 22.
 
39  467 Phil. 125; 422 SCRA 514 (2004).  
40  Records, pp. 342-343. 632
41  Id., at pp. 345-360.
632 SUPREME COURT REPORTS ANNOTATED
42  Id., at pp. 374-376.
43  CA Rollo, pp. 3-50. Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
44  Id., at pp. 683-709. Our Ruling
   
  The Petition has no merit.
631  
VOL. 796, JULY 13, 2016 631 The Secretary of Labor and Em-
ployment correctly certified the
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union subject labor dispute to the NLRC
merit. GNC filed a Motion for Reconsideration 45 thereto which, however, was for compulsory arbitration.
likewise denied in the Resolution46dated December 3, 2012.  
Hence, this Petition for Review on Certiorari. GNC asserts that it is the voluntary arbitrator which has jurisdiction over the
  grounds cited by respondents in their notice of strike in view of Section 17 of the
Issue parties’ 1994-1999 CBA. The said provision contains the agreement of the parties on
  a “no strike, no lockout” policy and on grievance resolution and voluntary arbitration
WHETHER THE COURT OF APPEALS X X X COMMITTED GRIEVOUS AND which was carried over to their subsequent CBAs up to the existing one. According
IRREVERSIBLE ERROR WHEN, IN ITS DECISION DATED 26 SEPTEMBER to GNC, respondents should not have filed a notice of strike in view of such “no
2012 AND RESOLUTION DATED 3 DECEMBER 2012, IT DISMISSED [GNC’s] strike, no lockout” clause and also since respondents’ grounds for strike are within
PETITION FOR CERTIORARI AND MOTION FOR RECONSIDERATION[,] the scope of “grievance” to be resolved in accordance with the said Section 17. It
RESPECTIVELY[,] FOR LACK OF MERIT, THEREBY AFFIRMING THE argues that respondents, by the simple expedient of filing a notice of strike, were able
DECISION DATED 31 MARCH 2011 AND RESOLUTION DATED 25 MAY to circumvent the “no strike, no lockout” clause and the grievance machinery and
2011 OF THE NATIONAL LABOR RELATIONS COMMISSION. X X X47 voluntary arbitration provision of their CBA.
  Indeed, the parties through their CBA, agreed to a “no strike, no lockout” policy
Essential to the determination of the issue raised is the resolution of the and to resolve their disputes through grievance machinery and voluntary arbitration.
following: Despite these, respondents were justified in filing a notice of strike in light of the
facts of this case. It is settled that a “no strike, no lockout” provision in the CBA

76
“may [only] be invoked by [an] employer when the strike is economic in nature or Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
one which is conducted to force wage or other agreements from the employer that are facts of the present case. Hence, the Court’s ruling in the said case squarely applies
not mandated to be granted by law. It [is not applicable when the strike] is grounded here.
on unfair labor prac- In University of San Agustin, the University of San Agustin (the University) and
  the University of San Agustin Employees’ Union (Union) entered into a five-year
  CBA in 2000. Complementary to the economic provisions of the said CBA is Section
633 3, Article 8 thereof which provides for salary increases for school years 2000-2003.
VOL. 796, JULY 13, 2016 633 Such salary increases shall take the form of either lump sum or a percentage of the
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union tuition incremental proceeds (TIP). Moreover and just like in the present case, the
tice.”48 Here, while respondents enumerated four grounds in their notice of strike, the parties’ CBA therein contained a “no strike, no lockout” clause, a grievance
facts of the case reveal that what primarily impelled them to file said notice was their machinery procedure, and a voluntary arbitration mechanism.
perception of bad faith bargaining and violation of the duty to bargain collectively by When the parties were renegotiating the economic provisions of their CBA, they
GNC — charges which constitute unfair labor practice under Article 248(g) of the could not agree on the manner of computing the TIP. In view of this impasse, the
Labor Code.49 Union declared a bargaining deadlock. When the Union filed a Notice of Strike
To recall, respondents acted prudently when they filed a preventive mediation before the NCMB, the University opposed the same by filing a Motion to Strike Out
case the first time that GNC refused to acknowledge at the plant level that the parties Notice of Strike and to Refer the Dispute to Voluntary Arbitration invoking the “no
already agreed on the terms of their incoming CBA. However, GNC again rebuffed strike, no lockout” clause of their CBA. The NCMB, however, failed to resolve the
that the parties had already entered into an agreement when respondents submitted said motion. The parties then jointly requested the Secretary of Labor and
the purported final CBA draft of the parties to the NCMB. Hence, respondents Employment to assume jurisdiction over the dispute. When the Secretary of Labor
cannot be faulted into believing that GNC was bargaining in bad faith and had no and Employment assumed jurisdiction, it proceeded to hear and decide on the
genuine intention to comply with its duty to bargain collectively since it denied dispute. Eventually, a Decision was rendered wherein the economic issues over
arriving at an agreement with respondents not once but twice. This belief in good which the parties had a deadlock in the collective bargaining were resolved, among
faith prompted them to file a notice of strike. Clearly, respondents’ intention was to others.
protest what they perceived to be acts of unfair labor practice on the part of GNC The CA, on certiorari petition, found merit in the University’s argument that the
through the exercise of their right to strike enshrined in the Constitution and not to Secretary of Labor abused his/her discretion in resolving the economic issues on the
circumvent the “no strike, no lockout” clause and the grievance machinery and ground that the same were proper subject of the grievance machinery as embodied in
voluntary arbitration provision of the CBA. the parties’ CBA. Accordingly, the said court directed the parties to submit the
GNC relies heavily on University of San Agustin.50According to it, the facts economic issues to voluntary arbitration.
therein are similar if not identical to the  
_______________  
635
48  A. Soriano Aviation v. Employees Association of A. Soriano Aviation, 612 VOL. 796, JULY 13, 2016 635
Phil. 1093, 1103; 596 SCRA 189, 195 (2009). Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
49  ART. 248. Unfair labor practices of employers.—It shall be unlawful for This Court affirmed the CA’s ruling based on the following ratiocinations:
an employer to commit any of the following unfair labor practice: We x x x find logic in the CA’s directive for the herein parties to proceed with
x x x x voluntary arbitration as provided in their CBA. As we see it, the issue as to the
          (g) To violate the duty to bargain collectively as prescribed by this Code. economic benefits, which included the issue on the formula in computing the TIP
x x x x share of the employees, is one that arises from the interpretation or implementation
50  University of San Agustin Employees’ Union-FFW (USAEU-FFW) v. Court of the CBA. To be sure, the parties’ CBA provides for a grievance machinery to
of Appeals, supra note 34. resolve any ‘complaint or dissatisfaction arising from the interpretation or
  implementation of the CBA and those arising from the interpretation of enforcement
  of company personnel policies.’ Moreover, the same CBA provides that should the
634 grievance machinery fail to resolve the grievance or dispute, the same shall be
634 SUPREME COURT REPORTS ANNOTATED ‘referred to a Voluntary Arbitrator for arbitration and final resolution.’ However,

77
through no fault of the University these processes were not exhausted. It must be The University filed a Motion to Strike Out Notice of Strike and to Refer the
recalled that while undergoing preventive mediation proceedings before the NCMB, Dispute to Voluntary Arbitration precisely to call the attention of the NCMB and the
the Union declared a bargaining deadlock, filed a notice of strike and thereafter, went  
on strike. The University filed a Motion to Strike Out Notice of Strike and to Refer  
the Dispute to Voluntary Arbitration but the motion was not acted upon by the 637
NCMB. As borne by the records, the University has been consistent in its position VOL. 796, JULY 13, 2016 637
that the Union must exhaust the grievance machinery provisions of the CBA which
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
ends in voluntary arbitration.
The University’s stance is consistent with Articles 261 and 262 of the Labor Union to the fact that the CBA provides for a grievance machinery and the parties’
Code, as amended which respectively provide[s]: obligation to exhaust and honor said mechanism. Accordingly, the NCMB should
Art. 261. Jurisdiction of voluntary arbitrators or panel of voluntary have directed the Union to honor its agreement with the University to exhaust
arbitrators.—The Voluntary Arbitrator or panel of Voluntary Arbitrators administrative grievance measures and bring the alleged deadlock to voluntary
shall have original and exclusive jurisdiction to hear and decide all arbitration. Unfortunately, the NCMB did not resolve the University’s motion thus
unresolved grievances arising from the interpretation or implementation of paving the way for the strike on September 19, 2003 and the deliberate
the collective bargaining agreement and those circumvention of the CBA’s grievance machinery and voluntary arbitration
  provisions.
  As we see it, the failure or refusal of the NCMB and thereafter the [Secretary of
636 Labor and Employment] to recognize, honor and enforce the grievance machinery
and voluntary arbitration provisions of the parties’ CBA unwittingly rendered said
636 SUPREME COURT REPORTS ANNOTATED provisions, as well as Articles 261 and 262 of the Labor Code, useless and
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union inoperative. As here, a union can easily circumvent the grievance machinery and
arising from the interpretation or enforcement of company personnel policies previous agreement to resolve differences or conflicts through voluntary arbitration
referred to in the immediately preceding article. Accordingly, violations of a through the simple expedient of filing a notice of strike. On the other hand,
collective bargaining agreement, except those which are gross in character, management can avoid the grievance machinery and voluntary arbitration provisions
shall no longer be treated as unfair labor practice and shall be resolved as of its CBA by simply filing a notice of lockout.51
grievances under the collective bargaining agreement. For purposes of this  
Article, gross violations of a collective bargaining agreement shall mean It must be noted that under the facts of University of San Agustin, the dispute
flagrant and/or malicious refusal to comply with the economic provisions of between the parties primarily involved the formula in computing the TIP share of the
such agreement. employees — one which clearly arose from the interpretation or implementation of
The Commission, its Regional Offices and the Regional Directors of the the CBA. Pursuant to Article 261 of the Labor Code,52 such a grievance falls under
Department of Labor and Employment shall not entertain disputes, the original and exclusive
grievances or matters under the exclusive and original jurisdiction of the _______________
voluntary arbitrator or panel of voluntary arbitrators and shall immediately
dispose and refer the same to the grievance machinery or voluntary 51  Id., at pp. 413-415; pp. 540-542; citations omitted.
arbitration provided in the collective bargaining agreement. 52  Article 261. Jurisdiction of Voluntary Arbitrators or panel of Voluntary
Art. 262. Jurisdiction over other labor disputes.—The Voluntary Arbitrators.—The Voluntary Arbitrator or panel of Voluntary Arbitrators shall have
Arbitrator or panel of Voluntary Arbitrators, upon agreement of the parties, original and exclusive jurisdiction to hear and decide all unresolved grievances
shall also hear and decide all other labor disputes including unfair labor arising from the interpretation or implementation of the Collective Bargaining
practices and bargaining deadlocks. Agreement and those arising from the interpretation or enforcement of company
The grievance machinery and no strike, no lockout provisions of the CBA forged personnel policies referred to in the immediately preceding article. Accordingly,
by the University and the Union are founded on Articles 261 and 262 quoted above. violations of a Collective Bargaining Agreement, except
The parties agreed that practically all disputes — including bargaining deadlocks —  
shall be referred to the grievance machinery which ends in voluntary arbitration.  
Moreover, no strike or no lockout shall ensue while the matter is being resolved. 638
638 SUPREME COURT REPORTS ANNOTATED

78
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union resolution procedure which ends in voluntary arbitration, it is the voluntary arbitrator
jurisdiction of the voluntary arbitrator or panel of voluntary arbitrators. Even if which has jurisdiction in view of Article 262 of the Labor Code.
otherwise, the dispute would still fall under the said jurisdiction pursuant to Article The grievance resolution and arbitration provision of the parties’ CBA provides
26253 of the same Code since the parties agreed in their CBA that practically all in part, viz.:
disputes, including bargaining deadlock, shall be referred to grievance machinery 17. Grievance Machinery
that ends in voluntary arbitration. The parties hereto agree on the principle that all disputes between labor and
It can safely be concluded, therefore, that the clear showing of the voluntary management may be settled through friendly negotiations, that the parties have the
arbitrator’s jurisdiction over the parties’ dispute in University of San Agustin is the same interest in the continuity of work until all matters in dispute shall have been
underlying reason why the Court upheld the CA’s directive for the parties to proceed discussed and settled in a manner to the mutual benefit of the parties herein, that an
to voluntary arbitration in accordance with their CBA. After all, it is the declared open conflict in any form involves losses to the parties, hence, all efforts must be
policy of the State to promote and emphasize the primacy of voluntary arbitration as exerted to avoid such an open conflict. In the furtherance of the foregoing principle,
a mode of settling labor or industrial disputes.54 the parties agree to establish a procedure for the adjustment of any grievance to
Contrary to GNC’s contention, however, there is a marked difference between provide the widest opportunity for discussion of any dispute, request or complaint
the facts of University of San Agustin and of the present case which makes the ruling and establish the procedure for the processing and settlement of grievances.
in the former inapplicable to the latter. Unlike in University of San Agustin, the main A grievance is defined as any protest, misunderstanding or difference of opinion
cause of the dispute between the parties in this case, i.e., GNC’s alleged commission or dispute affecting the COLLEGE and the UNION or affecting any employee
of unfair labor practice, did not arise from the interpretation or implementation of the covered by this Agreement with respect to:
parties’ CBA, or neither from the interpretation or enforcement of
_______________ 1. Meaning, interpretation, implementation or violation of any of the
provisions of this Agreement;
those which are gross in character, shall no longer be treated as unfair labor practice
and shall be resolved as grievances under the Collective Bargaining Agreement. For  
purposes of this article, gross violations of Collective Bargaining Agreement shall  
mean flagrant and/or malicious refusal to comply with the economic provisions of 640
such agreement. 640 SUPREME COURT REPORTS ANNOTATED
x x x x
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
53  Article 262. Jurisdiction over other labor disputes.—The Voluntary
Arbitrator or panel of Voluntary Arbitrators, upon agreement of the parties, shall also
hear and decide all other labor disputes including unfair labor practices and 2. Any matter directly relating or affecting the terms and conditions of
bargaining deadlocks. employment including all personnel policies;         
54  Sec. 3, Article XIII, 1987 Constitution; Article 211 of the Labor code. 3. Dismissal, suspension and/or any other disciplinary action;         
4. Any other matter or dispute which may arise and is not settled by
  means other than the grievance machinery.
639
VOL. 796, JULY 13, 2016 639 x x x x55
 
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
Plainly, a charge of unfair labor practice does not fall under the first three
company personnel policies. Hence, it does not fall under the original and exclusive definition of grievance as above quoted. Neither can it be considered as embraced by
jurisdiction of the voluntary arbitrator or panel of voluntary arbitrators under the the fourth which at first blush, appears to be a “catch-all” definition of grievance
aforementioned Article 261. Be that as it may, GNC argues that since the grounds because of the phrase “[a]ny other matter or dispute.” It has been held that while the
cited by respondents in their notice of strike come within the scope of “grievance” phrase “all other labor dispute” or its variant “any other matter or dispute” may
under the grievance resolution and voluntary arbitration provision of the parties’ include unfair labor practices, it is imperative, however, that the agreement between
CBA, the same is cognizable by the voluntary arbitrator. Otherwise stated, since the the union and the company states in unequivocal language that the parties conform to
parties allegedly agreed to submit a dispute of this kind to their CBA’s grievance the submission of unfair labor practices to voluntary arbitration. 56 It is not sufficient
to merely say that parties to the CBA agree on principle that “all disputes” or as in
79
this case, “any other matter or dispute,” should be submitted to the grievance 58  Vivero v. Court of Appeals, supra note 56 at p. 170; p. 279.
machinery and eventually to the voluntary arbitrator. There is a need for an express 59  Records, p. 168. GNC stated, viz.: “Finally, although there is a charge of
stipulation in the CBA that unfair labor practices should be resolved in the ultimate unfair labor practice in the Unions’ Notice of Strike, which matter should
by the voluntary arbitrator or panel of voluntary arbitrators since the same fall within ordinarily be certified for compulsory arbitration, the records will indubitably
a special class of disputes that are generally within the exclusive original jurisdiction show — apart from the baselessness of the charge — that the proximate cause of the
of the Labor Arbiter by express provision of the law. 57 “Absent such express labor
stipulation, the phrase ‘all  
_______________  
650
55  Records, p. 83. 650 SUPREME COURT REPORTS ANNOTATED
56  Vivero v. Court of Appeals, 398 Phil. 158, 169; 344 SCRA 268, 279 (2000),
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
citing San Miguel Corp. v. National Labor Relations Commission, 325 Phil. 401; 255
SCRA 133 (1996). GNC further avers that under the parties’ CBA, there are only two instances
57  Art. 217 of the Labor Code provides in part: where compulsory arbitration may be resorted to, to wit: (1) at the grievance
  machinery level, if respondents are not satisfied with GNC’s decision on a grievance;
  and (2) at the voluntary arbitration level, when the parties cannot agree on the third
641 member of the Arbitration Committee. GNC thus contends that submission of the
parties’ dispute to compulsory arbitration is but another violation of their agreement
VOL. 796, JULY 13, 2016 641 embodied in the CBA.
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union The argument is specious.
disputes’ [or “any other matter or dispute” for that matter] should be construed as As expounded by both the NLRC and the CA, the Secretary of Labor and
limited to the areas of conflict traditionally within the jurisdiction of Voluntary Employment’s certification for compulsory arbitration of a dispute over which he/she
Arbitrators, i.e., disputes relating to contract-interpretation, contract-implementation, has assumed jurisdiction is but an exercise of the powers granted to him/her by
or interpretation or enforcement of company personnel policies. [Unfair labor Article 263(g) of the Labor Code as amended. “[These] powers x x x have been
practices cases] — not falling within any of these categories — should then be characterized as an exercise of the police power of the State, aimed at promoting the
considered as a special area of interest governed by a specific provision of law.”58 public good. When the Secretary exercises these powers, he[/she] is granted ‘great
In the absence here of an express stipulation in the CBA that GNC and breadth of discretion’ to find a solution to a labor dispute.” 60 The Court therefore
respondents agreed to submit cases of unfair labor practice to their grievance cannot subscribe to GNC’s contention since to say that compulsory arbitration may
machinery and eventually to voluntary arbitration, jurisdiction over the parties’ only be resorted to in instances agreed upon by the parties would limit the power of
dispute does not vest upon the voluntary arbitrator. The reason behind the ruling the Secretary of Labor and Employment to certify cases that are proper subject of
in University of San Agustin is therefore not attendant in this case and so does not compulsory arbitration. The great breadth of discretion granted to the Secretary of
find any application here. As it stands, the parties’ dispute which centers on the Labor and Employment for him/her to find an immediate solution to a labor dispute
charge of unfair labor practice is the proper subject of compulsory arbitration. In would unnecessarily be diminished if such would be the case.
fact, GNC itself acknowledged in its June 24, 2010 letter to the Secretary of Labor  
and Employment that a charge of unfair labor practice in a notice of strike is  
ordinarily certified for compulsory arbitration.59 _______________
 
_______________ dispute is the parties[’] differences in collective bargaining.” (Emphasis supplied)
60  Steel Corporation of the Philippines v. SCP Employees Union-National
Art. 217. Jurisdiction of Labor Arbiters and the Commission.— Federation of Labor Unions, 574 Phil. 716, 732; 551 SCRA 594, 609 (2008).
(a) Except as otherwise provided under this Code, the Labor Arbiters shall have  
original and exclusive jurisdiction to hear and decide x x x the following cases  
involving all workers, whether agricultural or nonagricultural: 643
(1) Unfair labor practices cases. VOL. 796, JULY 13, 2016 643
x x x x
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
80
In view of the above discourse, the Court finds that the Secretary of Labor and Here, the collective conduct of GNC is indicative of its failure to meet its duty to
Employment correctly certified the parties’ dispute to the NLRC for compulsory bargain in good faith. Badges of bad faith attended its actuations both at the plant and
arbitration. NCMB levels.
  At the plant level, GNC failed to comply with the mandatory requirement of
GNC engaged in bad faith serving a reply/counterproposal within 10 calendar days from receipt of a
bargaining and thus vio- proposal,63 a fact which by itself is already an indication of lack of genuine interest to
lated its duty to bargain. bargain.64 Then, it led respondents to believe that it was doing away with the
  reply/counterproposal when it proceeded to just
GNC insists that it is not guilty of bad faith bargaining nor did it commit any _______________
violation of its duty to bargain by pointing out that it consistently engaged in
negotiations with the respondents both at the plant and NCMB levels. It underscores 61  The Hongkong and Shanghai Banking Corporation Employees Union v.
that following its submission of a counterproposal to the NCMB, it even manifested National Labor Relations Commission, 346 Phil. 524, 534; 281 SCRA 509, 518
that it was willing to negotiate on a marathon basis. This negates any ill will, bad (1997).
faith, fraud or conduct oppressive to labor on its part. In any case, there is no truth to 62  Id.
respondents’ assertion that the parties have already reached an agreement when GNC 63  Article 250 of the Labor Code provides:
submitted a counterproposal. Hence, it cannot be said that GNC engaged in dilatory Article 250. Procedure in collective bargaining.—The following procedures shall
tactics to avoid the signing of the CBA since there was yet no final agreement to be observed in collective bargaining:
speak of. GNC likewise justifies its submission of counterproposal asserting that the (a) When a party desires to negotiate an agreement, it shall serve a written
same was necessary in view of the chronic financial situation of GNC, the need to notice upon the other party with a statement of its proposals. The other party
conclude a separate CBA for GNCFLU and GNCNTMLU, and in order to introduce shall make a reply thereto not later than ten (10) calendar days from receipt of
thereon improved provisions for the mutual benefit of the parties. such notice.
The duty to bargain collectively is defined under Article 252 of the Labor Code x x x x
to, viz.: 64  General Milling Corporation v. Court of Appeals, supra note 39 at p. 135; p.
ARTICLE 252. Meaning of duty to bargain collectively.—The duty to 522.
bargain collectively means the performance of a mutual obligation to meet and  
convene promptly and expeditiously in good faith for the purpose of negotiating an  
agreement with respect to wages, hours of work and all other terms and conditions of 645
employment including proposals for adjusting any grievances or questions arising VOL. 796, JULY 13, 2016 645
under such agreements and executing a contract incorporating such agreements if re-
  Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
  orally discuss the economic terms. After a series of negotiation meetings, the parties
644 finally agreed on the economic terms which based on the records was the only
contentious issue between them. In fact, in their meeting of August 24, 2009,
644 SUPREME COURT REPORTS ANNOTATED Rodriguez, in her capacity as member of the management panel, already announced
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union the benefits included under the CBA for 2009-2014. 65 She then stated that the signing
quested by either party but such duty does not compel any party to agree to a thereof would be underway. In the days that followed, however, GNC ignored the
proposal or to make any agreement. (Emphasis supplied) follow-ups made by respondents regarding the signing. It then suddenly capitalized
  on the fact that it had not yet submitted a reply/counterproposal and thereupon served
“It has been held that the crucial question whether or not a party has met his one upon respondents despite the parties already having reached an agreement.
statutory duty to bargain in good faith typically turns on the facts of the individual It could not be any clearer from the above circumstances that GNC has no
case. There is no per se test of good faith in bargaining. Good faith or bad faith is an genuine intention to comply with its duty to bargain. It merely went through the
inference to be drawn from the facts.”61 “The effect of an employer’s or a union’s motions of negotiations and then entered into an agreement with respondents which
actions individually is not the test of good faith bargaining, but the impact of all such turned out to be an empty one since it later denounced the same by submitting a
occasions or actions, considered as a whole. x x x”62 reply/counterproposal. Worse, when respondents tried to clear out matters with the

81
GNC President through their letter of January 8, 2010, GNC did not even bother to _______________
respond.
To persuade the Court that no agreement has yet been reached by the parties, 66  Id.
GNC refers to the minutes of the October 9, 2009 meeting indicating that the 67  Id., at p. 313.
economic benefits were still to be discussed with the President of GNC. GNC takes  
this to mean that the economic benefits were at that time still subject to the approval  
of the GNC President and, hence, not yet final. The Court, however, notes that GNC 647
conveniently disregarded not only the previous minutes of the parties’ meetings but VOL. 796, JULY 13, 2016 647
also the other significant portions of the October 9, 2009 minutes it alluded to. The
minutes of the meeting held on August 24, 2009 clearly shows that Rodriguez Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
categorically announced and enumerated all the benefits every reasonable effort to reach an agreement. 68 There must be common willingness
_______________ among the parties to discuss freely and fully their respective claims and demands
and, when these are opposed, to justify them on reason. 69However, instead of laying
65  See Minutes of the Meeting, Records, p. 312. all its card on the table, GNC for reasons only known to it, chose to forego the
  opportunity of discussing its claimed financial predicament with respondents as
  shown by the following: (1) GNC did not submit a reply/counterproposal within 10
646 calendar days from its receipt of respondents’ proposed CBA on April 3, 2009 as
required by law; (2) while it later manifested through a letter dated May 27, 2009
646 SUPREME COURT REPORTS ANNOTATED that it is not inclined to grant the economic provisions in respondents’ proposal, it
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union did not fully discuss or explain to respondents its claimed opposition; (3) Atty.
“given by the school in the CBA 2009-2014.” 66 Plainly, this means that the Sampang did not make good on the promise he made in the meeting of June 16, 2009
announced benefits were already approved by GNC. On the other hand, the minutes that GNC would submit its counterproposal to respondents’ economic provisions
of the meeting on October 09, 2009 states in full: with the corresponding explanation;70 and (4) as shown by the minutes of the
III. [Ms. Rodriguez] cited all the benefits of the permanent faculty and covered meetings, the members of the management panel simply made general statements
employees granted in the previous CBAs. that GNC was having financial difficulties but failed to elaborate on the same. As it
She requested to [sum] up all these benefits and privileges including the [additional is, GNC allowed itself to go through the process of negotiating with respondents
benefits] acquired on this present CBA [which shall] be discussed with the without fully discussing its financial status and despite this, knowingly entered into
President, so next time we will be on the signing.67 (Emphasis supplied) an agreement with them. It cannot, therefore, be allowed to later interpose an
  opposition to the terms of the CBA based on financial incapacity by belatedly
Nowhere from the aforequoted minutes of the meeting can it be deduced that the submitting a counterproposal, which from the circumstances, is an obvious attempt
terms of the CBA is still subject to the approval of the GNC President. There is no to stall what would have been the last step of the process — the execution of the
clear showing that the purpose of discussing the economic benefits with him is to CBA. The Court cannot be expected to affix its imprimatur to such a dubious
secure his approval thereto. If at all, the purported discussion appears to be a mere maneuver.71
formality since the signing of the CBA was not made dependent to the result of the _______________
discussion with him. As can be seen, the statement that “next time they will be on the
signing” is clearly unqualified. Indubitably, all indications lead to the conclusion that 68  Herald Delivery Carriers Union v. Herald Publication, Inc., 154 Phil. 662,
the parties already agreed on the terms of the CBA and it was only the execution 669; 55 SCRA 713, 720 (1974).
thereof that needs to be done. 69  Id.
Anent GNC’s claim that it was suffering from financial difficulties which 70  Records, p. 307.
according to it was one of the reasons why it saw the need to submit a counter- 71  Kiok Loy v. National Labor Relations Commission, 225 Phil. 138, 146; 141
proposal, suffice it to say that GNC should have squarely raised this early on in the SCRA 179, 187 (1986).
negotiations. After all, the employer’s duty to negotiate in good faith with its  
employees consists of matching the latter’s proposals, if unacceptable, with  
counterproposals, and of making 648
  648 SUPREME COURT REPORTS ANNOTATED

82
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union too late in the day since at that point there already exists a “final draft” submitted by
With respect to GNC’s assertion that its submission of a counterproposal was the respondents in accordance with the understanding reached by the parties in the
also impelled by the need to conclude a separate CBA for GNCFLU and conciliation/meetings conducted by the NCMB.
GNCNTMLU and to improve certain provisions, records reveal that during the In view of the foregoing, the Court finds that GNC engaged in bad faith
negotiations at the plant level, GNC did not at all entertain this idea. This explains bargaining and by the same violated its duty to bargain collectively as mandated by
why the matter was not brought to fore during the negotiations therein. The idea was law.
only introduced to GNC by Atty. Padilla when the former asked him to evaluate the Before turning to the next issue, however, the Court finds proper to pass upon the
final draft of the CBA submitted by respondents to the NCMB. Eventually, the same matter of GNC’s unilateral withdrawal of employee’s benefits as found by the
was used as a ground for GNC’s opposition to the said final draft as contained in the NLRC. GNC laments that while it squarely raised this matter before the CA, the said
counterproposal that GNC submitted to the NCMB. The matter, however, loses its court ignored the same.
significance in the light of the Court’s succeeding discussion as to the inopportune Guided by the basic rule that he who alleges must prove, 75 the Court finds that
submission of the said counterproposal. respondents failed to substantiate its claim that GNC unilaterally stopped the release
The overall conduct of GNC at the plant level, without a doubt, illustrates bad of certain benefits to its employees. All that respondents advanced were bare
faith bargaining. And as already stated, this display of bad faith continued even at the allegations without any proof. On the other hand, GNC was able to show that
NCMB. benefits such as clothing benefit76 and annual retreat were already extended to its
True, GNC participated in the conciliation meetings in the NCMB. In fact, the employees. The protégé benefit, although subjected to stricter implementation
minutes of the proceedings would show that the parties were able to settle certain _______________
matters about the signing bonus.72 Further, during the April 15, 2010
conciliation/meeting, it was agreed that respondents will come up with the “final 75  Lim v. Equitable PCI Bank, now known as the Banco De Oro Unibank, Inc.,
draft” of the parties to be submitted to the NCMB and copy furnished 724 Phil. 453, 454; 713 SCRA 555, 556 (2014).
GNC.73Respondents complied with the said undertaking such that the minutes of the 76  Records, pp. 244-245.
May 14, 2010 conciliation/meeting reveals that the only thing left for the parties to  
do was to go over the details of the final draft of the CBA for fine-tuning.74  
However, GNC again engaged itself in the scheme of denying that the parties 650
have already reached an agreement. It denies that the draft submitted by the 650 SUPREME COURT REPORTS ANNOTATED
respondents to the Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
_______________ guidelines, was likewise still in effect. 77 And while rice assistance was last given in
December 2009, the grant of the same was shown to be on a best effort
72  Minutes dated March 29, 2010, CA Rollo, p. 358. basis.78 Notably, respondents were not able to refute GNC’s explanation. Thus, the
73  Minutes dated April 15, 2010, id., at p. 359. Court finds the charge of unilateral withdrawal of benefits against GNC without
74  Minutes dated May 14, 2010, id., at p. 361. basis. Be that as it may, let it be made clear that this does not have any effect and
  therefore does not change the finding that GNC committed a violation of its duty to
  bargain as extensively discussed above.
649  
VOL. 796, JULY 13, 2016 649 The final CBA draft submitted
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union by respondents to the NCMB was
NCMB was the parties’ final draft. It instead asserts that the document was merely correctly imposed by the NLRC
respondents’ draft which was still subject to GNC’s consideration. The Court, as the parties’ CBA for the period
however, finds no merit in this assertion since as shown above, the minutes of the June 1, 2009 to May 31, 2014.
proceedings before the NCMB reveal otherwise.  
As proof of its claimed faithful intention to comply with its duty to bargain, GNC In the cases of Kiok Loy,79 Divine Word University of Tacloban v. Secretary of
asserts that it even manifested before the NCMB that it was willing to negotiate on a Labor and Employment,80 and General Milling Corporation,81 the Court unilaterally
marathon basis following its submission of a counterproposal. Suffice it to say, imposed upon the employers the CBAs proposed by the unions after the employers
however, that such manifestation, as well as the said counterproposal, already came were found to have violated their duty to bargain collectively. This is on the premise

83
that the said employers, by their acts which bespeak of insincerity, had lost their
statutory right to negotiate or renegotiate the terms and conditions contained in the
unions’ proposed CBAs.
Here, the Court finds nothing wrong in the pronouncement of the NLRC that the
final CBA draft submitted by respondents to the NCMB should serve as the parties’
CBA for the period June 1, 2009 to May 31, 2014. More than the fact that GNC is
the erring party in this case, records show that the said draft is actually the final CBA
draft of the parties which
_______________

77  Id., at pp. 242-243.


78  Id., at p. 250.
79  Supra note 71.
80  G.R. No. 91915, September 11, 1992, 213 SCRA 759.
81  General Milling Corporation v. Court of Appeals, supra note 39.
 
 
651
VOL. 796, JULY 13, 2016 651
Guagua National Colleges vs. Guagua National Colleges Faculty Labor Union
incorporates their agreements. Indeed and as held by the NLRC, fairness, equity and
social justice are best served if the said final CBA draft shall govern their industrial
relationship.
All told, the Court finds that the CA correctly affirmed the ruling of the NLRC
and denied GNC’s Petition for Certiorari for lack of merit.
WHEREFORE, the Petition is hereby DENIED. The assailed Decision dated
September 26, 2012 and Resolution dated December 3, 2012 of the Court of Appeals
in C.A.-G.R. S.P. No. 120669 are AFFIRMED.
SO ORDERED.
Carpio (Chairperson), Brion and Leonen, JJ., concur.
Mendoza, J., On Official Leave.
Petition denied, judgment and resolution affirmed.
Notes.—The Voluntary Arbitrator’s (VA’s) decision may still be reconsidered on
the basis of a motion for reconsideration seasonably filed within 10 days from receipt
thereof; Seasonable filing of a motion for reconsideration is a mandatory requirement
to forestall the finality of such decision. (Teng vs. Pahagac, 635 SCRA 173 [2010])
Article 263(g) of the Labor Code gives the Secretary of Labor discretion to
assume jurisdiction over a labor dispute likely to cause a strike or a lockout in an G.R. No. 179732. September 13, 2017.*
industry indispensable to the national interest and to decide the controversy or to  
refer the same to the National Labor Relations Commission (NLRC) for compulsory DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS,
arbitration. (Santuyo vs. Remerco Garments Manufacturing, Inc., 616 SCRA 333 petitioner, vs. CMC/MONARK/PACIFIC/HI-TRI JOINT VENTURE,
[2010]) respondent.
——o0o—— Pleadings and Practice; Certification against Forum Shopping; It is settled
that certification against forum shopping must be executed by the party or principal

84
and not by counsel.—This Court has long enforced the strict procedural requirement Construction Industry; Construction Industry Arbitration Commission;
of verification and certification against non-forum shopping. It is settled that Jurisdiction; Construction Industry Arbitration Commission’s (CIAC’s) specific
certification against forum shopping must be executed by the party or principal and purpose is the “early and expeditious settlement of disputes” in the construction
not by counsel. In Anderson v. Ho, 688 SCRA 8 (2013), this Court explained that it industry as a recognition of the industry’s role in “the furtherance of national
is the party who is in the best position to know whether he or she has filed a case development goals.”—CIAC was created under Executive Order No. 1008, or the
before any courts. It is clear in this case that counsel for petitioner, Atty. Valderama, “Construction Industry Arbitration Law.” It was originally under the administrative
was not clothed with authority to sign on petitioner’s behalf. supervision of the Philippine Domestic Construction Board which, in turn, was an
Same; Same; The Supreme Court (SC) ruled before that: “the lack of a implementing agency of the Construction Industry Authority of the Philippines. The
certification against forum shopping, unlike that of verification, is generally not Construction Industry Authority of the Philippines is presently a part of the
cured by its submission after the filing of the petition.” Nevertheless, exceptions Department of Trade and Industry as an attached agency. CIAC’s specific purpose is
exist, as in the case at bar, and it is more prudent to resolve the case on its merits the “early and expeditious settlement of disputes” in the construction industry as a
than dismiss it on purely technical grounds.—This Court ruled before that: “the lack recognition of the industry’s role in “the furtherance of national development goals.”
of a certification against forum shopping, unlike that of verification, is generally not  
cured by its submission after the filing of the petition.” Nevertheless, exceptions  
exist, as in the case at bar, and it is more 399
_______________ VOL. 839, SEPTEMBER 13, 2017 399
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
*  THIRD DIVISION.
  Joint Venture
  Same; Same; Same; As a general rule, findings of fact of Construction
398 Industry Arbitration Commission (CIAC), a quasi-judicial tribunal which has
398 SUPREME COURT REPORTS ANNOTATED expertise on matters regarding the construction industry, should be respected and
upheld.—As a general rule, findings of fact of CIAC, a quasi-judicial tribunal which
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri has expertise on matters regarding the construction industry, should be respected and
Joint Venture upheld. In National Housing Authority v. First United Constructors Corp., 657
prudent to resolve the case on its merits than dismiss it on purely technical SCRA 175 (2011), this Court held that CIAC’s factual findings, as affirmed by the
grounds. Court of Appeals, will not be overturned except as to the most compelling of
Moot and Academic; Exceptions exist that would not prevent a court from reasons: As this finding of fact by the CIAC was affirmed by the Court of Appeals,
taking cognizance of cases seemingly moot and academic.—Indeed, the rule is that and it being apparent that the CIAC arrived at said finding after a thorough
courts will not rule on moot cases. However, the moot and academic principle is “not consideration of the evidence presented by both parties, the same may no longer be
a magical formula that can automatically dissuade the courts in resolving a case.” reviewed by this Court. The all too familiar rule is that the Court will not, in a
Exceptions exist that would not prevent a court from taking cognizance of cases petition for review on certiorari, entertain matters factual in nature, save for the
seemingly moot and academic. most compelling and cogent reasons, like when such factual findings were drawn
Remedial Law; Civil Procedure; Exhaustion of Administrative Remedies; from a vacuum or arbitrarily reached, or are grounded entirely on speculation or
Under the doctrine of exhaustion of administrative remedies, the concerned conjectures, are conflicting or are premised on the supposed evidence and
administrative agency must be given the opportunity to decide a matter within its contradicted by the evidence on record or when the inference made is manifestly
jurisdiction before an action is brought before the courts, otherwise, the action will mistaken or absurd. This conclusion is made more compelling by the fact that the
be declared premature.—Under the doctrine of exhaustion of administrative reme- CIAC is a quasi-judicial body whose jurisdiction is confined to construction disputes.
dies, the concerned administrative agency must be given the opportunity to decide a Indeed, settled is the rule that findings of fact of administrative agencies and quasi-
matter within its jurisdiction before an action is brought before the courts, otherwise, judicial bodies, which have acquired expertise because their jurisdiction is confined
the action will be declared premature. In this case, CIAC found and correctly ruled to specific matters, are generally accorded not only respect, but finality when
that respondent had duly complied with the contractual obligation to exhaust affirmed by the Court of Appeals.
administrative remedies provided for under subclause 67.1 of the Conditions of Arbitration; “Commercial Arbitration” and “Voluntary Arbitration,”
Contract before it brought the case before the tribunal. Distinguished.—In distinguishing between commercial arbitration, voluntary
arbitration under Article 219(14) of the Labor Code, and construction

85
arbitration, Freuhauf Electronics Philippines Corporation v. Technology Electronics organized by governments like the Asian Development Bank, is an executive or
Assembly and Management Pacific, 810 SCRA 280 (2016), ruled that commercial international agreement contemplated by 
arbitral tribunals are purely ad hoc bodies operating through contractual consent,  
hence, they are not quasi-judicial agencies. In contrast, voluntary arbitration under  
the Labor Code and construction arbitration derive their authority from statute in 401
recognition of the public interest inherent in their respective spheres. Furthermore, VOL. 839, SEPTEMBER 13, 2017 401
voluntary arbitration under the Labor Code and construction arbitration exist inde-
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
 
  Joint Venture
400 our government procurement system.—This Court has held that a foreign loan
400 SUPREME COURT REPORTS ANNOTATED agreement with international financial institutions, such as a multilateral lending
agency organized by governments like the Asian Development Bank, is an executive
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri or international agreement contemplated by our government procurement system.
Joint Venture Remedial Law; Civil Procedure; Specific Denials; Under Rule 8, Section 10 of
pendently of the will of the contracting parties: Voluntary Arbitrators resolve the Rules of Court, the “defendant must specify each material allegation of fact the
labor disputes and grievances arising from the interpretation of Collective Bargaining truth of which he does not admit and, whenever practicable, shall set forth the
Agreements. These disputes were specifically excluded from the coverage of both substance of the matters upon which he relies to support his denial.”—Under Rule 8,
the Arbitration Law and the ADR Law. Unlike purely commercial relationships, the Section 10 of the Rules of Court, the “defendant must specify each material
relationship between capital and labor are heavily impressed with public interest. allegation of fact the truth of which he does not admit and, whenever practicable,
Because of this, Voluntary Arbitrators authorized to resolve labor disputes have been shall set forth the substance of the matters upon which he relies to support his
clothed with quasi-judicial authority. On the other hand, commercial relationships denial.” There are three (3) modes of specific denial provided for under the Rules: 1)
covered by our commercial arbitration laws are purely private and contractual in by specifying each material allegation of the fact in the complaint, the truth of which
nature. Unlike labor relationships, they do not possess the same compelling state the defendant does not admit, and whenever practicable, setting forth the substance
interest that would justify state interference into the autonomy of contracts. Hence, of the matters which he will rely upon to support his denial; (2) by specifying so
commercial arbitration is a purely private system of adjudication facilitated by much of an averment in the complaint as is true and material and denying only the
private citizens instead of government instrumentalities wielding quasi-judicial remainder; (3) by stating that the defendant is without knowledge or information
powers. Moreover, judicial or quasi-judicial jurisdiction cannot be conferred upon a sufficient to form a belief as to the truth of a material averment in the complaint,
tribunal by the parties alone. The Labor Code itself confers subject-matter which has the effect of a denial.
jurisdiction to Voluntary Arbitrators. Notably, the other arbitration body listed in Same; Same; Same; The denial in the answer must be definite as to what is
Rule 43 — the Construction Industry Arbitration Commission (CIAC) — is also a admitted and what is denied, such that the adverse party will not have to resort to
government agency attached to the Department of Trade and Industry. Its guesswork over “what is admitted, what is denied, and what is covered by denials of
jurisdiction is likewise conferred by statute. By contrast, the subject matter knowledge as sufficient to form a belief.”—In Aquintey v. Spouses Tibong, 511
jurisdiction of commercial arbitrators is stipulated by the parties. SCRA 414 (2006), this Court held that using “specifically” in a general denial does
Remedial Law; Civil Procedure; Factual Findings; Findings of fact of not automatically convert that general denial to a specific one. The denial in the
administrative agencies and quasi-judicial bodies are entitled to great respect and answer must be definite as to what is admitted and what is denied, such that the
even finality when affirmed by the appellate court.—To reiterate, findings of fact of adverse party will not have to resort to guesswork over “what is admitted, what is
administrative agencies and quasi-judicial bodies are entitled to great respect and denied, and what is covered by denials of knowledge as sufficient to form a belief.”
even finality when affirmed by the appellate court. In this case, the Court of Appeals Civil Law; Contracts; It is fundamental that a contract is the law between the
found that respondent was entitled to the time extensions as evaluated by CIAC, the parties and, absent any showing that its provisions are wholly or in part contrary to
agency tasked to resolve issues regarding the construction industry. Both tribunal law, morals, good customs, public order, or public policy, it shall be enforced to the
found that respondent was entitled to the extensions due to petitioners delayed letter by the 
payments, peace and order situation, and Variation Order No. 2. These findings are  
clearly supported by the facts on record.  
Executive Agreements; Foreign Loan Agreements; A foreign loan agreement 402
with international financial institutions, such as a multilateral lending agency 402 SUPREME COURT REPORTS ANNOTATED
86
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri for Banks and Sections 4305Q.1, 43058.3 and 4303P.1 of the Manual of
Regulations for Non-Bank Financial Institutions are hereby amended accordingly.
Joint Venture
This Circular shall take effect on 1 July 2013.
courts.—It is fundamental that a contract is the law between the parties and, Civil Law; Before Nacar v. Gallery Frames, 703 SCRA 439 (2013), and
absent any showing that its provisions are wholly or in part contrary to law, morals, Bangko Sentral ng Pilipinas-Monetary Board (BSP-MB) Resolution No. 796 dated
good customs, public order, or public policy, it shall be enforced to the letter by the May 16, 2013, the rate of legal interest was pegged at twelve percent (12%) per
courts. Respondent was not able to establish the basis of its claim that it is entitled to annum from finality of judgment until its satisfaction, “this interim period being
an award of 24% interest. Moreover, as found by the Court of Appeals and CIAC, deemed to be by then an equivalent to a forbearance of credit.”—Before Nacar v.
the parties had agreed to delete the provision on interest on delayed payments, since Gallery Frames, 703 SCRA 439 (2013), and Bangko Sentral ng Pilipinas-Monetary
the project was funded by the Asian Development Bank. There is also no basis to Board Resolution No. 796 dated May 16, 2013, the rate of legal interest was pegged
award respondent 24% interest as actual damages for the additional expenses it at 12% per annum from finality of judgment until its satisfaction, “this interim period
incurred due to petitioner’s delayed payments. being deemed to be by then an equivalent to a forbearance of credit.” With this
Same; Damages; Actual Damages; The issue on the amount of actual or Court’s pronouncement in Nacar, the rate of interest imposed should be modified.
compensatory damages is a question of fact, and except as provided by law or by The monetary awards, as computed by the CIAC, should earn legal interest at the
stipulation, one is entitled to adequate compensation only for pecuniary loss duly rate of 12% per annum until June 30, 2013, after which, it shall earn legal interest at
proven.—Before actual damages may be awarded, it is imperative that the claimant the rate of 6% per annum until full satisfaction.
proves its claims first. The issue on the amount of actual or compensatory damages is PETITION for review on certiorari of a decision of the Court of Appeals.
a question of fact, and except as provided by law or by stipulation, one is entitled to The facts are stated in the opinion of the Court.
adequate compensation only for pecuniary loss duly proven. In this case, respondent    Office of the Solicitor General for petitioner.
has not sufficiently shown how awarding it 24% interest per annum on delayed    Aguirre, Abaño, Pamfilo, Paras, Pineda & Agustin Law Offices for
payments corresponds to the actual damages it allegedly suffered. Respondent failed respondent.
to show a causal relation between the alleged losses and the injury it suffered from LEONEN, J.:
petitioner’s actions.  
Interest Rates; On May 16, 2013, the Monetary Board of the Bangko Sentral As the administrative agency tasked with resolving issues pertaining to the
ng Pilipinas (BSP) issued Resolution No. 796, which revised the interest rate to be construction industry, the Construction Industry Arbitration Commission enjoys a
imposed on the loan or forbearance of any money, goods, or credits.—On May 16, wide latitude in recognition of its technical expertise and experience. Its factual
2013, the Monetary Board of the Bangko Sentral ng Pilipinas issued Resolution No. findings are, thus, accorded respect and even finality, particularly when they are
796, which revised the interest rate to be imposed on the loan or forbearance of any affirmed by an appellate court.
money, goods, or credits. This was implemented in Bangko Sentral ng  
Pilipinas Circular No.799 Series of 2013, which reads: The Monetary Board, in its  
Resolution No. 796 dated 16 May 2013, approved the following revisions governing 403
the rate of interest in the absence of stipulation in loan contracts, thereby amending
Section 2 of Circular No. 905, Series of 1982: Section 1. The rate of interest for the VOL. 839, SEPTEMBER 13, 2017 403
loan or forbearance of any money, goods or credits and the rate allowed in Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
judgments, in the absence of an express contract as to such rate of interest, shall be Joint Venture
six percent (6%) per annum. Section 2. In view of the above, Subsection X305.1 of This is a Petition for Review on Certiorari1 assailing the Court of Appeals’
the Manual of Regulations Decision2 dated September 20, 2007 in C.A.-G.R. S.P. Nos. 88953 and 88911, which
  affirmed the March 1, 2005 Award of the Construction Industry Arbitration Com-
  mission (CIAC).
403 On April 29, 1999, Republic of the Philippines, through the Department of
VOL. 839, SEPTEMBER 13, 2017 403 Public Works and Highways (DPWH), and CMC/Monark/Pacific/Hi-Tri J.V. (the
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri Joint Venture) executed “Contract Agreement for the Construction of Contract Pack-
age 6MI-9, Pagadian-Buug Section, Zamboanga del Sur, Sixth Road Project, Road
Joint Venture
Improvement Component Loan No. 1473-PHI”3 (Contract) for a total contract
amount of P713,330,885.28.4

87
Parts I (General Conditions with forms of tender + agreement) and II (Conditions On March 3, 2004, the Joint Venture filed a Complaint 11against DPWH before
of Particular Application + Guidelines for Preparation of Part II Clauses) of the CIAC. Joint Venture’ claims, which amounted to P77,206,047.88, were as follows:
“Conditions of Contract for Works of Civil Engineering Construction of the _______________
Federation International Des Ingenieurs — Conseils” (Conditions of Contract)
formed part of the Contract.5 DPWH hired 6   Id.
_______________ 7   Id., at pp. 491-492, Joint Venture’s Complaint before the CIAC and pp. 742-
744, CIAC Award.
1  Rollo, pp. 398-463. 8   Id., at p. 728, CIAC Award.
2  Id., at pp. 464-480. The Decision was penned by Associate Justice Myrna 9   Id.
Dimaranan Vidal and concurred in by Associate Justices Jose C. Reyes, Jr. and Japar 10  Id., at p. 740.
B. Dimaampao of the Special Eighth Division, Court of Appeals, Manila. 11  Id., at pp. 486-500.
3  Id., at pp. 481-485.  
4  Id., at p. 482.  
5  Id., at p. 401. The “Conditions of Contract for Works of Civil Engineering 406
Construction” is a standard contract form prepared by the Federation 406 SUPREME COURT REPORTS ANNOTATED
International Des Ingenieurs — Conseils (FIDIC). The standard contract is
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
recommended for general use for the purpose of construction of such works where
tenders are invited on an international basis. The Conditions of Contract are also Joint Venture
equally suitable for use on domestic contracts. It is commonly referred to as the Red  
Book in the construction industry. Available at <http://fidic.org/bookshop/about- CLAIMANT’S CLAIM
bookshop/which-fidic-contract-should-i-use> (last accessed on September 4, 2017). Meanwhile, on July 8, 2004, the Joint Venture sent a “Notice of Mutual
  Termination of Contract”13 to DPWH requesting for a mutual termination of the
  contract subject of the arbitration case. This is due to its diminished financial
405 capability due to DPWH’s late payments, changes in the project involving payment
VOL. 839, SEPTEMBER 13, 2017 405 terms, peace and order problems, and previous agreement by the parties.
On July 16, 2004, then DPWH Acting Secretary Florante Soriquez accepted the
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri Joint Venture’s request for mutual termination of the contract.14
Joint Venture _______________
BCEOM French Engineering Consultants to oversee the project.6
On October 23, 2002, or while the project was ongoing, the Joint Venture’s truck 12  Id., at p. 732, CIAC Award.
and equipment were set on fire. On March 11, 2003, a bomb exploded at Joint 13  Id., at pp. 553-555.
Venture’s hatching plant located at Brgy. West Boyogan, Kumalarang, Zamboanga 14  Id., at pp. 338-339.
del Sur. According to reports, the bombing incident was caused by members of the  
Moro Islamic Liberation Front.7  
The Joint Venture made several written demands for extension and payment of 407
the foreign component of the Contract. There were efforts between the parties to VOL. 839, SEPTEMBER 13, 2017 407
settle the unpaid Payment Certificates amounting to P26,737,029.49. Thus, only the
foreign component of US$358,227.95 was up for negotiations subject to further Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
reduction of the amount on account of payments subsequently received by the Joint Joint Venture
Venture from DPWH.8 After hearing and submission of the parties’ respective memoranda, 15 CIAC
In a letter dated September 18, 2003, BCEOM French Engineering Consultants promulgated an Award16 on March 1, 2005, directing DPWH to pay the Joint
recommended that DPWH promptly pay the outstanding monies due the Joint Venture its money claims plus legal interest. CIAC, however, denied the Joint
Venture.9 The letter also stated that the actual volume of the Joint Venture’s Venture’s claim for price adjustment due to the delay in the issuance of a Notice to
accomplishment was “2,732m2 of hardrock and 4,444m3 of rippable rock,” making Proceed under Presidential Decree No. 1594 or the “Policies, Guidelines, Rules, and
the project 80% complete when it was halted.10

88
Regulations for Government Infrastructure Contracts.” 17The dispositive portion of such interest payment in the Contract. However, the Court of Appeals ruled that
the Award read: CIAC was correct when it awarded legal interest.23
WHEREFORE, premises considered and in view of the resolution of the issues The Court of Appeals sustained the Joint Venture’s argument on the
presented, an Award is hereby rendered ordering the Respondent DPWH to pay the noninclusion of a clear finding of its entitlement to time extensions in the dispositive
Claimant the following: portion of the CIAC Award. 24 The Court of Appeals held that CIAC did not clearly
1. Foreign Component of US$358,227.95 plus legal interest of US$18,313.79; dispose of the matter:
2. Equipment and Plant Losses of P5,080,000, plus legal interest of Yet, a close scrutiny of the foregoing disposition shows that it does not refer to
P464,298.08; the 133 days as per Variation Order No. 2 since CIAC made mention that the project
3. Additional Costs resulting from the Bombing of P6,267,410.48 plus legal is already terminated and the entire volume under said
interest of P320,410.63; and _______________
4. Additional Costs in the contract price under Clause 69.4 of P20,311,072.66
plus legal interest of [P]1,038,368.78. 19  Id., at pp. 78-79.
The claim of Claimant for adjustment under [Presidential Decree No.] 1594 of 20  Id., at pp. 464-480.
P18,626,805.81 is hereby denied. 21  Id., at p. 480.
Pursuant to the case of Eastern Shipping Lines v. Court of Appeals, 234 SCRA 22  Id., at pp. 473-474.
78, the foregoing monetary awards shall earn interest at the rate of 12% per 23  Id., at pp. 474-475.
annum from the date the Award becomes final and executor until its satisfaction. 24  Id., at pp. 475-476.
SO ORDERED.18  
_______________  
409
15  Id., at p. 733, CIAC Award. VOL. 839, SEPTEMBER 13, 2017 409
16  Id., at pp. 726-751.
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
17  Id., at pp. 741-742 (CIAC Award).
18  Id., at pp. 750-751. Joint Venture
  Order “will not be consumed.” Whether or not the Claimant then deserves to get the
  full 133 calendar days is a matter that has to be clearly resolved. On this, We hold
408 that this Court is not prepared to engage into a technical bout that only the expertise
408 SUPREME COURT REPORTS ANNOTATED of the CIAC can pass upon.25
 
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri On the other hand, the Court of Appeals did not accept DPWH’s argument that
Joint Venture the case was already moot and academic. According to the Court of Appeals, when
DPWH and the Joint Venture filed their respective petitions for review before the the Joint Venture requested for the mutual termination of the Contract on July 8,
Court of Appeals.19 2004, it did not waive its right to be paid the amounts due to it.26
The Court of Appeals in its Decision20 dated September 20, 2007, sustained The Court of Appeals, however, raised a concern with regard to CIAC’s order for
CIAC’s Award with certain modifications and remanded the case to CIAC for the DPWH to pay its liabilities in US dollars. It held that the parties have agreed that “all
determination of the number of days’ extension that the Joint Venture is entitled to payments for works carried out after 31 May 2003 and related price escalation claims
and “the conversion rate in pesos of the awarded foreign exchange payments and retention releases in the contract will be in pesos only, therefore no foreign
stated.”21 exchange payments.” This was never contested by the Joint Venture; hence, it may
The Court of Appeals held that CIAC did not commit reversible error in not be presumed that it acquiesced to the request of the DPWH.27
awarding the price adjustment sought by the Joint Venture under Presidential Decree The dispositive portion of the Court of Appeals’ Decision read:
No. 1594 since it was the Asian Development Bank’s Guidelines on procurement WHEREFORE, premises considered, the assailed Decision is
that was applicable and not Presidential Decree No. 1594.22 hereby AFFIRMED with MODIFICATION to include the award to the Claimant
The Court of Appeals also held that CIAC did not err in not awarding actual of time extensions per: 1) delay in payment at One Hundred Eight (108) days, and 2)
damages in the form of interest at the rate of 24% since there was no provision for extension Twenty-Nine (29) days due to peace and order situation.

89
Re 1) the award of time extension per Variation Order No. 2 — as stated earlier 410 SUPREME COURT REPORTS ANNOTATED
elsewhere in the
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
_______________
Joint Venture
25  Id., at p. 477. Fifth, whether or not the Joint Venture is entitled to a price adjustment due to the
26  Id., at pp. 477-478. delay of the issuance of the Notice of the Proceed;
27  Id., at p. 479. Sixth, whether or not the Asian Development Bank Guidelines on Procurement or
  Presidential Decree 1594 applies with regard to once adjustments due to the delay of
  the issuance of the Notice to Proceed;
410 Seventh, whether or not the Joint Venture is entitled to its claim for equipment
410 SUPREME COURT REPORTS ANNOTATED and financial losses due to peace and order situation (additional costs);
Eighth, whether or not the Joint Venture is entitled to actual damages and interest
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri on its claims; and
Joint Venture Finally, whether or not the Joint Venture should be paid in local currency or in
Decision, the CIAC must make a vivid presentation of the number of calendar days U.S. dollars.
the Claimant is entitled to, and 2) the conversion rate in pesos of the awarded foreign  
exchange payments states, supra, in the assailed Decision, these matters are I
hereby REMANDED to the CIAC for proper disposition. Accordingly, the rest of  
the challenged Decision STANDS. According to respondent Joint Venture, the Petition suffers from a fatal defect in
SO ORDERED.28 (Emphasis in the original) its certification against non-forum shopping. The verification and certification
  against non-forum shopping was signed only by petitioner’s counsel, Atty. Mary
Petitioner DPWH filed the present Petition for Review 29assailing the Court of Jean D. Valderama, from the Office of the Solicitor General. 33
Appeals’ Decision. In a Resolution30dated January 28, 2008, this Court required This Court has long enforced the strict procedural requirement of verification and
respondent Joint Venture to file its Comment. certification against non-forum shopping.34 It is settled that certification against
On March 27, 2008, respondent filed its comment/opposition.31 Petitioner forum shopping must be executed by the party or principal and not by
thereafter filed its Reply32 on September 3, 2008. counsel.35 In Anderson v. Ho,36 this Court explained that it is
The issues for resolution in this case are: _______________
First, whether or not the case has become moot and academic due to the parties’
mutual termination of the Construction Contract; 33  Id., at p. 461.
Second, whether or not the case is premature due to Joint Venture’s 34  Anderson v. Ho, 701 Phil. 6, 13-15; 688 SCRA 8, 15-16 (2013) [Per J. Del
noncompliance with the doctrine of exhaustion of administrative remedies; Castillo, Second Division]; Clavecilla v. Quitain, 518 Phil. 53, 62-64; 482 SCRA
Third, whether or not the Joint Venture is entitled to the foreign component of 623, 631 (2006) [Per J. Austria-Martinez, First Division].
the Project in the amount of US$358,227.95; 35  Agustin v. Cruz-Herrera, 726 Phil. 533, 542-543; 716 SCRA 42, 52-53
Fourth, whether or not the Joint Venture is entitled to time extensions due to (2014) [Per J. Reyes, First Division]; Mariveles Shipyard 
Variation Order No. 2, peace and order problems, and delay in payment;  
_______________  
412
28  Id., at pp. 479-480. 412 SUPREME COURT REPORTS ANNOTATED
29  Id., at pp. 398-463.
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
30  Id., at p. 779.
31  Id., at pp. 785-815. Joint Venture
32  Id., at pp. 823-852. the party who is in the best position to know whether he or she has filed a case before
  any courts.37 It is clear in this case that counsel for petitioner, Atty. Valderama, was
  not clothed with authority to sign on petitioner’s behalf.
410

90
In Resolution38 dated December 10, 2007, this Court noted petitioner’s prejudice to our outstanding claims and entitlements that are lawfully due to
Manifestation that after the petition was posted, the verification page signed by us.43 (Emphasis supplied)
DPWH Secretary Hermogenes E. Ebdane was submitted to the Office of the Solicitor  
General. In the same Resolution, this Court granted the Office of the Solicitor Petitioner argues that the Court of Appeals erred in rendering the assailed
General’s motion to admit the attached verification and to substitute and attach it to Decision, considering that the case is already moot and academic. Petitioner insists
the petition. that “the parties’ mutual termination of their contract prior to the adjudication of this
This Court ruled before that: “the lack of a certification against forum shopping, case by the CIAC on March 1, 2005, rendered the proceedings before CIAC moot
unlike that of verification, is generally not cured by its submission after the filing of and academic.”44
the petition.”39 Nevertheless, exceptions40 exist, as in the case at bar, and it is more According to petitioner, the principle of unjust enrichment does not apply in this
prudent to resolve the case on its merits than dismiss it on purely technical grounds.41 case “because respondent has incurred negative slippage/delay in carrying out their
  contractual obligations due to reasons attributable to it. Moreover, the parties’ mutual
II termination of the contract rendered the proceedings before the CIAC moot because
  there was no more contract to be enforced.”45
In the assailed Decision, the Court of Appeals held that the mutual termination of Petitioner’s argument is untenable.
the Contract by the parties did not render the case moot and academic. 42 Accordingly, _______________
when
_______________ 43  Id., at p. 555.
44  Id., at p. 426.
Corp. v. Court of Appeals, 461 Phil. 249, 263; 415 SCRA 573, 583-584 (2003) 45  Id., at p. 414.
[Per J. Quisumbing, Second Division].  
36  Anderson v. Ho, supra note 34.  
37  Id., at p. 14; p. 17. 414
38  Rollo, p. 396A. 414 SUPREME COURT REPORTS ANNOTATED
39  Clavecilla v. Quitain, supra note 34 at p. 63; p. 632.
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
40  Donato v. Court of Appeals, 462 Phil. 676, 690; 417 SCRA 216, 227 (2003)
[Per J. Austria-Martinez, Second Division]; Wee v. Galvez, 479 Phil. 737; 436 SCRA Joint Venture
96 (2004) [Per J. Quisumbing, First Division]. Indeed, the rule is that courts will not rule on moot cases. 46 However, the moot
41  See Diamond Taxi v. Llamas, Jr., 729 Phil. 364, 379; 719 SCRA 10, 24-25 and academic principle is “not a magical formula that can automatically dissuade the
(2014) [Per J. Brion, Second Division]. courts in resolving a case.” 47 Exceptions exist that would not prevent a court from
42  Rollo, pp. 477-478. taking cognizance of cases seemingly moot and academic.48
  In Carpio v. Court of Appeals,49 this Court held that a case could not be deemed
  moot and academic when there remains an unresolved justiciable controversy. In that
413 case, this Court affirmed the Court of Appeals’ assailed resolutions, which denied
VOL. 839, SEPTEMBER 13, 2017 413 petitioner’s prayer for dismissal based on the argument that the Sheriff’s execution
pending appeal of the trial court’s decision rendered the case moot and academic.
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri This Court held that:
Joint Venture  [I]t is obvious that there remains an unresolved justiciable controversy in the
respondent requested for the mutual termination of the Contract, it did not waive its appealed case for accion publiciana. In particular, did respondent-spouses Oria
right to be paid the amounts due to it as shown in its letter:= really encroach on the land of petitioner? If they did, does he have the right to
In view of the above considerations, we hereby respectfully request for recover possession of the property? Furthermore, without preempting the disposition
MUTUAL TERMINATION of our Contract. Our availment of this remedy does not of the case for accion publiciana pending before the CA, we note that if respondents
mean though that we are waiving our rights (1) to be paid for any and all monetary built structures on the subject land, and if they were builders in good faith, they
benefits due and owing to us under the contract such as but not limited to payments would be entitled to appropriate rights under the Civil Code. This Court merely
for works already done, materials delivered on site which are intended solely for the points out that there are still issues that the CA needs to resolve in the appealed case
construction and completion of the project, price escalation, etc., (2) and without before it.

91
Moreover, there are also the questions of whether respondents should be made to 51  Rollo, pp. 426-427.
pay back monthly rentals  
_______________  
416
46  Pasig Printing Corporation v. Rockland Construction Company, Inc., 726 416 SUPREME COURT REPORTS ANNOTATED
Phil. 256, 265; 715 SCRA 466, 475-476 (2014) [Per J. Mendoza, Third Division].
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
47  David v. Macapagal-Arroyo, 522 Phil. 705, 754; 489 SCRA 160, 214 (2006)
[Per J. Sandoval-Gutierrez, En Banc]. Joint Venture
48  Id. at least 17 demand letters to petitioner, four (4) of which were sent to the DPWH
49  705 Phil. 153; 692 SCRA 162 (2013) [Per CJ. Sereno, First Division]. Secretary directly.52
  Petitioner’s argument fails to convince.
  The case is not premature. The pertinent provision on available administrative
415 remedies can be found in Sub-Clause 67(1) of the Conditions of Contract:
VOL. 839, SEPTEMBER 13, 2017 415 Settlement of Disputes
 
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri Engineer’s Decision 67(1) If a dispute of any kind whatsoever arises between the
Joint Venture Employer and the Contractor in connection with, or arising out of, the Contract or the
for the alleged encroachment; and whether the reward of attorney’s fees, which are execution of the Works, whether during the execution of the Works or after their
also being questioned, was proper. The pronouncements of the CA on these issues completion and whether before or after repudiation or other termination of the
would certainly be of practical value to the parties. After all, should it find that there Contract, including any dispute as to any opinion, instruction, determination,
was no encroachment, for instance, respondents would be entitled to substantial certificate or valuation of the Engineer, the matter in dispute shall, in the first place,
relief. In view of all these considerations, it cannot be said that the main case has be referred in writing to the Engineer, with a copy to the other party. Such reference
become moot and academic.50(Emphasis supplied) shall state that it is made pursuant to this Clause. No later than the eighty-fourth day
  after the day on which he received such reference the Engineer shall give notice of
In this case, issues arising from the mutually terminated Contract are not moot his decision to the Employer and the Contractor. Such decision shall state that it is
and academic. As the Court of Appeals found, there are actual substantial reliefs that made pursuant to this Clause.
respondent is entitled to. There is a practical use or value to decide on the issues Unless the Contract has already been repudiated or terminated, the Contractor shall,
raised by the parties despite the mutual termination of the Contract between them. in every case, continue to proceed with the Works with all due diligence and the
These issues include the determination of amounts payable to respondent by virtue of Contractor and the Employer shall give effect forthwith to every such decision of the
the time extensions, respondent’s entitlement to price adjustments due to the delay of Engineer unless and until the same shall be revised, as hereinafter provided, in an
the issuance of the Notice to Proceed, additional costs, actual damages, and interest amicable settlement or an arbitral award.
on its claims. The agreement to mutually terminate the Contract did not wipe out If either the Employer or the Contractor be dissatisfied with any decision of the
petitioner’s obligation to pay respondent on works done before the Contract’s Engineer, or if the Engineer fails to give notice of his decision on or before the
termination on October 27, 2004. eighty-fourth day after the day on which he received the
  _______________
III
  52  Id., at pp. 793-794.
According to petitioner, the filing of the claim before CIAC was premature, since  
under CIAC rules, there must be an exhaustion of administrative remedies first  
before government contracts are brought to it for arbitration.51 417
Respondent, on the other hand, denies violating the rule on exhaustion of VOL. 839, SEPTEMBER 13, 2017 417
administrative remedies. It claims that it sent
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
_______________
Joint Venture
50  Id., at p. 164; pp. 174-175.

92
reference, then either the Employer or the Contractor may, on or before the documentation. Moreover, Respondent has not indicated any practical benefit of
seventieth day after the day on which he received notice of such decision, or on or resending the demand to the Secretary nor any prejudice for not doing so.
before the seventieth day after the day on which the said period of 84 days expired, In this particular contract project, the procedural requirements governing the
as the case may be, give notice to the other party, with a copy for information to the Settlement of Disputes is specifically provided under Clause 67 of the Conditions of
Engineer, of his intention to commence arbitration, as hereinafter provided, as to the the Contract which Claimant has complied with pursuant to the first paragraph of its
matter in dispute. Such notice shall establish the entitlement of the party giving the letter dated September 10, 2004 (Annex R) pertinent provisions thereof is read, as
same to commence arbitration, as hereinafter provided, as to such dispute and, follows:
subject to Sub-Clause 67.4, no arbitration in respect thereof may be commenced “Pursuant to the provision of Clause 67.1 of the conditions of contracts,
unless such notice is given. we are formally referring to your good office several office several [sic]
If the Engineer has given notice of his decision as to a matter in dispute to the points of disagreement between the position you have taken and the position
Employer and the Contractor and no notice of intention to commence arbitration as we have argued for. These were already the subject of voluminous
to such dispute has been given by either the Employer or the Contractor on or before correspondence between your good self and our company but no clear-cut
the seventieth day after the day on which the parties received notice as to such deci - resolution of the issues raised was ever made.”
sion from the Engineer, the said decision shall become final and binding upon the In the last paragraph of the letter on September 10, 2004 (Annex “R”), Claimant
Employer and the Contractor.53 (Emphasis supplied) has requested Respondent for a definitive ruling on the disputes which were enume-
  rated therein so that Claimant could avail of the remedies given to it by the aforesaid
Under the doctrine of exhaustion of administrative remedies, the concerned Clause 67.1. In spite of Claimant’s request, respondent DPWH did not act on the
administrative agency must be given the opportunity to decide a matter within its same.
jurisdiction before an action is brought before the courts, otherwise, the action will  
be declared premature.54  
In this case, CIAC found and correctly ruled that respondent had duly complied 419
with the contractual obligation to exhaust administrative remedies provided for under VOL. 839, SEPTEMBER 13, 2017 419
_______________
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
53  <http://www.quantumconsult.org/wp-contentuploads/2012/01/2927771- Joint Venture
FIDIC-for-civil-engineeing-construction-1987.pdf>  (Accessed on September 4, The evidence also disclosed that as far as delayed payments are concerned,
2017). Claimant made various verbal and written demands for payment as evidenced by
54  See University of Santo Tomas v. Sanchez, 640 Phil. 189, 194-195; 626 Exhibits “E” to “E-16” or starting December 5, 2000. The demands were not
SCRA 126, 132 (2010) [Per J. Del Castillo, First Division]. heeded.55
  A total of 17 demand letters were sent to petitioner to no avail. To require
  respondent to wait for the DPWH Secretary’s response while respondent continued
418 to suffer financially would be to condone petitioner’s avoidance of its obligations to
418 SUPREME COURT REPORTS ANNOTATED respondent. Hence, even assuming that subclause 67.1 was not applicable, the case
would still fall within the exceptions to the doctrine of exhaustion of administrative
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri remedies56 since strict application of the doctrine will be set aside when requiring it
Joint Venture would only be unreasonable under the circumstances. 57
subclause 67.1 of the Conditions of Contract before it brought the case before the  
tribunal: IV
The Claimant further alleged that, despite of such knowledge, no relief from the  
Secretary was forthcoming. It would therefore be an exercise in futility if Claimant, Petitioner avers that the Court of Appeals gravely erred in rendering the assailed
after it had sent respondent the seventeen (17) demand letters and despite the decision because it completely ignored, overlooked, or misappreciated facts of
unequivocal admission by Respondent’s foreign consultant in charge of the project substance, which, if duly considered, would materially affect the outcome of the
of respondent’s liability and failure to pay (Annex C of the Complaint), will further case. Petitioner argues that the present case is an exception to the rule that only
be required to undergo another series of presentation and exchange of questions of law may be raised in a Petition for Review under Rule 45 of the Rules
of Court.58

93
Before delving into the issues raised, it is imperative to understand CIAC’s role 62  Exec. Order No. 1008, Sec. 2.
as the arbitral tribunal at the center of this dispute. 63  Id., 3rd Whereas Clause.
_______________  
 
55  Rollo, p. 735. 421
56  Paat v. Court of Appeals, 334 Phil. 146, 153; 266 SCRA 167, 174 (1997) VOL. 839, SEPTEMBER 13, 2017 421
[Per J. Torres, Jr., Second Division].
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
57  Information Technology Foundation of the Philippines v. Commission on
Elections, 464 Phil. 173, 207; 419 SCRA 141, 163 (2004) [Per J. Panganiban, En Joint Venture
Banc]. Excluded from the coverage of this law are disputes arising from employer-
58  Rollo, pp. 430-431. employee relationships which shall continue to be covered by the Labor Code of the
  Philippines.
   
420 Republic Act No. 9184 or the “Government Procurement Reform Act,”
420 SUPREME COURT REPORTS ANNOTATED recognized CIAC’s competence in arbitrating over contractual disputes within the
construction industry:
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri Section 59. Arbitration.—Any and all disputes arising from the implementation of
Joint Venture a contract covered by this Act shall be submitted to arbitration in the Philippines
CIAC was created under Executive Order No. 1008, or the “Construction according to the provisions of Republic Act No. 876, otherwise known as the
Industry Arbitration Law.” It was originally under the administrative supervision of “Arbitration Law”: Provided, however, That, disputes that are within the
the Philippine Domestic Construction Board 59 which, in turn, was an implementing competence of the Construction Industry Arbitration Commission to resolve shall be
agency of the Construction Industry Authority of the Philippines. 60 The Construction referred thereto. The process of arbitration shall be incorporated as a provision in the
Industry Authority of the Philippines is presently a part of the Department of Trade contract that will be executed pursuant to the provisions of this Act: Provided, That
and Industry as an attached agency.61 by mutual agreement, the parties may agree in writing to resort to alternative modes
CIAC’s specific purpose is the “early and expeditious settlement of disputes”62 in of dispute resolution. (Emphasis supplied)
the construction industry as a recognition of the industry’s role in “the furtherance of  
national development goals.”63 CIAC’s authority to arbitrate construction disputes was then incorporated into the
Section 4 of the Construction Industry Arbitration Law lays out CIAC’s general statutory framework on alternative dispute resolution through Republic Act
jurisdiction: No. 9285, the “Alternative Dispute Resolution Act of 2004.” Section 34 of Republic
Section 4. Jurisdiction.—The CIAC shall have original and exclusive jurisdiction Act No. 9285 specifically referred to the Construction Industry Arbitration Law,
over disputes arising from, or connected with, contracts entered into by parties while Section 35 confirmed CIAC’s jurisdiction:
involved in construction in the Philippines, whether the dispute arises before or after CHAPTER 6 – ARBITRATION OF CONSTRUCTION DISPUTES
the completion of the contract, or after the abandonment or breach thereof. These  
disputes may involve government or private contracts. For the Board to acquire Section 34. Arbitration of Construction Disputes: Governing Law.—The
jurisdiction, the parties to a dispute must agree to submit the same to voluntary arbitration of construction disputes shall be governed by Executive Order No. 1008,
arbitration. otherwise known as the Constitution Industry Arbitration Law.
The jurisdiction of the CIAC may include but is not limited to violation of  
specifications for materials and workmanship; violation of the terms of agreement;  
interpretation and/or application of contractual time and delays; maintenance and 422
defects; payment, default of employer or contractor and changes in contract cost. 422 SUPREME COURT REPORTS ANNOTATED
_______________
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
59  Exec. Order No. 1008, Sec. 3. Joint Venture
60  Id., 4th Whereas Clause. Section 35. Coverage of the Law.—Construction disputes which fall within the
61  <http://www.dti.gov.ph/about/the-organization/attached-agencies>. original and exclusive jurisdiction of the Construction Industry Arbitration Commis-

94
sion (the “Commission”) shall include those between or among parties to, or who are agencies. In contrast, voluntary arbitration under the Labor Code and construction
otherwise bound by, an arbitration agreement, directly or by reference whether such arbitration derive their authority from statute in recognition of the public interest
parties are project owner, contractor, subcontractor, quantity surveyor, bondsman or inherent in their respective spheres. Furthermore, voluntary arbitration under the
issuer of an insurance policy in a construction project. Labor Code and construction arbitration exist independently of the will of the
The Commission shall continue to exercise original and exclusive jurisdiction contracting parties:
over construction disputes although the arbitration is “commercial” pursuant to _______________
Section 21 of this Act.
  65  Id., at p. 658; pp. 210-211.
As a general rule, findings of fact of CIAC, a quasi-judicial tribunal which has 66  Labor Code, Art. 212(14) provides:
expertise on matters regarding the construction industry, should be respected and Article 212. Definitions.—
upheld. In National Housing Authority v. First United Constructors Corp.,64 this . . . .
Court held that CIAC’s factual findings, as affirmed by the Court of Appeals, will 14. “Voluntary Arbitrator” means any person accredited by the Board as such
not be overturned except as to the most compelling of reasons: or any person named or designated in the Collective Bargaining Agreement by the
As this finding of fact by the CIAC was affirmed by the Court of Appeals, and it parties to act as their Voluntary Arbitrator, or one chosen with or without the
being apparent that the CIAC arrived at said finding after a thorough consideration of assistance of the National Conciliation and Mediation Board, pursuant to a selection
the evidence presented by both parties, the same may no longer be reviewed by this procedure agreed upon in the Collective Bargaining Agreement, or any official that
Court. The all too familiar rule is that the Court will not, in a petition for review on may be authorized by the Secretary of Labor and Employment to act as Voluntary
certiorari, entertain matters factual in nature, save for the most compelling and Arbitrator upon the written request and agreement of the parties to a labor dispute.
cogent reasons, like when such factual findings were drawn from a vacuum or 67  G.R. No. 204197, November 23, 2016, 810 SCRA 280.
arbitrarily reached, or are grounded entirely on speculation or conjectures, are  
conflicting or are premised on the supposed evidence and contradicted by the  
evidence on record or when the inference made is manifestly mistaken or absurd. 424
This conclusion is made 424 SUPREME COURT REPORTS ANNOTATED
_______________
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
64  672 Phil. 621; 657 SCRA 175 (2011) [Per J. Perez, Second Division]. Joint Venture
  Voluntary Arbitrators resolve labor disputes and grievances arising from the
  interpretation of Collective Bargaining Agreements. These disputes were specifically
423 excluded from the coverage of both the Arbitration Law and the ADR Law.
VOL. 839, SEPTEMBER 13, 2017 423 Unlike purely commercial relationships, the relationship between capital and
labor are heavily impressed with public interest. Because of this, Voluntary Arbit-
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri rators authorized to resolve labor disputes have been clothed with quasi-judicial
Joint Venture authority.
more compelling by the fact that the CIAC is a quasi-judicial body whose On the other hand, commercial relationships covered by our commercial
jurisdiction is confined to construction disputes. Indeed, settled is the rule that arbitration laws are purely private and contractual in nature. Unlike labor
findings of fact of administrative agencies and quasi-judicial bodies, which have relationships, they do not possess the same compelling state interest that would
acquired expertise because their jurisdiction is confined to specific matters, are justify state interference into the autonomy of contracts. Hence, commercial
generally accorded not only respect, but finality when affirmed by the Court of arbitration is a purely private system of adjudication facilitated by private citizens
Appeals.65 (Emphasis supplied) instead of government instrumentalities wielding quasi-judicial powers.
  Moreover, judicial or quasi-judicial jurisdiction cannot be conferred upon a
In distinguishing between commercial arbitration, voluntary arbitration under tribunal by the parties alone. The Labor Code itself confers subject-matter
Article 219(14) of the Labor Code,66 and construction arbitration, Freuhauf jurisdiction to Voluntary Arbitrators.
Electronics Philippines Corporation v. Technology Electronics Assembly and Notably, the other arbitration body listed in Rule 43 — the Construction Industry
Management Pacific67 ruled that commercial arbitral tribunals are purely ad Arbitration Commission (CIAC) — is also a government agency attached to the
hoc bodies operating through contractual consent, hence, they are not quasi-judicial Department of Trade and Industry. Its jurisdiction is likewise conferred by statute.

95
By contrast, the subject matter jurisdiction of commercial arbitrators is stipulated by 70  Id., at pp. 738-739.
the parties.68 (Emphasis supplied) 71  Id., at pp. 432-433.
  72  Id., at pp. 433-434.
V 73  Id., at p. 434.
   
Petitioner argues that respondent is not entitled to US$358,227.95, as the foreign  
component of the Contract, because it is not yet legally demandable. 69 In declaring 426
that 426 SUPREME COURT REPORTS ANNOTATED
_______________
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
68  Id., at pp. 307-308. Joint Venture
69  Rollo, pp. 431-435. period had already expired and petitioner did not act on respondent’s requests for
  extension.74 In addition, evidence shows that “the main reason of the nonpayment of
  dollar component was due to unresolved issues, the right-of-way acquisition problem
425 between ADB and the [government], wherein ADB was forced to suspend the loan
VOL. 839, SEPTEMBER 13, 2017 425 disbursement for the entire 6th Road Improvement Project effective 1 June 2003 due
to this conflict.”75 Nevertheless, respondent admitted that the mutual termination of
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri the Contract rendered the requirement of a Letter of Credit for the release of the
Joint Venture $358,227.95 moot and academic.76
petitioner should pay the amount as the foreign component of the project, CIAC held This Court affirms the findings of CIAC and the Court of Appeals that
that petitioner did not deny said amount in its answer and that respondent’s failure to respondent is entitled to the foreign component of the Contract.
renew its Letter of Credit does not justify petitioner’s act in withholding the dollar CIAC found that petitioner was not justified in withholding the payment for the
component of the project.70 dollar component of the Contract. 77 Further, it found that respondent was justified
Petitioner maintains that the delay in payment was due to the negative slippage and not at fault for not reviewing the Letter of Credit. It held that:
incurred by respondent and its failure to renew its Letter of Credit. Petitioner argues The Arbitral Tribunal is persuaded that the main reason for the nonpayment of
that under Clause 60.11 of the Conditions of the Contract, Part II, an irrevocable the dollar component was due to the unresolved issues (right-of-way acquisition)
standby letter of credit is required before petitioner can release the advance between the ADB and the Government of the Philippines where the Loan
payment.71 Petitioner states: Disbursement was suspended by ADB for the 6th Road Improvement Project
In this case, respondent does not deny that its LC No. OIDS-00022-00027-0 effective 01 June 2003 . . . The foreign Consultant even admonished Respondent
issued by the United Coconut Planters Bank (UCPB) expired on October 15, DPWH and reiterated that it should take prompt action to effect payment of
2003. Petitioner reminded respondent several times on the imperative need for the outstanding monies due, and nothing was ever mentioned of the failure to renew the
renewal of its LC to avoid delay in the processing of its billing. The purpose of said Letter of Credit. (Paragraph 3.2 of Affidavit by Ferdinand Mariano)
LC is to guarantee the return of the advance payment by petitioner to respondent.72 _______________
 
Hence, petitioner claims that respondent cannot compel the payment of the 74  Id., at p. 798.
foreign component of the Contract because it did not comply with the letter of credit 75  Id.
requirement. Moreover, petitioner asserts that “In directing petitioner to pay the said 76  Id., at pp. 798-799.
award to respondent without the latter posting the said letter of credit, the CIAC and 77  Id., at p. 738.
the Court of Appeals effectively amended the stipulation thereon in the contract  
which is legally impermissible.”73  
For respondent’s part, it argues that it was impossible to renew the Letter of 427
Credit. It explained that banks refused the renewal of the Letter of Credit since the VOL. 839, SEPTEMBER 13, 2017 427
original contract
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
_______________
Joint Venture

96
Moreover, Claimant explained to the Respondent why the Letter of credit could Petitioner also assails the findings of the Court of Appeals with regard to the time
not be renewed in its letter of 01 and 15 March 2004 (Exh. “C-16” and “C-17”). It extensions respondent is entitled to. Petitioner argues that both the CIAC and the
appears that one of the bank’s requirements for issuance of the Letter of Credit was Court of Appeals failed to consider the subsequent payments made to respondent
the approved time extension and the extension of the contract, but Respondent after the conclusion of the arbitration hearings. Thus, the tribunal’s finding that
refused to issue any document extending the contract. petitioner still owes respondent US$358,227.95 is factually erroneous.
On the other hand, the Respondent’s justification was only based on its Petitioner claims that “respondent failed to prove that it is entitled to the time
accounting requirement. It asserted that the LC guaranteed the advance payment as extensions of: (1) 133 calendar days in addition to the 144 calendar days previously
well as the work completion. It further stated that the LC was a requirement by the agreed by the parties, and (2) 108 calendar days due to delayed payments.”81
funding bank. (By Subair S. Diron, paragraph 3.1.1 of Joint Affidavit by Heinz On the other hand, respondent argues that it is entitled to time extensions in
Reister, Diron and Pandapatan)78 (Emphasis supplied) addition to the 144 calendar days granted to it under Variation Order No.
  2.82 Respondent claims it is entitled to a total of 277 calendar days based on the
In National Housing Authority v. First United Constructors Corp.,79 this Court approved revised Project Evaluation Review Tracking Critical Path Method (PERT-
held that the respondent contractor was entitled to the payment of its claims, as the CPM) diagram and S-Curve.83As explained by witness Engr. Reyes, rock excavation
non-posting of the required Payment Guarantee Bond was due to the inaction of requires special skills, equipment, and explosives. These factors were not considered
petitioner National Housing Authority: when the original contract schedule was prepared. 84
Petitioner’s subsequent refusal to process and pay these claims despite FUCC’s _______________
willingness to submit a surety bond to secure the balance of the advance payment
still to be recouped by NHA — as the parties had agreed upon — which bond would 81  Rollo, p. 435.
be submitted when the check payment for the claim is about to be released, clearly 82  Id., at pp. 799-801.
constitutes a violation by NHA of FUCC’s right to be paid these acknowledged and 83  Id., at p. 800.
recognized claims. Thus, respondent had an accrued cause of action against 84  Id.
petitioner for these claims at the time it filed its Complaint, the constitutive elements  
of which are clearly set forth therein.80 (Emphasis supplied)  
_______________ 429
VOL. 839, SEPTEMBER 13, 2017 429
78  Id., at p. 739.
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
79  National Housing Authority v. First United Constructors
Corporation, supra note 64. Joint Venture
80  Id., at p. 653; p. 205. Respondent further claims that it is entitled to another time extension due to the
  delay in payment. Respondent maintains that it infused more than double the 10%
  credit line amounting to P157,747,945.00.85 Respondent also claims that it had
428 already mobilized working and state-of-the-art equipment.86
428 SUPREME COURT REPORTS ANNOTATED The DPWH Bureau of Construction evaluated respondent’s request for time
extension and recommended its approval to the Secretary. 87 However, the
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri recommendation was withdrawn “on the pretext that said DPWH guidelines for
Joint Venture computation of time extension due to delayed payments [were] revised and
In the present case, the renewal of the Letter of Credit hinged on the extension of modified.”88
the contract period. Despite notice by respondent of the bank’s requirement for the Respondent points out that petitioner, through Engr. Pierre Castelli, had
renewal of the Letter of Credit, petitioner chose to ignore respondent’s requests for acknowledged that the delayed payment had greatly affected respondent’s cash
time extensions. Therefore, petitioner cannot shift the blame to respondent and claim flow.89
that the Letter of Credit was a condition sine qua non for the payment of the dollar Respondent likewise asserts that it is entitled to a time extension due to peace
component of the project. and order problems. Petitioner did not object to respondent’s entitlement to an
  extension due to the peace and order situation. Hence, the only thing required is to
VI determine the number of calendar days’ extension respondent is entitled to based on
  the circumstances.90

97
Chief Resident Engineer Andre Drockur of BCEOM French Engineering 92  Id., at p. 740.
Consultant recommended a time extension of 29 calendar days due to the peace and 93  Id., at p. 477.
order situation. While respondent did not agree with the consultant’s recommen- 94  Id., at pp. 476-477.
dation, it still adopted such recommendation to expedite the computation of time 95  Id., at pp. 740-741.
extension due to peace and order problems.91 96  Id., at p. 741.
_______________  
 
85  Id., at p. 801. 431
86  Id., at p. 802. VOL. 839, SEPTEMBER 13, 2017 431
87  Id.
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
88  Id.
89  Id., at p. 803. Joint Venture
90  Id., at pp. 803-805. Order No. 2; 2) due to the delay in payment; and 3) due to the peace and order
91  Id., at p. 805. situation, since these are supported by the evidence on record.
  To reiterate, findings of fact of administrative agencies and quasi-judicial bodies
  are entitled to great respect and even finality when affirmed by the appellate
430 court.97 In this case, the Court of Appeals found that respondent was entitled to the
430 SUPREME COURT REPORTS ANNOTATED time extensions as evaluated by CIAC, the agency tasked to resolve issues regarding
the construction industry. Both tribunal found that respondent was entitled to the
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri extensions due to petitioner’s delayed payments, peace and order situation, and
Joint Venture Variation Order No. 2. These findings are clearly supported by the facts on record.
According to CIAC, respondent was entitled to time extensions in addition to the However, in light of the mutual termination of the Contract, the remand of the
144-calendar day extension agreed upon by the parties, as per Variation Order No. 2: case to CIAC will serve no practical purpose and is, therefore, unnecessary.
The Arbitral tribunal finds that the computation presented by the Claimant based  
form the approved revised PERT/CPM and S-Curve is acceptable and the 277 VII
calendar days should have been granted by the Respondent or an additional of 133  
calendar days. However, the project is now terminated. The actual accomplishment According to respondent the delay in the issuance of the Notice to Proceed
as per letter of [Chief Resident Engineer] to DPWH dated September 18, 2003 shows entitles it to a price adjustment under Presidential Decree No. 1594. Bidding was
that the actual volume of accomplishment was only 2,732 m2 of hardrock an 4,444 conducted in January 1998 and respondent was declared the winning bidder. The
m3 of rippable rock. Thus, the entire volume under Change Order #2 [or Variation Contract was signed on April 29, 1999. However, the Notice to Proceed was issued
Order No. 2] will not be consumed as the work is no 80% complete[.] 92 on May 5, 1999, or after a delay of more than 120 days from the bidding date, which
  entitles the bidder to an adjustment in the contract unit price under Presidential
The Court of Appeals affirmed that respondent was entitled to a 133-day time Decree No. 1594.98
extension in addition to the 144 calendar days under Variation Order No. On the other hand, petitioner claims that respondent did not question the findings
2.93 However, the Court of Appeals noted that CIAC did not specify whether of the Court of Appeals regarding price adjustment and claim for actual damages.
respondent was entitled to the full 133 days extension, considering that it found that Hence, it
the entire volume in Variation Order No. 2 will not be fully used up due to _______________
respondent’s 80% accomplishment.94
CIAC also held that respondent was entitled to a time extension of 108 calendar 97  See Keppel Cebu Shipyard, Inc. v. Pioneer Insurance and Surety
days due to petitioner’s delayed payments95 and another time extension of 29 Corporation, 695 Phil. 169, 194; 681 SCRA 44, 66-67 (2012) [Per J.Mendoza, En
calendar days due to the peace and order situation in the project area.96 Banc].
This Court sees no reason to deviate from the findings of both CIAC and the 98  Rollo, pp. 806-807.
Court of Appeals with regard to respondent’s entitlement to time extensions: 1)  
under Variation  
_______________ 432

98
432 SUPREME COURT REPORTS ANNOTATED the inception of the project, We hold that it is unjustified for the Claimant not to be
bound by the ADB guidelines under the pretext that it fails to get the supposed price
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
adjustment.100 (Emphasis supplied)
Joint Venture  
should not be allowed to assail the Court of Appeals’ ruling on this issue before this While respondent did not appeal the Court of Appeals’ ruling with regard to its
Court.99 entitlement to a price adjustment under Presidential Decree No. 1594, for purposes of
Both CIAC and the Court of Appeals found that respondent was not entitled to a clarity and to finally settle the matter, this Court affirms the findings of CIAC and
price adjustment: the Court of Appeals.
As to the first issue raised by the Claimant, this Court finds that the CIAC This Court has held that a foreign loan agreement with international financial
committed no reversible error in not awarding the price adjustment being sought by institutions, such as a multilateral lending agency organized by governments like the
the Claimant under P.D. 1594, finding as flawed its claim based on the alleged Asian Development Bank, is an executive or international agreement contemplated
DPWH’s delay in the issuance of the notice to proceed. by our government procurement system.101
We quote with approval the pertinent ratiocination of the CIAC on this point, In Abaya v. Ebdane, Jr.,102 this Court upheld the applicability of the Japan Bank
thus: for International Cooperation’s Procurement Guidelines to the implementation of the
. . . . projects to be undertaken pursuant to the loan agreement between the
However, the Claimant is not entitled to a price adjustment under P.D. _______________
1594 because it is the ADB Guideline[s] on Procurement which should be
followed, and not the provisions on P.D. 1594. In fact the bid of the 100  Id., at pp. 473-474.
Contractor was awarded despite its being above the approved Agency 101  Department of Budget and Management Procurement Service v. Kolonwel
Estimates (AAE), based on the ADB guidelines, and against the provisions of Trading, 551 Phil. 1030, 1049; 524 SCRA 591, 608 (2007) [Per J. Garcia, En Banc].
P.D. 1594 (paragraph 7.2 of Joint Affidavit by Heinz Reister, Diron and This case applied the provisions of Rep. Act No. 9184 or the Government
Pandapatan). Procurement Reform Act which came into effect in 2003.
The Arbitral Tribunal finds that the Guidelines of the Asian Development 102  544 Phil. 645; 515 SCRA 720 (2007) [Per J. Callejo, Sr., Third Division].
Bank govern this subject Project. Moreover, P.D. 1594 honors the treaties  
and international or executive agreements to which the Philippine  
Government is a signatory. Loan agreements such as those entered into with 434
international funding institutions like ADB are considered to be within the 434 SUPREME COURT REPORTS ANNOTATED
ambit of DOJ opinion No. 46, S. 1987 and are therefore exempt from the
application of P.D. No. 1594 as amended Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
_______________ Joint Venture
Republic of the Philippines and Japan Bank for International Cooperation. 103
99  Id., at pp. 845-848. While the Implementing Rules and Regulations104 of Presidential Decree No.
  1594 provides the formula for price adjustment in case of delay in the issuance of a
  notice to proceed, the law does not proscribe parties from making certain contractual
433 stipulations. In this case, the Construction Contract is clear that in case of price
VOL. 839, SEPTEMBER 13, 2017 433 adjustments, Clause 70 of the Conditions of Contract will apply:
It is unclear from the records, however, whether the Asian Development Bank
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
Guidelines was substantially the same as Clause 70 of the Conditions of Contract.
Joint Venture Nevertheless, as in
(paragraph 7.1.1 of Joint Affidavit by Heinz Reister, Diron and Pandapatan). _______________
. . . .
If the Claimant’s bid was awarded despite its being above the approved Agency 103  Id., at p. 687; pp. 761-762.
Estimates based on the ADB guidelines, and against the provisions of P.D. 1594, We 104  IB 10.10 – ISSUANCE OF NOTICE TO PROCEED
cannot see the rationale on why the Claimant now refuses to abide by the ADB 1. The concerned government office/agency/corporation should issue the
guidelines on procurement. After the claimant was benefited by the approved bid at Notice to Proceed (NTP) to the successful bidder not later than fifteen (15) calendar

99
days from the date of approval of the contract by the concerned/authorized Petitioner’s arguments are untenable.
government official. The effectivity date of the NTP shall be specified by the agency It has been sufficiently established that a peace and order problem arose at the
concerned. project site:
2. For projects whereby the Notice to Proceed (NTP) is issued after 120 _______________
calendar days from the bidding date, the awarded bidder may request for a contract
unit price adjustment using the parametric formulae updated to the month of the 106  Id., at p. 442.
NTP. Computation of the unit price adjustment shall be the original contract unit 107  Id., at p. 447.
price multiplied by the fluctuation factor K without deducting the 5%. Such updated 108  Id., at pp. 449-450.
unit prices shall be used as basis for computing the regular progress billings, and 109  Id., at p. 807.
price escalation for work accomplishment shall be calculated using the parametric  
formulae herein prescribed as applied to the updated unit prices reckoned from the  
month of the NTP. Adjustment of unit prices shall be made within fourteen (14) 436
calendar days from the date the required indices are available/issued by the 436 SUPREME COURT REPORTS ANNOTATED
appropriate govemment agency.
3. That computation and payment of contract prices adjustment will be applied Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
in accordance with Clause 70 of the Conditions of Contract.105 Joint Venture
105  Rollo, p. 482. The Arbitral Tribunal was persuaded by the fact that six (6) named persons and
  four (4) John Does were accused of Destructive Arson in the Municipal Circuit Trial
  Court of Dumalinao Zamboanga del Sur for feloniously setting on fire
435 simultaneously one (1) unit of Kumatsu Payloader amounting to Php3,000,000.00
VOL. 839, SEPTEMBER 13, 2017 435 and one (1) unit Isuzu 10 Wheeler Dump Truck amounting to Php800,000.00, both
belonging to the Claimant. The accused are believed NP’s with motives of hatred due
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri to vain collection of revolutionary taxes from Claimant (Exh. “C-5”).
Joint Venture The burning of the Payloader and Dump Truck, subject of the criminal case
the Abaya case, it should be the guidelines that the parties have agreed upon, i.e., the (Exh. “C-5’’) was corroborated in its entirety by the testimony of Pedrito G.
Asian Development Bank Guidelines, that should govern in case of issues arising Palancos, operator of the burnt Payloader in his affidavit, paragraph 6.6 to 6.9, part
from the contract. Respondent failed to proffer evidence on what the Asian of the Records of this case.
Development Bank Guidelines provide, if any, in the event of a delay in the issuance The Chief of Police of Kumalarang, Zamboanga del Sur submitted a Special
of a Notice to Proceed. Written Report to the PNP Provincial Director, regarding the bombing at Claimant’s
  hatching plant in Boyugan, Kumalarang, del Sur on 11 March 2003.
VIII The bombing incident revealed that it resulted in conflagration causing damage
  to the Generator Set, Caterpillar Brand KVA 180-180 and the Conveyor, with total
Petitioner argues that “CIAC and the Court of Appeals grossly erred in awarding estimated cost of Php7,300,000.00.
P5,080,000.00, plus legal interest of P464,298.08 for the alleged equipment and Intelligence Action Agent gathered information that MILF Members, all armed
financial losses; and additional cost resulting from the alleged bombing incident of with undetermined numbers, but believed to be under Commander Susob Edris, were
P6,267,410.48, plus legal interest of P320,410.63.”106 sighted by the barangayofficials and the neighbor of the Plant location, when the
Furthermore, petitioner asserts that “the award to respondent of additional costs incident occurred (Exh. “C-9”).
in the contract price under Clause 69.4 of the General Conditions of the Contract in The two incidents described above, one costing approximately Php3,800,000.00
the amount of P20,311,072.66, plus legal interest of P1,038,368.78 is and the other costing approximately Php7,300,000.00, will have a total of
improper.”107 Petitioner maintains that the award to respondent of additional costs in approximately Php11,100,000.00 or Php11,347,410.48 to be exact. This is the
the contract price under Clause 69.4 of the General Conditions of Contract was amount that Claimant is entitled due to the peace and order situation at the Project
baseless, since the Engineer had not yet consulted with the parties to determine the site.110
amount of additional costs.108 _______________
In contrast, respondent claims that it is entitled to equipment and financial losses
due to the peace and order situation.109 110  Id., at pp. 742-743.

100
  Petitioner further insists that respondent is not yet entitled to the claim because
  there is no determination by the Engineer of the costs incurred, as required under
437 Clause 69.4 of the Conditions of Contract.112
VOL. 839, SEPTEMBER 13, 2017 437 In its Answer before CIAC, petitioner denied respondent’s claims for additional
costs under Clause 69.4. Petitioner stated that its denial will be explained more
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
specifically in its Affirmative Defenses:
Joint Venture 6. DENIES the allegations in paragraphs 12, 13, 14, 15 and 16 of the complaint for
This Court finds that CIAC and the Court of Appeals did not err when they found being preposterous, misleading and patently without legal and factual basis, the truth
that respondent was entitled to its claim for equipment and financial losses. The being that as per the Conditions of Contract, complainant is not entitled to the
situation was an assumed risk of petitioner as employer and is, thus, compensable payment of additional cost on slowdown or suspension of work on the project, reim-
under Clause 20.4 of the Conditions of Contract, which lists the Employer’s risks as: bursement for alleged equipment losses and additional time extensions to complete
 (a) war, hostilities (whether war be declared or not), invasion, act of foreign the project specifically stated/discussed in the Affirmative Defenses
enemies, hereof.113 (Emphasis supplied)
 (b) rebellion, revolution, insurrection, or military or usurped power, or civil war,  
 (c) ionising radiations, or contamination by radio-activity from any nuclear fuel, or However, a perusal of petitioner’s Affirmative Defenses reveals that no such
from any nuclear waste from the combustion of nuclear fuel, radio active toxic qualification was made.
explosive, or other hazardous properties of any explosive nuclear assembly or Under Rule 8, Section 10 of the Rules of Court, the “defendant must specify each
nuclear component thereof, material allegation of fact the truth of which he does not admit and, whenever
 (d) pressure waves caused by aircraft or other aerial devices travelling at sonic or practicable, shall set forth the substance of the matters upon which he relies to
supersonic speeds, support his denial.” There are three (3) modes of specific denial provided for under
(e) riot, commotion or disorder, unless solely restricted to employees of the the Rules:
Contractor or of his Subcontractors and arising from the conduct of the Works, _______________
(f) loss or damage due to the use or occupation by the Employer of any Section or
part of the Permanent Works, except as may be provided for in the Contract, 112  Id., at pp. 449-450.
(g) loss or damage to the extent that it is due to the design of the Works, other any 113  Id., at p. 503.
part of the design provided by the Contractor or for which the Contractor is  
responsible,  
(h) any operation of the forces of nature against which an experienced contractor 439
could not reasonably have been expected to take precautions.111 (Emphasis supplied) VOL. 839, SEPTEMBER 13, 2017 439
_______________
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
111  Id., at p. 530. See <http://www.quantumconsult.org/wp-content/ Joint Venture
uploads/2012/01/2927771-FIDIC-for-civil-engineeing-construction-1987.pdf> (last 1) by specifying each material allegation of the fact in the complaint, the truth of
accessed on September 4, 2017). which the defendant does not admit, and whenever practicable, setting forth the
  substance of the matters which he will rely upon to support his denial; (2) by
  specifying so much of an averment in the complaint as is true and material and
438 denying only the remainder; (3) by stating that the defendant is without knowledge
438 SUPREME COURT REPORTS ANNOTATED or information sufficient to form a belief as to the truth of a material averment in the
complaint, which has the effect of a denial.114
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
 
Joint Venture In Aquintey v. Spouses Tibong,115 this Court held that using “specifically” in a
It is clear from the above provision that the assumed risks of the employer under general denial does not automatically convert that general denial to a specific one.
Clause 20.4 of the Conditions of Contract include rebellion, revolution, insurrection, The denial in the answer must be definite as to what is admitted and what is denied,
or military or usurped power, or civil war. such that the adverse party will not have to resort to guesswork over “what is

101
admitted, what is denied, and what is covered by denials of knowledge as sufficient the receipt of the first demand letter for payment sent by respondent, as a result of
to form a belief.”116 delay in the payment for work accomplished.120
The petitioner only tackled the issue on the claim for additional costs in the Joint The Court is not convinced.
Affidavit of petitioner’s witnesses Heinz Reister, Subair S. Diron, and Abdulfatak A. It is fundamental that a contract is the law between the parties and, absent any
Pandapatan: showing that its provisions are wholly
Issue No. 9. Is claimant entitled to additional cost under Clause 69.4 of the General _______________
Conditions of Contract? If so, how much?
Subair S. Diron and Abdulfatak A. Pandapatan testifying: 118  Id., at p. 747.
9.1 Q: Is claimant entitled to additional cost/charges under Clause 69.4 of the 119  Id., at p. 813.
General Conditions of Contract? 120  Id.
A: Not yet, the claimant should establish that it is allowed. 117  
_______________  
441
114  Philippine Bank of Communications v. Go, 658 Phil. 43, 57; 642 SCRA VOL. 839, SEPTEMBER 13, 2017 441
693, 707 (2011) [Per J. Mendoza, Second Division].
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
115  540 Phil. 422; 511 SCRA 414 (2006) [Per J. Callejo, Sr., First Division].
116  Id., at p. 441; p. 433. Joint Venture
117  Rollo, p. 579. or in part contrary to law, morals, good customs, public order, or public policy, it
  shall be enforced to the letter by the courts.121
  Respondent was not able to establish the basis of its claim that it is entitled to an
440 award of 24% interest. Moreover, as found by the Court of Appeals and CIAC, the
440 SUPREME COURT REPORTS ANNOTATED parties had agreed to delete the provision on interest on delayed payments, since the
project was funded by the Asian Development Bank.122
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri There is also no basis to award respondent 24% interest as actual damages for the
Joint Venture additional expenses it incurred due to petitioner’s delayed payments.
This Court finds that petitioner failed to specifically deny the claims of Before actual damages may be awarded, it is imperative that the claimant proves
respondent and had, therefore, admitted such claims. This Court agrees that its claims first. The issue on the amount of actual or compensatory damages is a
respondent was able to establish its claims before the CIAC. This Court notes that question of fact,123 and except as provided by law or by stipulation, one is entitled to
the project was in Mindanao, and mobilization of workers and equipment is not an adequate compensation only for pecuniary loss duly proven.124
easy feat and not without cost. Respondent believed that the suspension would only In this case, respondent has not sufficiently shown how awarding it 24%
be temporary and work could resume at any time once petitioner settled its interest per annum on delayed payments corresponds to the actual damages it
obligation. Petitioner must compensate respondent for the costs it incurred without allegedly suffered. Respondent failed to show a causal relation between the alleged
any fault on respondent’s part. losses and the injury it suffered from petitioner’s actions.
   
IX X
   
During the arbitration hearing before the CIAC, respondent itself admitted that Respondent claims that it should be paid in U.S. dollars as specified in the
there was no provision in the Conditions of Contract for interest at the rate of Contract.125 It argues that the present case is
24% per annum on delayed payments.118 _______________
Respondent tries to excuse the lack of contractual stipulations by claiming that
the amount of 24% interest is payment for actual damages and not stipulated 121  Stronghold Insurance Company, Incorporated v. Interpacific Container
interest.119 Services, 762 Phil. 483, 491; 761 SCRA 210, 218-219 (2015) [Per J. Perez, First
Respondent claims that petitioner is liable for the amounts respondent owes its Division].
creditors in the total amounts of P10,297,090.42 and USD$118,094.93. In addition, 122  Rollo, pp. 474-475.
respondent avers that petitioner should pay it 6% interest per annum computed from

102
123  City of Dagupan v. Maramba, 738 Phil. 71, 96; 728 SCRA 520, 547 (2014) Joint Venture
[Per J. Leonen, Third Division]. Again, considering that respondent did not appeal the Court of Appeals’
124  Civil Code, Art. 2199. decision, the appellate court’s ruling on this issue is deemed final as to respondent,
125  Id., at pp. 813-814. and there is no need to remand this issue to the CIAC. Issues not raised on appeal are
  already final and cannot be disturbed.128
   
442 XI
442 SUPREME COURT REPORTS ANNOTATED  
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri CIAC imposed legal interest in its Award as follows:
Joint Venture In view of the foregoing, the Claimant is entitled to payment of legal interest of
6% per annum from the receipt of its extrajudicial demand.
an exception to the general rule that obligations should be paid in Philippine
Thus, under Issue No. 3 where the Claimant was awarded US$358,227.95, the
currency.126
Claimant is entitled to legal interest of 6% per annum commencing from 2 March
The Court of Appeals held that the parties subsequently agreed that payments
2004 up to this date (or 311 days) in the amount of US$18,313.79.
made after March 31, 2003 shall be in pesos only:
Under Issue No. 8 where the Claimant was awarded P11,347,410.48, the
However, one aspect in the CIAC’s decision is shrouded with cloud. This
Claimant is entitled to legal interest of 6% per annum for the Equipment and Plant of
concerns CIAC’s order to DPWH to pay its alleged liability to the Claimant in US
P5,080,000.00 commencing from 1 July 2003 (or 556 days) in the amount of
dollars. It is worthy to note that aside from the agreement of the parties —
P464,298.08 and for the resulting Additional Expenses of P6,267,410.48
particularly in paragraph 5 of the contract, supra, to fix the exchange rate at P34.9
commencing from 2 March 2004 (or 311 days) in the amount of P320,410.63.
for every US$1.00, the Claimant itself has acknowledged in its request that it was
Under Issue No. 9 where the Claimant was awarded P20,311,072.66, the
advised by the DPWH per its letter dated 13 August 2003 that all payments for
Claimant is entitled to legal interest of 6% per annum for Additional Cost under 69.4
works earned out after 31 March 2003 and related price escalation claims and
of the Conditions of Contract commencing from 2 March 2004 (or 311 days) in the
retention releases in the contract will be in pesos only, therefore no foreign
amount of P1,038,368.78.
exchange payments. This fact was never contested by the Claimant thereby creating a
Under Issue No. 10 with respect to the delayed payment of billings for various
presumption that it has acquiesced to the request of the DPWH. Thus, We cannot see
amounts and on various dates, the Claimant is entitled to legal interest of 6% per 
Our way through on why the CIAC has still to make a ruling on the Interest
_______________
Computation of Delayed Payment at 6% Per Annum at US$45,206.14 as well as the
Foreign Component of US$358,227.95 plus legal interest at US$18,313.79 citing the
128  See A.C. Ransom Labor Union-CCLU v. National Labor Relations
exemption of transactions where the funds involved are the proceeds of loans or
Commission, 226 Phil. 199, 204; 142 SCRA 269, 272 (1986) [Per J.Melencio-
investments made through bona fide intermediaries or agents, by foreign government
Herrera, First Division].
and banking institutions such as the Asian Development Bank (ADB) from the
 
coverage of Republic Act 529 otherwise known a[s] “An Act to Assure Uniform
 
Value to Philippine Coin and Currency.” Worse, there was no mention about the
444
subsequent notice by the DPWH to the Claimant, supra, about their subsequent
understanding on “no foreign exchange payments.” This is indeed one dubious area 444 SUPREME COURT REPORTS ANNOTATED
that needs to be clarified by no less than the CIAC itself.127 (Emphasis supplied) Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
_______________ Joint Venture
annum as detailed in Attachment 1, in the amount of US$45,206.14 and
126  Id., at p. 814. P2,175,516.63.
127  Id., at pp. 478-479 (Court of Appeals Decision). However, pursuant to the Eastern Shipping Lines v. Court of Appeals, 234 SCRA
  78 (1994), a monetary award shall earn interest at the rate of 12% per annum from
  the date when the award becomes final and executory until its satisfaction.129
443  
VOL. 839, SEPTEMBER 13, 2017 443 On May 16, 2013, the Monetary Board of the Bangko Sentral ng Pilipinas issued
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri Resolution No. 796, which revised the interest rate to be imposed on the loan or
103
forbearance of any money, goods, or credits. This was implemented in Bangko 2. When an obligation, not constituting a loan or forbearance of money, is breached,
Sentral ng Pilipinas Circular No.799130 Series of 2013, which reads: an interest on the amount of damages awarded may be imposed at the discretion
The Monetary Board, in its Resolution No. 796 dated 16 May 2013, approved the of the court at the rate of 6% per annum. No interest, however, shall be adjudged
following revisions governing the rate of interest in the absence of stipulation in loan on unliquidated claims or damages, except when or until the demand can be
contracts, thereby amending Section 2 of Circular No. 905, Series of 1982: established with reasonable certainty. Accordingly, where the demand is
Section 1. The rate of interest for the loan or forbearance of any money, goods _______________
or credits and the rate allowed in judgments, in the absence of an express
contract as to such rate of interest, shall be six percent (6%) per annum. 131  Nacar v. Gallery Frames, 716 Phil. 267; 703 SCRA 439 (2013)
Section 2. In view of the above, Subsection X305.1 of the Manual of [Per J. Peralta, En Banc].
Regulations for Banks and Sections 4305Q.1, 43058.3 and 4303P.1 of the  
Manual of Regulations for Non-Bank Financial Institutions are hereby amended  
accordingly. 446
This Circular shall take effect on 1 July 2013. 446 SUPREME COURT REPORTS ANNOTATED
_______________
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
129  Rollo, p. 749. Joint Venture
130  The subject of Bangko Sentral ng Pilipinas Circular No. 799 dated June 21, established with reasonable certainty, the interest shall begin to run from the time
2013 is the “[r]ate of interest in the absence of stipulation.” the claim is made judicially or extrajudicially (Art. 1169, Civil Code), but when
  such certainty cannot be so reasonably established at the time the demand is
  made, the interest shall begin to run only from the date the judgment of the court
445 is made (at which time the quantification of damages may be deemed to have
VOL. 839, SEPTEMBER 13, 2017 445 been reasonably ascertained). The actual base for the computation of legal
interest shall, in any case, be on the amount finally adjudged.
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri 3. When the judgment of the court awarding a sum of money becomes final and
Joint Venture executory, the rate of legal interest, whether the case falls under paragraph 1 or
Nacar v. Gallery Frames131 then laid down the guidelines for the imposition of paragraph 2, above, shall be 6% per annum from such finality until its
legal interest: satisfaction, this interim period being deemed to be by then an equivalent to a
To recapitulate and for future guidance, the guidelines laid down in the case forbearance of credit.
of Eastern Shipping Lines are accordingly modified to embody BSP-MB Circular And, in addition to the above judgments that have become final and executory
No. 799, as follows: prior to July 1, 2013, shall not be disturbed and shall continue to be implemented
I. When an obligation, regardless of its source, i.e., law, contracts, quasi-contracts, applying the rate of interest fixed therein.132
delicts or quasi-delicts is breached, the contravenor can be held liable for damages.  
The provisions under Title XVIII on “Damages” of the Civil Code govern in Before Nacar and Bangko Sentral ng Pilipinas-Monetary Board Resolution No.
determining the measure of recoverable damages. 796 dated May 16, 2013, the rate of legal interest was pegged at 12% per annumfrom
II. With regard particularly to an award of interest in the concept of actual and finality of judgment until its satisfaction, “this interim period being deemed to be by
compensatory damages, the rate of interest, as well as the accrual thereof, is then an equivalent to a forbearance of credit.”133
imposed, as follows: With this Court’s pronouncement in Nacar, the rate of interest imposed should
1. When the obligation is breached, and it consists in the payment of a sum of be modified. The monetary awards, as computed by the CIAC, should earn legal
money, i.e., a loan or forbearance of money, the interest due should be that which interest at the rate of 12% per annum until June 30, 2013, after which, it shall earn
may have been stipulated in writing. Furthermore, the interest due shall itself legal interest at the rate of 6% per annum until full satisfaction.
earn legal interest from the time it is judicially demanded. In the absence of _______________
stipulation, the rate of interest shall be 6% per annum to be computed from
default, i.e., from judicial or extrajudicial demand under and subject to the 132  Id., at pp. 281-283; pp. 457-458.
provisions of Article 1169 of the Civil Code. 133  See Eastern Shipping Lines, Inc. v. Court of Appeals, 304 Phil. 236, 254;
234 SCRA 78, 97 (1994) [Per J. Vitug, En Banc].

104
 
 
447
VOL. 839, SEPTEMBER 13, 2017 447
Department of Public Works and Highways vs. CMC/Monark/Pacific/Hi-Tri
Joint Venture
The other issues raised by the parties were no longer discussed due to the mutual
termination of the Contract by parties, which rendered them moot and academic.
WHEREFORE, the Petition is DENIED. The Court of Appeals’ Decision dated
September 20, 2007 in C.A.-G.R. S.P. Nos. 88953 and 88911 is AFFIRMED with
MODIFICATIONS as follows: (1) that the order remanding the case to the
Construction Industry Arbitration Commission for proper disposition
is REVERSED for being moot and academic; and (2) that the legal interest rate is
pegged at twelve percent (12%) per annum until June 30, 2013, and then at six
percent (6%) per annum until full satisfaction.
SO ORDERED.
Velasco, Jr. (Chairperson), Bersamin, Martires andGesmundo, JJ., concur.
Petition denied, judgment affirmed with modifications.
Notes.—It has been repeatedly emphasized that in the case of natural persons,
the certification against forum shopping must be signed by the principal parties
themselves and not by the attorney. (Agustin vs. Cruz-Herrera, 716 SCRA 42
[2014])
Where the plaintiffs or petitioners share a common interest and invoke a common
cause of action or defense — the rule requiring all such plaintiffs or petitioners to
sign the certification against forum shopping may be relaxed. (Fernandez vs.
Villegas, 733 SCRA 548 [2014])
 
——o0o——

105

You might also like