RAB Portable Shelter Pondok Cabe Dengan Kansten Perimeter
RAB Portable Shelter Pondok Cabe Dengan Kansten Perimeter
TOTAL 618,977,219.83
PPN 10% -
GRAND TOTAL 618,977,219.83
DIBULATKAN 619,000,000.00
HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME
SATUAN HARGA
HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME
SATUAN HARGA
HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME
SATUAN HARGA
I PEKERJAAN PERSIAPAN
1 Pek. Pembersihan lahan 1,196.80 m2 24,200 28,962,560
2 Pek. Bowplank 138.80 m1 217,907 30,245,450
3 Pek. Site Office 9.00 m2 1,706,560 15,359,037
4 Pek. Gudang Material dan Alat 15.00 m2 1,005,077 15,076,149
5 Pek. Barak Pekerjan 15.00 m2 1,706,560 25,598,395
II PEKERJAAN TANAH
1 Pek. Galian Tanah 184.38 m3 176,617 32,564,597
2 Pek. Pemadatan 390.60 m2 28,490 11,128,194
3 Pek. Buang Sisa Galian Tanah 147.50 m3 45,760 6,749,783
4 Pek. Urugan Sirtu dan pemadatan, ketebalan 30 cm