Professional Documents
Culture Documents
1 s2.0 S0360544217312707 Main
1 s2.0 S0360544217312707 Main
Energy
journal homepage: www.elsevier.com/locate/energy
a r t i c l e i n f o a b s t r a c t
Article history: In this paper, a general model for the optimization of the energy supply systems of buildings is proposed.
Received 6 March 2017 The model is based on a general superstructure that allows to include all the existing and future tech-
Received in revised form nologies, covering heating, domestic hot water, cooling and electricity. The model is linked to a Mixed
23 June 2017
Integer Linear Programming (MILP) problem that allows the selection of equipment and its operation,
Accepted 13 July 2017
Available online 18 July 2017
enabling the minimization of the annual cost for a set of constraints imposed by the designer, such as a
Non-Renewable Primary Energy (NRPE) consumption limit.
The model has been applied to a case study consisting of a domestic building located in Bilbao
Keywords:
Optimization
(Northern Spain). 13 different technologies were taken under consideration together with the specific
MILP conditions of the Spanish context. Three different objectives were determined: (i) the optimal cost; (ii)
nZEB the Zero Energy Building (ZEB); and (iii) the ZEB0 , an alternative ZEB where the whole electricity con-
ZEB sumption is considered for the calculation of the NRPE. The 3 cases were compared and analyzed and,
finally, a parametric evaluation was carried out, setting the aspects that limit the feasibility of low energy
buildings: economic feasibility and physical constraints such as roof availability for renewables.
© 2017 Elsevier Ltd. All rights reserved.
http://dx.doi.org/10.1016/j.energy.2017.07.094
0360-5442/© 2017 Elsevier Ltd. All rights reserved.
E. Iturriaga et al. / Energy 138 (2017) 954e966 955
alternative energy supply systems [5]. Hamdy et al. presented a joint simulation software, to perform a two-step design and operational
optimization of energy saving methods and energy supply systems optimization applied to four commercial buildings in Japan [20],
by parametric analysis, finding the cost optimality for a single- whilst Ren and Gao developed a hierarchical process for the opti-
family house in Finland [6]. For this analysis, 8 different alterna- mization of unit selection and operating scheduling described on a
tive systems where considered in total, covering heating, cooling MILP model [21]. On the other hand, Rezvan et al. calculated the
and electricity production. Analogously, Becchio et al. evaluate the optimal installation that minimizes the operation costs of the
cost-optimality of the renovation of an ex-industrial building, distributed generation system for a hospital in Teheran [22]. Addi-
considering 4 different energy production and renewable energy tionally, Lindberg et al. presented a MILP based optimization model
systems [7]. Owing to the computational expense of each evalua- for the design and operation of energy supply systems considering a
tion, parametric optimizations only consider a limited number of broader set of technologies [23]. However, the set of technologies
alternatives that should be previously defined in detail by the user. and the connections between them were defined a priori, and only
This limitation can be overcome by more sophisticated optimi- continuous load regulation of the technologies was considered.
zation routines, for instance, genetic algorithms. More specifically, The aim of this paper is to present a general model based on
simple genetic algorithms have been extensively used to solve MILP for the optimization of energy supply systems of buildings
many design and control problems in buildings with relative ease under the framework of the nZEB standard. The main contribution
[8]. In the literature, several works coupling genetic algorithms of this paper is the development of a flexible and simple mathe-
with state-of-the-art building energy simulation programs can be matical optimization model that allows the selection of best energy
found, which minimize the number of evaluations. Ferrara et al. use supply system designs, as well as their hourly operation from a
a computing environment that combines TRNSYS, a building quasi-infinite set of solutions. It includes binary variables to cover
simulation environment, with GenOpt®, a generic optimization the operation of the technologies with restricted load regulation by
program, to get cost-optimal designs for a case study situated in using a unit commitment approach. To the best knowledge of the
France. Four different energy supply systems were used for that aim authors, this is an innovative approach not found in any related
and combined with other decision variables; more than ten thou- research up to date, and presents a true potential for facing the
sand building configurations were evaluated [9]. Analogously, implementation of the nZEB standard.
Ascione et al. analyzed the optimal energy retrofit of a hospital, The model is based on the definition of a general superstructure
situated in southern Italy, using genetic algorithms through the that represents all possible technologies, integration patterns and
combination of EnergyPlus and MATLAB [10]. However, although operation strategies for energy supply systems in buildings. The
this approach reduces the number of required energy simulations, mathematical model divides the whole energy supply systems into
these simulations are still costly, and require a detailed definition of different modules that make up the general superstructure. It aims
the building and the solutions to be previously defined ad-hoc by to include all the technologies available in the market, allowing the
the user, i.e. system configuration and operation strategy. energy flow interaction between these modules and the integration
A different approach to these limitations is mathematical pro- within the building environment, such as electrical or district
gramming, such as Mixed-Integer Linear Programming (MILP). heating and cooling networks. The time horizon has been dis-
MILP-based optimization problems have largely been applied to cretized in a set of independent reference days, allowing the model
building design and operation. There is a substantial literature to be optimized by state-of-the-art solvers within acceptable
regarding algorithms for solving MILP models that are used by the calculation times.
state-of-the-art optimization engines, see the seminal work [11], a The model allows the partial load operation of the different
review of the last fifty years in Ref. [12] and algorithmic and technologies within a certain range that depends on the technology
computational examples in Ref. [13]. In general, the decision vari- itself, as well as the unit commitment of the technologies. Even
ables are, schematically, the number of units of each technology to though this leads to significantly higher computational expenses, it
be integrated in the system (integer variables), and their load represents the actual operation of some technologies, such as
condition for each time period (continuous variables). cogeneration devices. The unit commitment problem has been
Focusing on energy supply systems, MILP-based optimization broadly studied in the past decades (see Ref. [24] for a generalized
comprises two different aspects: the design or selection of the formulation) and a series of works have presented specific models
technology and the operation of the selected technologies. for a vast variety of working conditions; see the literature surveys in
Regarding design optimization, Mehleri et al. presented a MILP Refs. [25] and [26].
model for the optimal selection of technologies and pipeline The method is applied to the energy supply system design and
network design at neighborhood level [14]. Similarly, Omu et al. operation of a residential building located in Bilbao (Northern
used a MILP model for the optimization of the location and char- Spain) covering heating, Domestic Hot Water (DHW) and electricity
acteristics of the generation nodes for a cluster of commercial and loads, defined by representative monthly reference days. Main
residential buildings [15]. More recently, Di Somma et al. focused on technologies available in the market have been included in the
a Pareto optimal trade-off between total annual cost and exergy model by self-tailored cost estimation models. Then, the optimal
efficiency for distributed energy systems design optimization [16]. energy supply systems configurations, which minimize the annual
On the other hand, there are in the literature several works con- cost, have been obtained for several NRPE consumption limits. The
cerning operation optimization. Amongst them, Milan et al. pre- case study has the objective of assessing the potential of the
sented an approach for determining, by linear programming, an method rather than showing its full potential; therefore, some
optimal energy supply system consisting of solar systems, energy simplifications were taken for its adaptation to the legal and
storage and heat pumps with the objective of getting a net ZEB for a technical constraints in northern Spain.
case study in Denmark [17], whereas Bischi et al. developed a The rest of the paper is organized in 5 sections, as follows:
detailed MILP model for the optimal short-term operation schedule Section 2 presents the optimization methodology consisting of the
of a cogeneration system [18]. Furthermore, some papers focus on superstructure definition, the economic model and the optimiza-
both design and operation optimization. Wang et al. optimized the tion itself. The methodology is applied to a case study in Section 3,
energy supply of a hotel in Beijing using the energy consumption and the results are covered by Section 4. Section 5 discusses the
and the CO2 emissions by two different objective functions [19]. In a main implications of the model and, finally, the main contributions
bi-level perspective, Ruan et al. used HEATMAP, an energy system of the paper and future research are summarized in Section 6.
956 E. Iturriaga et al. / Energy 138 (2017) 954e966
eOUT
pk ;k;d;h ¼ hNMAN
f ;k $EfNMAN
;k;d;h cf 2FNMAN ; k2K; d2D; h2Hd (4)
2.1.2. Module modeling
Thus, constraint (1) defines the production ratio between the
The different modules include all the technologies with the
main product and the rest of the products. Similarly, equation (2)
same main product. Additionally, they may include any storage
calculates the need for energy consumption from other modules,
device that allows production and load decoupling. The integration
equation (3) defines the need for manageable fuel consumption
of the products of the technologies with the storage and outputs
and, finally, equation (4) defines the need for non-manageable fuel
from the module is schematically depicted by Fig. 4.
consumption; all of them to produce the main product ð pk Þ.
Additionally, equation (5) bounds the maximum production for Every module needs to satisfy the load (Ld;h
s ) at every interval h
the technology, considering all the installed units. Notice that only of every reference day d (for the high temperature heating module,
the production of technologies with full load regulation, set KFR , can this would be equal to zero for new or recently constructed
be aggregated in this way: buildings). Equation (8) defines a module energy balance where the
load should equal the sum of the produced energy ( eOUT s;k;d;h
), the
eOUT MAX
s;k;d;h Es;k $nk cs2S; k2KFR ; d2D; h2Hd (5) resultant of the energy exchanged with the external environment
(the purchased energy, eBUY
s;d;h
, minus the sold energy, eSELL
s;d;h
), minus
The production of technologies with restricted load regulation,
the energy consumption within the system itself ( eIN ) and the
set KRR , is constrained by unit commitment binary variables (ud;h k
), s;k;d;h
see equation (6). As shown in equation (7), such technologies are energy transferred to the storage units, eSTOd;h
s;d;h
.
modeled disaggregated in a unit perspective. Therefore, replicas of
units must be provided to the model in order to allow solutions X X
eOUT BUY
s;k;d;h þ es;d;h eIN SELL STO
s;k;d;h es;d;h es;d;h
with multiple units of these technologies. To ensure consistency, k2K k2K
the lower bound of the number of installed units ( nk ) is set to 1 if a
unit is active in at least one-time interval, or to 0 otherwise. ¼ Ld;h
s cs2S; d2D; h2Hd (8)
beginning of the time interval (qd;h s ) and the energy transferred " #
X X X X
during the interval (eSTO
s;d;h
) are equal to the available storage energy BUY SELL
es;d;h es;d;h $Ws þ OUT
es;k;d;h $Ws;k
for the next interval (qd;hþ1
s ) multiplied by the corresponding effi- s2S d2D h2Hd k2K
0
ciency that accounts for the storage losses ðhQ s Þ: It is important to NRPE LIM (14b)
note that, in order to get a continuous series of daily cycles, the
Secondly, the surface used by the technologies is bounded by
storage units need to be discharged at the first and last interval,
jHd j, of every reference day, see equations (10) and (12). Finally, the the facility area availability, AMAX
j , in the building, see equation (15).
stored energy of each module is upper bounded by the sum of the X
maximum storage capacity, see equation (13), where nTESs is the Aj;k $nk AMAX
j cj2J (15)
number of storage units installed. k2K
d;jHd j
qs þ eSTO
s;d;jHd j ¼ 0 cs2S; d2D (12) Energy supply systems imply an economic impact consisting of
fixed and variable costs. In this paper, the methodology proposed
by the Buildings Performance Institute Europe (BPIE) is considered
qd;h MAX
s Qs $nTESs cs2S; d2D; h2Hd (13) as a reference [28]. This methodology is based on the net present
value method defined by the standard En 15459 [29]. Thus, the
annual cost (Cannual ), considering a lifespan (LS), is defined as
2.1.3. Building constraints follows:
Some complementary constraints could be applied to the " #
XLS
building level. Specifically, a non-renewable primary energy con- annual 1 INI OP
C ¼ C þ Ci $Ri V (16)
sumption goal and facility area availability, such as space on the LS i¼0
roof for renewable or other technologies and space in the boiler
room for the location of the equipment, are here defined. where:
The annual non-renewable primary energy consumption limit is
specified as a new constraint expressed, alternatively, by equations X
CINI ¼ CkINV $nk $ 1 þ fkO&M (17)
(14a) or (14b), where the final energy values were translated into
k2K
primary energy according to [27], using the module and technology
based weighting factors Ws;k and Ws . Constraint (14a) excludes the 2
electricity module from the balance (uses set SNE ), whereas X X X X
CiOP ¼ 4 CsBUY $eBUY SELL SELL
constraint (14b) includes it.
Nd s;d;h Cs $es;d;h þ
d2D h2Hd s2S f 2FMAN
" # 3
X X X X X
eBUY SELL
s;d;h es;d;h $Ws þ eOUT
s;k;d;h $Ws;k CfMAN $eMAN 5
f ;k;d;h
s2SNE d2D h2Hd k2K k2K
NRPELIM (14a) (18)
E. Iturriaga et al. / Energy 138 (2017) 954e966 959
X
LSk 1 eOUT IN
V¼ CkINV $nk $ 1 $ (20) s;k;d;h ; es;k;d;h 0 cs2S; k2K; d2D; h2Hd (25)
k2K
LS ð1 þ rÞLS
d;h
C INI is the initial investment, which is the sum of the annual eBUY SELL
s;d;h ; es;d;h ; qs 0 cs2S; d2D; h2Hd (26)
amortization of the technologies CkINV , multiplied by the number of
installed units, nk , of the corresponding technology. The operation eMAN
f ;k;d;h 0 cf 2FMAN ; k2K; d2D; h2Hd (27)
and maintenance cost is added as a percentage of the investment of
each technology (fkO&M Þ.
CiOP are the yearly variable costs of each technology and consider 3. Case study
the costs and incomes of the system operations throughout the time
In this Section, the optimization method is applied to a case
horizon, in this case discretized in reference days d and intervals h.
study. A recently constructed residential building located in Bilbao
It is calculated by adding the energy bought in each module, eBUY s;d;h
,
(Spain) is considered for this purpose. The scope of the analysis is to
multiplied by the corresponding price, CsBUY , subtracting the income evaluate the optimal installation design for different NRPE con-
obtained from energy sold, eSELL
s;d;h
, multiplied by its price, CsSELL , and sumption limits. For the sake of clarity, only heating, DHW and
finally, by adding the consumed manageable fuel, eMAN , multiplied electric loads are considered in the case study, which is usual in
f ;k;d;h
residential buildings Bilbao owing to the temperate climate in
by the corresponding price of each fuel, CfMAN . northern Spain. The building is grid-connected, but there is no
Finally, Ri is the discount rate for year i and V, the final value of connection for the sale or purchase of thermal energy (i.e. district
technology j at the end of the lifespan of the project, which assigns heating), only heat release is eventually considered as energy sold
an extra cost or benefit when the lifespan of the technology, LSk , is at 0 V/kWh.
lower or higher than the lifespan of the project. The building consists of a new construction building of 9 levels
and 72 dwellings (8 per level) with an average useful area per
2.3. Optimization problem dwelling of 80.6 m2, giving rise to an overall area of 5805 m2. The
building has a total roof area of 687.5 m2, but only 25% is considered
Next, the optimization problem is presented by the objective as net available area for facilities, which means 175 m2. This limi-
function and the bounds for the variables used in the model. The tation to the maximum amount of solar thermal collectors and PV
optimization problem is subjected to the constraints defined by panels to be installed is due to the distance to be kept between
equations (1)e(15), where the energy balance of the different ele- them in order to avoid shading effects. The maximum thermal load
ments of the superstructure is covered. calculation (LPEAK ) of 286 kW was set up for the manageable
S
technologies (150 kW for DHW at MT and 136 for heating at LT).
2.3.1. Objective function Heating, DHW and electricity loads are respectively 20.20 kWh/
The objective function (21) minimizes the annual cost of satis-
m2y (Ld;h 2 d;h 2 d;h
LT ), 19.56 kWh/m y (LMT ) and 35 kWh/m y (LE ) which were
fying the load of each system module. Therefore, the optimization
get from the energy label of the building. These loads are consid-
problem integrates the energy model and the economic models
ered in an aggregated way since the European directive establishes
holistically.
a building-wise balance. These loads are hourly distributed into 12
reference days corresponding to each month. The distribution of
minCannual (21)
the DHW load was made following the guidelines of the Spanish
subject to: Institute for Diversification and Energy Saving (IDAE) [30]. Heating
load distribution was derived from the use of degree-days [31],
Technology energy balance constraints (1) to (7) considering occupation periods and standard daily outdoor tem-
Energy supply systems constraints (8) to (13) perature profiles. The European Electrical Standard profiles, by
Building constraints (14) to (15) Annex 42 of the IEA's ECBCS [32,33], were used for the electricity
Variable bounds (22) to (27) load distribution, where three different periods are defined. Addi-
tionally, global irradiance profiles were obtained for a 45 tilted
surface applying the method proposed by Gudalfajara [34]. These
profiles are presented in detail in Appendix A.
2.3.2. Variable bounds
The technologies considered in the case study are listed in
Variable nk counts the number of installed units of each tech-
Table 1, grouped in different modules, as formerly defined. Addi-
nology; therefore, it is integer and non-negative, see (22). The bi-
tionally, cost and efficiency values for each technology are included
nary variable ud;h
k
defines the commitment status of a unit, see (23). using cost and efficiency estimation models obtained from a self-
Variable eSTO
s;d;h
keeps track of the energy transferred towards the tailored top-down analysis of the Spanish market. In order to deal
storage unit and can be positive (charge) or negative (discharge), with the nonlinearities of these expressions for the integration into
see (24). The rest of the variables are continuous and non-negative, MILP programming, the cost and efficiency correlations for each
see constraints (25) to (27). technology were discretized into a finite set of equipment sizes. The
discretization was made by setting a lower power bound of 0 kW
nk 2Z; nk 0 ck2K (22) and an upper bound equal to the already defined peak power. Thus,
6 equally distributed sizes were taken for each technology. In the
ud;h 2f0; 1g ck2K; d2D; h2Hd (23) case of the solar technologies, the discretization base was the
k
number of panels.
The variable costs associated to the purchase and sale of energy
960 E. Iturriaga et al. / Energy 138 (2017) 954e966
Table 1
Technologies under consideration.
Table 3
Configuration for the three analyzed cases.
Table 4
Operation results for the three analyzed cases.
capacity in the ZEB0 case, as well as the substitution of part of its calculated, referenced to a base case consisting of a 300 kW natural
operation by a biomass boiler. gas boiler where all the electricity is imported from the grid. As the
The electricity load is covered by the CHP and PV production, as annual savings are of the same order for all cases, Payback shows a
well as the electricity imported from the grid. In this case, the trend of its variation with the NRPE limit similar to that shown by
electricity surplus is exported to the grid. The main difference be- the overall investment in Fig. 5.
tween the 3 cases is caused by the presence of the PV power plant, The optimization problem has been parametrically solved to
whose operation cannot be controlled and produces whenever it draw the optimal cost curve. Fig. 6 presents the optimal cost so-
receives radiation, irrespective of whether there are electricity lutions for different NRPE (NRPE and NRPE0 ) consumption limits. In
needs in the building. Electricity production by the CHP is related to this curve, the ZEB and ZEB0 cases are represented and the region of
what was explained for the heat production. The highest amount of feasible solutions is shadowed in grey.
imported electricity occurs in the ZEB case. In this case, the NRPE It can be seen that the optimal energy supply system solutions
limits the heat release and, therefore, the CHP operation are not economically feasible for NRPE limits below 26 kWh/m2y
(PES ¼ 12.88%), while, at the same time, the PV plant is much (NRPE’ ¼ 66.1 kWh/m2y), owing to payback values higher than the
smaller than in the ZEB0 case. lifespan of the plant (20 years). Thus, the ZEB case is achievable, but
The economic analysis is presented below. The investment not if the electricity load is considered within the energy con-
required for the different cases is presented in Fig. 5, where the sumption of the building, that is, ZEB0 is not achievable for the case
contribution of each technology to the total can be observed. It can study under consideration. Additionally, the solution where the
be seen that the PV power plant has the greatest impact on overall roof limit of the building is reached is represented in Fig. 6. As
investment, especially when the electric consumption of the stated, this limit occurs for an NRPE consumption slightly higher
dwellings is taken into consideration (ZEB0 ). than 0 (2 kWh/m2y), meaning that all the optimal energy supply
The economic analysis is evaluated by comparing the invest- solutions below this NRPE value require the installation of a PV
ment with the annual savings. The feasibility is evaluated by simple power plant nearby.
Payback and all the data is summarized in Table 5.
The variable costs represent the cost of the fuel needed for the 5. Discussion
operation of the plant plus the maintenance costs. The annual cost
includes, on an annual basis, the variable costs plus the amortiza- This work has presented a general model for the optimization of
tion traceable to a single year. Then, the annual savings are energy supply systems of buildings. The framework is based on the
962 E. Iturriaga et al. / Energy 138 (2017) 954e966
supply systems and energy saving measures. Energy supply sys- KMAN Manageable technologies ðKMAN 4KÞ, k
tems were covered by this work, but further research is needed KFR Technologies with full load regulation ðKFR 4KÞ, k
dealing with the integration of energy saving alternatives in the KRR Technologies with restricted load regulation ðKRR 4KÞ, k
optimization model. This entails the challenge of discretizing the S Modules, s
effects of the energy saving measures, i.e. facades, windows, etc., S Principal output module of a technology (pk 2S), pk
throughout the time horizon and will be covered in the near future. SNE Modules, excluding electricity ðSNE 4SÞ, k
FMAN Manageable fuels, f
6. Conclusions FNMAN Non-manageable fuels, f
D Reference days, d
In a context of energy transition and, specifically, under the need Hd Intervals in a reference day, h
for defining and developing the nZEB concept; a general model for J Facility location, j
the optimization of the design and operation of energy supply
systems of buildings has been proposed. Even though several Decision variables
optimization models can be found in the bibliography, none include nk Number of installed units of a technology
such a detailed treatment of the different elements that play a ud;h Commitment state of a unit
k
significant role in the energy supply system operation. In this paper,
eOUT
s;k;d;h
Total produced energy (kWh/h)
a general superstructure has been presented, making it possible to
include all the existing and future technologies covering heating, eIN
s;k;d;h
Total consumed energy (kWh/h)
DHW, cooling and electricity. The model allows the selection of eBUY Energy bought by the system (kWh/h)
s;d;h
equipment and its operation for a given set of load profiles. The
eSELL
s;d;h
Energy sold by the system (kWh/h)
operation includes the unit commitment of technologies with
limited load regulation capacity through binary control. This is a eSTO
s;d;h
Energy transferred to storage (kWh/h)
novel approach for this kind of analysis, allowing a more realistic eMAN Manageable fuel input (kWh/h)
f ;k;d;h
characterization of the hourly behavior of the technologies, at the
price of a significantly longer elapsed time for resolution. qd;h
s Stored energy at the beginning of the interval (kWh)
Thus, the proposed method allows the design energy supply
system for new and existing buildings; in the former, the optimi- Constant parameters
zation should be made along with the load optimization through Nd Yearly number of days of a reference day
energy saving methods. The model can be applied to minimize the Ld;h
s Load (kWh/h)
annual cost, but other different objective functions could be LPEAK
s Maximum load (kW)
applied, as well as constraints imposed by the designer. MAX
Es;k Production at maximum power (kW)
The model has been applied to a case study consisting of a do- MIN
Es;k Production at minimum power (kW)
mestic building located in Bilbao (Northern Spain) to get the
MAX
Qs;k Maximum storage capacity (kWh)
optimal energy supply system to meet heating, DHW and electricity
load. Cost estimation models have been determined and used to NPRELIM Non-renewable primary energy consumption limit,
include the performance and cost of each one of the 13 technologies excluding electricity (kWh/y)
under consideration. Three cases have been evaluated: the optimal NPRE LIM
0
Non-renewable primary energy consumption limit,
cost, the ZEB and the ZEB0 , an alternative ZEB where the whole including electricity (kWh/y)
electricity consumption is also considered for the calculation of the
AMAX
j Available area in a facility location (m2)
NRPE. The model offered different energy supply system configu-
rations, as well as its operation. The implications of the 3 cases were Aj;k Facility location area used by a technology unit (m2)
compared and analyzed and, finally, a parametric evaluation was Ws Module based primary energy weighting factors
carried out in order to set the aspects that limit the feasibility of low Ws;k Module and technology based primary energy weighting
energy buildings: economic feasibility and physical constraints factors
such as roof availability for renewables. EfNMAN
;k;d;h
Non-manageable fuel input (kWh/h)
Thus, the model showed a capacity for energy planning and fast
hQs Storage efficiency
estimation of the impact of different systems for the goals of
hOUT Production ratio with respect to the principal
reducing the NRPE towards the NZEB definition. s;k
hIN
s;k
Consumption ratio with respect to the principal
Acknowledgements hMAN
f ;k
Manageable fuel input ratio with respect to the principal
hNMAN
f ;k
Non-manageable fuel input ratio with respect to the
This research is supported by the Bizkaia Talent and European
principal
Commission through the COFUND program, awarded in the 2015
Aid Programme for Researchers with request reference number CkINV Initial investment cost (V)
AYD-000-280, and also by the Basque Government through the CsBUY Purchase cost (V/kWh)
BERC 2014e2017 program and by Spanish Ministry of Economy and CsSELL Sale income (V/kWh)
Competitiveness MINECO: BCAM Severo Ochoa excellence accred- CfMAN Purchase cost of manageable fuels (V/kWh)
itation SEV-2013-0323.
Appendix B. Definition of reference days for the case study
Appendix A. Nomenclature
Table A.1
DHW energy load (kWh/h). Hourly distribution for monthly reference day
Jan. Feb. Mar. Apr. May June July Aug. Sep. Oct. Nov. Dec.
1 3.96 3.88 3.88 3.88 3.72 3.56 3.39 3.39 3.48 3.56 3.80 3.88
2 1.65 1.62 1.62 1.62 1.55 1.48 1.41 1.41 1.45 1.48 1.58 1.62
3 1.32 1.29 1.29 1.29 1.24 1.19 1.13 1.13 1.16 1.19 1.27 1.29
4 0.66 0.65 0.65 0.65 0.62 0.59 0.57 0.57 0.58 0.59 0.63 0.65
5 0.66 0.65 0.65 0.65 0.62 0.59 0.57 0.57 0.58 0.59 0.63 0.65
6 1.98 1.94 1.94 1.94 1.86 1.78 1.70 1.70 1.74 1.78 1.90 1.94
7 8.91 8.73 8.73 8.73 8.36 8.00 7.64 7.64 7.82 8.01 8.55 8.73
8 33.01 32.34 32.34 32.32 30.98 29.63 28.29 28.29 28.96 29.65 31.67 32.34
9 23.11 22.64 22.64 22.63 21.69 20.74 19.80 19.80 20.27 20.75 22.17 22.64
10 24.76 24.26 24.26 24.24 23.23 22.22 21.21 21.21 21.72 22.24 23.75 24.26
11 20.47 20.05 20.05 20.04 19.21 18.37 17.54 17.54 17.95 18.38 19.63 20.05
12 18.49 18.11 18.11 18.10 17.35 16.59 15.84 15.84 16.22 16.60 17.73 18.11
13 15.85 15.52 15.52 15.52 14.87 14.22 13.58 13.58 13.90 14.23 15.20 15.52
14 15.85 15.52 15.52 15.52 14.87 14.22 13.58 13.58 13.90 14.23 15.20 15.52
15 13.54 13.26 13.26 13.25 12.70 12.15 11.60 11.60 11.87 12.16 12.98 13.26
16 10.89 10.67 10.67 10.67 10.22 9.78 9.33 9.33 9.56 9.78 10.45 10.67
17 12.88 12.61 12.61 12.61 12.08 11.56 11.03 11.03 11.29 11.56 12.35 12.61
18 12.55 12.29 12.29 12.28 11.77 11.26 10.75 10.75 11.00 11.27 12.03 12.29
19 17.17 16.82 16.82 16.81 16.11 15.41 14.71 14.71 15.06 15.42 16.47 16.82
20 23.11 22.64 22.64 22.63 21.69 20.74 19.80 19.80 20.27 20.75 22.17 22.64
21 18.82 18.43 18.43 18.43 17.66 16.89 16.12 16.12 16.51 16.90 18.05 18.43
22 20.80 20.38 20.38 20.36 19.52 18.67 17.82 17.82 18.24 18.68 19.95 20.38
23 15.85 15.52 15.52 15.52 14.87 14.22 13.58 13.58 13.90 14.23 15.20 15.52
24 17.17 16.82 16.82 16.81 16.11 15.41 14.71 14.71 15.06 15.42 16.47 16.82
Table A.2
Space heating load (kWh/h). Hourly distribution for monthly reference day
Jan. Feb. Mar. Apr. May June July Aug. Sep. Oct. Nov. Dec.
1 32.06 31.57 26.58 22.96 13.17 0.00 0.00 0.00 0.00 10.74 22.28 29.87
2 33.37 33.02 28.17 24.53 14.77 0.00 0.00 0.00 0.00 12.32 23.61 31.13
3 34.57 34.35 29.63 25.98 16.25 0.00 0.00 0.00 0.00 13.76 24.84 32.29
4 35.73 35.63 31.04 27.37 17.67 0.00 0.00 0.00 0.00 15.16 26.03 33.40
5 36.65 36.66 32.16 28.48 18.81 0.00 0.00 0.00 0.00 16.27 26.97 34.29
6 36.79 36.81 32.33 28.65 18.97 0.00 0.00 0.00 0.00 16.43 27.11 34.42
7 35.48 35.36 30.74 27.08 17.37 0.00 0.00 0.00 0.00 14.86 25.78 33.17
8 42.11 41.66 36.72 33.09 23.31 0.00 0.00 0.00 0.00 20.88 32.34 39.91
9 37.78 36.86 31.44 27.87 17.99 0.00 0.00 0.00 0.00 0.00 27.90 35.73
10 33.02 31.59 25.65 22.13 0.00 0.00 0.00 0.00 0.00 0.00 23.02 31.14
11 28.72 26.82 20.42 16.95 0.00 0.00 0.00 0.00 0.00 0.00 18.62 27.00
12 25.33 23.06 16.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 23.73
13 22.85 20.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21.33
14 21.16 18.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19.71
15 20.40 17.59 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18.97
16 20.87 18.12 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 19.43
17 22.77 20.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 21.26
18 25.79 23.58 16.86 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 24.18
19 29.25 27.41 21.07 17.59 0.00 0.00 0.00 0.00 0.00 0.00 19.16 27.51
20 32.42 30.92 24.92 21.41 0.00 0.00 0.00 0.00 0.00 0.00 22.41 30.56
21 34.95 33.72 28.00 24.45 0.00 0.00 0.00 0.00 0.00 0.00 25.00 33.00
22 36.92 35.91 30.40 26.84 16.93 0.00 0.00 0.00 0.00 0.00 27.02 34.90
23 38.63 37.80 32.48 28.89 19.03 0.00 0.00 0.00 0.00 16.68 28.77 36.55
24 30.59 29.94 24.79 21.18 11.36 0.00 0.00 0.00 0.00 8.97 20.77 28.45
Table A.3
Electricity load (kWh/h). Hourly distribution for monthly reference day
Jan. Feb. Mar. Apr. May June July Aug. Sep. Oct. Nov. Dec.
1 19.22 19.22 16.44 16.44 16.44 18.67 18.67 18.67 16.44 16.44 16.44 19.22
2 15.65 15.65 13.76 13.76 13.76 15.95 15.95 15.95 13.76 13.76 13.76 15.65
3 13.27 13.27 11.44 11.44 11.44 13.11 13.11 13.11 11.44 11.44 11.44 13.27
4 12.34 12.34 11.18 11.18 11.18 12.94 12.94 12.94 11.18 11.18 11.18 12.34
5 11.83 11.83 11.02 11.02 11.02 12.18 12.18 12.18 11.02 11.02 11.02 11.83
6 12.01 12.01 11.63 11.63 11.63 11.78 11.78 11.78 11.63 11.63 11.63 12.01
7 14.36 14.36 14.53 14.53 14.53 12.94 12.94 12.94 14.53 14.53 14.53 14.36
8 21.88 21.88 19.29 19.29 19.29 14.81 14.81 14.81 19.29 19.29 19.29 21.88
9 24.95 24.95 22.41 22.41 22.41 18.74 18.74 18.74 22.41 22.41 22.41 24.95
10 25.53 25.53 23.29 23.29 23.29 20.18 20.18 20.18 23.29 23.29 23.29 25.53
11 24.12 24.12 23.96 23.96 23.96 22.16 22.16 22.16 23.96 23.96 23.96 24.12
12 25.13 25.13 23.82 23.82 23.82 24.04 24.04 24.04 23.82 23.82 23.82 25.13
E. Iturriaga et al. / Energy 138 (2017) 954e966 965
Jan. Feb. Mar. Apr. May June July Aug. Sep. Oct. Nov. Dec.
13 25.61 25.61 25.01 25.01 25.01 24.83 24.83 24.83 25.01 25.01 25.01 25.61
14 26.78 26.78 24.38 24.38 24.38 24.88 24.88 24.88 24.38 24.38 24.38 26.78
15 26.05 26.05 24.19 24.19 24.19 23.78 23.78 23.78 24.19 24.19 24.19 26.05
16 28.82 28.82 24.86 24.86 24.86 23.87 23.87 23.87 24.86 24.86 24.86 28.82
17 35.57 35.57 28.82 28.82 28.82 24.80 24.80 24.80 28.82 28.82 28.82 35.57
18 41.40 41.40 30.17 30.17 30.17 27.90 27.90 27.90 30.17 30.17 30.17 41.40
19 44.98 44.98 32.15 32.15 32.15 27.90 27.90 27.90 32.15 32.15 32.15 44.98
20 43.99 43.99 34.94 34.94 34.94 28.41 28.41 28.41 34.94 34.94 34.94 43.99
21 41.04 41.04 34.70 34.70 34.70 27.60 27.60 27.60 34.70 34.70 34.70 41.04
22 37.41 37.41 32.11 32.11 32.11 29.45 29.45 29.45 32.11 32.11 32.11 37.41
23 31.92 31.92 27.65 27.65 27.65 28.01 28.01 28.01 27.65 27.65 27.65 31.92
24 24.76 24.76 21.54 21.54 21.54 23.83 23.83 23.83 21.54 21.54 21.54 24.76
Table A.4
Irradiance (kW/m2) on a 45 inclined surface. Hourly distribution for monthly reference day
Jan. Feb. Mar. Apr. May June July Aug. Sep. Oct. Nov. Dec.
1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
5 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 0.00 0.00 0.00 0.00 0.02 0.04 0.03 0.01 0.00 0.00 0.00 0.00
7 0.00 0.00 0.02 0.05 0.09 0.10 0.10 0.07 0.04 0.00 0.00 0.00
8 0.01 0.05 0.10 0.12 0.17 0.17 0.18 0.14 0.13 0.10 0.02 0.00
9 0.08 0.14 0.19 0.20 0.26 0.25 0.26 0.22 0.23 0.21 0.10 0.06
10 0.16 0.23 0.28 0.27 0.34 0.32 0.34 0.30 0.33 0.32 0.18 0.12
11 0.22 0.30 0.36 0.33 0.40 0.37 0.40 0.35 0.41 0.40 0.25 0.18
12 0.26 0.34 0.40 0.36 0.43 0.40 0.44 0.39 0.45 0.45 0.29 0.21
13 0.26 0.34 0.40 0.36 0.43 0.40 0.44 0.39 0.45 0.45 0.29 0.21
14 0.22 0.30 0.36 0.33 0.40 0.37 0.40 0.35 0.41 0.40 0.25 0.18
15 0.16 0.23 0.28 0.27 0.34 0.32 0.34 0.30 0.33 0.32 0.18 0.12
16 0.08 0.14 0.19 0.20 0.26 0.25 0.26 0.22 0.23 0.21 0.10 0.06
17 0.01 0.05 0.10 0.12 0.17 0.17 0.18 0.14 0.13 0.10 0.02 0.09
18 0.00 0.00 0.02 0.05 0.09 0.10 0.10 0.07 0.04 0.00 0.00 0.00
19 0.00 0.00 0.00 0.00 0.02 0.04 0.03 0.01 0.00 0.00 0.00 0.00
20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
[23] Lindberg KB, Fischer D, Doorman G, Korpås M, Sartori I. Cost-optimal energy general de urbanismo y política de vivienda. 2009. p. 23. Anexo III.
system design in Zero Energy Buildings with resulting grid impact: a case [31] Erbs DG, Klein SA, Beckman WM. Estimation of degrees-days and ambient
study of a German multi-family house. Energ Build 2016;127. 860e845. temperature bin data from monthly average temperatures. Ashrae J 1983;25:
[24] Baldick R. The generalized unit commitment problem. IEEE Trans Power Syst 60e5.
1995;10:65e475. [32] Standard European Electrical Profiles. IEA/ECBCS Annex 42. The simulation of
[25] Sheble GB, Fahd GN. Unit Commitment literature synopsis. IEEE Trans Power building-integrated fuel cell and other cogeneration systems. 2006.
Syst 1994;9:28e135. [33] Kreutzer N, Knight I. Social housing electrical energy consumption profiles in
[26] Padhy NP. Unit commitment-a bibliographical survey. IEEE Trans Power Syst the United Kingdom. In: 2nd international solar cities congress; 2006.
2004;19:1196e205. [34] Guadalfajara M. Evaluacio n de centrales solares te rmicas con acumulacion
[27] Factores de emisio n de CO2 y coeficientes de paso a energía primaria de estacional para el sector residencial en Espan ~ a. Trabajo Fin de Ma
ster. Uni-
diferentes fuentes de energía final consumidas en el sector de edificios en versidad de Zaragoza; 2013.
Espan~ a. Ministerio de Industria, Energía y Turismo; 2016. Documento reco- [35] Duffie John A, Beckman William A. Solar engineering of thermal processes.
nocido vigente a partir del 14 de Enero del. third ed. Wiley; 2006.
[28] Optimality Cost. Discussing methodology and challenges within the recast [36] Alonso Abella M, Chenlo F. Estimacion de la energía generada por un sistema
energy performance of buildings directive. Buildings Performance Institute fotovoltaico conectado a red. CIEMAT. Laboratorio de sistemas fotovoltaicos;
Europe (BPIE) Factsheet. 2010. 2005.
[29] EN 15459-Energy performance of buildings. Economic evaluation procedure [37] Real Decreto 616/2007, de 11 de mayo, sobre fomento de la cogeneracio n.
for energy systems in buildings. [38] IBM ILOG CPLEX optimizer. Website. http://www01.ibm.com/software/
[30] Condiciones de aceptacio n para programas informa ticos alternativos a LIDER y commerce/optimization/cplex-optimizer/.
CALENER. IDAE (Ministerio de Industria, Consumo y Comercio) y Direccio n [39] MATLAB version R2014a. Natick. Massachusetts: The MathWorks Inc.; 2014.