Skyscraper 50% Above 300 feet Above 300 Min 12 Min 80 Parking
increase in (No feet Kanal and feet
requirement
F.A.R @ Restriction), above
4% NOC from as per
Proportionate to CAA
specific use
height
mentioned in
* (e.g if height
Clause 3.11
is 400 ft then
F.A.R will be
400*0.04=16)
Note:
The building plans already submitted after 11-09-2019 till date will not be affected by these amendments and will be processed under the
provisions applicable on day of submission.
Extra Height Charges above 38 feet (Rs. 100/- per sft of covered area for apartment building & Rs.60/- per sft for
commercial building)
The increase in FAR above 300 feet in Skyscraper zone shall be proportionate to the actual proposed height
*Determination of FAR within Skyscraper shall be made on the basis of formula given in above table.
_______________________________________________________________________________________________________________
LDA BUIDLING AND ZONNING REGULATIONS 2019 (with all amendments approved till 28-01-2020)
7/8 th of plot N.A G+6 Upto 90 feet 10 Marla Not Required
area & 3/4th to less
on than 2
Subsequent Kanal
floor
Medium 7/8 th of plot 1:5.5 G+9 Upto 120 Min 2 Not Required
Rise-2 area & 3/4th feet Kanal and
on less than 4
kanal
Subsequent
floor
High Rise- 7/8 th of plot 1:8 G+14+Servic Upto 200 Min 4 One car space for
1 area & 3/4th e Floor feet Kanal and 1600 sft useable
on less than 8 area
Kanal
Subsequent
floor
High Rise 7/8 th of plot 1:12 G+23+Servic Upto 300 Min 8 One car space for
-2 area & 3/4th e Floor feet Kanal and 1600 sft useable
on less than area
12 Kanal
Subsequent
floor
Skyscrape 7/8 th of plot Above 300 feet Above 300 Min 12 One car space for
r area & 3/4th increase in (No feet Kanal and 1600 sft useable
on F.A.R @ Restriction), above area
4% NOC from
Subsequent
Proportionate CAA
floor to height (e.g if
height is 400 ft
then F.A.R will
be
400*0.04=16)
a. Only one basement is allowed with a maximum depth of 12ft (3.66m) from the road level
for plot area up to 1 kanal. However, plots fall in Medium Rise Zone-2 (upto 120 ft height)
may have more than one basement.
b. Amalgamation of plots is allowed, whereas sub division of plot in Civic Center is strictly
prohibited.
c. The Sponsor / Owner may utilize the designated parking space in front of Commercial
building for construction of underground parking after getting plan vetted by TEPA and
Town Planning, LDA.
d. As regards, the plots of Timber Market, Fruit and Vegetable Markets and other such
scheme where in the past type design buildings, the permission may be given to process
case on Low-Rise zones upto 38 feet with one basement (optional).
_______________________________________________________________________________________________________________
LDA BUIDLING AND ZONNING REGULATIONS 2019 (with all amendments approved till 28-01-2020)
Plot Size Rear Space Side Space
Less Than 5 Marlas 5-ft (1.52m) Not Required
3.6.1. (a)The building line in Gulberg Scheme for all categories of converted corner plots shall be
as specified by the Commercialization Committee. The other mandatory spaces shall be as
follows:
Sr. Size of Plot Front Mandatory Towards Longer Other Side Rear
No. Space Road Side Space Space Space
1 10 Marla upto 1- 30 FT Not Compulsory Not 7 FT
Kanal Compulsory
a. The floor level of mandatory open spaces for all buildings shall not be more than 6 inches
higher or lower than the adjoining road level.
b. No boundary wall between two adjoining commercial buildings to improve access of utility
vehicles.
c. Vehicular entry and exit shall be provided.
d. Except emergency exits, window and other openings on the upper floors shall not be
allowed, which may adversely affect the privacy of adjoining properties.
e. Parking shall be provided as laid down in these Building Regulations.
f. No structural changes shall be allowed in the buildings after grant of temporary / annual
commercialization.
g. The side spaces between two commercial buildings shall be kept at the same level for
common use.
h. Parking Basements can be constructed according to the soil conditions/water table in the
particular area
i. For mega projects, FAR, Ground Coverage, Height and similar architectural / planning
aspects shall be decided by the Authority (Board of Governor) on the request of owner(s)
in case of any difficulty, hardship pertaining to planning/ building standards and maximum
building plan period.
j. For energy efficiency, all new commercial building shall provide LED lights for lighting
k. In all new commercial buildings, solar energy systems, shall be provided at least for
corridors lights.
l. For plots abutting on 60-ft and above right of way, separate plans for basement shall be
submitted and sanctioned/released in the first phase in residential buildings.
m. Requirement of NOC from the Civil Aviation Authority shall be mandatory as per relevant
Rules of Civil Aviation Authority and directions received from time to time in multi-storey
building above 300-ft.
_______________________________________________________________________________________________________________