Communication - Reserve Estimation - 30jan2023
Communication - Reserve Estimation - 30jan2023
िवषय: Publishing of Quantum of Reserves in line with Detailed Procedure For Estimation of
the Requirement of Secondary Reserve Ancillary Service (SRAS) and Tertiary Reserve
Ancillary Service (TRAS) at regional level
महोदय,
CERC (Ancillary Services) Regulations, 2022 was notified on 31st January, 2022. As per the
gazette notification of Hon’ble Commission dated 31st October, 2022, the provisions of the
estimation of Secondary Reserve Ancillary Service (SRAS) and Tertiary Reserve Ancillary
Service (TRAS) of these regulations have come into force with effect from 05th December 2022.
In line with above regulations, Grid India submitted interim detailed procedure to CERC and
same was approved by CERC vide letter dated 2nd Dec 2022 (available at
https://posoco.in/download/detailed-procedure-for-estimation-of-the-requirement-of-
secondary-reserve-ancillary-service-sras-and-tertiary-reserve-ancillary-service-tras-at-
regional-level/?wpdmdl=49385 ).
Accordingly, the reserve requirement is assessed in accordance with approved procedures and
declared as follows:
(a) The reference contingency for the All India has been considered as 4500 MW.
(b) Data has been received from Assam, Chhattisgarh, UT Daman Diu, UT Dadra Nagar Haveli,
Gujarat, Goa and Madhya Pradesh.
(c) The secondary reserve requirement is estimated to be 11,052 MW and the tertiary reserve
requirement is estimated to be 16,681 MW for the Quarter 1 of FY 2023-24 (April-Jun).
This needs to be validated with the data provided by the States.
(d) As per Section 8.5 of the approved procedure for estimation of Secondary Reserve “The
all-India total of positive (and negative) secondary reserves capacity requirement on
regional basis shall be equal to the reference contingency or secondary reserve capacity
GRID CONTROLLER OF INDIA LIMITED
(Formerly known as Power System Operation Corporation Limited)
Format – RAS3
Detailed Procedure for Estimation of the Requirement of Secondary Reserve Ancillary Service (SRAS) and Tertiary Reserve Ancillary Service
(TRAS) at Regional Level
GRID CONTROLLER OF INDIA LIMITED
(Formerly known as Power System Operation Corporation Limited)
Format RAS5
Quarter-Ahead SRAS and TRAS Reserve requirement for Quarter 1 (April - June) of Year 2023-24 (Scaled for reference contigency of 4500 MW)
Detailed Procedure for Estimation of the Requirement of Secondary Reserve Ancillary Service (SRAS) and Tertiary Reserve Ancillary Service (TRAS) at Regional Level
GRID CONTROLLER OF INDIA LIMITED
(Formerly known as Power System Operation Corporation Limited)
Format RAS7
Quarter-Ahead ( Apr 2023 - Jun 2023)
Secondary Reserves Tertiary Reserves
State/ Union Territory UT Within in ISGS Within state Total Within in ISGS Within state Total
UT of Chandigarh 14 0 14 14 0 14
Uttarakhand 40 25 65 40 63 103
Goa 26 0 26 26 0 26
Kerala 43 24 67 43 89 132
UT of Puducherry 18 0 18 18 0 18
Sikkim 17 0 17 17 0 17
Arunanchal Pradesh 17 0 17 17 0 17
Assam 57 7 64 57 32 89
Manipur 12 0 12 12 0 12
Meghalaya 27 0 27 27 21 48
Mizoram 9 0 9 9 3 12
Nagaland 10 0 10 10 4 14
Tripura 14 15 28 14 25 39
Detailed Procedure for Estimation of the Requirement of Secondary Reserve Ancillary Service (SRAS) and Tertiary Reserve Ancillary Service
(TRAS) at Regional Level