No Uraian Pekerjaan Nilai Jumlah Nilai

I PEKERJAAN PONDASI TIANG 166,366,536.14 166,366,536.14

II PEKERJAAN PELEBARAN LANDASAN 265,936,283.68 265,936,283.68

III PEKERJAAN ERECTION SHELTER 186,674,400.00 186,674,400.00

TOTAL 618,977,219.83
PPN 10% -
GRAND TOTAL 618,977,219.83
DIBULATKAN 619,000,000.00

Terbilang : Enam Ratus Sembilan Belas Juta Rupiah

Bandung, 16 Mei 2023


2
RENCANA ANGGARAN BIAYA
PEKERJAAN PORTABLE SHELTER PONDOK CABE
DENGAN KANSTEEN PERIMETER LANTAI SHELTER

HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME
SATUAN HARGA

A PEKERJAAN ERECTION SHELTER


1 Pek. Erection Pintu Shelter 4,800.00 kg 9,570 45,936,000
Pek. Erection Rangka Shelter 10,000.00 kg 9,570 95,700,000
Pek. Erection Sistem Pintu 400.00 kg 9,570 3,828,000
Pek. Penutup Terpal Shelter 892.00 m2 46,200 41,210,400

Sub Total Dipindahkan ke Rekap 186,674,400


3
RENCANA ANGGARAN BIAYA
PEKERJAAN PONDASI PORTABLE SHELTER PONDOK CABE
DENGAN KANSTEEN PERIMETER LANTAI SHELTER

HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME
SATUAN HARGA

A PEKERJAAN PONDASI PINTU


II Pekerjaan Pondasi Beton
1 Pek. Bobokan Beton 1.43 m³ 953,304 1,361,318
2 Pek. Galian 9.55 m³ 153,340 1,464,336
3 Pek. Pasir Urug 0.39 m³ 281,380 109,249
4 Pek. Lantai Kerja 0.19 m³ 74,019 14,369
5 Pek. Beton 6.25 m³ 1,315,468 8,218,781
6 Pek. Pembesian Besi D13mm 332.17 kg 17,566 5,834,806
7 Pek. Angkur, panjang 100 cm 12.00 bh 159,500 1,914,000
8 Pek. Begisting 16.20 m² 303,507 4,916,805
9 Pek. Urugan Kembali 2.72 m³ 77,000 209,395
10 Pek. Buang Tanah 6.83 m³ 45,760 312,549
11 Pek. Pengecoran Landasan 1.04 m³ 1,315,468 1,373,349

III Pekerjaan Strauss Pile Ø 300mm L= 3.00 Meter


1 Pek. Galian Strauss Pile 1.70 m³ 284,236 481,951
2 Pek. Pembesian D13 242.94 kg 17,566 4,267,530
3 Pek. Pengecoran 1.70 m³ 1,315,468 2,230,508

B PEKERJAAN PONDASI TIANG SHELTER


II Pekerjaan Pondasi Beton
1 Pek. Bobokan Beton 11.66 m³ 953,304 11,119,338
2 Pek. Galian 30.99 m³ 153,340 4,752,720
3 Pek. Pasir Urug 2.89 m³ 281,380 813,401
4 Pek. Lantai Kerja 1.45 m³ 74,019 106,985
5 Pek. Beton 19.22 m³ 1,315,468 25,286,781
6 Pek. Pembesian Besi D13mm 2,028.94 kg 17,566 35,640,113
7 Pek. Angkur, panjang 40 cm 135.00 bh 71,500 9,652,500
8 Pek. Begisting 54.00 m² 303,507 16,389,351
9 Pek. Urugan Kembali 7.44 m³ 77,000 572,562
10 Pek. Buang Tanah 23.56 m³ 45,760 1,078,050
11 Pek. Pengecoran Landasan 3.56 m³ 1,315,468 4,688,328

III Pekerjaan Strauss Pile Ø 300mm L= 3.00 Meter


1 Pek. Galian Strauss Pile 5.72 m³ 284,236 1,626,585
2 Pek. Pembesian D13 819.94 kg 17,566 14,402,914
3 Pek. Pengecoran 5.72 m³ 1,315,468 7,527,963
Sub Total Dipindahkan ke Rekap 166,366,536
4
RENCANA ANGGARAN BIAYA
PEKERJAAN PELEBARAN LANDASAN PORTABLE SHELTER PONDOK CABE
DENGAN KANSTEEN PERIMETER LANTAI SHELTER

HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME
SATUAN HARGA

I PEKERJAAN PERSIAPAN
1 Pek. Pembersihan lahan 1,196.80 m2 24,200 28,962,560
2 Pek. Bowplank 138.80 m1 217,907 30,245,450
3 Pek. Site Office 9.00 m2 1,706,560 15,359,037
4 Pek. Gudang Material dan Alat 15.00 m2 1,005,077 15,076,149
5 Pek. Barak Pekerjan 15.00 m2 1,706,560 25,598,395

II PEKERJAAN TANAH
1 Pek. Galian Tanah 184.38 m3 176,617 32,564,597
2 Pek. Pemadatan 390.60 m2 28,490 11,128,194
3 Pek. Buang Sisa Galian Tanah 147.50 m3 45,760 6,749,783
4 Pek. Urugan Sirtu dan pemadatan, ketebalan 30 cm

III PEKERJAAN BETON PELEBARAN LANDASAN


1 Pek. Pasir Urug 4.41 m3 281,380 1,240,886
2 Pek. Lantai Kerja 8.82 m3 74,019 652,847
3 Pek. Beton, ketebalan 30 cm K-300 26.46 m3 1,315,468 34,807,283
4 Pek. Pembesian Wiremesh M8, 2 layer 176.40 m2 113,371 19,998,686
5 Pek. Begisting 16.96 m2 303,507 5,147,470

VI PEKERJAAN INSTALASI AIR KOTOR DAN BERSIH


Pek. Pemasangan Pipa Air Bersih AW 1/2" AW 50.00 m1 22,955 1,147,740
Pek. Pemasangan Pipa Air Kotor 4" AW 20.00 m1 59,291 1,185,822
Pek. Pemasangan Pipa Air Bekas 2" Aw 20.00 m1 198,407 3,968,140
Pek. Pembuatan Septic Tank Biotank 1m3 1.00 Unit 3,335,640 3,335,640
Pek. Sumur Resapan Ø 0.8 M Dalam 1,5 Meter 1.00 Unit 1,076,855 1,076,855

V PEKERJAAN KANSTEEN PERIMETER LANTAI SHELTER


1 Pek. Bobok Lantai 1.00 m3 953,304 953,304
2 Pek. Galian Kansteen 3.00 m3 176,617 529,850
3 Pek. Pasir Urug 1.04 m3 281,380 292,917
4 Pekerjaan Kansteen Tinggi 30cm Perimeter Lantai Shelter
101.40 m1 255,569 25,914,679

Sub Total Dipindahkan ke Rekap 265,936,284