You are on page 1of 57

No Uraian Pekerjaan Luas (m2) Sat Harga Satuan (Rp) Total Harga (Rp)

Bekisting Lt. 3

Zona 1
1 Bekisting Kolom 288.01 m2 472,226.22 136,005,873.62
2 Bekisting Balok - m 2

3 Bekisting Plat Lantai - m2


Zona 2
1 Bekisting Kolom 298.45 m2 161,937.29 48,330,184.20
2 Bekisting Balok - m 2

3 Bekisting Plat Lantai - m2


Bekisting Lt. 5
Zona 1
1 Bekisting Kolom 286.1 m2 472,226.22 135,103,921.54
2 Bekisting Balok 408.78 m 2
482,446.31 197,214,402.60
3 Bekisting Plat Lantai 862.85 m2 658,790.62 568,437,486.47
Zona 2
1 Bekisting Kolom 293.29 m2 161,937.29 47,494,587.78
2 Bekisting Balok 403.85 m 2
161,937.29 65,398,374.57
3 Bekisting Plat Lantai 737.76 m 2
161,937.29 119,470,855.07
Bekisting Lt. 6
Zona 1
1 Bekisting Kolom 282.36 m2 472,226.22 133,337,795.48
2 Bekisting Balok 408.78 m2 482,446.31 197,214,402.60
3 Bekisting Plat Lantai 862.85 m 2
658,790.62 568,437,486.47
Zona 2
1 Bekisting Kolom 200.29 m2 161,937.29 32,434,419.81
2 Bekisting Balok 403.85 m 2
161,937.29 65,398,374.57
3 Bekisting Plat Lantai 737.76 m 2
161,937.29 119,470,855.07
Bekisting Lt. 7
Zona 1
1 Bekisting Kolom 282.36 m2 472,226.22 133,337,795.48
2 Bekisting Balok 400.78 m 2
482,446.31 193,354,832.12
3 Bekisting Plat Lantai 887.98 m 2
658,790.62 584,992,894.75
Zona 2
1 Bekisting Kolom 200.29 m2 161,937.29 32,434,419.81
2 Bekisting Balok 393.52 m 2
161,937.29 63,725,562.36
3 Bekisting Plat Lantai 737.76 m 2
161,937.29 119,470,855.07
Bekisting Lt. 8
Zona 1
1 Bekisting Kolom 282.36 m2 472,226.22 133,337,795.48
2 Bekisting Balok 400.78 m 2
482,446.31 193,354,832.12
3 Bekisting Plat Lantai 887.98 m 2
658,790.62 584,992,894.75
Zona 2
1 Bekisting Kolom 200.29 m2 161,937.29 32,434,419.81
2 Bekisting Balok 393.52 m2 161,937.29 63,725,562.36
3 Bekisting Plat Lantai 737.76 m2 161,937.29 119,470,855.07
Bekisting Lt. 9
Zona 1
1 Bekisting Kolom 282.36 m2 472,226.22 133,337,795.48
2 Bekisting Balok 400.78 m 2
482,446.31 193,354,832.12
3 Bekisting Plat Lantai 887.98 m 2
658,790.62 584,992,894.75
Zona 2
1 Bekisting Kolom 200.29 m2 161,937.29 32,434,419.81
2 Bekisting Balok 393.52 m 2
161,937.29 63,725,562.36
3 Bekisting Plat Lantai 737.76 m 2
161,937.29 119,470,855.07
Bekisting Lt. 10
Zona 1
1 Bekisting Kolom 200.36 m2 472,226.22 94,615,245.44
2 Bekisting Balok 301.35 m 2
482,446.31 145,385,195.52
3 Bekisting Plat Lantai 925.97 m 2
658,790.62 610,020,350.40
Zona 2
1 Bekisting Kolom 254.18 m2 161,937.29 41,161,220.37
2 Bekisting Balok 337.52 m 2
161,937.29 54,657,074.12
3 Bekisting Plat Lantai 661.78 m 2
161,937.29 107,166,859.78
Bekisting Lt. 11
Zona 1
1 Bekisting Kolom 200.36 m2 472,226.22 94,615,245.44
2 Bekisting Balok 301.35 m2 482,446.31 145,385,195.52
3 Bekisting Plat Lantai 925.97 m2 658,790.62 610,020,350.40
Zona 2
1 Bekisting Kolom 254.18 m2 161,937.29 41,161,220.37
2 Bekisting Balok 337.52 m 2
161,937.29 54,657,074.12
3 Bekisting Plat Lantai 661.78 m 2
161,937.29 107,166,859.78
Bekisting Lt. 12
Zona 1
1 Bekisting Kolom 200.36 m2 472,226.22 94,615,245.44
2 Bekisting Balok 301.35 m 2
482,446.31 145,385,195.52
3 Bekisting Plat Lantai 925.97 m 2
658,790.62 610,020,350.40
Zona 2
1 Bekisting Kolom 254.18 m2 161,937.29 41,161,220.37
2 Bekisting Balok 337.52 m 2
161,937.29 54,657,074.12
3 Bekisting Plat Lantai 661.78 m 2
161,937.29 107,166,859.78
Bekisting Lt. 15
Zona 1
1 Bekisting Kolom 200.36 m2 472,226.22 94,615,245.44
2 Bekisting Balok 301.35 m 2
482,446.31 145,385,195.52
3 Bekisting Plat Lantai 925.97 m 2
658,790.62 610,020,350.40
Zona 2
1 Bekisting Kolom 254.18 m2 161,937.29 41,161,220.37
2 Bekisting Balok 337.52 m2 161,937.29 54,657,074.12
3 Bekisting Plat Lantai 661.78 m 2
161,937.29 107,166,859.78
Bekisting Lt. 16
Zona 1
1 Bekisting Kolom 183.36 m2 472,226.22 86,587,399.70
2 Bekisting Balok 271.35 m 2
482,446.31 130,911,806.22
3 Bekisting Plat Lantai 584.97 m 2
658,790.62 385,372,748.98
Zona 2
1 Bekisting Kolom 149.13 m2 161,937.29 24,149,708.06
2 Bekisting Balok 278.31 m 2
161,937.29 45,068,767.18
3 Bekisting Plat Lantai 791.7 m 2
161,937.29 128,205,752.49
Bekisting Lt. 17
Zona 1
1 Bekisting Kolom 152.57 m2 472,226.22 72,047,554.39
2 Bekisting Balok 271.35 m 2
482,446.31 130,911,806.22
3 Bekisting Plat Lantai 510.98 m 2
658,790.62 336,628,831.01
Zona 2
1 Bekisting Kolom 150.73 m2 161,937.29 24,408,807.72
2 Bekisting Balok 278.31 m 2
161,937.29 45,068,767.18
3 Bekisting Plat Lantai 791.7 m2 161,937.29 128,205,752.49
Bekisting Lt. 18
Zona 1
1 Bekisting Kolom 177.67 m2 472,226.22 83,900,432.51
2 Bekisting Balok 331.37 m 2
482,446.31 159,868,233.74
3 Bekisting Plat Lantai 829.4 m 2
658,790.62 546,400,940.23
Bekisting Lt. 19
Zona 1
1 Bekisting Kolom 184.17 m2 161,937.29 29,823,990.70
2 Bekisting Balok 353.6 m 2
161,937.29 57,261,025.74
3 Bekisting Plat Lantai 867.1 m 2
161,937.29 140,415,824.16
Bekisting Lt. 20
Zona 1
1 Bekisting Kolom 177.67 m2 472,226.22 83,900,432.51
2 Bekisting Balok 331.37 m2 482,446.31 159,868,233.74
3 Bekisting Plat Lantai 829.4 m 2
658,790.62 546,400,940.23
Bekisting Lt. 21
Zona 1
1 Bekisting Kolom 177.67 m2 161,937.29 28,771,398.31
2 Bekisting Balok 331.37 m 2
161,937.29 53,661,159.79
3 Bekisting Plat Lantai 829.4 m 2
161,937.29 134,310,788.33
Bekisting Lt. 23
Zona 1
1 Bekisting Kolom 177.67 m2 472,226.22 83,900,432.51
2 Bekisting Balok 331.37 m 2
482,446.31 159,868,233.74
3 Bekisting Plat Lantai 829.4 m 2
658,790.62 546,400,940.23
Bekisting Lt. 25
Zona 1
1 Bekisting Kolom 177.67 m2 161,937.29 28,771,398.31
2 Bekisting Balok 331.37 m 2
161,937.29 53,661,159.79
3 Bekisting Plat Lantai 829.4 m 2
161,937.29 134,310,788.33
Bekisting Roof
Zona 1
1 Bekisting Kolom
2 Bekisting Balok 325.94 m2 482,446.31 157,248,550.28
3 Bekisting Plat Lantai 791.7 m 2
658,790.62 521,564,533.85
15,139,593,146

Rp4,110,080,000 Lantai
Rp1,575,600,000 1
Rp858,000,000 2
Rp6,543,680,000 ### 3
4
Rp16,217,477,183.33 5
6
7
8
9
10
11
12

Lantai

13
14
15
16
17
18
19
20
21
22
23
24
No Uraian Pekerjaan Luas (m2) Sat

Bekisting Lt. 3

Zona 1
1 Bekisting Kolom 288.01 m2
2 Bekisting Balok - m2
3 Bekisting Plat Lantai - m2
Zona 2
1 Bekisting Kolom 298.45 m2
2 Bekisting Balok - m2
3 Bekisting Plat Lantai - m2
Bekisting Lt. 5
Zona 1
1 Bekisting Kolom 286.1 m2
2 Bekisting Balok 408.78 m2
3 Bekisting Plat Lantai 862.85 m2
Zona 2
1 Bekisting Kolom 293.29 m2
2 Bekisting Balok 403.85 m2
3 Bekisting Plat Lantai 737.76 m2
Bekisting Lt. 6
Zona 1
1 Bekisting Kolom 282.36 m2
2 Bekisting Balok 408.78 m2
3 Bekisting Plat Lantai 862.85 m2
Zona 2
1 Bekisting Kolom 200.29 m2
2 Bekisting Balok 403.85 m2
3 Bekisting Plat Lantai 737.76 m2
Bekisting Lt. 7 0
Zona 1 0
1 Bekisting Kolom 282.36 m2
2 Bekisting Balok 400.78 m2
3 Bekisting Plat Lantai 887.98 m2
Zona 2
1 Bekisting Kolom 200.29 m2
2 Bekisting Balok 393.52 m2
3 Bekisting Plat Lantai 737.76 m2
Bekisting Lt. 8
Zona 1
1 Bekisting Kolom 282.36 m2
2 Bekisting Balok 400.78 m2
3 Bekisting Plat Lantai 887.98 m2
Zona 2
1 Bekisting Kolom 200.29 m2
2 Bekisting Balok 393.52 m2
3 Bekisting Plat Lantai 737.76 m2
Bekisting Lt. 9
Zona 1
1 Bekisting Kolom 282.36 m2
2 Bekisting Balok 400.78 m2
3 Bekisting Plat Lantai 887.98 m2
Zona 2
1 Bekisting Kolom 200.29 m2
2 Bekisting Balok 393.52 m2
3 Bekisting Plat Lantai 737.76 m2
Bekisting Lt. 10
Zona 1
1 Bekisting Kolom 200.36 m2
2 Bekisting Balok 301.35 m2
3 Bekisting Plat Lantai 925.97 m2
Zona 2
1 Bekisting Kolom 254.18 m2
2 Bekisting Balok 337.52 m2
3 Bekisting Plat Lantai 661.78 m2
Bekisting Lt. 11
Zona 1
1 Bekisting Kolom 200.36 m2
2 Bekisting Balok 301.35 m2
3 Bekisting Plat Lantai 925.97 m2
Zona 2
1 Bekisting Kolom 254.18 m2
2 Bekisting Balok 337.52 m2
3 Bekisting Plat Lantai 661.78 m2
Bekisting Lt. 12
Zona 1
1 Bekisting Kolom 200.36 m2
2 Bekisting Balok 301.35 m2
3 Bekisting Plat Lantai 925.97 m2
Zona 2
1 Bekisting Kolom 254.18 m2
2 Bekisting Balok 337.52 m2
3 Bekisting Plat Lantai 661.78 m2
Bekisting Lt. 15
Zona 1
1 Bekisting Kolom 200.36 m2
2 Bekisting Balok 301.35 m2
3 Bekisting Plat Lantai 925.97 m2
Zona 2
1 Bekisting Kolom 254.18 m2
2 Bekisting Balok 337.52 m2
3 Bekisting Plat Lantai 661.78 m2
Bekisting Lt. 16
Zona 1
1 Bekisting Kolom 183.36 m2
2 Bekisting Balok 271.35 m2
3 Bekisting Plat Lantai 584.97 m2
Zona 2
1 Bekisting Kolom 149.13 m2
2 Bekisting Balok 278.31 m2
3 Bekisting Plat Lantai 791.7 m2
Bekisting Lt. 17
Zona 1
1 Bekisting Kolom 152.57 m2
2 Bekisting Balok 271.35 m2
3 Bekisting Plat Lantai 510.98 m2
Zona 2
1 Bekisting Kolom 150.73 m2
2 Bekisting Balok 278.31 m2
3 Bekisting Plat Lantai 791.7 m2
Bekisting Lt. 18
Zona 1
1 Bekisting Kolom 177.67 m2
2 Bekisting Balok 331.37 m2
3 Bekisting Plat Lantai 829.4 m2
Bekisting Lt. 19
Zona 1
1 Bekisting Kolom 184.17 m2
2 Bekisting Balok 353.6 m2
3 Bekisting Plat Lantai 867.1 m2
Bekisting Lt. 20
Zona 1
1 Bekisting Kolom 177.67 m2
2 Bekisting Balok 331.37 m2
3 Bekisting Plat Lantai 829.4 m2
Bekisting Lt. 21
Zona 1
1 Bekisting Kolom 177.67 m2
2 Bekisting Balok 331.37 m2
3 Bekisting Plat Lantai 829.4 m2
Bekisting Lt. 23
Zona 1
1 Bekisting Kolom 177.67 m2
2 Bekisting Balok 331.37 m2
3 Bekisting Plat Lantai 829.4 m2
Bekisting Lt. 25
Zona 1
1 Bekisting Kolom 177.67 m2
2 Bekisting Balok 331.37 m2
3 Bekisting Plat Lantai 829.4 m2
Bekisting Roof
Zona 1
1 Bekisting Kolom
2 Bekisting Balok 325.94 m2
3 Bekisting Plat Lantai 791.7 m2
TOTAL DURASI PEKERJAAN

deks kenaikan lantai ereksi pelat


1.000
1.000
1.000
1.000
1.000
1.000
1.000
1.018
1.037
1.055
1.075
1.094

Indeks
kenaikan
lantai
ereksi
pelat

1.114
1.134
1.155
1.176
1.197
1.219
1.241
1.264
1.287
1.31
1.334
1.358
Harga Satuan
Total Harga (Rp)
(Rp)

225,000.00 64,802,250.00

225,000.00 67,151,250.00

225,000.00 64,372,500.00
225,000.00 91,975,500.00
225,000.00 194,141,250.00

225,000.00 65,990,250.00
225,000.00 90,866,250.00
225,000.00 165,996,000.00

225,000.00 63,531,000.00
225,000.00 91,975,500.00
225,000.00 194,141,250.00

225,000.00 45,065,250.00
225,000.00 90,866,250.00
225,000.00 165,996,000.00

225,000.00 63,531,000.00
225,000.00 90,175,500.00
225,000.00 199,795,500.00

225,000.00 45,065,250.00
225,000.00 88,542,000.00
225,000.00 165,996,000.00

225,000.00 63,531,000.00
225,000.00 90,175,500.00
150,000.00 133,197,000.00
225,000.00 45,065,250.00
225,000.00 88,542,000.00
225,000.00 165,996,000.00

225,000.00 63,531,000.00
225,000.00 90,175,500.00
225,000.00 199,795,500.00

225,000.00 45,065,250.00
225,000.00 88,542,000.00
225,000.00 165,996,000.00

225,000.00 45,081,000.00
225,000.00 67,803,750.00
225,000.00 208,343,250.00

225,000.00 57,190,500.00
225,000.00 75,942,000.00
225,000.00 148,900,500.00

225,000.00 45,081,000.00
225,000.00 67,803,750.00
225,000.00 208,343,250.00

225,000.00 57,190,500.00
225,000.00 75,942,000.00
225,000.00 148,900,500.00

225,000.00 45,081,000.00
225,000.00 67,803,750.00
225,000.00 208,343,250.00

225,000.00 57,190,500.00
225,000.00 75,942,000.00
225,000.00 148,900,500.00

225,000.00 45,081,000.00
225,000.00 67,803,750.00
225,000.00 208,343,250.00

225,000.00 57,190,500.00
225,000.00 75,942,000.00
225,000.00 148,900,500.00

225,000.00 41,256,000.00
225,000.00 61,053,750.00
225,000.00 131,618,250.00

225,000.00 33,554,250.00
225,000.00 62,619,750.00
225,000.00 178,132,500.00

225,000.00 34,328,250.00
225,000.00 61,053,750.00
225,000.00 114,970,500.00

225,000.00 33,914,250.00
225,000.00 62,619,750.00
225,000.00 178,132,500.00

225,000.00 39,975,750.00
225,000.00 74,558,250.00
225,000.00 186,615,000.00

225,000.00 41,438,250.00
225,000.00 79,560,000.00
225,000.00 195,097,500.00

225,000.00 39,975,750.00
225,000.00 74,558,250.00
225,000.00 186,615,000.00

225,000.00 39,975,750.00
225,000.00 74,558,250.00
225,000.00 186,615,000.00

225,000.00 39,975,750.00
225,000.00 74,558,250.00
225,000.00 186,615,000.00
225,000.00 39,975,750.00
225,000.00 74,558,250.00
225,000.00 186,615,000.00

225,000.00 73,336,500.00
225,000.00 178,132,500.00
8,829,195,000.00
PERATURAN WALIKOTA MALANG
NOMOR :10 TAHUN 2023
TENTANG
HARGA SATUAN PEKERJAAN KONSTRUKSI

HARGA SATUAN BIAYA TENAGA KERJA

KODE URAIAN SATUAN HARGA 2022


L.01 Pekerja OH Rp 122,385
L.02 Tukang OH Rp 149,350
L.02.a Tukang kayu OH Rp 149,350
L.02.f Tukang Ereksi OH Rp 149,350
L.03 Kepala Tukang OH Rp 157,350
L.04 Mandor OH Rp 165,830
L.08.d Operator Tower Crane OH Rp 122,599
L.08.e Pembantu Operator Tower Crane OH Rp 122,599
L.08.f Operator Lift OH Rp 122,599

HARGA SATUAN BIAYA BAHAN BANGUNAN

KODE NAMA BAHAN SATUAN HARGA 2022


M.061.c Kayu Kaso 5 x 7 cm Kelas III m3 Rp 2,632,449
M.109.k paku 7 cm - 12 cm kg Rp 17,420
M.125 Triplek 3 mm lbr Rp 52,000
M.035 Besi hollow (50 x 50 x 3) mm kg Rp 14,560
M.119.d Baut Angkur kg Rp 24,336
M.120 Dinabolt Ø12 mm (10-15 cm) bh Rp 12,388
M.128.a Multiflex 12 mm lbr Rp 211,319
M.129.a Multiplex tebal 9mm lbr Rp 130,074
M.247 Lem kayu kg Rp 61,600
M.253.a Cat dasar kg Rp 45,677
M.253.h Cat dinding kg Rp 34,580
M.109.h Paku 5-12 cm kg Rp 17,420
M.284.a Agregat Kasar m3 Rp 196,106
M.284.j Agregat Halus m3 Rp 323,946

M.128 Multiflex 12 mm lbr Rp 211,319


M.061.c Balok Kayu Kls II m3 Rp 3,096,999
B.22 Bekisting m2 Rp 21,507
M.271 Lantai Kerja t= 10 cm m3 Rp 13,456,830
M.237.a Minyak Fluks lttr Rp 10,220
M.077.b Minyak Bekisting ltr Rp 4,749
M.263 Beton 1:2:3 m3 Rp 1,202,629
M.075.a PERALATAN btg Rp 42,401
M.264.i Beton K-400 m3 Rp 1,285,255
ANALISA HARGA SATUAN BEKISTING KONVENSIONAL
Pemasangan 1 m2 Bekisting untuk Kolom Bangunan Gedung (5x pakai)
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Harga Total (Rp)

A TENAGA KERJA
Pekerja L.01 OH 0.66 122,385.00 80,774.10
Tukang Kayu L.02 OH 0.33 149,350.00 49,285.50
Kepala Tukang L.03 OH 0.033 157,350.00 5,192.55
Mandor L.04 OH 0.033 122,599.00 4,045.77
JUMLAH HARGA TENAGA KERJA
B BAHAN
Papan Kayu kelas III M.061.c m3 0.040 2,632,449.00 105,297.96
Paku 5 cm – 12 cm M.109.h kg 0.400 17,420.00 6,968.00
Minyak bekisting M.077.b Liter 0.200 4,749.00 949.80
Balok kayu kelas II M.061.c m3 0.015 3,096,999.00 46,454.99
Multiplex tebal 9mm M.129.a Lbr 0.350 130,074.00 45,525.90
Dolken Kayu 8/10cm Panjang 4m M.075.a Batang 2.00 42,401.00 84,802.00
JUMLAH HARGA BAHAN
C PERALATAN -
-
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 429,296.56
F Biaya Umum dan Keuntungan 10% 42,929.66
G Harga Satuan Pekerjaan (E+F) 472,226.22

Pemasangan 1 m2 Bekisting untuk Balok Bangunan Gedung (5x pakai)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Harga Total (Rp)

A TENAGA KERJA
Pekerja L.01 OH 0.660 122,385.00 80,774.10
Tukang Kayu L.02 OH 0.330 149,350.00 49,285.50
Kepala Tukang L.03 OH 0.033 157,350.00 5,192.55
Mandor L.04 OH 0.033 122,599.00 4,045.77
JUMLAH HARGA TENAGA KERJA
B BAHAN
Papan Kayu kelas III M.061.c m3 0.040 2,632,449.00 105,297.96
Paku 5 cm – 12 cm M.109.h kg 0.400 17,420.00 6,968.00
Minyak bekisting M.077.b Liter 0.200 4,749.00 949.80
Balok kayu kelas II M.061.c m3 0.018 3,096,999.00 55,745.98
Multiplex tebal 9mm M.129.a Lbr 0.350 130,074.00 45,525.90
Dolken Kayu 8/10cm Panjang 4m M.075.a Batang 2 42,401.00 84,802.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 438,587.56
F Biaya Umum dan Keuntungan 10% 43,858.76
G Harga Satuan Pekerjaan (E+F) 482,446.31

Pemasangan 1 m2 Bekisting untuk Plat lantai Beton Bangunan Gedung (5x pakai)

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Harga Total (Rp)

A TENAGA KERJA
Pekerja L.01 OH 0.66 122,385.00 80,774.10
Tukang Kayu L.02 OH 0.33 149,350.00 49,285.50
Kepala Tukang L.03 OH 0.033 157,350.00 5,192.55
Mandor L.04 OH 0.033 122,599.00 4,045.77
JUMLAH HARGA TENAGA KERJA
B BAHAN
Kayu kelas III M.061.c m3 0.040 2,632,449.00 105,297.96
Paku 5 cm – 12 cm M.109.h kg 0.400 17,420.00 6,968.00
Minyak bekisting M.077.b Liter 0.200 4,749.00 949.80
Balok kayu kelas II M.061.c m3 0.015 3,096,999.00 46,454.99
Multiplex tebal 9mm M.129.a Lbr 0.350 130,074.00 45,525.90
Dolken Kayu 8/10cm Panjang 4m M.075.a Batang 6.000 42,401.00 254,406.00
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 598,900.56
F Biaya Umum dan Keuntungan 10% 59,890.06
G Harga Satuan Pekerjaan (E+F) 658,790.62
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Harga Total (Rp)

A TENAGA KERJA
Pekerja L.01 OH 0.660 122,385.00 80,774.10
Tukang Kayu L.02 OH 0.330 149,350.00 49,285.50
Kepala Tukang L.03 OH 0.033 157,350.00 5,192.55
Mandor L.04 OH 0.033 122,599.00 4,045.77
JUMLAH HARGA TENAGA KERJA
B BAHAN
Minyak bekisting M.077.b Liter 0.200 4,749.00 949.80
Paku 5 cm – 12 cm M.077.b kg 0.400 17,420.00 6,968.00
JUMLAH HARGA BAHAN
C PERALATAN -
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 147,215.72
F Biaya Umum dan Keuntungan 10% 14,721.57
G Harga Satuan Pekerjaan (E+F) 161,937.29

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Harga Total (Rp)

A TENAGA KERJA
Pekerja L.01 OH 0.660 122,385.00 80,774.10
Tukang Kayu L.02 OH 0.330 149,350.00 49,285.50
Kepala Tukang L.03 OH 0.033 157,350.00 5,192.55
Mandor L.04 OH 0.033 122,599.00 4,045.77
JUMLAH HARGA TENAGA KERJA
B BAHAN
Minyak bekisting M.077.b Liter 0.200 4,749 949.80
Paku 5 cm – 12 cm M.077.b kg 0.400 17,420 6,968.00
JUMLAH HARGA BAHAN
C PERALATAN -
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 147,215.72
F Biaya Umum dan Keuntungan 10% 14,721.57
G Harga Satuan Pekerjaan (E+F) 161,937.29

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Harga Total (Rp)

A TENAGA KERJA
Pekerja L.01 OH 0.660 122,385.00 80,774.10
Tukang Kayu L.02 OH 0.330 149,350.00 49,285.50
Kepala Tukang L.03 OH 0.033 157,350.00 5,192.55
Mandor L.04 OH 0.033 122,599.00 4,045.77
JUMLAH HARGA TENAGA KERJA
B BAHAN
Minyak bekisting M.077.b Liter 0.2 4,749 949.80
Paku 5 cm – 12 cm M.077.b kg 0.4 17,420 6,968.00
JUMLAH HARGA BAHAN
C PERALATAN -
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 147,215.72
F Biaya Umum dan Keuntungan 10% 14,721.57
G Harga Satuan Pekerjaan (E+F) 161,937.29
ESTIMASI WAKTU PEKERJAAN KOLOM,
BALOK, DAN PLAT LANTAI METODE SISTEM (PERI)
PERSIAPAN =
PASANG BEKISTING BALOK DAN PLAT = 1 HARI SETELAH BONGKAR
BEKISTING KOLOM
BONGKAR BEKISTING BALOK = 7 HARI SETELAH COR
BONGKAR BEKISTING PLAT = 7 HARI SETELAH COR
BONGKAR PIPE SUPPORT BALOK = 14 HARI SETELAH COR
BONGKAR PIPE SUPPORT PLAT = 14 HARI SETELAH COR
BONGKAR BEKISTING KOLOM = 1 HARI SETELAH COR
68.250
COR 506
PASANG BESI 503
BEKISTING PLAT 503 516

3.150
REPROPING PLAT 516 523
BEKISTING BALOK 503 516
REPROPING BALOK 516 523
LT. ROOF
65.100
COR 501
PASANG BESI 498
BEKISTING KOLOM 498 502
REPROPING KOLOM 502 502
COR 480

3.150
PASANG BESI 477
BEKISTING PLAT 477 490
REPROPING PLAT 490 497
BEKISTING BALOK 477 490
REPROPING BALOK 490 497
LT. 25
COR 475 61.950
PASANG BESI 472
BEKISTING KOLOM 472 476
REPROPING KOLOM 476 476
COR 454

3.150
PASANG BESI 451
BEKISTING PLAT 451 464
REPROPING PLAT 464 471
BEKISTING BALOK 451 464
REPROPING BALOK 464 471
LT.23 58.800
COR 449
PASANG BESI 446
BEKISTING KOLOM 446 450
REPROPING KOLOM 450 450
COR 428
3.150

PASANG BESI 425


BEKISTING PLAT 425 438
REPROPING PLAT 438 445
BEKISTING BALOK 425 438
REPROPING BALOK 438 445
LT.21 55.650
COR 423
PASANG BESI 420
BEKISTING KOLOM 420 424
REPROPING KOLOM 424 424
COR 402
3.650

PASANG BESI 399


BEKISTING PLAT 399 412
REPROPING PLAT 412 419
BEKISTING BALOK 399 412
REPROPING BALOK 412 419
LT.20 52.000
COR 397
PASANG BESI 394
2.650
BEKISTING KOLOM 394 398
REPROPING KOLOM 398 398
COR 376

2.650
PASANG BESI 373
BEKISTING PLAT 373 386
REPROPING PLAT 386 393
BEKISTING BALOK 373 386
REPROPING BALOK 386 393
LT.19 49.350
COR 371
PASANG BESI 368
BEKISTING KOLOM 368 372
REPROPING KOLOM 372 372
COR 350

3.150
PASANG BESI 347
BEKISTING PLAT 347 360
REPROPING PLAT 360 367
BEKISTING BALOK 347 360
REPROPING BALOK 360 367
LT.18 46.200
COR 344 339
PASANG BESI 341 337
BEKISTING KOLOM 341 346 337 341
REPROPING KOLOM 346 346 341 341
COR 323 319

3.150
PASANG BESI 316 312
BEKISTING PLAT 316 333 312 329
REPROPING PLAT 333 340 329 336
BEKISTING BALOK 316 333 312 329
REPROPING BALOK 333 340 329 336
LT.17 43.050
COR 313 309
PASANG BESI 310 307
BEKISTING KOLOM 310 315 307 311
REPROPING KOLOM 315 315 311 311
COR 292 289

3.150
PASANG BESI 285 282
BEKISTING PLAT 285 302 282 299
REPROPING PLAT 302 309 299 306
BEKISTING BALOK 285 302 282 299
REPROPING BALOK 302 309 299 306
LT.16 39.900
COR 282 279
PASANG BESI 279 277
BEKISTING KOLOM 279 284 277 281
REPROPING KOLOM 284 284 281 281
COR 261 259
3.150

PASANG BESI 254 252


BEKISTING PLAT 254 271 252 269
REPROPING PLAT 271 278 269 276
BEKISTING BALOK 254 271 252 269
REPROPING BALOK 271 278 269 276
LT.15 36.750
COR 251 249
PASANG BESI 248 247
BEKISTING KOLOM 248 253 247 251
REPROPING KOLOM 253 253 251 251
COR 230 229
3.150

PASANG BESI 223 222


BEKISTING PLAT 223 240 222 239
REPROPING PLAT 240 247 239 246
BEKISTING BALOK 223 240 222 239
REPROPING BALOK 240 247 239 246
LT.12 33.600
COR 220 219
PASANG BESI 217 217
3.150
BEKISTING KOLOM 217 222 217 221
REPROPING KOLOM 222 222 221 221
COR 199 199

3.150
PASANG BESI 192 192
BEKISTING PLAT 192 209 192 209
REPROPING PLAT 209 216 209 216
BEKISTING BALOK 192 209 192 209
REPROPING BALOK 209 216 209 216
LT.11 30.450
COR 189 189
PASANG BESI 186 187
BEKISTING KOLOM 186 191 187 191
REPROPING KOLOM 191 191 191 191
COR 168 169

3.150
PASANG BESI 161 162
BEKISTING PLAT 161 178 162 179
REPROPING PLAT 178 185 179 186
BEKISTING BALOK 161 178 162 179
REPROPING BALOK 178 185 179 186
LT.10 27.300
COR 158 159
PASANG BESI 155 157
BEKISTING KOLOM 155 160 157 161
REPROPING KOLOM 160 160 161 161
COR 137 139

3.150
PASANG BESI 130 132
BEKISTING PLAT 130 147 132 149
REPROPING PLAT 147 154 149 156
BEKISTING BALOK 130 147 132 149
REPROPING BALOK 147 154 149 156
LT.9 24.150
COR 127 129
PASANG BESI 124 127
BEKISTING KOLOM 124 129 127 131
REPROPING KOLOM 129 129 131 131
COR 106 109

3.150
PASANG BESI 99 102
BEKISTING PLAT 99 116 102 119
REPROPING PLAT 116 123 119 126
BEKISTING BALOK 99 116 102 119
REPROPING BALOK 116 123 119 126
LT.8 21.000
COR 96 99
PASANG BESI 93 97
BEKISTING KOLOM 93 98 97 101
REPROPING KOLOM 98 98 101 101
COR 75 79
3.150

PASANG BESI 68 72
BEKISTING PLAT 68 85 72 89
REPROPING PLAT 85 92 89 96
BEKISTING BALOK 68 85 72 89
REPROPING BALOK 85 92 89 96
LT.7 17.850
COR 65 69
PASANG BESI 62 67
BEKISTING KOLOM 62 67 67 71
REPROPING KOLOM 67 67 71 71
COR 44 49
3.150

PASANG BESI 37 42
BEKISTING PLAT 37 54 42 59
REPROPING PLAT 54 61 59 66
BEKISTING BALOK 37 54 42 59
REPROPING BALOK 54 61 59 66
LT.6 14.700
COR 34 39
PASANG BESI 31 37
3.150
BEKISTING KOLOM 31 36 37 41
REPROPING KOLOM 36 36 41 41
COR 13 19

3.150
PASANG BESI 6 12
BEKISTING PLAT 6 23 12 29
REPROPING PLAT 23 30 29 36
BEKISTING BALOK 6 23 12 29
REPROPING BALOK 23 30 29 36

LT.5 11.550
COR Hari ke- 3 Hari ke- 9
PASANG BESI Hari ke- 1 Hari ke- 6

3.150
BEKISTING KOLOM Hari ke- 1 5 Hari ke- 6 11
REPROPING KOLOM Hari ke- 5 5 Hari ke- 11 11
COR LT.3
BEKISTING PLAT 8.400

ZONA 1 ZONA 2
ESTIMASI WAKTU PEKERJAAN KOLOM,
BALOK, DAN PLAT LANTAI METODE KONVENSONAL

PERSIAPAN =
PASANG BEKISTING BALOK DAN PLAT = 1 HARI SETELAH BONGKAR
BEKISTING KOLOM
BONGKAR BEKISTING KOLOM = 1 HARI SETELAH COR

68.250
COR
PASANG BESI

3.150
BEKISTING PLAT
BEKISTING BALOK
LT. ROOF
65.100
COR
PASANG BESI
BEKISTING KOLOM

3.150
COR
PASANG BESI
BEKISTING PLAT
BEKISTING BALOK
LT. 25
61.950
COR
PASANG BESI
BEKISTING KOLOM

3.150
COR
PASANG BESI
BEKISTING PLAT
BEKISTING BALOK
LT.23
58.800
COR
PASANG BESI
BEKISTING KOLOM

3.150
COR
PASANG BESI
BEKISTING PLAT
BEKISTING BALOK
LT.21
55.650
COR
PASANG BESI
BEKISTING KOLOM
3.650

COR
PASANG BESI
BEKISTING PLAT
BEKISTING BALOK
LT.20
52.000
COR
PASANG BESI
BEKISTING KOLOM
2.650

COR
PASANG BESI
BEKISTING PLAT
BEKISTING BALOK
LT.19
49.350
COR
PASANG BESI
BEKISTING KOLOM
3.150

COR
3.150
PASANG BESI
BEKISTING PLAT
BEKISTING BALOK
LT.18
46.200
COR
PASANG BESI
BEKISTING KOLOM

3.150
COR
PASANG BESI
BEKISTING PLAT
BEKISTING BALOK
LT.17
43.050
COR
PASANG BESI
BEKISTING KOLOM

3.150
COR
PASANG BESI
BEKISTING PLAT
BEKISTING BALOK
LT.16
39.900
COR
PASANG BESI
BEKISTING KOLOM

3.150
COR
PASANG BESI
BEKISTING PLAT
BEKISTING BALOK
LT.15
36.750
COR
PASANG BESI
BEKISTING KOLOM

3.150
COR
PASANG BESI
BEKISTING PLAT
BEKISTING BALOK
LT.12
33.600
COR
PASANG BESI
BEKISTING KOLOM
3.150

COR
PASANG BESI
BEKISTING PLAT
BEKISTING BALOK
LT.11
COR 30.450
PASANG BESI
BEKISTING KOLOM
COR
3.150

PASANG BESI
BEKISTING PLAT
BEKISTING BALOK
LT.10
COR 27.300
PASANG BESI
BEKISTING KOLOM
COR
3.150

PASANG BESI
BEKISTING PLAT
BEKISTING BALOK
LT.9
COR 24.150
PASANG BESI
BEKISTING KOLOM
COR

3.150
PASANG BESI
BEKISTING PLAT
BEKISTING BALOK
LT.8
COR 21.000
PASANG BESI
BEKISTING KOLOM
COR

3.150
PASANG BESI
BEKISTING PLAT
BEKISTING BALOK
LT.7
COR 17.850
PASANG BESI
BEKISTING KOLOM
COR

3.150
PASANG BESI
BEKISTING PLAT
BEKISTING BALOK
LT.6
COR 14.700
PASANG BESI
BEKISTING KOLOM
COR

3.150
PASANG BESI
BEKISTING PLAT
BEKISTING BALOK
LT.5
11.550
COR Hari Hari
PASANG BESI Hari Hari

3.150
BEKISTING KOLOM Hari 1 Hari
REPROPING KOLOM Hari Hari
COR LT.3
BEKISTING PLAT 8.400
REPROPING PLAT
Bongkar

Bongkar
Pasang

Pasang

BEKISTING BALOK
REPROPING BALOK

ZONA 1 ZONA 2
LUAS BEKISTING
No LANTAI SAT
KOLOM BALOK PELAT
1 Lantai 3 m2 586.46 - -
2 Lantai5 m2 482.65 812.63 1,600.61
3 Lantai 6 m2 482.65 812.63 1,600.61
4 Lantai7 m2 482.65 794.30 1,625.74
5 Lantai8 m2 482.65 794.30 1,625.74
6 Lantai9 m2 482.65 794.30 1,625.74
7 Lantai10 m2 454.54 638.87 1,587.75
8 Lantai11 m2 454.54 638.87 1,587.75
9 Lantai12 m2 454.54 638.87 1,587.75
10 Lantai 15 m2 454.54 638.87 1,587.75
11 Lantai 16 m2 332.49 549.66 1,376.67
12 Lantai 17 m2 303.3 549.66 1,302.68
13 Lantai 18 m2 177.67 331.37 829.40
14 Lantai 19 m2 184.17 353.6 867.10
15 Lantai 20 m2 177.67 331.37 829.40
16 Lantai 21 m2 177.67 331.37 829.40
17 Lantai 23 m2 177.67 331.37 829.40
18 Lantai 25 m2 177.67 331.37 829.40
19 Lantai Roof m² 325.94 791.70
Total: 6,526.18 9,999.35 22,914.59
PENJABARAN PERHITUNGAN ESTIMASI WAKTU PENGGUNAAN BEKISTING KOLOM METODE KONVENSIONAL
Waktu Waktu
No Uraian
(hari) (Jam)
A Pekerjaan bekisting Lantai 3
1 Kolom
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
3.17 25.34
Luas = 288.01 X 0.66 Luas = 288.01 X 0.33 Luas = 288.01 X 0.033 Luas = 288.01 X 0.033
= 190.09 OH = 95.04 OH = 9.50 OH = 9.50 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 190.09 / 60 DP = 95.04 / 30 DP = 9.50 / 3 DP = 9.50 / 3
= 3.17 hari = 3.17 hari = 3.17 hari = 3.17 hari
= 3.17 X 8 = 3.17 X 8 = 3.17 X 8 = 3.17 X 8
= 25.34 jam = 25.34 jam = 25.34 jam = 25.34 jam
Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 298.45 X 0.66 Luas = 298.45 X 0.33 Luas = 298.45 X 0.033 Luas = 298.45 X 0.033
3.28 26.26
= 196.98 OH = 98.49 OH = 9.85 OH = 9.85 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 196.98 / 60 DP = 98.49 / 30 DP = 9.85 / 3 DP = 9.85 / 3
= 3.28 hari = 3.28 hari = 3.28 hari = 3.28 hari
= 3.28 X 8 = 3.28 X 8 = 3.28 X 8 = 3.28 X 8
= 26.26 jam = 26.26 jam = 26.26 jam = 26.26 jam

B Pekerjaan bekisting Lantai 5 6.45 51.61


1 Kolom
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 286.10 X 0.66 Luas = 286.10 X 0.33 Luas = 286.10 X 0.033 Luas = 286.10 X 0.033 3.15 25.18
= 188.83 OH = 94.41 OH = 9.44 OH = 9.44 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 188.83 / 60 DP = 94.41 / 30 DP = 9.44 / 3 DP = 9.44 / 3
= 3.15 hari = 3.15 hari = 3.15 hari = 3.15 hari
= 3.15 X 8 = 3.15 X 8 = 3.15 X 8 = 3.15 X 8
= 25.18 jam = 25.18 jam = 25.18 jam = 25.18 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 196.55 X 0.66 Luas = 196.55 X 0.33 Luas = 196.55 X 0.033 Luas = 196.55 X 0.033 2.16 17.30
= 129.72 OH = 64.86 OH = 6.49 OH = 6.49 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 129.72 / 60 DP = 64.86 / 30 DP = 6.49 / 3 DP = 6.49 / 3
= 2.16 hari = 2.16 hari = 2.16 hari = 2.16 hari
= 2.16 X 8 = 2.16 X 8 = 2.16 X 8 = 2.16 X 8
= 17.30 jam = 17.30 jam = 17.30 jam = 17.30 jam
2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 408.78 X 0.66 Luas = 408.78 X 0.33 Luas = 408.78 X 0.033 Luas = 408.78 X 0.033 4.50 35.97
= 269.79 OH = 134.90 OH = 13.49 OH = 13.49 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 269.79 / 60 DP = 134.90 / 30 DP = 13.49 / 3 DP = 13.49 / 3
= 4.50 hari = 4.50 hari = 4.50 hari = 4.50 hari
= 4.50 X 8 = 4.50 X 8 = 4.50 X 8 = 4.50 X 8
= 35.97 jam = 35.97 jam = 35.97 jam = 35.97 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 403.85 X 0.66 Luas = 403.85 X 0.33 Luas = 403.85 X 0.033 Luas = 403.85 X 0.033 4.44 35.54
= 266.54 OH = 133.27 OH = 13.33 OH = 13.33 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 266.54 / 60 DP = 133.27 / 30 DP = 13.33 / 3 DP = 13.33 / 3
= 4.44 hari = 4.44 hari = 4.44 hari = 4.44 hari
= 4.44 X 8 = 4.44 X 8 = 4.44 X 8 = 4.44 X 8
4.44 35.54

= 35.54 jam = 35.54 jam = 35.54 jam = 35.54 jam


3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 862.85 X 0.66 Luas = 862.85 X 0.33 Luas = 862.85 X 0.033 Luas = 862.85 X 0.033 9.49 75.93
= 569.48 OH = 284.74 OH = 28.47 OH = 28.47 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 569.48 / 60 DP = 284.74 / 30 DP = 28.47 / 3 DP = 28.47 / 3
= 9.49 hari = 9.49 hari = 9.49 hari = 9.49 hari
= 9.49 X 8 = 9.49 X 8 = 9.49 X 8 = 9.49 X 8
= 75.93 jam = 75.93 jam = 75.93 jam = 75.93 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 737.76 X 0.66 Luas = 737.76 X 0.33 Luas = 737.76 X 0.033 Luas = 737.76 X 0.033
= 486.92 OH = 243.46 OH = 24.35 OH = 24.35 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan 8.12
64.92
DP = 486.92 / 60 DP = 243.46 / 30 DP = 24.35 / 3 DP = 24.35 / 3
= 8.12 hari = 8.12 hari = 8.12 hari = 8.12 hari
= 8.12 X 8 = 8.12 X 8 = 8.12 X 8 = 8.12 X 8
= 64.92 jam = 64.92 jam = 64.92 jam = 64.92 jam

C Pekerjaan bekisting Lantai 6


1 Kolom
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 282.36 X 0.66 Luas = 282.36 X 0.33 Luas = 282.36 X 0.033 Luas = 282.36 X 0.033 3.11 24.85
= 186.36 OH = 93.18 OH = 9.32 OH = 9.32 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 186.36 / 60 DP = 93.18 / 30 DP = 9.32 / 3 DP = 9.32 / 3
= 3.11 hari = 3.11 hari = 3.11 hari = 3.11 hari
= 3.11 X 8 = 3.11 X 8 = 3.11 X 8 = 3.11 X 8
= 24.85 jam = 24.85 jam = 24.85 jam = 24.85 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 200.29 X 0.66 Luas = 200.29 X 0.33 Luas = 200.29 X 0.033 Luas = 200.29 X 0.033
= 132.19 OH = 66.10 OH = 6.61 OH = 6.61 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 132.19 / 60 DP = 66.10 / 30 DP = 6.61 / 3 DP = 6.61 / 3
= 2.20 hari = 2.20 hari = 2.20 hari = 2.20 hari
= 2.20 X 8 = 2.20 X 8 = 2.20 X 8 = 2.20 X 8
= 17.63 jam = 17.63 jam = 17.63 jam = 17.63 jam
2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 408.78 X 0.66 Luas = 408.78 X 0.33 Luas = 408.78 X 0.033 Luas = 408.78 X 0.033 4.50 35.97
= 269.79 OH = 134.90 OH = 13.49 OH = 13.49 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 269.79 / 60 DP = 134.90 / 30 DP = 13.49 / 3 DP = 13.49 / 3
= 4.50 hari = 4.50 hari = 4.50 hari = 4.50 hari
= 4.50 X 8 = 4.50 X 8 = 4.50 X 8 = 4.50 X 8
= 35.97 jam = 35.97 jam = 35.97 jam = 35.97 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 403.85 X 0.66 Luas = 403.85 X 0.33 Luas = 403.85 X 0.033 Luas = 403.85 X 0.033
= 266.54 OH = 133.27 OH = 13.33 OH = 13.33 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 266.54 / 60 DP = 133.27 / 30 DP = 13.33 / 3 DP = 13.33 / 3
= 4.44 hari = 4.44 hari = 4.44 hari = 4.44 hari
= 4.44 X 8 = 4.44 X 8 = 4.44 X 8 = 4.44 X 8
= 35.54 jam = 35.54 jam = 35.54 jam = 35.54 jam
3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 862.85 X 0.66 Luas = 862.85 X 0.33 Luas = 862.85 X 0.033 Luas = 862.85 X 0.033 9.49 75.93
= 569.48 OH = 284.74 OH = 28.47 OH = 28.47 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 569.48 / 60 DP = 284.74 / 30 DP = 28.47 / 3 DP = 28.47 / 3
= 9.49 hari = 9.49 hari = 9.49 hari = 9.49 hari
= 9.49 X 8 = 9.49 X 8 = 9.49 X 8 = 9.49 X 8
= 75.93 jam = 75.93 jam = 75.93 jam = 75.93 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 737.76 X 0.66 Luas = 737.76 X 0.33 Luas = 737.76 X 0.033 Luas = 737.76 X 0.033
= 486.92 OH = 243.46 OH = 24.35 OH = 24.35 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 486.92 / 60 DP = 243.46 / 30 DP = 24.35 / 3 DP = 24.35 / 3
= 8.12 hari = 8.12 hari = 8.12 hari = 8.12 hari
= 8.12 X 8 = 8.12 X 8 = 8.12 X 8 = 8.12 X 8
= 64.92 jam = 64.92 jam = 64.92 jam = 64.92 jam

D Pekerjaan bekisting Lantai 7


1 Kolom
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 282.36 X 0.66 Luas = 282.36 X 0.33 Luas = 282.36 X 0.033 Luas = 282.36 X 0.033 3.11 24.85
= 186.36 OH = 93.18 OH = 9.32 OH = 9.32 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 186.36 / 60 DP = 93.18 / 30 DP = 9.32 / 3 DP = 9.32 / 3
= 3.11 hari = 3.11 hari = 3.11 hari = 3.11 hari
= 3.11 X 8 = 3.11 X 8 = 3.11 X 8 = 3.11 X 8
= 24.85 jam = 24.85 jam = 24.85 jam = 24.85 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 200.29 X 0.66 Luas = 200.29 X 0.33 Luas = 200.29 X 0.033 Luas = 200.29 X 0.033
= 132.19 OH = 66.10 OH = 6.61 OH = 6.61 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 132.19 / 60 DP = 66.10 / 30 DP = 6.61 / 3 DP = 6.61 / 3
= 2.20 hari = 2.20 hari = 2.20 hari = 2.20 hari
= 2.20 X 8 = 2.20 X 8 = 2.20 X 8 = 2.20 X 8
= 17.63 jam = 17.63 jam = 17.63 jam = 17.63 jam
2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 408.78 X 0.66 Luas = 408.78 X 0.33 Luas = 408.78 X 0.033 Luas = 408.78 X 0.033 4.50 35.97
= 269.79 OH = 134.90 OH = 13.49 OH = 13.49 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 269.79 / 60 DP = 134.90 / 30 DP = 13.49 / 3 DP = 13.49 / 3
= 4.50 hari = 4.50 hari = 4.50 hari = 4.50 hari
= 4.50 X 8 = 4.50 X 8 = 4.50 X 8 = 4.50 X 8
= 35.97 jam = 35.97 jam = 35.97 jam = 35.97 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 393.52 X 0.66 Luas = 393.52 X 0.33 Luas = 393.52 X 0.033 Luas = 393.52 X 0.033
= 259.72 OH = 129.86 OH = 12.99 OH = 12.99 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 259.72 / 60 DP = 129.86 / 30 DP = 12.99 / 3 DP = 12.99 / 3
= 4.33 hari = 4.33 hari = 4.33 hari = 4.33 hari
= 4.33 X 8 = 4.33 X 8 = 4.33 X 8 = 4.33 X 8
= 34.63 jam = 34.63 jam = 34.63 jam = 34.63 jam
3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 887.98 X 0.66 Luas = 887.98 X 0.33 Luas = 887.98 X 0.033 Luas = 887.98 X 0.033 9.77 78.14
= 586.07 OH = 293.03 OH = 29.30 OH = 29.30 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 586.07 / 60 DP = 293.03 / 30 DP = 29.30 / 3 DP = 29.30 / 3
= 9.77 hari = 9.77 hari = 9.77 hari = 9.77 hari
= 9.77 X 8 = 9.77 X 8 = 9.77 X 8 = 9.77 X 8
= 78.14 jam = 78.14 jam = 78.14 jam = 78.14 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 737.76 X 0.66 Luas = 737.76 X 0.33 Luas = 737.76 X 0.033 Luas = 737.76 X 0.033
= 486.92 OH = 243.46 OH = 24.35 OH = 24.35 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 486.92 / 60 DP = 243.46 / 30 DP = 24.35 / 3 DP = 24.35 / 3
= 8.12 hari = 8.12 hari = 8.12 hari = 8.12 hari
= 8.12 X 8 = 8.12 X 8 = 8.12 X 8 = 8.12 X 8
= 64.92 jam = 64.92 jam = 64.92 jam = 64.92 jam

E Pekerjaan bekisting Lantai 8


1 Kolom
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 282.36 X 0.66 Luas = 282.36 X 0.33 Luas = 282.36 X 0.033 Luas = 282.36 X 0.033 3.11 24.85
= 186.36 OH = 93.18 OH = 9.32 OH = 9.32 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 186.36 / 60 DP = 93.18 / 30 DP = 9.32 / 3 DP = 9.32 / 3
= 3.11 hari = 3.11 hari = 3.11 hari = 3.11 hari
= 3.11 X 8 = 3.11 X 8 = 3.11 X 8 = 3.11 X 8
= 24.85 jam = 24.85 jam = 24.85 jam = 24.85 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 200.29 X 0.66 Luas = 200.29 X 0.33 Luas = 200.29 X 0.033 Luas = 200.29 X 0.033
= 132.19 OH = 66.10 OH = 6.61 OH = 6.61 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 132.19 / 60 DP = 66.10 / 30 DP = 6.61 / 3 DP = 6.61 / 3
= 2.20 hari = 2.20 hari = 2.20 hari = 2.20 hari
= 2.20 X 8 = 2.20 X 8 = 2.20 X 8 = 2.20 X 8
= 17.63 jam = 17.63 jam = 17.63 jam = 17.63 jam
2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 400.78 X 0.66 Luas = 400.78 X 0.33 Luas = 400.78 X 0.033 Luas = 400.78 X 0.033 4.41 35.27
= 264.51 OH = 132.26 OH = 13.23 OH = 13.23 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 264.51 / 60 DP = 132.26 / 30 DP = 13.23 / 3 DP = 13.23 / 3
= 4.41 hari = 4.41 hari = 4.41 hari = 4.41 hari
= 4.41 X 8 = 4.41 X 8 = 4.41 X 8 = 4.41 X 8
= 35.27 jam = 35.27 jam = 35.27 jam = 35.27 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 393.52 X 0.66 Luas = 393.52 X 0.33 Luas = 393.52 X 0.033 Luas = 393.52 X 0.033
= 259.72 OH = 129.86 OH = 12.99 OH = 12.99 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 259.72 / 60 DP = 129.86 / 30 DP = 12.99 / 3 DP = 12.99 / 3
= 4.33 hari = 4.33 hari = 4.33 hari = 4.33 hari
= 4.33 X 8 = 4.33 X 8 = 4.33 X 8 = 4.33 X 8
= 34.63 jam = 34.63 jam = 34.63 jam = 34.63 jam
3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 887.98 X 0.66 Luas = 887.98 X 0.33 Luas = 887.98 X 0.033 Luas = 887.98 X 0.033 9.77 78.14
9.77 78.14
= 586.07 OH = 293.03 OH = 29.30 OH = 29.30 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 586.07 / 60 DP = 293.03 / 30 DP = 29.30 / 3 DP = 29.30 / 3
= 9.77 hari = 9.77 hari = 9.77 hari = 9.77 hari
= 9.77 X 8 = 9.77 X 8 = 9.77 X 8 = 9.77 X 8
= 78.14 jam = 78.14 jam = 78.14 jam = 78.14 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 737.76 X 0.66 Luas = 737.76 X 0.33 Luas = 737.76 X 0.033 Luas = 737.76 X 0.033
= 486.92 OH = 243.46 OH = 24.35 OH = 24.35 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 486.92 / 60 DP = 243.46 / 30 DP = 24.35 / 3 DP = 24.35 / 3
= 8.12 hari = 8.12 hari = 8.12 hari = 8.12 hari
= 8.12 X 8 = 8.12 X 8 = 8.12 X 8 = 8.12 X 8
= 64.92 jam = 64.92 jam = 64.92 jam = 64.92 jam

F Pekerjaan bekisting Lantai 9


1 Kolom
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 282.36 X 0.66 Luas = 282.36 X 0.33 Luas = 282.36 X 0.033 Luas = 282.36 X 0.033 3.11 24.85
= 186.36 OH = 93.18 OH = 9.32 OH = 9.32 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 186.36 / 60 DP = 93.18 / 30 DP = 9.32 / 3 DP = 9.32 / 3
= 3.11 hari = 3.11 hari = 3.11 hari = 3.11 hari
= 3.11 X 8 = 3.11 X 8 = 3.11 X 8 = 3.11 X 8
= 24.85 jam = 24.85 jam = 24.85 jam = 24.85 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 200.29 X 0.66 Luas = 200.29 X 0.33 Luas = 200.29 X 0.033 Luas = 200.29 X 0.033
= 132.19 OH = 66.10 OH = 6.61 OH = 6.61 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 132.19 / 60 DP = 66.10 / 30 DP = 6.61 / 3 DP = 6.61 / 3
= 2.20 hari = 2.20 hari = 2.20 hari = 2.20 hari
= 2.20 X 8 = 2.20 X 8 = 2.20 X 8 = 2.20 X 8
= 17.63 jam = 17.63 jam = 17.63 jam = 17.63 jam
2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 400.78 X 0.66 Luas = 400.78 X 0.33 Luas = 400.78 X 0.033 Luas = 400.78 X 0.033 4.41 35.27
= 264.51 OH = 132.26 OH = 13.23 OH = 13.23 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 264.51 / 60 DP = 132.26 / 30 DP = 13.23 / 3 DP = 13.23 / 3
= 4.41 hari = 4.41 hari = 4.41 hari = 4.41 hari
= 4.41 X 8 = 4.41 X 8 = 4.41 X 8 = 4.41 X 8
= 35.27 jam = 35.27 jam = 35.27 jam = 35.27 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 393.52 X 0.66 Luas = 393.52 X 0.33 Luas = 393.52 X 0.033 Luas = 393.52 X 0.033
= 259.72 OH = 129.86 OH = 12.99 OH = 12.99 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 259.72 / 60 DP = 129.86 / 30 DP = 12.99 / 3 DP = 12.99 / 3
= 4.33 hari = 4.33 hari = 4.33 hari = 4.33 hari
= 4.33 X 8 = 4.33 X 8 = 4.33 X 8 = 4.33 X 8
= 34.63 jam = 34.63 jam = 34.63 jam = 34.63 jam
3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 887.98 X 0.66 Luas = 887.98 X 0.33 Luas = 887.98 X 0.033 Luas = 887.98 X 0.033 9.77 78.14
= 586.07 OH = 293.03 OH = 29.30 OH = 29.30 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 586.07 / 60 DP = 293.03 / 30 DP = 29.30 / 3 DP = 29.30 / 3
9.77 78.14

= 9.77 hari = 9.77 hari = 9.77 hari = 9.77 hari


= 9.77 X 8 = 9.77 X 8 = 9.77 X 8 = 9.77 X 8
= 78.14 jam = 78.14 jam = 78.14 jam = 78.14 jam

Zona 2
a. pekerja 1,625.74 b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 737.76 X 0.66 Luas = 737.76 X 0.33 Luas = 737.76 X 0.033 Luas = 737.76 X 0.033
= 486.92 OH = 243.46 OH = 24.35 OH = 24.35 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 486.92 / 60 DP = 243.46 / 30 DP = 24.35 / 3 DP = 24.35 / 3
= 8.12 hari = 8.12 hari = 8.12 hari = 8.12 hari
= 8.12 X 8 = 8.12 X 8 = 8.12 X 8 = 8.12 X 8
= 64.92 jam = 64.92 jam = 64.92 jam = 64.92 jam

G Pekerjaan bekisting Lantai 10


1 Kolom
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 200.36 X 0.66 Luas = 200.36 X 0.33 Luas = 200.36 X 0.033 Luas = 200.36 X 0.033 2.20 17.63
= 132.24 OH = 66.12 OH = 6.61 OH = 6.61 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 132.24 / 60 DP = 66.12 / 30 DP = 6.61 / 3 DP = 6.61 / 3
= 2.20 hari = 2.20 hari = 2.20 hari = 2.20 hari
= 2.20 X 8 = 2.20 X 8 = 2.20 X 8 = 2.20 X 8
= 17.63 jam = 17.63 jam = 17.63 jam = 17.63 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 254.18 X 0.66 Luas = 254.18 X 0.33 Luas = 254.18 X 0.033 Luas = 254.18 X 0.033
= 167.76 OH = 83.88 OH = 8.39 OH = 8.39 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 167.76 / 60 DP = 83.88 / 30 DP = 8.39 / 3 DP = 8.39 / 3
= 2.80 hari = 2.80 hari = 2.80 hari = 2.80 hari
= 2.80 X 8 = 2.80 X 8 = 2.80 X 8 = 2.80 X 8
= 22.37 jam = 22.37 jam = 22.37 jam = 22.37 jam
2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 301.35 X 0.66 Luas = 301.35 X 0.33 Luas = 301.35 X 0.033 Luas = 301.35 X 0.033 3.31 26.52
= 198.89 OH = 99.45 OH = 9.94 OH = 9.94 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 198.89 / 60 DP = 99.45 / 30 DP = 9.94 / 3 DP = 9.94 / 3
= 3.31 hari = 3.31 hari = 3.31 hari = 3.31 hari
= 3.31 X 8 = 3.31 X 8 = 3.31 X 8 = 3.31 X 8
= 26.52 jam = 26.52 jam = 26.52 jam = 26.52 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 337.52 X 0.66 Luas = 337.52 X 0.33 Luas = 337.52 X 0.033 Luas = 337.52 X 0.033
= 222.76 OH = 111.38 OH = 11.14 OH = 11.14 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 222.76 / 60 DP = 111.38 / 30 DP = 11.14 / 3 DP = 11.14 / 3
= 3.71 hari = 3.71 hari = 3.71 hari = 3.71 hari
= 3.71 X 8 = 3.71 X 8 = 3.71 X 8 = 3.71 X 8
= 29.70 jam = 29.70 jam = 29.70 jam = 29.70 jam
3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 925.97 X 0.66 Luas = 925.97 X 0.33 Luas = 925.97 X 0.033 Luas = 925.97 X 0.033 10.19 81.49
= 611.14 OH = 305.57 OH = 30.56 OH = 30.56 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 611.14 / 60 DP = 305.57 / 30 DP = 30.56 / 3 DP = 30.56 / 3
= 10.19 hari = 10.19 hari = 10.19 hari = 10.19 hari
= 10.19 X 8 = 10.19 X 8 = 10.19 X 8 = 10.19 X 8
= 81.49 jam = 81.49 jam = 81.49 jam = 81.49 jam
10.19 81.49

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 661.78 X 0.66 Luas = 661.78 X 0.33 Luas = 661.78 X 0.033 Luas = 661.78 X 0.033
= 436.77 OH = 218.39 OH = 21.84 OH = 21.84 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 436.77 / 60 DP = 218.39 / 30 DP = 21.84 / 3 DP = 21.84 / 3
= 7.28 hari = 7.28 hari = 7.28 hari = 7.28 hari
= 7.28 X 8 = 7.28 X 8 = 7.28 X 8 = 7.28 X 8
= 58.24 jam = 58.24 jam = 58.24 jam = 58.24 jam

H Pekerjaan bekisting Lantai 11


2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 200.36 X 0.66 Luas = 200.36 X 0.33 Luas = 200.36 X 0.033 Luas = 200.36 X 0.033 2.20 17.63
= 132.24 OH = 66.12 OH = 6.61 OH = 6.61 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 132.24 / 60 DP = 66.12 / 30 DP = 6.61 / 3 DP = 6.61 / 3
= 2.20 hari = 2.20 hari = 2.20 hari = 2.20 hari
= 2.20 X 8 = 2.20 X 8 = 2.20 X 8 = 2.20 X 8
= 17.63 jam = 17.63 jam = 17.63 jam = 17.63 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 254.18 X 0.66 Luas = 254.18 X 0.33 Luas = 254.18 X 0.033 Luas = 254.18 X 0.033
= 167.76 OH = 83.88 OH = 8.39 OH = 8.39 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 167.76 / 60 DP = 83.88 / 30 DP = 8.39 / 3 DP = 8.39 / 3
= 2.80 hari = 2.80 hari = 2.80 hari = 2.80 hari
= 2.80 X 8 = 2.80 X 8 = 2.80 X 8 = 2.80 X 8
= 22.37 jam = 22.37 jam = 22.37 jam = 22.37 jam
2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 301.35 X 0.66 Luas = 301.35 X 0.33 Luas = 301.35 X 0.033 Luas = 301.35 X 0.033 3.31 26.52
= 198.89 OH = 99.45 OH = 9.94 OH = 9.94 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 198.89 / 60 DP = 99.45 / 30 DP = 9.94 / 3 DP = 9.94 / 3
= 3.31 hari = 3.31 hari = 3.31 hari = 3.31 hari
= 3.31 X 8 = 3.31 X 8 = 3.31 X 8 = 3.31 X 8
= 26.52 jam = 26.52 jam = 26.52 jam = 26.52 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 337.52 X 0.66 Luas = 337.52 X 0.33 Luas = 337.52 X 0.033 Luas = 337.52 X 0.033
= 222.76 OH = 111.38 OH = 11.14 OH = 11.14 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 222.76 / 60 DP = 111.38 / 30 DP = 11.14 / 3 DP = 11.14 / 3
= 3.71 hari = 3.71 hari = 3.71 hari = 3.71 hari
= 3.71 X 8 = 3.71 X 8 = 3.71 X 8 = 3.71 X 8
= 29.70 jam = 29.70 jam = 29.70 jam = 29.70 jam
3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 925.97 X 0.66 Luas = 925.97 X 0.33 Luas = 925.97 X 0.033 Luas = 925.97 X 0.033 10.19 81.49
= 611.14 OH = 305.57 OH = 30.56 OH = 30.56 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 611.14 / 60 DP = 305.57 / 30 DP = 30.56 / 3 DP = 30.56 / 3
= 10.19 hari = 10.19 hari = 10.19 hari = 10.19 hari
= 10.19 X 8 = 10.19 X 8 = 10.19 X 8 = 10.19 X 8
= 81.49 jam = 81.49 jam = 81.49 jam = 81.49 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 661.78 X 0.66 Luas = 661.78 X 0.33 Luas = 661.78 X 0.033 Luas = 661.78 X 0.033
= 436.77 OH = 218.39 OH = 21.84 OH = 21.84 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 436.77 / 60 DP = 218.39 / 30 DP = 21.84 / 3 DP = 21.84 / 3
= 7.28 hari = 7.28 hari = 7.28 hari = 7.28 hari
= 7.28 X 8 = 7.28 X 8 = 7.28 X 8 = 7.28 X 8
= 58.24 jam = 58.24 jam = 58.24 jam = 58.24 jam

I Pekerjaan bekisting Lantai 12


1 Kolom
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 200.36 X 0.66 Luas = 200.36 X 0.33 Luas = 200.36 X 0.033 Luas = 200.36 X 0.033 2.20 17.63
= 132.24 OH = 66.12 OH = 6.61 OH = 6.61 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 132.24 / 60 DP = 66.12 / 30 DP = 6.61 / 3 DP = 6.61 / 3
= 2.20 hari = 2.20 hari = 2.20 hari = 2.20 hari
= 2.20 X 8 = 2.20 X 8 = 2.20 X 8 = 2.20 X 8
= 17.63 jam = 17.63 jam = 17.63 jam = 17.63 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 254.18 X 0.66 Luas = 254.18 X 0.33 Luas = 254.18 X 0.033 Luas = 254.18 X 0.033
= 167.76 OH = 83.88 OH = 8.39 OH = 8.39 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 167.76 / 60 DP = 83.88 / 30 DP = 8.39 / 3 DP = 8.39 / 3
= 2.80 hari = 2.80 hari = 2.80 hari = 2.80 hari
= 2.80 X 8 = 2.80 X 8 = 2.80 X 8 = 2.80 X 8
= 22.37 jam = 22.37 jam = 22.37 jam = 22.37 jam
2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 301.35 X 0.66 Luas = 301.35 X 0.33 Luas = 301.35 X 0.033 Luas = 301.35 X 0.033 3.31 26.52
= 198.89 OH = 99.45 OH = 9.94 OH = 9.94 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 198.89 / 60 DP = 99.45 / 30 DP = 9.94 / 3 DP = 9.94 / 3
= 3.31 hari = 3.31 hari = 3.31 hari = 3.31 hari
= 3.31 X 8 = 3.31 X 8 = 3.31 X 8 = 3.31 X 8
= 26.52 jam = 26.52 jam = 26.52 jam = 26.52 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 337.52 X 0.66 Luas = 337.52 X 0.33 Luas = 337.52 X 0.033 Luas = 337.52 X 0.033
= 222.76 OH = 111.38 OH = 11.14 OH = 11.14 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 222.76 / 60 DP = 111.38 / 30 DP = 11.14 / 3 DP = 11.14 / 3
= 3.71 hari = 3.71 hari = 3.71 hari = 3.71 hari
= 3.71 X 8 = 3.71 X 8 = 3.71 X 8 = 3.71 X 8
= 29.70 jam = 29.70 jam = 29.70 jam = 29.70 jam
3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 925.97 X 0.66 Luas = 925.97 X 0.33 Luas = 925.97 X 0.033 Luas = 925.97 X 0.033 10.19 81.49
= 611.14 OH = 305.57 OH = 30.56 OH = 30.56 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 611.14 / 60 DP = 305.57 / 30 DP = 30.56 / 3 DP = 30.56 / 3
= 10.19 hari = 10.19 hari = 10.19 hari = 10.19 hari
= 10.19 X 8 = 10.19 X 8 = 10.19 X 8 = 10.19 X 8
= 81.49 jam = 81.49 jam = 81.49 jam = 81.49 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 661.78 X 0.66 Luas = 661.78 X 0.33 Luas = 661.78 X 0.033 Luas = 661.78 X 0.033
= 436.77 OH = 218.39 OH = 21.84 OH = 21.84 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 436.77 / 60 DP = 218.39 / 30 DP = 21.84 / 3 DP = 21.84 / 3
= 7.28 hari = 7.28 hari = 7.28 hari = 7.28 hari
= 7.28 X 8 = 7.28 X 8 = 7.28 X 8 = 7.28 X 8
= 58.24 jam = 58.24 jam = 58.24 jam = 58.24 jam

J Pekerjaan bekisting Lantai 15


1 Kolom
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 200.36 X 0.66 Luas = 200.36 X 0.33 Luas = 200.36 X 0.033 Luas = 200.36 X 0.033 2.20 17.63
= 132.24 OH = 66.12 OH = 6.61 OH = 6.61 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 132.24 / 60 DP = 66.12 / 30 DP = 6.61 / 3 DP = 6.61 / 3
= 2.20 hari = 2.20 hari = 2.20 hari = 2.20 hari
= 2.20 X 8 = 2.20 X 8 = 2.20 X 8 = 2.20 X 8
= 17.63 jam = 17.63 jam = 17.63 jam = 17.63 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 254.18 X 0.66 Luas = 254.18 X 0.33 Luas = 254.18 X 0.033 Luas = 254.18 X 0.033
= 167.76 OH = 83.88 OH = 8.39 OH = 8.39 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 167.76 / 60 DP = 83.88 / 30 DP = 8.39 / 3 DP = 8.39 / 3
= 2.80 hari = 2.80 hari = 2.80 hari = 2.80 hari
= 2.80 X 8 = 2.80 X 8 = 2.80 X 8 = 2.80 X 8
= 22.37 jam = 22.37 jam = 22.37 jam = 22.37 jam
2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 301.35 X 0.66 Luas = 301.35 X 0.33 Luas = 301.35 X 0.033 Luas = 301.35 X 0.033 3.31 26.52
= 198.89 OH = 99.45 OH = 9.94 OH = 9.94 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 198.89 / 60 DP = 99.45 / 30 DP = 9.94 / 3 DP = 9.94 / 3
= 3.31 hari = 3.31 hari = 3.31 hari = 3.31 hari
= 3.31 X 8 = 3.31 X 8 = 3.31 X 8 = 3.31 X 8
= 26.52 jam = 26.52 jam = 26.52 jam = 26.52 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 337.52 X 0.66 Luas = 337.52 X 0.33 Luas = 337.52 X 0.033 Luas = 337.52 X 0.033
= 222.76 OH = 111.38 OH = 11.14 OH = 11.14 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 222.76 / 60 DP = 111.38 / 30 DP = 11.14 / 3 DP = 11.14 / 3
= 3.71 hari = 3.71 hari = 3.71 hari = 3.71 hari
= 3.71 X 8 = 3.71 X 8 = 3.71 X 8 = 3.71 X 8
= 29.70 jam = 29.70 jam = 29.70 jam = 29.70 jam
3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 925.97 X 0.66 Luas = 925.97 X 0.33 Luas = 925.97 X 0.033 Luas = 925.97 X 0.033 10.19 81.49
= 611.14 OH = 305.57 OH = 30.56 OH = 30.56 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 611.14 / 60 DP = 305.57 / 30 DP = 30.56 / 3 DP = 30.56 / 3
= 10.19 hari = 10.19 hari = 10.19 hari = 10.19 hari
= 10.19 X 8 = 10.19 X 8 = 10.19 X 8 = 10.19 X 8
= 81.49 jam = 81.49 jam = 81.49 jam = 81.49 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 661.78 X 0.66 Luas = 661.78 X 0.33 Luas = 661.78 X 0.033 Luas = 661.78 X 0.033
= 436.77 OH = 218.39 OH = 21.84 OH = 21.84 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 436.77 / 60 DP = 218.39 / 30 DP = 21.84 / 3 DP = 21.84 / 3
= 7.28 hari = 7.28 hari = 7.28 hari = 7.28 hari
= 7.28 X 8 = 7.28 X 8 = 7.28 X 8 = 7.28 X 8
= 58.24 jam = 58.24 jam = 58.24 jam = 58.24 jam

K Pekerjaan bekisting Lantai 16


1 Kolom
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 183.36 X 0.66 Luas = 183.36 X 0.33 Luas = 183.36 X 0.033 Luas = 183.36 X 0.033 2.02 16.14
= 121.02 OH = 60.51 OH = 6.05 OH = 6.05 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 121.02 / 60 DP = 60.51 / 30 DP = 6.05 / 3 DP = 6.05 / 3
= 2.02 hari = 2.02 hari = 2.02 hari = 2.02 hari
= 2.02 X 8 = 2.02 X 8 = 2.02 X 8 = 2.02 X 8
= 16.14 jam = 16.14 jam = 16.14 jam = 16.14 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 149.13 X 0.66 Luas = 149.13 X 0.33 Luas = 149.13 X 0.033 Luas = 149.13 X 0.033
= 98.43 OH = 49.21 OH = 4.92 OH = 4.92 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 98.43 / 60 DP = 49.21 / 30 DP = 4.92 / 3 DP = 4.92 / 3
= 1.64 hari = 1.64 hari = 1.64 hari = 1.64 hari
= 1.64 X 8 = 1.64 X 8 = 1.64 X 8 = 1.64 X 8
= 13.12 jam = 13.12 jam = 13.12 jam = 13.12 jam
2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 271.35 X 0.66 Luas = 271.35 X 0.33 Luas = 271.35 X 0.033 Luas = 271.35 X 0.033 2.98 23.88
= 179.09 OH = 89.55 OH = 8.95 OH = 8.95 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 179.09 / 60 DP = 89.55 / 30 DP = 8.95 / 3 DP = 8.95 / 3
= 2.98 hari = 2.98 hari = 2.98 hari = 2.98 hari
= 2.98 X 8 = 2.98 X 8 = 2.98 X 8 = 2.98 X 8
= 23.88 jam = 23.88 jam = 23.88 jam = 23.88 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 278.31 X 0.66 Luas = 278.31 X 0.33 Luas = 278.31 X 0.033 Luas = 278.31 X 0.033
= 183.68 OH = 91.84 OH = 9.18 OH = 9.18 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 183.68 / 60 DP = 91.84 / 30 DP = 9.18 / 3 DP = 9.18 / 3
= 3.06 hari = 3.06 hari = 3.06 hari = 3.06 hari
= 3.06 X 8 = 3.06 X 8 = 3.06 X 8 = 3.06 X 8
= 24.49 jam = 24.49 jam = 24.49 jam = 24.49 jam
3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 584.97 X 0.66 Luas = 584.97 X 0.33 Luas = 584.97 X 0.033 Luas = 584.97 X 0.033 6.43 51.48
= 386.08 OH = 193.04 OH = 19.30 OH = 19.30 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 386.08 / 60 DP = 193.04 / 30 DP = 19.30 / 3 DP = 19.30 / 3
= 6.43 hari = 6.43 hari = 6.43 hari = 6.43 hari
= 6.43 X 8 = 6.43 X 8 = 6.43 X 8 = 6.43 X 8
= 51.48 jam = 51.48 jam = 51.48 jam = 51.48 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 791.70 X 0.66 Luas = 791.70 X 0.33 Luas = 791.70 X 0.033 Luas = 791.70 X 0.033
= 522.52 OH = 261.26 OH = 26.13 OH = 26.13 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 522.52 / 60 DP = 261.26 / 30 DP = 26.13 / 3 DP = 26.13 / 3
= 8.71 hari = 8.71 hari = 8.71 hari = 8.71 hari
= 8.71 X 8 = 8.71 X 8 = 8.71 X 8 = 8.71 X 8
= 69.67 jam = 69.67 jam = 69.67 jam = 69.67 jam

L Pekerjaan bekisting Lantai 17


1 Kolom
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 152.57 X 0.66 Luas = 152.57 X 0.33 Luas = 152.57 X 0.033 Luas = 152.57 X 0.033 1.68 13.43
= 100.70 OH = 50.35 OH = 5.03 OH = 5.03 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 100.70 / 60 DP = 50.35 / 30 DP = 5.03 / 3 DP = 5.03 / 3
= 1.68 hari = 1.68 hari = 1.68 hari = 1.68 hari
= 1.68 X 8 = 1.68 X 8 = 1.68 X 8 = 1.68 X 8
= 13.43 jam = 13.43 jam = 13.43 jam = 13.43 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 150.73 X 0.66 Luas = 150.73 X 0.33 Luas = 150.73 X 0.033 Luas = 150.73 X 0.033
= 99.48 OH = 49.74 OH = 4.97 OH = 4.97 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 99.48 / 60 DP = 49.74 / 30 DP = 4.97 / 3 DP = 4.97 / 3
= 1.66 hari = 1.66 hari = 1.66 hari = 1.66 hari
= 1.66 X 8 = 1.66 X 8 = 1.66 X 8 = 1.66 X 8
= 13.26 jam = 13.26 jam = 13.26 jam = 13.26 jam
2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 271.35 X 0.66 Luas = 271.35 X 0.33 Luas = 271.35 X 0.033 Luas = 271.35 X 0.033 2.98 23.88
= 179.09 OH = 89.55 OH = 8.95 OH = 8.95 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 179.09 / 60 DP = 89.55 / 30 DP = 8.95 / 3 DP = 8.95 / 3
= 2.98 hari = 2.98 hari = 2.98 hari = 2.98 hari
= 2.98 X 8 = 2.98 X 8 = 2.98 X 8 = 2.98 X 8
= 23.88 jam = 23.88 jam = 23.88 jam = 23.88 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 278.31 X 0.66 Luas = 278.31 X 0.33 Luas = 278.31 X 0.033 Luas = 278.31 X 0.033
= 183.68 OH = 91.84 OH = 9.18 OH = 9.18 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 183.68 / 60 DP = 91.84 / 30 DP = 9.18 / 3 DP = 9.18 / 3
= 3.06 hari = 3.06 hari = 3.06 hari = 3.06 hari
= 3.06 X 8 = 3.06 X 8 = 3.06 X 8 = 3.06 X 8
= 24.49 jam = 24.49 jam = 24.49 jam = 24.49 jam
3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 510.98 X 0.66 Luas = 510.98 X 0.33 Luas = 510.98 X 0.033 Luas = 510.98 X 0.033 5.62 44.97
= 337.25 OH = 168.62 OH = 16.86 OH = 16.86 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 337.25 / 60 DP = 168.62 / 30 DP = 16.86 / 3 DP = 16.86 / 3
= 5.62 hari = 5.62 hari = 5.62 hari = 5.62 hari
= 5.62 X 8 = 5.62 X 8 = 5.62 X 8 = 5.62 X 8
= 44.97 jam = 44.97 jam = 44.97 jam = 44.97 jam

Zona 2
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 791.70 X 0.66 Luas = 791.70 X 0.33 Luas = 791.70 X 0.033 Luas = 791.70 X 0.033
= 522.52 OH = 261.26 OH = 26.13 OH = 26.13 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 522.52 / 60 DP = 261.26 / 30 DP = 26.13 / 3 DP = 26.13 / 3
= 8.71 hari = 8.71 hari = 8.71 hari = 8.71 hari
= 8.71 X 8 = 8.71 X 8 = 8.71 X 8 = 8.71 X 8
= 69.67 jam = 69.67 jam = 69.67 jam = 69.67 jam
M Pekerjaan bekisting Lantai 18
1 Kolom
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
1.95 15.63
Luas = 177.67 X 0.66 Luas = 177.67 X 0.33 Luas = 177.67 X 0.033 Luas = 177.67 X 0.033
= 117.26 OH = 58.63 OH = 5.86 OH = 5.86 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 117.26 / 60 DP = 58.63 / 30 DP = 5.86 / 3 DP = 5.86 / 3
= 1.95 hari = 1.95 hari = 1.95 hari = 1.95 hari
= 1.95 X 8 = 1.95 X 8 = 1.95 X 8 = 1.95 X 8
= 15.63 jam = 15.63 jam = 15.63 jam = 15.63 jam
2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 331.37 X 0.66 Luas = 331.37 X 0.33 Luas = 331.37 X 0.033 Luas = 331.37 X 0.033 3.65 29.16
= 218.70 OH = 109.35 OH = 10.94 OH = 10.94 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 218.70 / 60 DP = 109.35 / 30 DP = 10.94 / 3 DP = 10.94 / 3
= 3.65 hari = 3.65 hari = 3.65 hari = 3.65 hari
= 3.65 X 8 = 3.65 X 8 = 3.65 X 8 = 3.65 X 8
= 29.16 jam = 29.16 jam = 29.16 jam = 29.16 jam

3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
9.12 72.99
Luas = 829.40 X 0.66 Luas = 829.40 X 0.33 Luas = 829.40 X 0.033 Luas = 829.40 X 0.033
= 547.40 OH = 273.70 OH = 27.37 OH = 27.37 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 547.40 / 60 DP = 273.70 / 30 DP = 27.37 / 3 DP = 27.37 / 3
= 9.12 hari = 9.12 hari = 9.12 hari = 9.12 hari
= 9.12 X 8 = 9.12 X 8 = 9.12 X 8 = 9.12 X 8
= 72.99 jam = 72.99 jam = 72.99 jam = 72.99 jam

N Pekerjaan bekisting Lantai 19


! Kolom
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 184.17 X 0.66 Luas = 184.17 X 0.33 Luas = 184.17 X 0.033 Luas = 184.17 X 0.033 2.03 16.21
= 121.55 OH = 60.78 OH = 6.08 OH = 6.08 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 121.55 / 60 DP = 60.78 / 30 DP = 6.08 / 3 DP = 6.08 / 3
= 2.03 hari = 2.03 hari = 2.03 hari = 2.03 hari
= 2.03 X 8 = 2.03 X 8 = 2.03 X 8 = 2.03 X 8
= 16.21 jam = 16.21 jam = 16.21 jam = 16.21 jam

2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
3.89 31.12
Luas = 353.60 X 0.66 Luas = 353.60 X 0.33 Luas = 353.60 X 0.033 Luas = 353.60 X 0.033
= 233.38 OH = 116.69 OH = 11.67 OH = 11.67 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 233.38 / 60 DP = 116.69 / 30 DP = 11.67 / 3 DP = 11.67 / 3
= 3.89 hari = 3.89 hari = 3.89 hari = 3.89 hari
= 3.89 X 8 = 3.89 X 8 = 3.89 X 8 = 3.89 X 8
= 31.12 jam = 31.12 jam = 31.12 jam = 31.12 jam
3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
9.54 76.30
Luas = 867.10 X 0.66 Luas = 867.10 X 0.33 Luas = 867.10 X 0.033 Luas = 867.10 X 0.033
= 572.29 OH = 286.14 OH = 28.61 OH = 28.61 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 572.29 / 60 DP = 286.14 / 30 DP = 28.61 / 3 DP = 28.61 / 3
= 9.54 hari = 9.54 hari = 9.54 hari = 9.54 hari
= 9.54 X 8 = 9.54 X 8 = 9.54 X 8 = 9.54 X 8
= 76.30 jam = 76.30 jam = 76.30 jam = 76.30 jam
O Pekerjaan bekisting Lantai 20
1 Kolom
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 177.67 X 0.66 Luas = 177.67 X 0.33 Luas = 177.67 X 0.033 Luas = 177.67 X 0.033 1.95 15.63
= 117.26 OH = 58.63 OH = 5.86 OH = 5.86 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 117.26 / 60 DP = 58.63 / 30 DP = 5.86 / 3 DP = 5.86 / 3
= 1.95 hari = 1.95 hari = 1.95 hari = 1.95 hari
= 1.95 X 8 = 1.95 X 8 = 1.95 X 8 = 1.95 X 8
= 15.63 jam = 15.63 jam = 15.63 jam = 15.63 jam

2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 331.37 X 0.66 Luas = 331.37 X 0.33 Luas = 331.37 X 0.033 Luas = 331.37 X 0.033 3.65 29.16
= 218.70 OH = 109.35 OH = 10.94 OH = 10.94 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 218.70 / 60 DP = 109.35 / 30 DP = 10.94 / 3 DP = 10.94 / 3
= 3.65 hari = 3.65 hari = 3.65 hari = 3.65 hari
= 3.65 X 8 = 3.65 X 8 = 3.65 X 8 = 3.65 X 8
= 29.16 jam = 29.16 jam = 29.16 jam = 29.16 jam

3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 829.40 X 0.66 Luas = 829.40 X 0.33 Luas = 829.40 X 0.033 Luas = 829.40 X 0.033 9.12 72.99
= 547.40 OH = 273.70 OH = 27.37 OH = 27.37 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 547.40 / 60 DP = 273.70 / 30 DP = 27.37 / 3 DP = 27.37 / 3
= 9.12 hari = 9.12 hari = 9.12 hari = 9.12 hari
= 9.12 X 8 = 9.12 X 8 = 9.12 X 8 = 9.12 X 8
= 72.99 jam = 72.99 jam = 72.99 jam = 72.99 jam

P Pekerjaan bekisting Lantai 21


1 Kolom
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 177.67 X 0.66 Luas = 177.67 X 0.33 Luas = 177.67 X 0.033 Luas = 177.67 X 0.033 1.95 15.63
= 117.26 OH = 58.63 OH = 5.86 OH = 5.86 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 117.26 / 60 DP = 58.63 / 30 DP = 5.86 / 3 DP = 5.86 / 3
= 1.95 hari = 1.95 hari = 1.95 hari = 1.95 hari
= 1.95 X 8 = 1.95 X 8 = 1.95 X 8 = 1.95 X 8
= 15.63 jam = 15.63 jam = 15.63 jam = 15.63 jam

2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 331.37 X 0.66 Luas = 331.37 X 0.33 Luas = 331.37 X 0.033 Luas = 331.37 X 0.033 3.65 29.16
= 218.70 OH = 109.35 OH = 10.94 OH = 10.94 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 218.70 / 60 DP = 109.35 / 30 DP = 10.94 / 3 DP = 10.94 / 3
= 3.65 hari = 3.65 hari = 3.65 hari = 3.65 hari
= 3.65 X 8 = 3.65 X 8 = 3.65 X 8 = 3.65 X 8
= 29.16 jam = 29.16 jam = 29.16 jam = 29.16 jam

3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 829.40 X 0.66 Luas = 829.40 X 0.33 Luas = 829.40 X 0.033 Luas = 829.40 X 0.033 9.12 72.99
= 547.40 OH = 273.70 OH = 27.37 OH = 27.37 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 547.40 / 60 DP = 273.70 / 30 DP = 27.37 / 3 DP = 27.37 / 3
9.12 72.99

= 9.12 hari = 9.12 hari = 9.12 hari = 9.12 hari


= 9.12 X 8 = 9.12 X 8 = 9.12 X 8 = 9.12 X 8
= 72.99 jam = 72.99 jam = 72.99 jam = 72.99 jam

Q Pekerjaan bekisting Lantai 23


1 Kolom
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 177.67 X 0.66 Luas = 177.67 X 0.33 Luas = 177.67 X 0.033 Luas = 177.67 X 0.033 1.95 15.63
= 117.26 OH = 58.63 OH = 5.86 OH = 5.86 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 117.26 / 60 DP = 58.63 / 30 DP = 5.86 / 3 DP = 5.86 / 3
= 1.95 hari = 1.95 hari = 1.95 hari = 1.95 hari
= 1.95 X 8 = 1.95 X 8 = 1.95 X 8 = 1.95 X 8
= 15.63 jam = 15.63 jam = 15.63 jam = 15.63 jam

2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 331.37 X 0.66 Luas = 331.37 X 0.33 Luas = 331.37 X 0.033 Luas = 331.37 X 0.033 3.65 29.16
= 218.70 OH = 109.35 OH = 10.94 OH = 10.94 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 218.70 / 60 DP = 109.35 / 30 DP = 10.94 / 3 DP = 10.94 / 3
= 3.65 hari = 3.65 hari = 3.65 hari = 3.65 hari
= 3.65 X 8 = 3.65 X 8 = 3.65 X 8 = 3.65 X 8
= 29.16 jam = 29.16 jam = 29.16 jam = 29.16 jam

3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 829.40 X 0.66 Luas = 829.40 X 0.33 Luas = 829.40 X 0.033 Luas = 829.40 X 0.033 9.12 72.99
= 547.40 OH = 273.70 OH = 27.37 OH = 27.37 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 547.40 / 60 DP = 273.70 / 30 DP = 27.37 / 3 DP = 27.37 / 3
= 9.12 hari = 9.12 hari = 9.12 hari = 9.12 hari
= 9.12 X 8 = 9.12 X 8 = 9.12 X 8 = 9.12 X 8
= 72.99 jam = 72.99 jam = 72.99 jam = 72.99 jam

R Pekerjaan bekisting Lantai 25


1 Kolom
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 177.67 X 0.66 Luas = 177.67 X 0.33 Luas = 177.67 X 0.033 Luas = 177.67 X 0.033 1.95 15.63
= 117.26 OH = 58.63 OH = 5.86 OH = 5.86 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 117.26 / 60 DP = 58.63 / 30 DP = 5.86 / 3 DP = 5.86 / 3
= 1.95 hari = 1.95 hari = 1.95 hari = 1.95 hari
= 1.95 X 8 = 1.95 X 8 = 1.95 X 8 = 1.95 X 8
= 15.63 jam = 15.63 jam = 15.63 jam = 15.63 jam

2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 331.37 X 0.66 Luas = 331.37 X 0.33 Luas = 331.37 X 0.033 Luas = 331.37 X 0.033 3.65 29.16
= 218.70 OH = 109.35 OH = 10.94 OH = 10.94 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 218.70 / 60 DP = 109.35 / 30 DP = 10.94 / 3 DP = 10.94 / 3
= 3.65 hari = 3.65 hari = 3.65 hari = 3.65 hari
= 3.65 X 8 = 3.65 X 8 = 3.65 X 8 = 3.65 X 8
= 29.16 jam = 29.16 jam = 29.16 jam = 29.16 jam

3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
9.12 72.99
Luas = 829.40 X 0.66 Luas = 829.40 X 0.33 Luas = 829.40 X 0.033 Luas = 829.40 X 0.033 9.12 72.99
= 547.40 OH = 273.70 OH = 27.37 OH = 27.37 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 547.40 / 60 DP = 273.70 / 30 DP = 27.37 / 3 DP = 27.37 / 3
= 9.12 hari = 9.12 hari = 9.12 hari = 9.12 hari
= 9.12 X 8 = 9.12 X 8 = 9.12 X 8 = 9.12 X 8
= 72.99 jam = 72.99 jam = 72.99 jam = 72.99 jam

S Pekerjaan bekisting Lantai Roof


2 Balok
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 325.94 X 0.66 Luas = 325.94 X 0.33 Luas = 325.94 X 0.033 Luas = 325.94 X 0.033 3.59 28.68
= 215.12 OH = 107.56 OH = 10.76 OH = 10.76 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 215.12 / 60 DP = 107.56 / 30 DP = 10.76 / 3 DP = 10.76 / 3
= 3.59 hari = 3.59 hari = 3.59 hari = 3.59 hari
= 3.59 X 8 = 3.59 X 8 = 3.59 X 8 = 3.59 X 8
= 28.68 jam = 28.68 jam = 28.68 jam = 28.68 jam

3 Plat
Zona 1
a. pekerja b. Tukang Kayu c. Kepala Tukang d. Mandor
1 m² = 0.66 OH 1 m² = 0.33 OH 1 m² = 0.033 OH 1 m² = 0.033 OH
1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam 1 hari = 8 jam
Tenaga = 60 org Tenaga = 30 org Tenaga = 3 org Tenaga = 3 org
- Pek Kolom - Pek Kolom - Pek Kolom - Pek Kolom
Luas = 791.70 X 0.66 Luas = 791.70 X 0.33 Luas = 791.70 X 0.033 Luas = 791.70 X 0.033 8.71 69.67
= 522.52 OH = 261.26 OH = 26.13 OH = 26.13 OH
- Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan - Durasi Pekerjaan
DP = 522.52 / 60 DP = 261.26 / 30 DP = 26.13 / 3 DP = 26.13 / 3
= 8.71 hari = 8.71 hari = 8.71 hari = 8.71 hari
= 8.71 X 8 = 8.71 X 8 = 8.71 X 8 = 8.71 X 8
= 69.67 jam = 69.67 jam = 69.67 jam = 69.67 jam
ESTIMASI WAKTU PRODUKTIFITAS PASANG BESI BALOK
Waktu
No Uraian
(Hari)
A Lantai 5
- Balok - Balok
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 39,219.93 kg kebutuhan besi = 39,219.93 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
6.86
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 kg/hari = 571.43 kg/hari
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 39,219.93 / 5,714.29 - Waktu = 39,219.93 / 5,714.29
= 6.86 hari = 6.86 hari
B Lantai 6
- Balok - Balok
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 39,219.93 kg kebutuhan besi = 39,219.93 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
6.86
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 39,219.93 / 5,714.29 - Waktu = 39,219.93 / 5,714.29
= 6.86 hari = 6.86 hari
C Lantai 7
- Balok - Balok
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 39,120.89 kg kebutuhan besi = 39,120.89 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
6.85
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 39,120.89 / 5,714.29 - Waktu = 39,120.89 / 5,714.29
= 6.85 hari = 6.85 hari
D Lantai 8
- Balok - Balok
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 39,120.89 kg kebutuhan besi = 39,120.89 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
6.85
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 39,120.89 / 5,714.29 - Waktu = 39,120.89 / 5,714.29
= 6.85 hari = 6.85 hari
F Lantai 9
- Balok - Balok
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 32,034.49 kg kebutuhan besi = 32,034.49 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
5.61
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 32,034.49 / 5,714.29 - Waktu = 32,034.49 / 5,714.29
= 5.61 hari = 5.61 hari
G Lantai 10
- Balok - Balok
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 32,034.49 kg kebutuhan besi = 32,034.49 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
5.61
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 32,034.49 / 5,714.29 - Waktu = 32,034.49 / 5,714.29
= 5.61 hari = 5.61 hari
H Lantai 11
- Balok - Balok
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 31,805.53 kg kebutuhan besi = 31,805.53 kg
Tenaga = 40 org Tenaga = 40 org
5.57
- Pek Besi - Pek Besi
5.57
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
- Waktu = 40.00 / 0.07 - Waktu = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
= 31,805.53 / 5,714.29 = 31,805.53 / 5,714.29
= 5.57 hari = 5.57 hari
I Lantai 12
- Balok - Balok
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 31,805.53 kg kebutuhan besi = 31,805.53 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
5.57
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 31,805.53 / 5,714.29 - Waktu = 31,805.53 / 5,714.29
= 5.57 hari = 5.57 hari
J Lantai 15
- Balok - Balok
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 31,805.53 kg kebutuhan besi = 31,805.53 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
5.57
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 31,805.53 / 5,714.29 - Waktu = 31,805.53 / 5,714.29
= 5.57 hari = 5.57 hari
K Lantai 16
- Balok - Balok
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 27,895.28 kg kebutuhan besi = 27,895.28 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
4.88
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 27,895.28 / 5,714.29 - Waktu = 27,895.28 / 5,714.29
= 4.88 hari = 4.88 hari
L Lantai 17
- Balok - Balok
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 27,895.28 kg kebutuhan besi = 27,895.28 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
4.88
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 27,895.28 / 5,714.29 - Waktu = 27,895.28 / 5,714.29
= 4.88 hari = 4.88 hari
M Lantai 18
- Balok - Balok
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 15,909.80 kg kebutuhan besi = 15,909.80 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
2.78
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 15,909.80 / 5,714.29 - Waktu = 15,909.80 / 5,714.29
= 2.78 hari = 2.78 hari
N Lantai 19
- Balok - Balok
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 16,305.52 kg kebutuhan besi = 16,305.52 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
2.85
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 16,305.52 / 5,714.29 - Waktu = 16,305.52 / 5,714.29
= 2.85 hari = 2.85 hari
O Lantai 20
- Balok - Balok

2.62
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 14,995.83 kg kebutuhan besi = 14,995.83 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
2.62
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 14,995.83 / 5,714.29 - Waktu = 14,995.83 / 5,714.29
= 2.62 hari = 2.62 hari
P Lantai 21
- Balok - Balok
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 14,995.83 kg kebutuhan besi = 14,995.83 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
2.62
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 14,995.83 / 5,714.29 - Waktu = 14,995.83 / 5,714.29
= 2.62 hari = 2.62 hari
Q Lantai 23
- Balok - Balok
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 14,995.83 kg kebutuhan besi = 14,995.83 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
2.62
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 14,995.83 / 5,714.29 - Waktu = 14,995.83 / 5,714.29
= 2.62 hari = 2.62 hari
R Lantai 25
- Balok - Balok
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 14,995.83 kg kebutuhan besi = 14,995.83 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
2.62
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 14,995.83 / 5,714.29 - Waktu = 14,995.83 / 5,714.29
= 2.62 hari = 2.62 hari
S Lantai ROOF
- Balok - Balok
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 14,995.83 kg kebutuhan besi = 14,995.83 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
2.62
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 14,995.83 / 5,714.29 - Waktu = 14,995.83 / 5,714.29
= 2.62 hari = 2.62 hari
83.85
ESTIMASI WAKTU PRODUKTIFITAS PASANG BESI KOLOM
Waktu
No Uraian
(Hari)
A Lantai 3
- Kolom - Kolom
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 28,328.11 kg kebutuhan besi = 28,328.11 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
4.96
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 kg/hari = 571.43 kg/hari
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 28,328.11 / 5,714.29 - Waktu = 28,328.11 / 5,714.29
= 4.96 hari = 4.96 hari
B Lantai 5
- Kolom - Kolom
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 27,374.85 kg kebutuhan besi = 27,374.85 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
4.79
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 kg/hari = 571.43 kg/hari
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 27,374.85 / 5,714.29 - Waktu = 27,374.85 / 5,714.29
= 4.79 hari = 4.79 hari
C Lantai 6
- Kolom - Kolom
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 27,374.85 kg kebutuhan besi = 27,374.85 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
4.79
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 27,374.85 / 5,714.29 - Waktu = 27,374.85 / 5,714.29
= 4.79 hari = 4.79 hari
D Lantai 7
- Kolom - Kolom
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 27,374.85 kg kebutuhan besi = 27,374.85 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
4.79
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 27,374.85 / 5,714.29 - Waktu = 27,374.85 / 5,714.29
= 4.79 hari = 4.79 hari
E Lantai 8
- Kolom - Kolom
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 27,374.85 kg kebutuhan besi = 27,374.85 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
4.79
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 27,374.85 / 5,714.29 - Waktu = 27,374.85 / 5,714.29
= 4.79 hari = 4.79 hari
F Lantai 9
- Kolom - Kolom
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 23,140.09 kg kebutuhan besi = 23,140.09 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
4.05
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 23,140.09 / 5,714.29 - Waktu = 23,140.09 / 5,714.29
= 4.05 hari = 4.05 hari
H Lantai 10
- Kolom - Kolom
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 18,914.87 kg kebutuhan besi = 18,914.87 kg
Tenaga = 40 org Tenaga = 40 org
3.31
- Pek Besi - Pek Besi
3.31
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 18,914.87 / 5,714.29 - Waktu = 18,914.87 / 5,714.29
= 3.31 hari = 3.31 hari
I Lantai 11
- Kolom - Kolom
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 18,914.87 kg kebutuhan besi = 18,914.87 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
3.31
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 18,914.87 / 5,714.29 - Waktu = 18,914.87 / 5,714.29
= 3.31 hari = 3.31 hari
J Lantai 12
- Kolom - Kolom
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 18,914.87 kg kebutuhan besi = 18,914.87 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
3.31
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 18,914.87 / 5,714.29 - Waktu = 18,914.87 / 5,714.29
= 3.31 hari = 3.31 hari
K Lantai 15
- Kolom - Kolom
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 14,594.74 kg kebutuhan besi = 14,594.74 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
2.55
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 14,594.74 / 5,714.29 - Waktu = 14,594.74 / 5,714.29
= 2.55 hari = 2.55 hari
L Lantai 16
- Kolom - Kolom
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 13,028.15 kg kebutuhan besi = 13,028.15 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
2.28
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 13,028.15 / 5,714.29 - Waktu = 13,028.15 / 5,714.29
= 2.28 hari = 2.28 hari
M Lantai 17
- Kolom - Kolom
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 9,540.66 kg kebutuhan besi = 9,540.66 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
1.67
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 9,540.66 / 5,714.29 - Waktu = 9,540.66 / 5,714.29
= 1.67 hari = 1.67 hari
N Lantai 18

a. pekerja b. Tukang besi


10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 8,753.02 kg kebutuhan besi = 8,753.02 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
1.53
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 8,753.02 / 5,714.29 - Waktu = 8,753.02 / 5,714.29
= 1.53 hari = 1.53 hari
O Lantai 19

1.14
a. pekerja b. Tukang besi
10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 6,513.45 kg kebutuhan besi = 6,513.45 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
1.14
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 6,513.45 / 5,714.29 - Waktu = 6,513.45 / 5,714.29
= 1.14 hari = 1.14 hari
P Lantai 20

a. pekerja b. Tukang besi


10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 6,227.72 kg kebutuhan besi = 6,227.72 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
1.09
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 6,227.72 / 5,714.29 - Waktu = 6,227.72 / 5,714.29
= 1.09 hari = 1.09 hari
Q Lantai 21

a. pekerja b. Tukang besi


10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 6,227.72 kg kebutuhan besi = 6,227.72 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
1.09
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 6,227.72 / 5,714.29 - Waktu = 6,227.72 / 5,714.29
= 1.09 hari = 1.09 hari
R Lantai 23

a. pekerja b. Tukang besi


10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 6,227.72 kg kebutuhan besi = 6,227.72 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
1.09
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 6,227.72 / 5,714.29 - Waktu = 6,227.72 / 5,714.29
= 1.09 hari = 1.09 hari
S Lantai 25

a. pekerja b. Tukang besi


10 kg = 0.07 OH 10 kg = 0.07 OH
kebutuhan besi = 6,227.72 kg kebutuhan besi = 6,227.72 kg
Tenaga = 40 org Tenaga = 40 org
- Pek Besi - Pek Besi
1.09
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 40.00 / 0.07 = 40.00 / 0.07
= 571.43 = 571.43
- Produktifitas - Produktifitas
= 571.43 x 10 = 571.43 x 10
= 5,714.29 kg/hari = 5,714.29 kg/hari
- Waktu = 6,227.72 / 5,714.29 - Waktu = 6,227.72 / 5,714.29
= 1.09 hari = 1.09 hari
51.63
ESTIMASI WAKTU PRODUKTIFITAS PASANG BESI PLAT
Waktu
No Uraian
(Hari)
B Lantai 5
- Plat - Plat
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 20,020.06 kg kebutuhan besi = 20,020.06 kg
Tenaga = 20 org Tenaga = 20 org
- Pek Besi - Pek Besi
2.50
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 20,020.06 / 8,000.00 - Waktu = 20,020.06 / 8,000.00
= 2.50 hari = 2.50 hari
C Lantai 6
- Plat - Plat
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 20,020.06 kg kebutuhan besi = 20,020.06 kg
Tenaga = 20 org Tenaga = 20 org
- Pek Besi - Pek Besi
2.50
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 20,020.06 / 8,000.00 - Waktu = 20,020.06 / 8,000.00
= 2.50 hari = 2.50 hari
D Lantai 7
- Plat - Plat
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 19,080.57 kg kebutuhan besi = 19,080.57 kg
Tenaga = 20 org Tenaga = 20 org
- Pek Besi - Pek Besi
2.39
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 19,080.57 / 8,000.00 - Waktu = 19,080.57 / 8,000.00
= 2.39 hari = 2.39 hari
E Lantai 8
- Plat - Plat
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 19,080.57 kg kebutuhan besi = 19,080.57 kg
Tenaga = 20 org Tenaga = 20 org
- Pek Besi - Pek Besi
2.39
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 19,080.57 / 8,000.00 - Waktu = 19,080.57 / 8,000.00
= 2.39 hari = 2.39 hari
F Lantai 9
- Plat - Plat
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 20,429.31 kg kebutuhan besi = 20,429.31 kg
Tenaga = 20 org Tenaga = 20 org
- Pek Besi - Pek Besi
2.55
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 20,429.31 / 8,000.00 - Waktu = 20,429.31 / 8,000.00
= 2.55 hari = 2.55 hari
H Lantai 10
- Plat - Plat
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 14,928.47 kg kebutuhan besi = 14,928.47 kg
Tenaga = 20 org Tenaga = 20 org
- Pek Besi - Pek Besi
1.87
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 14,928.47 / 8,000.00 - Waktu = 14,928.47 / 8,000.00
= 1.87 hari = 1.87 hari
I Lantai 11
- Plat - Plat
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 14,945.47 kg kebutuhan besi = 14,945.47 kg
Tenaga = 20 org Tenaga = 20 org
1.87
- Pek Besi - Pek Besi
1.87
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 14,945.47 / 8,000.00 - Waktu = 14,945.47 / 8,000.00
= 1.87 hari = 1.87 hari
J Lantai 12
- Plat - Plat
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 15,027.47 kg kebutuhan besi = 15,027.47 kg
Tenaga = 20 org Tenaga = 20 org
- Pek Besi - Pek Besi
1.88
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 15,027.47 / 8,000.00 - Waktu = 15,027.47 / 8,000.00
= 1.88 hari = 1.88 hari
K Lantai 15
- Plat - Plat
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 28,328.11 kg kebutuhan besi = 28,328.11 kg
Tenaga = 20 org Tenaga = 20 org
- Pek Besi - Pek Besi
3.54
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 28,328.11 / 8,000.00 - Waktu = 28,328.11 / 8,000.00
= 3.54 hari = 3.54 hari
L Lantai 16
- Plat - Plat
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 13,175.92 kg kebutuhan besi = 13,175.92 kg
Tenaga = 20 org Tenaga = 20 org
- Pek Besi - Pek Besi
1.65
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 13,175.92 / 8,000.00 - Waktu = 13,175.92 / 8,000.00
= 1.65 hari = 1.65 hari
M Lantai 17
- Plat - Plat
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 13,575.38 kg kebutuhan besi = 13,575.38 kg
Tenaga = 20 org Tenaga = 20 org
- Pek Besi - Pek Besi
1.70
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 13,575.38 / 8,000.00 - Waktu = 13,575.38 / 8,000.00
= 1.70 hari = 1.70 hari
N Lantai 18
- Plat - Plat
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 7,966.05 kg kebutuhan besi = 7,966.05 kg
Tenaga = 20 org Tenaga = 20 org
- Pek Besi - Pek Besi
1.00
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 7,966.05 / 8,000.00 - Waktu = 7,966.05 / 8,000.00
= 1.00 hari = 1.00 hari
O Lantai 19
- Plat - Plat
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 8,365.75 kg kebutuhan besi = 8,365.75 kg
Tenaga = 20 org Tenaga = 20 org
- Pek Besi - Pek Besi
1.05
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 8,365.75 / 8,000.00 - Waktu = 8,365.75 / 8,000.00
= 1.05 hari = 1.05 hari
P Lantai 20
- Plat - Plat

1.00
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 7,967.80 kg kebutuhan besi = 7,967.80 kg
Tenaga = 20 org Tenaga = 20 org
- Pek Besi - Pek Besi
1.00
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 7,967.80 / 8,000.00 - Waktu = 7,967.80 / 8,000.00
= 1.00 hari = 1.00 hari
Q Lantai 21
- Plat - Plat
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 7,967.80 kg kebutuhan besi = 7,967.80 kg
Tenaga = 20 org Tenaga = 20 org
- Pek Besi - Pek Besi
1.00
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 7,967.80 / 8,000.00 - Waktu = 7,967.80 / 8,000.00
= 1.00 hari = 1.00 hari
R Lantai 23
- Plat - Plat
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 7,967.80 kg kebutuhan besi = 7,967.80 kg
Tenaga = 20 org Tenaga = 20 org
- Pek Besi - Pek Besi
1.00
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 7,967.80 / 8,000.00 - Waktu = 7,967.80 / 8,000.00
= 1.00 hari = 1.00 hari
S Lantai 25
- Plat - Plat
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 7,967.80 kg kebutuhan besi = 7,967.80 kg
Tenaga = 20 org Tenaga = 20 org
- Pek Besi - Pek Besi
1.00
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 7,967.80 / 8,000.00 - Waktu = 7,967.80 / 8,000.00
= 1.00 hari = 1.00 hari
T Lantai ROOF
- Plat - Plat
a. pekerja b. Tukang besi
10 kg = 0.025 OH 10 kg = 0.025 OH
kebutuhan besi = 7,867.80 kg kebutuhan besi = 7,867.80 kg
Tenaga = 20 org Tenaga = 20 org
- Pek Besi - Pek Besi
0.98
= jml pekerja / koef. Prod = jml pekerja / koef. Prod
= 20.00 / 0.025 = 20.00 / 0.025
= 800.00 = 800.00
- Produktifitas - Produktifitas
= 800.00 x 10 = 800.00 x 10
= 8,000.00 kg/hari = 8,000.00 kg/hari
- Waktu = 7,867.80 / 8,000.00 - Waktu = 7,867.80 / 8,000.00
= 0.98 hari = 0.98 hari
31.84
ESTIMASI WAKTU PENGECORAN KOLOM
Uraian Waktu
No
(Hari)
A Lantai 3
- kolom 96.01 m³
a. pekerja
1 m³ = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
- Pek Cor
2.40
V = 96.01 X 1
= 96.01 OH
- Durasi Pekerjaan
DP = 96.01 / 40
= 2.40 hari
= 2.40 X 8
= 19.20 jam
B Lantai 5
- kolom 95.52 m³
a. pekerja
1 m3 = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
- Pek Cor
2.39
V = 95.52 X 1
= 95.52 OH
- Durasi Pekerjaan
DP = 95.52 / 40
= 2.39 hari
= 2.39 X 8
= 19.10 jam
C Lantai 6
- kolom 95.49 m³
a. pekerja
1 m3 = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
- Pek Cor
2.39
V = 95.49 X 1
= 95.49 OH
- Durasi Pekerjaan
DP = 95.49 / 40
= 2.39 hari
= 2.39 X 8
= 19.10 jam
D Lantai 7
- kolom 95.39 m³
a. pekerja
1 m3 = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
- Pek Cor
2.38
V = 95.39 X 1
= 95.39 OH
- Durasi Pekerjaan
DP = 95.39 / 40
= 2.38 hari
= 2.38 X 8
= 19.08 jam
E Lantai 8
- kolom 95.39 m³
a. pekerja
1 m3 = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
2.38
- Pek Cor
2.38
V = 95.39 X 1
= 95.39 OH
- Durasi Pekerjaan
DP = 95.39 / 40
= 2.38 hari
= 2.38 X 8
= 19.08 jam
F Lantai 9
- kolom 77.27 m³
a. pekerja
1 m3 = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
- Pek Cor
1.93
V = 77.27 X 1
= 77.27 OH
- Durasi Pekerjaan
DP = 77.27 / 40
= 1.93 hari
= 1.93 X 8
= 15.45 jam
G Lantai 10
- kolom 77.20 m³
a. pekerja
1 m3 = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
- Pek Cor
1.93
V = 77.20 X 1
= 77.20 OH
- Durasi Pekerjaan
DP = 77.20 / 40
= 1.93 hari
= 1.93 X 8
= 15.44 jam
H Lantai 11
- kolom 69.55 m³
a. pekerja
1 m3 = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
- Pek Cor
1.74
V = 69.55 X 1
= 69.55 OH
- Durasi Pekerjaan
DP = 69.55 / 40
= 1.74 hari
= 1.74 X 8
= 13.91 jam
I Lantai 12
- kolom 69.55 m³
a. pekerja
1 m3 = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
- Pek Cor
1.74
V = 69.55 X 1
= 69.55 OH
- Durasi Pekerjaan
DP = 69.55 / 40
= 1.74 hari
= 1.74 X 8
= 13.91 jam
J Lantai 15
- kolom 50.37 m³
a. pekerja

1.26
1 m3 = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
- Pek Cor
1.26
V = 50.37 X 1
= 50.37 OH
- Durasi Pekerjaan
DP = 50.37 / 40
= 1.26 hari
= 1.26 X 8
= 10.07 jam
K Lantai 16
- kolom 49.55 m³
a. pekerja
1 m3 = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
- Pek Cor
1.24
V = 49.55 X 1
= 49.55 OH
- Durasi Pekerjaan
DP = 49.55 / 40
= 1.24 hari
= 1.24 X 8
= 9.91 jam
L Lantai 17
- kolom 41.09 m³
a. pekerja
1 m3 = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
- Pek Cor
1.03
V = 41.09 X 1
= 41.09 OH
- Durasi Pekerjaan
DP = 41.09 / 40
= 1.03 hari
= 1.03 X 8
= 8.22 jam
M Lantai 18
- kolom 32.19 m³
a. pekerja
1 m3 = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
- Pek Cor
0.80
V = 32.19 X 1
= 32.19 OH
- Durasi Pekerjaan
DP = 32.19 / 40
= 0.80 hari
= 0.80 X 8
= 6.44 jam
N Lantai 19
- kolom 26.17 m³
a. pekerja
1 m3 = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
- Pek Cor
0.65
V = 26.17 X 1
= 26.17 OH
- Durasi Pekerjaan
DP = 26.17 / 40
= 0.65 hari
= 0.65 X 8
= 5.23 jam
O Lantai 20
- kolom 25.38 m³
a. pekerja
1 m3 = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
- Pek Cor
0.63
V = 25.38 X 1
= 25.38 OH
- Durasi Pekerjaan
DP = 25.38 / 40
= 0.63 hari
= 0.63 X 8
= 5.08 jam
P Lantai 21
- kolom 25.38 m³
a. pekerja
1 m3 = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
- Pek Cor
0.63
V = 25.38 X 1
= 25.38 OH
- Durasi Pekerjaan
DP = 25.38 / 40
= 0.63 hari
= 0.63 X 8
= 5.08 jam
Q Lantai 23
- kolom 25.38 m³
a. pekerja
1 m3 = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
- Pek Cor
0.63
V = 25.38 X 1
= 25.38 OH
- Durasi Pekerjaan
DP = 25.38 / 40
= 0.63 hari
= 0.63 X 8
= 5.08 jam
R Lantai 25
- kolom 25.38 m³
a. pekerja
1 m3 = 1.00 OH
1 hari = 8.00 jam
Tenaga = 40 org
- Pek Cor
0.63
V = 25.38 X 1
= 25.38 OH
- Durasi Pekerjaan
DP = 25.38 / 40
= 0.63 hari
= 0.63 X 8
= 5.08 jam
26.81
ESTIMASI WAKTU PENGECORAN BALOK DAN PLAT
Uraian Waktu Uraian Waktu
No No
(Hari) (Hari)
A Lantai 5 A Lantai 5
- Balok 103.64 m³ - Plat 225.01 m³
a. pekerja a. pekerja
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
2.59 5.63
V = 103.64 X 1 V = 225.01 X 1
= 103.64 OH = 225.01 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 103.64 / 40 DP = 225.01 / 40
= 2.59 hari = 5.63 hari
= 2.59 X 8 = 5.63 X 8
= 20.73 jam = 45.00 jam
B Lantai 6 B Lantai 6
- Balok 125.96 m³ - Plat 272.20 m³
a. pekerja a. pekerja
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
3.15 6.81
V = 125.96 X 1 V = 272.20 X 1
= 125.96 OH = 272.20 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 125.96 / 40 DP = 272.20 / 40
= 3.15 hari = 6.81 hari
= 3.15 X 8 = 6.81 X 8
= 25.19 jam = 54.44 jam
C Lantai 7 C Lantai 7
- Balok 123.52 m³ - Plat 258.53 m³
a. pekerja a. pekerja
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
3.09 6.46
V = 123.52 X 1 V = 258.53 X 1
= 123.52 OH = 258.53 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 123.52 / 40 DP = 258.53 / 40
= 3.09 hari = 6.46 hari
= 3.09 X 8 = 6.46 X 8
= 24.70 jam = 51.71 jam
D Lantai 8 D Lantai 8
- Balok 123.52 m³ - Plat 258.53 m³
a. pekerja a. pekerja

3.09 6.46
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
3.09 6.46
V = 123.52 X 1 V = 258.53 X 1
= 123.52 OH = 258.53 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 123.52 / 40 DP = 258.53 / 40
= 3.09 hari = 6.46 hari
= 3.09 X 8 = 6.46 X 8
= 24.70 jam = 51.71 jam
E Lantai 9 E Lantai 9
- Balok 130.12 m³ - Plat 273.68 m³
a. pekerja a. pekerja
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
3.25 6.84
V = 130.12 X 1 V = 273.68 X 1
= 130.12 OH = 273.68 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 130.12 / 40 DP = 273.68 / 40
= 3.25 hari = 6.84 hari
= 3.25 X 8 = 6.84 X 8
= 26.02 jam = 54.74 jam
F Lantai 10 F Lantai 10
- Balok 98.51 m³ - Plat 202.24 m³
a. pekerja a. pekerja
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
2.46 5.06
V = 98.51 X 1 V = 202.24 X 1
= 98.51 OH = 202.24 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 98.51 / 40 DP = 202.24 / 40
= 2.46 hari = 5.06 hari
= 2.46 X 8 = 5.06 X 8
= 19.70 jam = 40.45 jam
G Lantai 11 G Lantai 11
- Balok 98.29 m³ - Plat 202.58 m³
a. pekerja a. pekerja
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
2.46 5.06
V = 98.29 X 1 V = 202.58 X 1
= 98.29 OH = 202.58 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 98.29 / 40 DP = 202.58 / 40
2.46 5.06

= 2.46 hari = 5.06 hari


= 2.46 X 8 = 5.06 X 8
= 19.66 jam = 40.52 jam
H Lantai 12 H Lantai 12
- Balok 98.29 m³ - Plat 203.70 m³
a. pekerja a. pekerja
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
2.46 5.09
V = 98.29 X 1 V = 203.70 X 1
= 98.29 OH = 203.70 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 98.29 / 40 DP = 203.70 / 40
= 2.46 hari = 5.09 hari
= 2.46 X 8 = 5.09 X 8
= 19.66 jam = 40.74 jam
I Lantai 15 I Lantai 15
- Balok 98.29 m³ - Plat 214.58 m³
a. pekerja a. pekerja
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
2.46 5.36
V = 98.29 X 1 V = 214.58 X 1
= 98.29 OH = 214.58 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 98.29 / 40 DP = 214.58 / 40
= 2.46 hari = 5.36 hari
= 2.46 X 8 = 5.36 X 8
= 19.66 jam = 42.92 jam
J Lantai 16 J Lantai 16
- Balok 84.61 m³ - Plat 178.73 m³
a. pekerja a. pekerja
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
2.12 4.47
V = 84.61 X 1 V = 178.73 X 1
= 84.61 OH = 178.73 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 84.61 / 40 DP = 178.73 / 40
= 2.12 hari = 4.47 hari
= 2.12 X 8 = 4.47 X 8
= 16.92 jam = 35.75 jam
K Lantai 17 K Lantai 17
- Balok 88.79 m³ - Plat 184.05 m³
a. pekerja a. pekerja
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam

2.22 4.60
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
2.22 4.60
V = 88.79 X 1 V = 184.05 X 1
= 88.79 OH = 184.05 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 88.79 / 40 DP = 184.05 / 40
= 2.22 hari = 4.60 hari
= 2.22 X 8 = 4.60 X 8
= 17.76 jam = 36.81 jam
L Lantai 18 L Lantai 18
- Balok 50.63 m³ - Plat 108.37 m³
a. pekerja a. pekerja
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
1.27 2.71
V = 50.63 X 1 V = 108.37 X 1
= 50.63 OH = 108.37 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 50.63 / 40 DP = 108.37 / 40
= 1.27 hari = 2.71 hari
= 1.27 X 8 = 2.71 X 8
= 10.13 jam = 21.67 jam
M Lantai 19 M Lantai 19
- Balok 54.27 m³ - Plat 113.79 m³
a. pekerja a. pekerja
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
1.36 2.84
V = 54.27 X 1 V = 113.79 X 1
= 54.27 OH = 113.79 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 54.27 / 40 DP = 113.79 / 40
= 1.36 hari = 2.84 hari
= 1.36 X 8 = 2.84 X 8
= 10.85 jam = 22.76 jam
N Lantai 20 N Lantai 20
- Balok 51.62 m³ - Plat 108.30 m³
a. pekerja a. pekerja
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
1.29 2.71
V = 51.62 X 1 V = 108.30 X 1
= 51.62 OH = 108.30 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 51.62 / 40 DP = 108.30 / 40
= 1.29 hari = 2.71 hari
= 1.29 X 8 = 2.71 X 8
= 10.32 jam = 21.66 jam
O Lantai 21 O Lantai 21
- Balok 51.62 m³ - Plat 108.30 m³
a. pekerja a. pekerja
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
1.29 2.71
V = 51.62 X 1 V = 108.30 X 1
= 51.62 OH = 108.30 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 51.62 / 40 DP = 108.30 / 40
= 1.29 hari = 2.71 hari
= 1.29 X 8 = 2.71 X 8
= 10.32 jam = 21.66 jam
P Lantai 23 P Lantai 23
- Balok 51.62 m³ - Plat 108.30 m³
a. pekerja a. pekerja
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
1.29 2.71
V = 51.62 X 1 V = 108.30 X 1
= 51.62 OH = 108.30 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 51.62 / 40 DP = 108.30 / 40
= 1.29 hari = 2.71 hari
= 1.29 X 8 = 2.71 X 8
= 10.32 jam = 21.66 jam
Q Lantai 25 Q Lantai 25
- Balok 51.62 m³ - Plat 108.30 m³
a. pekerja a. pekerja
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
1.29 2.71
V = 51.62 X 1 V = 108.30 X 1
= 51.62 OH = 108.30 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 51.62 / 40 DP = 108.30 / 40
= 1.29 hari = 2.71 hari
= 1.29 X 8 = 2.71 X 8
= 10.32 jam = 21.66 jam
R Lantai ROOF R Lantai ROOF
- Balok 51.56 m³ - Plat 123.47 m³
a. pekerja a. pekerja
1 m³ = 1.00 OH 1 m³ = 1.00 OH
1 hari = 8.00 jam 1 hari = 8.00 jam
Tenaga = 40 org Tenaga = 40 org
- Pek Cor - Pek Cor
1.29 3.09
1.29 3.09
V = 51.56 X 1 V = 123.47 X 1
= 51.56 OH = 123.47 OH
- Durasi Pekerjaan - Durasi Pekerjaan
DP = 51.56 / 40 DP = 123.47 / 40
= 1.29 hari = 3.09 hari
= 1.29 X 8 = 3.09 X 8
= 10.31 jam = 24.69 jam
38.41 81.32

You might also like