Professional Documents
Culture Documents
Draft
Standard Bidding Documents
Procurement of Works
Introduction....................................................................................................................
[date]
According to the authorization of the Employer, [Full Name of Executive Agency] invite
eligible (local or local and foreign) bidders to bid for the following package (more specific
information may be added if necessary) :
[Scope of Work}:
[Source of Fund]:
[Name of Project and General Description of the Project]:
Interested Bidders may obtain further information and purchase the Bid Document from the
Employer from ………..(hour)…………..(date) ………….(month)………to ………..(hour)
…………..(date) ………….(month)………at the office of:
(Note: This Announcement of Bid shall only be used on public media and should not be
included in the Bid Document)
6
Date………..Month…………Year…………
[Full Name of Employer] intends to call bids for procurement of works for the following
project (indicate the following principle information):
[Name of Project}:
[Source of Fund]:
[General Description of Project]:
[Scope of Work]:
(Name of Employer) invite (…) to bid. A complete set of bidding documents may be
purchased by interested bidders upon payment of a nonrefundable fee of ……. from …am to
…pm on …/…/200.. to …/…/200..at the office of :
Bids must be delivered to the above office on or before [time] (Vietnamese time) on [date]
(called Deadline for submission of bids). Bids shall remain valid for the period of …. days
counting from the Deadline for submission of bids.
Bids must be accompanied by a security of [fixed sum in figure and in words]. Bid security
must be submitted with the Bid or sent to the above office on or before the deadline for
submission of bids. Validity period of the bid security shall be … days [indicate specific
number of days and normally, it is equal to validity period of Bid plus 30 days] counting
from the deadline for submission of bids.
Bids will be opened in the presence of bidders’ representatives who choose to attend at [time
and date] at the offices of [address of appropriate office]. The Employer invites the Bidder
to attend the Bid Opening Ceremony.
PURCHASER
[Signed and Sealed]
7
Instruction to Bidders provide the information necessary for bidders to prepare responsive
bids in accordance with the requirements of the Employer. This section also gives
information on bid submission, opening, and evaluation, and on the award of contract.
Section II.2. Bid Data Sheet consists of provisions that supplement, amend, or specify
in detail information or requirements included in Section II.1 and which are specific
to each procurement.
A. GENERAL
1. Scope of Bid 1.1 The Employer wishes to invite Bids for the construction of Project
Name of project and scope of work as described in the Bid Data
Sheet.
2. Source of Funds The Employer has received funds for the Project as specified in the
Bid Data Sheet.
3. Eligible Bidders 3.1. This Invitation for Bids is open to all Bidders and firms which are
legally set up, having legal business registration (under the law of
Bidder’s country) and registered business areas appropriate to the
scope of works, having essential financial capacity, experience and
technical capability to execute and complete the Works as
specified in the Bidding Documents, having fulfilled all of its
taxation obligations, not being listed as the prohibited bidders in
Vietnam and meeting all the requirements applied by the Lender
and other requirements as specified in the Bid Data Sheet.
4. Qualification of 4.1 Bidders shall meet the minimum qualification criteria on capability
the Bidder and experience as defined in Sub-Clause 4.2, and shall submit the
documents as specified in Sub-Clause 12 to demonstrate their
capability and experience.
4.2.1. During the last five (5) years, Bidders shall have experience as a
prime contractor or a partner of joint venture in the role of
construction and installation. Number and scope of projects shall
be specified in the Bid Data Sheet.
performed during the last 3 years shall meet the minimum criteria
specified in the Bid Data Sheet.
4.2.3. Liquid assets and/or credit facilities shall meet the minimum
criteria specified in the Bid Data Sheet.
4.2.5. Site manager and key technical personnel shall be engineer in the
area appropriate to the scope of works and have experience in
works similar to this contract at least 5 years or shall meet the
requirements specified in the Bid Data Sheet.
4.3.1. The Bidder shall submit the documents as specified in Clause 12.
4.3.3. Unless otherwise specified in the Bid Data Sheet, the capability of
the joint venture shall be total capability of all member of the joint
venture.
5. One Bid per 5.1 Each Bidder shall submit only one Bid, either by himself, or as a
Bidder partner in a joint venture. All Bids submitted or participated by a
Bidder who submits or participates in more than one Bid (except
the case of being sub-contractor or proposal of alternative bid as
permitted) shall be disqualified. In case a Corporation to be named
as a Bidder, its units which are financial dependent shall not be
allowed to submit Bids either by itself or as a partner in a
consortium.
6. Cost of Bidding 6.1 The Bidder shall bear all costs associated with the preparation and
submission of his Bid as well as the expenses for contract
negotiation and completion thereafter.
7. Site Visit and 7.1 The bidder is advised to visit and examine the Site of Works and
Pre-Bid its surroundings and obtain for itself on its own responsibility all
Meeting information that may be necessary for preparing the bid. The costs
of visiting the Site shall be at the bidder’s own expense.
The time and detailed plan for the pre-Bid meeting and site
visit (if any) are specified in the Bid Data Sheet or will be
10
All matters discussed during the site visit and the pre-Bid
meeting shall be recorded in the Minutes of Meeting by the
Employer and it will be sent to each Bidder including those
who did not participate in the site visit or the pre-Bid meeting.
B. BIDDING DOCUMENTS
8. Content of 8.1 The set of Bidding documents comprises 6 sections listed in the
Bidding table below:
Documents
Section I: Invitation for Bids
Section II: Instructions to Bidders
Section III: Contract Agreement and Conditions of Contract
Section IV: General Information of Project
Section V: Specifications and Drawings
Section VI: Bill of Quantities
Section VII: Form of Bid and Other Forms
10. Amendment of 10.1 At any time, but no later than 10 days prior to the deadline for
Bidding submission of Bids, the Employer, for any reason, may modify the
Documents Bidding Documents by issuing addenda. In case of amendment of
Bidding Documents, Bidder may require clarification of the
Amendment of Bidding Documents and the Employer shall
respond to any request for clarification received earlier than 10
days prior to the deadline for submission of Bids.
11
10.2 Any addendum thus issued shall be part of the Bidding documents
and shall be communicated in writing or by cable to all purchasers
of the Bidding Documents. Prospective Bidders shall
acknowledge receipt of each addendum by cable to the Employer
and the original of acknowledgement shall be enclosed in the Bid.
C. PREPARATION OF BIDS
11. Language of 11.1 The bid, and all correspondence and documents related to the bid
Bid exchanged by the bidder and the Employer shall be written in the
bid language stipulated in the Bid Data Sheet. Supporting
documents and printed literature furnished by the bidder may be in
another language provided they are accompanied by an accurate
translation of the relevant passages in the above stated language, in
which case, the Bidder shall be responsible for the accuracy of the
translation.
12. Documents 12.1 The Bid submitted by the Bidder shall comprise the following:
Comprising the
Bid (a) The Bid
(b) Bid Security;
(c) Price Schedule (in the form provided in the Bidding
Document);
(d) List of documents received by the Bidder including all
Bidding Documents, clarifications and addendum
(e) Documents demonstrating the legal status, capacity and
experience of the Bidder.
(f) Bidder’s site organization and proposed technical solutions
(g) Alternative offers where invited;
12.2 To comply with clause 3 and sub-clause 12.1 (e), Bidders shall
submit with their Bids, documentary evidence that the Bidder was
legally set up and obtained legal business registration to allow the
Bidder doing business in the sector suitable to the required scope
of the works. The person signing the Bid shall be legal
1
Note: Time periods mentioned in ITB 8 and 9 can be shorter in case of small package and shall be specified in
the Bid Data Sheet.
12
- Plan for mobilizing liquid assets for the project: Bidders shall
submit a plan for mobilizing liquid assets (equity and/or loans
commitment) to meet the required construction schedule. The
minimum liquid assets of Bidders shall be not less than the
minimum value specified in sub-clause In case the liquid assets is
less than the required amount, the Bidders may provide credit-line
from banks for this project with the value equal to the deficient
capital.
14. Currencies of 14.1 Unit rates and prices shall be quoted by the Bidder entirely in
Bid and Payment Vietnamese Dong except otherwise specified in the Bid Data
Sheet.
15. Bid Validity 15.1 Bids shall remain valid for the period specified in the Invitation for
Bids after the closing time. A bid offers the validity for a shorter
period shall be rejected by the Employer as non-responsive.
16. Bid Security According to Clause 12.1, the Bidder shall furnish, as part of the
Bid, a Bid Security in the currency and amount specified in the
Invitation for Bids.
16.2 Any Bid not accompanied by Bid Security as required above shall
be rejected by the Employer.
16.4 The Bid Security of the successful Bidder will be discharged when
the Bidder has signed the Contract Agreement and furnished the
required Performance Security as specified in Clause 32.
(a) if the Bidder withdraws the Bid after Bid opening during the
period of Bid validity;
(b) in the case of a successful Bidder, if the Bidder fails within the
specified time limit to
(i) sign the Agreement; or
(ii) furnish the required Performance Security.; or
17. Alternative 17.1 Bidders may submit alternative offers provided that they comply
Proposals by with the requirements of the Bidding documents. Alternatives will
Bidders only be considered, if allowed in the Bid Data Sheet.
18. Format and 18.1 The Bidder shall prepare one original of bid comprising the
Signing of Bid documents as described in Clause 12 of these Instructions to
Bidders, bound with the volume containing the Form of Bid, and
clearly marked “ORIGINAL.” In addition, the Bidder shall submit
five n (05) copies of the Bid (or in the number specified in the Bid
Data Sheet), and clearly marked as “COPIES.” In the event of
discrepancy between them, the original shall prevail.
18.2 The original and the copies of the bid shall be typed or written in
indelible ink and shall be paged continuously. The Bid Form, all
pages of amended printed literature, guaranteed technical
characteristics and modification or clarification of the Bid (in the
original copy of the Bid) shall be initialed by a person or persons
duly authorized to bind the Bidder to the contract. In case the
person duly authorized signed the Bid, the Bid should be
accompanied by a power of attorney as indicated in the ITB Clause
12.6.
D. SUBMISSION OF BIDS
19. Sealing and 19.1 The Bidder shall seal their Bids by it own way. The Bids should be
Marking of Bids clearly marked as “ORIGINAL” and “COPIES”.
(c) provide a statement “DO NOT OPEN BEFORE [date & time],
to be completed with the time and date for Bid opening as
specified in the Bid Data Sheet.
19.4 If the outer envelope is not sealed and marked as above, the
Employer will assume no responsibility for the misplacement or
premature opening of the Bid.
20. Deadline for 20.1 Bids shall be delivered to the Employer at the address specified
Sub-mission of above not later than the time and date specified in the Bid Data
Bids Sheet.
20.2 The Employer may extend the deadline for submission of Bids in
accordance with Clause 10, in which case all rights and obligations
of the Employer and the Bidders previously subject to the original
deadline will then be subject to the new deadline.
21. Late Bids 21.1 Any Bid received by the Employer after the deadline prescribed in
Clause 20 will be returned unopened to the Bidder when it is
received at the address for submission of bids.
22. Modification 22.1 Bidders may modify or withdraw their Bids provided that the
and Withdrawal notice of modification or withdrawal of bid is received by the
of Bids Employer before the deadline for submission of Bids.
22.4 Bidders are not permitted to withdraw their Bids during the period
between the deadline for submission of Bids and the expiration of
the period of Bid validity as stated in their Bid Form or as
extended pursuant to Sub-Clause 15.2. If they do so, it may result
in the forfeiture of the Bid Security pursuant to Clause 16.
23. Bid Opening 23.1 The Employer will open the Bids at the time and address specified
in the Invitation for Bids. The Bidder’s representatives shall be
invited to attend the Bid opening and sign the Minute of Bid
Opening.
23.2 The Bidders’ names, the Bid prices as stated in Bid Form, Bid price
for alternative Bid (if alternatives have been requested or
19
23.3 The Minute of Bid Opening shall be sent to the Bidder whose
Representative attended the Bid Opening.
24. Clarification 24.1 During the evaluation of bids, the Employer may, at the
of Bids Employer’s discretion, ask any Bidder for clarification of the
Bidder’s Bid. Request and responses thereto shall be made in
writing. No change in the price or substance of the Bid shall be
sought, offered, or permitted.
24.2 The Purchaser may, if necessary, at its discretion, ask the Bidder
for extension of the validity of its Bids and bid security
respectively. The content of the request for extension shall be
provided in the letter of request sent to the Bidder. Bidder, at its
discretion, may refuse the extension of bid validity without
forfeiting its bid security.
25. Primary 25.1 Prior to the detailed evaluation of Bids, the Employer will
Examination of determine whether each Bid (a) meets the eligibility criteria defined
Bids and in Clause 3; (b) has been properly signed; (c) is accompanied by
Determination of the required Bid securities; (d) is substantially responsive to the
Responsiveness precedent requirements of the Bidding documents.
25.3 Bids may be rejected by the Employer for the reasons including,
but not limited to;
(d) The required bid security is not furnished or the amount of bid
security is insufficient or the validity of the bid security is
shorter than the required period;
(e) Bid is not signed properly (or lack of proper seal in case of
local bidder)
26.2 The amount stated in the Bid will be adjusted by the Employer in
21
27. Conversion to For comparison of Bids, the Employer shall convert Bid price to
Single
single currency as specified in Bid Data Sheet with the exchange
Currency
rate published by State Bank of Vietnam on the date of bid
opening.
28. Evaluation 28.1 The Employer will evaluate and compare only the Bids determined
and Comparison to be substantially responsive in accordance with Clause 25&26.
of Bids
28.2 The Employer will evaluate the Bids in the following 2 steps.
* Time schedule;
28.3 The Employer reserves the right to accept or reject any variation or
alternative offer. Where the alternative offer is invited, only the
alternative offer of the Bidder whose Bid is determined to be the
lowest evaluated Bid will be considered for evaluation and contract
negotiation. Variations and alternative offers and other factors
which are in excess of the requirements of the Bidding documents
or otherwise result in unsolicited benefits for the Employer will not
be taken into account in Bid evaluation.
F. AWARD OF CONTRACT
29. Award 29.1 Subject to Clause 30, the Employer will award the Contract to the
Criteria Bidder whose Bid has been determined to be substantially
responsive to the Bidding documents and lowest evaluated Bid
price and whose proposed price for award contract is within the
approved bidding plan, provided that such Bidder has been
determined to be (a) eligible in accordance with the provisions of
Clause 3, and (b) qualified in accordance with the provisions of
Clause 4.
30. Employer’s 30.1 The Employer reserves the right to accept or reject any Bid, and to
Right to Accept cancel the Bidding process and reject all Bids, at any time prior to
any Bid and to the award of Contract, without thereby incurring any liability to
Reject any or all the affected Bidder or Bidders or any obligation to inform the
Bids affected Bidder or Bidders of the grounds for the Employer’s
23
action.
31. Notification of 31.1 Upon the approval of bidding result, the Employer shall invite the
Award and first ranking Bidder to negotiate the contract. The purpose of the
Signing of contract negotiation is to clarify and modify those matters that
Agreement have arisen during the invitation, submission and evaluation of
Bids.
31.2 Within 30 days of receipt of the Notification of Award, the
successful Bidder shall negotiate with the Employer to complete
and sign the Contract between the Employer and successful
Bidder shall consist of all agreements between two parties.
32. Performance 32.1 Within 15 days after receipt of the Notification of Award, the
Security successful Bidder shall deliver to the Employer a Performance
Security in the amount of 10% of the contract price in accordance
with the conditions of contract and in the form provided in
Bidding Documents or other forms accepted by the Employer.
33. Advance 33.1 The Employer will provide an Advance Payment of the Contract
Payment Price as stipulated in the Conditions of Contract, subject to a
maximum amount, as stated in the Bid Data Sheet.
34. Settlement of 34.1 Any disputes arising during the performance of the Contract shall
Disputes be settled by the Economic Court in Vietnam and in accordance
with the laws of Vietnam or otherwise provided in Bid Data
Sheet.
35. Settlement of Any Bidder engaging in any negative and/or deceitful action shall
Violation be treated in accordance with the Ordinance on Bidding.
24
The following specific data for the Works to be procured shall complement, amend, or
supplement the provisions in the Instructions to Bidders. Whenever there is a conflict, the
provisions herein shall prevail over those in the Instructions to Bidders.
ITB Contents
1.1 Name of Project:
Scope of the Works:
Ex. During the last five years, the Bidder shall have experience in
the construction of a similar road (or a substation, civil works) with
the value of …
4.2.2 The average annual volume of construction and erection works
performed by the Bidder during the last 3 years.
Ex. During the last 3 years, the Bidder should meet the average
annual volume of construction and erection of … (insert the value)
Ex. The Bidder shall have to undertake the liquid assets and credit
facilities for this bid package excluding the liquid assets and credit
facilities mobilized for other package (or the liquid assets and credit
facilities in general) of …(insert the value)
25
(if the above documents are written in various volumes or parts, the
No of volume and page should be indicated)
10.1 For the small bid package, the time for amendment of Bidding
Documents may be five (5) days.
12.1.1 The other documents should be submitted by the Bidder.
12.7 Time Schedules.
12.7 The value of subcontracts the Bidder allowed to assign to sub-
contractors.(shall not exceed %)
13 The Bid Price in item 13.3 shall be adjusted on the
basis……………. (the principles for price adjustment shall be
indicated such as formula, factor, adjustment time…)
1. Evaluation Procedures:
The completeness and legality of Bids are examined through comparison with the
requirements in Bidding Documents. A Bid, which does not meet any criterion, set forth in
Clause 25 – ITB shall be rejected.
1.2. Examination of Bidders’ eligibility
Bidders are required to meet all requirements in respect to eligibility (finance, profession)
and experience as stipulated in Clause 4.2.1, 4.2.2, 4.2.3 – ITB and in Bid Data Sheet. For
each package, a bid failing to meet one of those requirements shall be rejected.
For the Consortium, the capability of the consortium shall be total capability of all member
of the consortium. The examination shall only be taken to the member who is named in
official Consortium Agreement and meets the requirements on legal status and has the
business registration certificate appropriate to its assignment.
Step 2: Detail evaluation: After preliminary examination, the responsive bids shall be
evaluated in detail as follows:
a. Technical evaluation:
Technical evaluation shall be carried out based on the requirements set forth in the Bidding
Documents. “Marking” or “Yes or No” evaluation method shall be use to evaluate the Bids in
the following criteria:
Bidders who meet all requirements or score of 70% of total points (or over depending on
each package) shall be selected to the short list for financial and commercial evaluation.
In technical evaluation step, the detail evaluation on deviations, which in the experts’ opinion
may cause the cost variation during implementation, shall be carried out in order to give
marks and to adjust offered price. The principles for adjustment is specified in item 2.3.
Bids are determined responsive through technical evaluation shall be checked for arithmetic
errors. The correction of arithmetic shall be based on the quantity and unit price stated in the
bid, and follow the stipulations in the Clause 26 – ITB. The details of arithmetic correction
shall be officially notified to the Bidder and the Bidder shall be required to acknowledge of
acceptance within the time as required. If the Bidder does not accept the correction and/or the
total value of arithmetic errors exceed 15% of offered price, the Bid shall be rejected.
The detail financial and commercial evaluation shall be based on the stipulations in Clause
28-ITB of Bidding Documents.
After examination of offered price of all bids, it is necessary to determine which bid(s) offer
a too high price and which bid(s) a too low price in comparison with the existing price
regulated by the State and in comparison with the other bidders’ offered price as well.
If there is a material difference (about 2 times or over), the Employer may require
clarification from the Bidder in order to ensure the feasibility of the offered price. This
evaluation is for purpose of contract negotiation thereafter. During contract negotiation, if
necessary, the Employer may require the Bidder increase the amount of Performance
Security in order to avoid risks.
If the Bidder offer a deviation on payment schedule which may cause losses for the
Employer, price adjustment for this deviation shall be done properly based on the procedure
stated in Bidding Documents (for example: interest for the payment in advance).
The detail evaluation on these aspects shall be made based on the comparison with the
conditions stated in Bidding Documents.
If a bidder offers an alternative, the alternative shall be evaluated in detail for purpose of
contract negotiation. The evaluation shall only be done for the responsive lowest evaluated
bid.
- Scope of works: Bids offering non-material omissions and/or redundancies shall not be
rejected. The value of an omission shall be added to the offered price on the basis of the
highest price among the unit prices for such item offered by other responsive bids. The
value of an omission shall be eliminated from the bid price. However, if total value of
adjustment for omissions and redundancies is more than 10% of the offered price, such
bid shall be rejected.
After error correction and adjustment for scope of works, a bid if offer a price higher than
the approved price for the package shall be rejected. In case all offer prices of all bids
higher than the approved price for the package, the Evaluation Team shall further
evaluate the bids, especially on the appropriateness of offer price and submit to
authorized level for consideration and settlement.
- For the permanent equipment and materials installed into the project.
A bid offering permanent equipment and materials with minor deviations which are not
rejected in technical evaluation shall be adjusted by adding to the offer price the highest
price among the unit prices for such item offered by other responsive bids or the market
price for such item as considered properly by the Evaluation Team.
- Adjustment for deviation in payment schedule: If a bid requires a faster payment stream
than specified in the bidding documents, the interest rate regulated by the Bank of 7%
annually shall be added to offered price of such bid.
- Other financial and commercial conditions which deviate from the bidding documents
should be evaluated on the basis of conversion to the same level.
- After all evaluation as above, the bid with the lowest evaluated price shall be proposed
for invitation for contract negotiation accompanied by other recommendations which
should be taken into account in the contract negotiation.
30
TABLE 1:
Example of numerical ratings for technical and quality evaluation
II Construction Methodology 60
1 Site Maneger 5
Requirements: Site Manager shall be engineer of civil or industrial
construction with at least 5 years’ experience in works including at least 3
projects with comparable nature and complexity as project manager. If the
proposed site manager does not meet these requirements, he shall be
required to replace. After required, the site manager is not replaced by the
Bidder, their Bid shall be rejected.
IV Time Schedule: 15
1 7
Diagram for time schedule and personnel:
- Without or poor diagram: 0 point.
- With bar diagram for time schedule and personnel with some non-
detailed items: 50% of max. point;
- With detailed and appropriate bar diagram for time schedule and
personnel: 100% of max. point.
2 8
Time for completion of the project:
- 25% of max. point shall be deducted from total point for each week of
delay. If a bid offering the delay for over 30 days, it shall be rejected.
100
Total
32
33
Name of Project/Works:
Project Reference No. (if any)":
Name of Contractor:
Project Site:
Contract No.:
PART A
CONTRACT AGREEMENT
35
Pursuant to . . . . . . .
Pursuant to . . . . . . .
Pursuant to . . . . . . .
Pursuant to the Decision No . . . date . . . month . . . year . . . of (Name of competent
authority) on approval the Detail Design of project . . . (name of project);
Pursuant to the Decision No . . . date . . . month . . . year . . . of (Name of competent
authority) on approval the Bidding Result of project . . . (name of project);
Pursuant to (other relevant existing legal documents or documents of sponsor/lender)
Name of Employer:
Representative:
Position:
Address:
Account No.:
Tax code:
Tel.:
Fax.:
36
Power of Attorney for signing the Contract (in the event of delegation of power to sign
the Contract):
Now, both parties agree to enter into the Construction and Installation Contract for (name of
project) with the following terms and conditions:
1.1. The Employer has organized bidding and the Contractor was selected as the
successful Bidder for construction and installation works on the “entire package” (or
adjustable price) basis. The Detail Design was prepared by (name of consulting
company), which has been approved by (name of authority) with a letter No…. dated
……
1.2. The Scope of Works indicated in the Contract as per Appendix No. … attached shall
be performed by the Contractor. This Appendix has been prepared on the basis of the
Bidding Documents and an agreement reached between both parties during the
Contract negotiation.
(The Contractor’s Materials and Plants with the technical specifications shall be
specified in the Bill of Quantities as requested by Party A in the Bidding Documents).
Sub-contracts which are carried out by Party B (e.g., Contracts for testing,
modification, supplying of power for testing works, water supply system, fire protection
system… or the work implemented to ensure the safe right-of-way in accordance with
37
regulations provided in the Decree No. 54/1999/ND-CP and other construction and
installation works as stated in the Contract).
2.2 The Contractor shall carry out the Works in accordance with the following schedule.
The General and Special Conditions on Time for Completion are included in the
Appendix No. … of this Contract.
The Contract Price shall be: _________ VND (in words and figures), consisting of:
- Contract Price without VAT:
- VAT:
The breakdown of the Contract Price for each item of work is shown in the Appendix No….
… percent (…%) of the Contract Price shall be paid by the Employer as Advance
Payment to the Contractor, within .......... days after submission by the Contractor to the
Employer a complete set of the following documents but after the Effective Date of the
Contract:
The Advance Payment shall be repaid by deducting ............. (.......%) of each amount
of the succeeding invoices, until the advance payment is fully recovered by the
Employer, but not later than the time when the progress of the Works has reached 80%
of the total amount in terms of the Contract Price.
Party A shall pay Party B in accordance with the working progress and (Contract Price
in case of “entire package” contract or Contract unit price in case of “adjustable”
contract”) based on the results of quality and quantity commissioning at each relevant
payment. The progress of payment shall be defined in the Bidding Documents and
agreed during contract negotiation. At each payment, the Party A shall deduct the
advance paid amount equivalent to .........% (the percentage for deduction shall be
defined in the Bidding Documents and agreed during contract negotiation) until the
advance payment is fully recovered and a retention money at the rate of .........% of
payment amount. (This retention money shall be two times of amount kept for
Contractor’s warranty obligation as promulgated by Government Regulation).
Upon receipt of invoices from the Party B, within 14 days, the Party A shall appraise
and submit to the competent capital management authority.
+ Fifty percent (50%) of the retention money shall be paid to the Contractor upon
Contractor’s submission of documents for drawing the balance sheet which are
acceptable to the Employer.
+ Remaining fifty percent (50%) of the retention money shall be paid to the Contractor
upon issuance of Defect Liability Certificate for the whole Works or receipt of a Bank
Guarantee as a defect liability security.
The Contractor shall be deemed to have completed his obligations under the Contract
including any obligations during the Defect Liability Period only when the Defect
Liability Certificate for the whole of the Works has been issued by the Employer.
Telegraphic Transfer (T/T) (or others as compliance with the loan agreement)
39
Upon the completion, commissioning and putting into operation of the Works, Parties
shall draw the balance sheet and liquidate the Contract in compliance with provisions
of Bidding Documents, Contract and Contract’s Appendixes and in-force relevant
regulations.
5.1.2 The Employer’s site supervisors will be at site to supervise the Works and to inspect
the qualities and quantities thereof.
5.1.3 The Employer shall take over the Works completed by the Contractor.
5.1.4 The Employer shall pay to the Contractor the Contract Price pursuant to Article 4
hereof.
5.2.1 After the Contractor has been given a possession of the Site from the Employer, the
Contractor shall be responsible for security thereof, order and method of construction,
labor, safety, fire prevention, environmental protection, etc. within the scope of the
Contractor specified in the Contract.
5.2.2 The Works shall be completed within the Completion Date specified in Article 2.2 of
the Contract Agreement and the Construction Schedule attached hereto as Attachment
3.
5.2.3 The Works shall be carried out in accordance with the qualities, specifications, and
approved design as stipulated in the Specifications.
40
5.2.4 The Contractor shall be prepared to retain sufficient amount of materials to carry out
the Works in accordance with technical requirements stipulated in the Specifications.
5.2.5 The Contractor shall prepare a construction method, construction drawings for the
Works and a detailed schedule, and submit them to the Employer in accordance with
the Contract.
5.2.6 The Contractor shall prepare a complete set of technical documents and invoices
required for payment in accordance with the current regulations of the State of
Vietnam and provisions stipulated in the Bidding document.
5.2.7 The Contractor shall prepare the stores for maintenance of the Works’ Materials. The
Contractor shall take out insurance in accordance with the requirements specified in
the General Conditions of Contract.
5.2.8 The Contractor shall not assign any rights and obligations under the Contract in any
form to the third party without prior acceptance of the Employer.
5.2.9 The Contractor shall obtain prior approval of the Employer before subcontracting any
part of the Works.
6.1 Within fourteen (14) days after receiving the Letter of Acceptance issued by the
Employer, the Contractor shall submit a Performance Security to the Employer in a
form of unconditional bank guarantee and in the amount equal to 10% of the Contract
Price.
6.2 The Performance Security shall be valid until the commencement of defect liability
period.
Liquidated Damages
7.1 In case that the Contractor has not fully performed their obligations to complete the
whole of the Works in time under Article 5.2.2 hereof (except in the cases of force
majeure), the Contractor shall pay the following amounts as Liquidated Damages.
41
1) For the first ten (10) days of delay, the liquidated damages for delay in
completion of the Works shall be two percent (2%) of the Contract Price.
2) For the next following ten (10) days of delay, the liquidated damages for delay
in completion of the Works shall be zero point eight (0.8%) of the Contract
Price
3) Amount of Liquidated Damages for delay in completion shall not exceed eight
percent (8 %) of the Contract Price of the whole of the Works.
7.2 In case the Contractor breaks his obligations to ensure the quality of the Works under
Article 5.2.3, the Contractor shall bear all costs for repair at the Employer’s requests
and shall pay liquidated damages of ten percent (10%) of the Contract Price. In case
of the delay in completion due to such repair, the Contractor shall also pay the
liquidated damages for delay as stipulated in Article 7.1.
7.3 In case the Contractor does not carry out the Works, the Contractor shall pay the
liquidated damages of twelve percent (12%) of the Contract Price.
7.4 If the delay in completion of the Works lasts more than one month or the Contractor
breaks his obligation to ensure the quality of the Works seriously, the Employer shall
have the right to terminate the Contract. In this case, the Contractor shall pay the
liquidated damages for not carrying out of the Works and the Employer may, at his
discretion, consider not to accept the attendance of the Contractor in the coming
bidding for other Works.
7.5 Interest for late payment by the Employer: ......% of the late payment amount shall be
paid to the Contractor (the percentage of interest for late payment shall be agreed
between Parties in the Contract).
Bonus
7.6 (In case where it is necessary to encourage the Contractor to better carry out of the
Works, the Employer may pay additional amount to the Contractor as a bonus. The
amount of a bonus will be determined based on percentage of the Contract Price or a
fixed amount as stated by the Employer.)
8.1 The Contract shall become effective when it is signed by the Employer and the
Contractor (or approved by the authorities).
8.2 The Contract may expire when both parties agreed to terminate the Contract in
accordance with the Contract provisions or by laws of Vietnam.
The following documents form part of the Contract and their priority shall be as follows.
1. Contract Agreement.
2. Decision on Bidding Results
3. Minutes of Contract Negotiation
4. Special Conditions of Contract (SCC)
5. General Conditions of Contract (GCC)
6. Appendix 1: Bill of Quantities with unit prices
7. Appendix 2: Specifications and Drawings
8. Appendix 3: Construction Schedule
9. Appendix 4: Bidding Documents and other technical, commercial documents
10. Appendix 5: Bid of the Contractor.
11. Other documents
The Contract is made … sets in total; … sets shall be kept by the Employer (Party A) and …
sets shall be kept by the Contractor (Party B).
_____________________________ ____________________________
(Note: Prior to the signing of this Contract, all data should be provided in accordance with
the approved contents during bidding procedure or contents of contract awarding.)
43
PART B:
CONTRACT DATA SHEET
[Note: Except requirements provided in other parts of this Bidding Document, please
be aware the followings upon the using of this Contract Data Sheet:
In the Bidding Document: The Employer shall provide clearly his requirements
by completing all listed items.
On submitting offer: The Contractor shall fill in and make his comments on the
Employer’s requirements provided in this Contract Data Sheet.
At signing of Contract: This Contract Data Sheet shall be filled in fully and shall
forms part of the Contract.]
INSURANCE
PART C:
GENERAL CONDITIONS OF CONTRACT
1. General Provision
1.1 Definitions:
In the Contract as defined below, the words and expressions defined shall have the
following meanings assigned to them:
1.1.1 “Party A” (Employer) means the person named in the Contract Agreement or in the
official notice to the Contractor who shall be legal representative of the Employer.
1.1.2 “Party B” (Contractor) means the Contractor to be accepted by the Party A to sign the
Agreement in order to implement the construction of the Works.
1.1.3 “Parties” means both the Party A and Party B.
1.1.4 “Portion of the Contract” means a portion of contracted quantity to be agreed,
committed by the Parties and is bound by the committed time for completion.
1.1.5 “Arbitrator” means the person to be assigned by both the Employer and the
Contractor to resolve disputes arisen in connection with the Contract, as provided in
the Clause 15.
1.1.6 “Price Schedule” (Bill of Quantities and Unit Price attached) means the table
including the quantities, unit price and total price as submitted by the Contractor in
his Bid which have been modified and supplemented during the contract negotiation
and to be an Appendix of this Contract.
1.1.7 “Bid” means the complete Contractor’s proposal to be submitted by the Contractor to
the Employer and updated up to the time of invitation for contract negotiation.
1.1.8 “Contract Price” means the price to be agreed by the Parties in the Agreement and
allocated in the Price Schedule and Appendix of the Contract.
1.1.9 “Days” means calendar days, “Months” means calendar months.
1.1.10 “Default” means any uncompleted section of the Work as required by the Contract.
1.1.11 “Warranty Period for the Work” means the period to be specified in the Special
Conditions of Contract which be counted from the Completion Date.
1.1.12 “Engineering Drawings” consist of all drawings, diagrams, calculations and other
information provided by the Party A or approved by the Party A based on the Party
B’s proposal.
1.1.13 “Contractor’s Equipment” means all apparatus, machinery, vehicles and other things
required for the execution of the Works temporarily located in the Site.
1.1.14 “Time for Completion” means the time for completing the Works by the Contractor
and taking over to the Employer as stated in the Contract Data Sheet and calculated
from the Commencement Date.
1.1.15 “Committed Completion Date” means the date of completion of the Works to be
committed by the Contractor. Committed Completion Date is provided in the
Contract Data Sheet.
1.1.16 “Materials” means things of all kinds to be supplied to the Site, including consumable
things to be utilized by the Contractor to form or forming part of the Works.
47
1.1.17 “Plant” means any undivided part of the Works having functions to form or forming
the designed product line to be utilized for the purpose of project operation upon its
completion.
1.1.18 “Site” means the places to be specified in the Special Conditions of Contract.
1.1.19 “Site Investigation Report” means reports attached to the Bidding Document and
actual reports explaining the surface and underground conditions of the Site and
others which might effect to the Works.
1.1.20 “Technical Specifications” means all technical requirements of the Works to be
provided in the attached Appendix and might be modified, supplemented or accepted
of the modification and supplementation by the Party A during the implementation of
the Contract.
1.1.21 “Commencement Date” means the date to be specified in the Special Conditions of
Contract. It is the latest date in which the Contractor have to commence the Works.
1.1.22 “Sub-contractor” means any person or organization signing the contract with the
Contractor to carry out a portion of the Works in the Contract, including the works at
Site.
1.1.23 “Temporary Works” means all works necessary for the construction and installation
of the Works to be designed, constructed, installed and unloaded by the Contractor.
1.1.24 “Variations” means any request made by the Party A to vary the Works.
1.1.25 “Works” means the works of every kind requested to be constructed, installed and
handed over by the Contractor as specified in the Special Conditions of Contract.
1.2 Interpretation
1.2.1 In interpretation of Conditions of this Contract, titles shall have no special meanings,
words shall have the normal meanings except otherwise defined specially. The
Employer shall interpretation of the Conditions of Contract.
1.2.2 If the completion of any section of the Works to be specified in the Contract Data
Sheet or Special Conditions of Contract, the references to the Works, the Time for
Completion and the Committed Completion Date as provided in the Conditions of
Contract shall be applied for such section of the Works except the references to the
Time for Completion and the Committed Completion Date applied for the whole
Works.
The language of Contract shall be Vietnamese (or English) and the Contract shall be
governed by the Laws of Vietnam.
1.4 Communications
2. The Employer:
48
The Employer shall provide the Site and right of access thereto at the times stated in the
Contract Data Sheet.
The Employer shall, if requested by the Contractor, assist him in applying for permits,
licenses or approvals which are required for the Works by the current laws.
The Contractor shall comply with all instructions given by the Employer in respect of the
Works including the suspension of all or part of the Works.
The Employer shall give the Contractor right of access to, and possession of, all parts of
the Site within the time (or times) stated in the Special Conditions of Contract or the
Appendix attached. If the possession of any part of the Site is not given on the specified
date, the Employer shall be responsible for the delay in commencement of relevant
activities, and this shall be taken into consideration of a compensatory event.
The Contractor shall allow the Employer or any person to be authorized by the Employer
to come in the Site or other places relevant to the Works of Contract which are being
carried out or intended to be carried out.
3. Employer’s Representatives
The Employer may appoint a firm or individual to carry out certain duties. The appointee
must be named in the Appendix, or notified by the Employer to the Contractor from time
to time. The Employer shall notify the Contractor of the delegated duties and authority of
this Employer’s representative.
4. The Contractor
The Contractor shall carry out the Works properly and in accordance with the Contract.
The Contractor shall provide all supervision, labor, Materials, Plant and Contractor’s
Equipment on Site shall be deemed to be the property of the Employer.
The Contractor shall submit to the Employer for consent the name and particulars of the
person authorized to receive instructions on behalf of the Contractor.
4.3 Subcontracting
The Contractor shall not subcontract the whole of the Works. The Contractor shall not
subcontract any part of the Works without the consent of the Employer.
The Contractor shall deliver to the Employer a performance security in a form and
procedure as approved by the Employer at the time prior to the effectiveness of the
Contract or other time as specified in the Contract Data Sheet.
5. Design by Contractor
The Contractor shall carry out design to the extent specified, as referred to in the Special
Conditions or Appendix of Contract. The Contractor shall promptly submit to the
Employer all designs prepared by him. Within 14 days of receipt the Employer shall
notify any comments or, if the design submitted is not in accordance with the Contract,
shall reject it stating the reasons. The Contractor shall not construct any element of the
permanent work designed by him within 14 days after the design has been submitted to
the Employer or where the design for that element has been rejected. Design that has
been rejected shall be promptly amended and resubmitted. The Contractor shall resubmit
all designs commented on taking these comments into account as necessary.
The Contractor shall remain responsible for his tendered design and the design under this
Clause, both of which shall be fit for the intended purposes defined in the Contract and he
shall also remain responsible for any infringement of any patent or copyright in respect of
the same. The Employer shall be responsible for the Specification and Drawings issued
by him.
6. Employer’s Risks
war, hostilities (whether war be declared or not), invasion, act of foreign enemies,
within the Country,
rebellion, terrorism, revolution, insurrection, military or usurped power, or civil war,
within the Country,
riot, commotion or disorder by persons other than the Contractor’s personnel and
other employees, affecting the Site and/or the Works,
ionising radiations, or contamination by radio-activity from any nuclear fuel, or from
any nuclear waste from the combustion of nuclear fuel, radio-active toxic explosive,
or other hazardous properties of any explosive nuclear assembly or nuclear
component of such an assembly, except to the extent to which the Contractor may be
responsible for the use of any radio-active material,
pressure waves caused by aircraft or other aerial devices travelling at sonic or
supersonic speeds,
use or occupation by the Employer of any part of the Works, except as may be
specified in the Contract,
design of any part of the Works by the Employer’s personnel or by others for whom
the Employer is responsible, and
any operation of the forces of nature affecting the Site and/or the Works, which was
unforeseeable or against which an experienced contractor could not reasonably have
been expected to take precautions.
Force Majeure,
a suspension under Sub Clause 12.3 unless it is attributable to the Contractor’s
failure,
any failure of the Employer,
physical obstructions or physical conditions other than climatic conditions,
encountered on the Site during the performance of the Works, which obstructions or
conditions were not reasonably foreseeable by an experienced contractor and which
the Contractor immediately notified to the Employer,
any delay or disruption caused by any Variation,
any change to the law of the Contract after the date of the Contractor’s offered as
stated in the Agreement,
losses arising out of the Employer’s right to have the permanent work executed on,
over, under, in or through any land, and to occupy this land for the permanent work,
and
damage which is an unavoidable result of the Contractor’s obligations to execute the
Works and to remedy any defects.
The Contractor shall commence the Works on the Commencement Date and shall
proceed expeditiously and without delay and shall complete the Works within the Time
51
for Completion as specified in the Agreement. The Time for Completion may be
specified for each section of the Works as stated in the Contract Data Sheet.
7.2 Programme:
Within a specified time in the Contract Data Sheet, the Contractor shall submit to the
Employer a detailed time programme in the form agreed by the Parties for
concurrence by the Employer. This program shall be the basis for implementation of
the project.
Within a specified time in the Contract Data Sheet, the Contractor shall submit to the
Director of the Project Management Board for approval a detailed construction plan
including general methodology, allocation, ranking and time table for all activities of
the Works.
Updated construction plan shall be a plan presenting the actual progress acquired for
each portion and its effects to the time for completion of remaining portions,
including also the changing of portion’s ranking.
The Contractor shall submit to the Director of the Project Management Board for
approval a construction plan to be updated at the time specified in the Special
Conditions of Contract. If at the required time, the Contractor fails to submit the
updated construction plan, the Director of Project Management Board shall, at his
discretion, keep an amount as specified in the Special Conditions of Contract in the
following certification for payment. Such amount shall be paid in the installment
followed the completion date of the overdue construction plan have been submitted.
The approval of the construction plan made by the Director of Project Management
Board shall not release the Contractor from any of his obligations. The Contractor
may revise the construction plan and submit to the Director of Project Management
Board at any time. The revised construction plan shall clarify the effects of changes
and compensatory events.
Subject to Sub-Clause 10.3, the Contractor shall be entitled to an extension to the Time
for Completion if he is or will be delayed by any of the Employer’s liabilities. On receipt
of an application from the Contractor, the Employer shall consider all supporting details
provided by the Contractor and shall extend the Time for Completion as appropriate.
If the Contractor fails to complete the Works within the Time for Completion, the
Contractor shall be responsible for paying the amount stated in the Contract Data Sheet.
8. Taking-over
8.1 Completion
52
The Contractor shall have the responsibility to notify the Employer when he considers
that the Works are complete actually.
The Employer may notify the Contractor in order to remind the date of completion and
taking-over. On the other hand, the Contractor shall have the responsibility to notify the
Employer the intended completion and taking-over dates for preparation of commission
and taking-over plan as promulgated and for request to the Contractor to complete any
outstanding work, subject to Clause 9.
9. Remedying Defects
The Employer may at any time prior to the expiry of the warranty period, notify the
Contractor of any defects (if any). If the defect is defined not be incurred from the
Contractor’s fault or not in the scope of Contractor’s obligation to warrant, the Contractor
shall not be responsible for compensation. All other defects and damages shall be
remedied by the Contractor at his own cost.
The Employer may request for testing and inspection of any work carried out by the
Contractor under the Contract. The Employer shall bear all costs for testing and
inspection to be deemed as an additional costs stated in the Sub-Clause 10.2 except the
case of through such testing and inspection, it is found out that the defects incurred from
the Contractor’s fault, the Contractor shall bear all costs.
Variation orders shall be valued as follows and be the ground for payment:
A Party shall notify the other as soon as he is aware of any circumstance which may
delay or disrupt the Works, or which may give rise to a claim for additional payment. The
Contractor shall take all reasonable steps to minimize these effects.
If the Contractor incurs additional costs as a result of any of the Employer’s risks, the
Contractor shall be entitled to the amount of such costs.
The Contractor shall submit to the Employer the calculation of the value of Variations
and claims within 28 days of the instruction or of the event giving rise to the claim. The
Employer shall check and if possible agree the value. In the absence of agreement, the
Employer shall determine the value.
The Works shall be valued as provided for in the Agreement, subject to Clause 10.
Details of payment conditions shall be specified in the Agreement and Contract Data
Sheet.
The Contractor shall be entitled to interest at the rate stated in the Contract Data Sheet for
each day the Employer fails to pay beyond the period of payment provided in the
Contract at the Contractor’s request.
If the Contractor does not commence the Works or not perform the Works as instructed
by the Employer stated in the Contract, the Employer shall notify the Contractor and
remind the delay in performance of the Works. If the Contractor does not have the
reasonable remedy within 14 days of the receipt of notification, the Employer shall notify
the Contractor second time to request the Contractor suspend the Works. In this case, the
54
Contractor shall be responsible to withdraw from the Site but the Materials shall be
remained at the Site at the Employer’s request for the purpose of continuing the
performance and completion of the Works.
If the Employer does not fulfill his payment obligation or other obligations stated in the
Contract, the Contractor shall notify the Employer of this delay. If the Employer does not
have the reasonable remedy within 07 days of the receipt of notification, the Contractor
shall notify the Employer of his suspension of a portion or whole of the Works. Within
28 days, if the Employer does not implement his payment obligation, the Contractor shall
notify of his suspension of Works and withdrawal from the Site.
12.3 Bankruptcy. If any party fails in bankruptcy under its governing laws, other party
may give notice of termination immediately. The Contractor shall leave the site. If the
Contractor fails in bankruptcy, when leaving, he shall be required by the Employer to
leave equipment and materials for continuous construction up to the completion.
12.4 Upon the termination of the contract, the Contractor shall be entitled to be paid for the
works done or materials and equipment delivered to the site by the following principles:
The balance shall be paid by the Employer (or repaid by the Contractor) within 28 days from
the date of termination.
The Contractor shall take full responsibility for the care of the Works from the
Commencement Date until the date of the Employer’s notice under Sub-Clause 8.2 to
hand-over the Works. Responsibility shall then pass to the Employer. During the whole
progress of Works as prescribed above, the Contractor shall bear all costs relating to the
performance of the Works satisfied the conditions stated in the Contract.
No Party shall be responsible for not fulfilling of his contracted obligation in the case
of Force Majeure event.
If a Force Majeure event happens, the Contractor shall try his best to minimise the
effects of such event and propose methods to overcome consequences of the Force
Majeure. And the Contractor shall continue the Works, including propose of his
entitlement to additional costs and extension of time for completion.
In case of a Force Majeure event, the Contractor shall still be provided the certificate
for completed portion of the Works and to be paid for such completed work, whether
or not such work have been destroyed by the Force Majeure.
A Party will be released from performing any of its obligations under the Contract by
Force Majeure, then it shall give notice to the other Party of the event immediately. If
necessary, the Contractor shall suspense the Works, then agree with the Employer to
withdraw its personnel from the Site.
In case the Force Majeure event prolongs more than 84 days, one Party might give notice
to other Party for termination of the Contract within 28 days of receipt such notice.
After the Works is suspended, the Contractor shall be entitled to the payment for
completed portions of the Works and the costs of Contractor’s Plant and Materials at the
Site as follows:
The different amount calculated as above mentioned shall be paid by the Employer (or
repaid by the Contractor) within 28 days of the suspension date.
14.Insurance
14.1 The Employer shall buy the following insurances in the joint names with Contractor:
Insurance of Construction and Installation of the Works and Works’ Plant and
Materials from the Commencement Date
Third party liability insurance.
14.3 Any changes to the insurance policies shall not be allowed if there’s no agreement of
the Employer in writing, except otherwise provided in the Contract or Appendix or
agreed by both Parties.
14.4 Failure to insurance: If the Contractor fails to effect or keep in force any of the
insurances referred to in the previous Sub-Clause, or fails to provide satisfactory
evidence, policies or receipts the Employer may, without prejudice to any other right or
remedy, effect insurance for the cover relevant to such default and pay the premiums due
and recover the same as a dedcution form any other monies due to the Contractor.
15.Resolution of Disputes
15.1 During the effective period of the Contract, if there is any dispute incurred between
the Employer and the Contractor, the Employer and the Contractor shall cooperate to
resolve such dispute amicably.
15.2 If the Employer and the Contractor have been unable to resolve amicably a Contract
dispute, either party may require that the dispute be referred for resolution to Vietnam
economic court (if the dispute arising out between the Employer and Vietnamese
Contractor) or to Vietnam International Arbitration Center (if the dispute arising out
between the Employer and foreign Contractor) in accordance with its rules or other
arbitration center as specified in SCC. Fees and costs incurred in the progress of dispute
resolution at the Court shall be born by the failure party.
All changes to the resolution of disputes shall be agreed by both Parties in writing prior to
the commencement of dispute resolution progress or to be provided in the Contract Data
Sheet.
The language of Contract shall be specified in SCC. All correspondence between parties
shall be in such language.
57
PART C:
SPECIAL CONDITIONS OF CONTRACT
[Note: The followings are guidance as some examples in preparation of this section]
Clause Contents
1. - Employer:
- Employer’s representatives:
- Project Management Board:
- Director of Project Management Board:
(specify the project management form and the person in charge. If the Project
Management Board hires the Engineers for supervision work, the rights of
Engineer shall be stated)
- Name of number of Contract:
- Scope of Project as stated in the Section 6 - Bill of Quantities
- Commencement Date (latest):
- Project Site:
Warranty Period: ……. months counting from the completion date
Committed completion date: …… days counting from effective date of
Contract.
4. The issues requested the consent of the Employer shall include but not
limited:
- Monthly certificate for completed works
- Approval of sub-contractors
- Variation on quantity, price and structure of the Works
- Extension of time for completion
- Issuance of Completion Certificate
- Issuance of Completion of Contractor’s Warranty Liability
7.1 Sub-contractor of amount of work sub-contracted (not exceed … % of
Contract Price)
9.1 List and position of the Contractor’s key personnel
13.1 Insurance: amount and form type of cover of insurance bought by each Party
shall be specified, level of exclusions, endorsement conditions.
21.1 Date of handing-over the Site: … days counting from the receipt of Accep-
tance Letter on principles regarding to handing-over the Site.
58
Clause Contents
25.3 Arbitration Institution: Economic Court
27.1 The Contractor is required to submit a detail construction plan within …. days
counting from the signing date of Contract.
27.3 Time for submittal of updated construction plans by the Contractor: 30
days/time. Total retention amount due to delay in submittal of updated
construction plan: not exceed 10% (ten percent) of amount due for the next
payment.
35.1 Defect Liability Period (Warranty Period): …. months
46.1 Percentage of payment of retention money: ……. %
47.1 This clause shall amend the provisions in the General Conditions.
E.g., liquidated damages for delay in completion of the whole Works is 0…..%
(zero point …) of the contract price for the delayed section of the Works.
Total amount of liquidated damages for delay in completion shall not exceed
10% of the Contract Price.
48.1 Advance payment: … % of the Contract Price (as promulgated by the Bidding
Regulation)
The advance payment shall be paid not later than 30 days of the Contract
signing date (subject to conditions of each Contract, the Contractor shall be
required to submit advance payment guarantee)
49.1 Performance Security:
- Performance Security: … % of Contract Price (as promulgated by the
Bidding Regulation)
- The performance security shall be issued by the Bank acceptable to the
Employer and shall be unconditional guarantee.
54.1 Within 15 days from the receipt of the full and appropriate filling form made
by the Contractor, the Director of Project Management Board shall issue the
Certificate on completion of the Contractor’s defect liability and the
Certificate for all final amounts due to the Contractor.
If the Contractor’s filling form is not full or appropriate, the Employer, within
15 days shall issue the amendment or supplement.
55.1 Date of instruction for operation and maintenance: not applicable
Date of submittal of built-in drawings: 30 days after completion date.
55.2 Retention amount due to not submittal of built-in drawings on the required
date: 0.1% (zero point one percent) of the Contract Price for each delayed
day.
57.1 Percentage applicable for uncompleted works in case of termination of
Contract due to Contractor’s faults:
59
60
SECTION IV:
GENERAL DESCRIPTION OF PROJECT
I. Location of Project
II. Characteristics
III. Technical Specifications
Commencement Date
Completion Date
SECTION V:
TECHNICAL SPECIFICATIONS AND DRAWINGS
This Section explains the technical requirements in the approved Technical Design or Detail
Design.
If the Designs had not been approved or was not detailed sufficiently, it should be written
clearly in this section with the following contents:
This section is very important for the project in respect of quality. In addition to the
requirements set forth in Bill of Quantity and design drawings, this section should
supplement and clarify the requirements on the material used for construction of project. For
example:
- Cement: Cement used for concrete should be PC-30 produced by Hoang Thach, Bim Son,
HaTien, or Chinh Phong Factories.
- Ashley paving stone:
+ for three-step stair case in the main entrance should be Granite in dark red with
thickness of 30mm;
+ for floor in main lobby should be Granite 400 x 400 Class A in dark red;
+ for first floor should be Granite Thach Ban 400 x 400 Class A.
- Iron and steel:
- Sand:
- Stone:
- Air-conditioner:
- ...
a. Scope of Work:
b. Design solution:
c. Construction methodology:
E.g.:
- There is an existing administration building in the Site which shall be replaced by the
parterre of the new project. Therefore, during the construction progress, the Contractor
shall build surrounding fences to provide a safe temporary right-of-way for Employer’s
temporary utilization. Upon the taking-over of the main building, the Employer shall
remove to the new main building. Then the Contractor shall destroy the old
administration building in order to continue the construction of project.
- Method for consolidation of foundation: it is only allowed to utilize the method of bored
pilling, not the method of press pilling.
- Concreting: it is only allowed to utilize the concreting pump.
62
Total:
64
SECTION VI:
BILL OF QUANTITIES
II Construction methodology 60
The items in this section shall be evaluated and weighed
as follows:
- Substantial non-responsive: 0
- Substantial responsive but there are some
unreasonable minor items: 50% maximum merit
point.
- Sufficient and clear presentation but not enough of
details: 80% merit point
- Sufficient, clear, detailed and reasonable
presentation: 100%.
1 Site organization: 20
- General site organization: 5
- Explanation and construction methodology: 10
- Construction procedures 5
IV Construction Schedules: 15
1 Master of Construction Schedules and labor path: 7
Total 100
67
SECTION VII:
FORM OF BID AND SAMPLES FORMS
A. FORM OF BID
To: ................................
Having reviewed the detailed contents of the Bidding Documents and supplemental letter No.
.... (if any) the receipt of which has been confirmed by us as indicated in the attachment to
this Form of Bid, we, the undersigned, undertake to perform the construction, erection and
completion of ...................... (name of package) in accordance with the Conditions of
Contract and other requirements stipulated in the Bidding Documents with additional
clarifications attached to this Bid, for the sum of:
We undertake, if our Bid is accepted, we will obtain the guarantee of a bank in a sum
equivalent to ten (10) percent of the Contract Price for the due performance of the Contract,
in the form prescribed by the Purchaser and we commit to commence the Works upon the
signing of Contract on ..... and complete the Works within ..... days from the Commencement
Date in accordance with the detail time schedule as described in this Bid.
We agree to abide by this Bid for a period of ........ days from the date fixed for Bid opening,
and it shall remain binding upon us and may be accepted at any time before the expiration of
that period.
Until a formal Contract is prepared and executed, this Bid, together with your written
acceptance thereof and your notification of award, shall constitute a binding Contract
between us.
The Bid Security in the amount of _____ issued by (name of the issuing Bank) is valid for
_____ days as specified in Bidding Documents.
B. QUALIFICATION INFORMATION
1. General Information
Telephone N0_____
Telephone N0_____
Year of establishment: accompanied by a copy of the license and business registration and
ownership
etc.
At Site:
1. Mr. ......... Site Manager
KCS Engineer
Supervision
Engineer
Technical expert
........
70
3. Description of the relationship between Head office and the site management
5. Chart of labor arrangement (clearly state position of skilled labor, experience and
grade of each team).
71
1. Transportation
2. Foundation works
3. Stringing works
4. Testing
5. Others
Bidding Data clearly states the kinds and the minimum required number of equipment. In listing up
the equipment, those equipment that are stated in the Bidding Data shall be given priority, followed
by other additional and alternative items of equipment.
Project Total value of contract Name Percentage of work not Value of (Scheduled)C Scheduled
name of completed yet parts not ommencement completion
project completed date date
manage yet
r
Percentage
Total Percentage of Total of work
work implem-
implemented ented by the
by the Bidder Bidder
74
7. Financial Capabilities
Bidder’s Name: ____________________________________
A Summary of assets and liabilities on the basis of the audited financial statements during the
last three financial years.
1. Total assets
2. Current assets
3. Total liabilities
4. Current liabilities
5. Net worth
6. Working capital
7. Turnover
(working capital is defined as the balance between current assets and current liabilities)
B. The capital or liquid assets available for this project: _______ Vietnamese Dong. In which:
+ Available cash:
+ Bank credit (with data listed and committed):
+ .............
1. Name and address of commercial Bank providing the Credit line _________________
Notes: The figures as listed herein must be supported by a copy of the audited financial statements of
the last three financial years as specified in Clause 12.4 of Instruction to the Bidder. This information
shall be provided by each member of joint venture.
For and on behalf of the Bidder
Address: __________________________
Leader
Partner
Partner
Partner
9. Sub-Contractors
(List the names of Sub-Constructors with the descriptions of their capabilities, experience, etc.)
77
C. OTHER FORMS
1. Form Of Bid Security
Date ______ month ______ year_____
To: ...........................................................
Whereas __________ (indicate the Bidder’s name) (hereinafter referred as the “Party B”) has
submitted his Bid on ____________ (indicate the date of bid submittal) for the construction and
installation of _____________ (indicate name and/or brief description of the Works – package)
(hereinafter referred as the “Bid”),
We, the Bank (indicate Bank name) (hereinafter referred as the “Bank”) with its registered Head
office at______ (indicate Bank address) is bound unto (the Bidder’s name) in the sum of ______
(indicate the currency and the amount of security in figures and in words) to ensure for hereby
commit that we will pay to the __________ (indicate the Employer’s name) (hereinafter referred as
the “Party A”) with the said amount.
1. If the Bidder withdraws its Bid during the period of validity of Bids as stipulated in the Form
of Bid; or
2. If the Bidder, having been notified of the award by the Project Management Board during the
period of validity of Bid;
Name of Bank
Whereas the Contractor (indicate the Contractor’s name) has committed to perform the
Contract No. (name and reference number of Contract) on date _______ for the Works
_______ (hereinafter referred as the “Contract”),
Whereas, (name of the party calling for Bids) required the Contractor to provide a
performance security in the amount of ______ (clearly state amount), to ensure that the
Contractor performs its obligations under the signed contract,
We provide a performance security and state that we are, on behalf of the Contractor, directly
responsible to (name of party calling for Bid) in the amount of ___________ (clearly state
amount in figures and words).
When receiving a letter of demand from (name of party calling for Bid), we will undertake to
pay to (name of party calling for Bid) up to the amount of ______ (clearly state the said
amount) without any explanation of the reasons for the demand.
________________________________________________________________ (Address)
79
[name of Contract]
Gentlemen:
In accordance with the provisions of the Conditions of Contract, Clause ________ of the above-
mentioned Contract dated of ______, [name and address of Contractor] (hereinafter called “the
Contractor”) shall deposit with [name of Employer] a Bank Guarantee to guarantee his proper and
faithful performance under the said Clause of the Contract in an amount of [amount of Guarantee]
[amount in figures and words].
We, the [Bank or Financial Institution], agree unconditionally and irrevocably to guarantee as
primary obligator and not as Surety merely, the payment to [name of Employer] on his first demand
without whatsoever right of objection on our part and without his first claim to the Contractor, in the
amount not exceeding [amount of Guarantee] [amount in figures and words].
We further agree that no change or addition to or other modification of the terms of the Contract or of
Works to be performed thereunder or of any of the Contract documents which may be made between
[name of Employer] and the Contractor, shall in any way release us from any liability under this
Guarantee, and we hereby waive notice of any such change, addition, or modification.
This Guarantee shall remain valid and in full effect from the date of the advance payment under the
Contract until [name of Employer] receives full repayment of the same amount from the Contractor.
Yours truly,
Address:
Date:
80
4. Letter of Acceptance
To: _____________________
This is to notify you that your Bid dated __________ concerning the construction and installation of
(name and description of the Contract) in the amount of _______ as adjusted in accordance with the
Instructions to Bidders is accepted by our Bidding Council under the Decision N o ______ date ______
month ______ year _____.
We ________ accept ________ to be appointed as arbitrators for dispute resolution which are raised
from such Contract.
We, hereby, require _______ (name of Contractor) to carry out the Works in accordance with the
signed Contract.
(Employer’s name)
81
To: ...........................................................
Whereas __________ (indicate the Bidder’s name) (hereinafter referred as the “Party B”) has
submitted his Bid on ____________ (indicate the date of bid submittal) for the construction and
installation of _____________ (indicate name and/or brief description of the Works – package)
(hereinafter referred as the “Bid”),
We, the Bank (indicate Bank name) (hereinafter referred as the “Bank”) with its registered Head
office at______ (indicate Bank address) hereby commit that (the Bidder’s name) will get the credit
with .. ( amount of ) if If the Bidder is notified of the award of the above contract.
This commitment will remain in force up to and including thirty (150) days
after the closing date.
Name of Bank