Professional Documents
Culture Documents
IET Electrical Syst in Trans - 2020 - de
IET Electrical Syst in Trans - 2020 - de
Research Article
Abstract: The increasing pollution due to vehicular emissions demands a quick review of the present transportation structure.
Replacing the present transportation system with an electric-based public transportation system is a possible solution. This
system will use high-capacity storage devices that will be placed at the bus stops to store energy from the electric grid and then
charge the buses. The implementation of such a system will require a systematic energy flow between entities such as the grid,
energy storage systems, and buses. This energy flow may get interrupted due to failures between the entities and thus cause
failures in the system. The objective of this work is to investigate various failures that can occur and propose strategies to
minimise the impact of the failures on the operation of the system. In order to achieve this objective, a simulation model of the
transportation system is developed for the analysis of different issues, which exist in the system and the fuzzy logic controller
has been designed to provide solutions to these issues. The results show that with the proper working of the controller it is
possible to mitigate failures that are caused due to critical energy flow disruptions.
1 Introduction technologies [11, 12], no such appreciable work has been found on
failure analysis and hence on possible solutions. The primary
In the last decade, major cities around the world have experienced question that will be addressed in this work is ‘what are the
a significant rise in air pollution [1]. Recently, New Delhi, capital potential failures that can occur in the system and what failure
of India, was in news for unprecedented levels of air pollution and management issues can be addressed to ensure unhindered
very poor air quality [2]. The primary factor for the deteriorated air service?’
quality in mega cities is road transport based on the internal The failures and contingencies that the EBTS can experience
combustion engine vehicles. One of the potential solutions is to are as follows:
expand the network of the multimodal public transportation system
(TS) powered by electricity such as trolley buses, electric buses, i. failure between the grid and the electric bus stop (charging
electric car-based taxis etc. These electricity-based TSs (EBTS) station),
can be made sustainable by use of renewable energy sources such
ii. traffic congestion, and
as wind energy and solar photovoltaic (PV) systems, and many
cities around the world have deployed or are in the process of iii. unbalance between energy demand and resources.
deploying such solutions [3–5].
The success of such electricity-based vehicles primarily Referring to Fig. 1, it can be seen that the above issues will result
depends on three factors, namely in disruption of energy flow between the grid, HCSD and
supercapacitor in the E-bus.
a. The ability of the distribution grid to meet the energy An intelligent strategy should ensure minimum disruption in
demand of the EBTS. service due to the failures. The strategy proposed in this work is
based on the fuzzy rule base, and it is shown, through simulations,
b. Proper energy management between the grid, renewable
that the proposed strategy ensures that the bus services are not
generation, and EBTS to ensure reliable operation.
interrupted in the event of above-mentioned failures. The reason
c. Understanding of possible failures and strategies to address for opting FLC over other control techniques is due to its linguistic
failures and contingencies, and to minimise their impact on representation of rules and mode of approximate reasoning, which
the EBTS. resembles the decision-making process of humans. In addition to
this, an FLC is not based on mathematical modelling and can solve
The point (a) is especially important for Indian cities because the problems under uncertain and highly non-linear conditions. Thus,
electricity distribution network in Indian cities is overburdened [6, in this work using FLC to formulate the charging and discharging
7] and will not be able to sustain any additional load of EBTS. To rate of a large number of E-buses becomes easier. To demonstrate
address this issue, an EBTS was proposed in [8, 9]. This EBTS the efficacy of the proposed strategy, it was tested for different
uses a high-capacity storage device (HCSD) as a buffer between months (to take into account seasonal variations in renewable
the grid and the EBTS, and also enables large-scale integration of generation). All the simulations are done for the Guwahati city,
renewable energy. A smart energy management system is used in India, and to keep the simulations as realistic as possible, the
this EBTS and it ensures that the grid is not overburdened and the electricity consumption profiles are taken from Assam Power
e-buses have access to uninterrupted energy. The issue of energy Distribution Company Limited (APDCL).
management between the grid, renewable generation, and EBTS The paper is organised as follows: Section 2 describes the
has been discussed in [10]. The focus of this work is to address system layout and the structure of the entities. Section 3 explains
point (c) that is possible failures and strategies to minimise the the system modelling and energy calculation of the EBTS. Section
impact of these failures with respect to the system shown in Fig. 1. 4 presents the contingency analysis of the proposed EBTS. The
Literature review shows that though there has been quite a results and discussion are given in Section 5 and Section 6 presents
remarkable work on vehicle-to-grid and grid-to-vehicle
hence, can initiate command for any support required by that • Grid to HCSD: The HCSDs placed at the EBSs are connected to
particular EBS. The SCADA centre will send the grid information the grid (33/11 kV) via a distribution network of 11/0.420 kV.
to the TCC, and this information is then conveyed to the fuzzy Furthermore, a bidirectional converter is used for the energy
logic controller (FLC). The contingency management algorithm is flow between these two entities. The amount of energy thus
also located in the TCC; the TCC uses these data to identify the stored in the HCSD depends upon the thorough analysis of the
congestion that may have occurred at a particular location and then energy requirement of the proposed system, which is presented
initiate the FLC for control signals. Thus, it can be noted that TCC in the next section.
only sends and receives information (both in normal and fault • PV to HCSD: Distributed solar PV panels are used in the
condition) and therefore does not have any impact of the faults proposed work as an additional source of energy to the EBTS.
occurring on the system. Therefore, any interruption between PV and HCSD will not
cause disruption in the system as the HCSD is connected to the
2.3 Fuzzy logic controller (FLC) grid and thus it can charge the E-buses. Considering the future
TS demand solar PV can also be used to provide full support to
FLC, which is based on the rule base and membership functions the TS. Thus replacing the energy requirement (for TS) from the
(MFs), will decide the control action, which is the direction of city distribution grid. In that case, an interruption between PV
power flow from/to the HCSD. A rule base is hence designed and HCSD will result in energy disruption and hence the
based upon the basic necessity of the proposed system which is possible scenarios have been studied here.
• HCSD to E-bus: Each E-bus has a supercapacitor as a primary
• 24 h of energy support to the EBTS. source of energy. These supercapacitors are charged from the
• HCSD to be charged from the grid during off-peak hours of the HCSDs when the E-bus stops at a particular EBS. The energy
grid. from the HCSD to the supercapacitor flows through a converter
• The energy stored in the HCSD from the grid and solar energy and the supercapacitor is charged using the flash charging
will be utilised firstly for EBTS support and then for grid method.
support.
A fault in any of the above three pathways can result in
The control strategy uses three steps: disruption of the system. The possible energy disruptions that can
occur are shown in Fig. 6
i. Fuzzification: convert the classical data or crisp data into fuzzy
data or MFs, then a. Energy flow between the grid and the HCSD is disrupted.
ii. Fuzzy inference process: which combine the MFs with the b. Energy flow between the solar PV and the HCSD is
control rules to derive the fuzzy output. disrupted.
iii. Defuzzification: converts the fuzzy variables into a binary c. Energy flow between the HCSD and E-bus is disrupted.
output.
In this section, the elaboration of the system architecture has
The inputs to the FLC presented in Fig. 4 are the bus frequency been presented along with the functions of the main subsystems.
(Bf), SOC and the per unit voltage (Vp.u). The output of the FLC is This gives a clear idea of the critical energy pathways and therefore
the power flow to-n-from the HCSD. the energy disruptions that can possibly occur. The brief
Thus, these three subsystems together ensure the smooth description is necessary to understand and analyse the faults in the
operation of the entire system. Furthermore, from Figs. 1 and 2, it system due to these energy disruptions. Although analysis of these
can be seen that there are three critical energy pathways, as shown cases requires data of the proposed system, energy requirements
in Fig. 5, and they are along with the grid profile of locations where the EBSs are placed.
Hence, the system model and major data (grid and EBTS) analysis
Fig. 6 Energy disruptions that can occur between the different entities of
the system and hence can disrupt the smooth operation of the system are
(a) Between grid and HCSD, (b) Between HCSD and E-bus, (c) Between solar PV and
HCSD
has been presented in the next section and followed by the analysis
of different energy disruption cases.
Fig. 9 Solar radiation data for an entire year presenting the monthly i. Connection of HCSD and solar PV with EBTS: HCSD is
variation in solar irradiation, i.e. variation in solar radiation season wise placed in between the grid and EBTS and the solar PV module
are placed in a way that it is directly connected to the grid and
Table 1 Specification of an E-bus considered for this study HCSD as well.
[24] ii. Basis of energy flow from grid to HCSD: The system is so
Parameters Values designed that the EBTS will be given support for 24 h. This
mass 10,000 kg support is taken from the grid, i.e. EBTS takes energy from the
length 10 m grid during GOHs only and this energy flow via the HCSD.
width 2 m iii. Basis of energy flow between solar PV panel, HCSD and the
height 3 m
grid: The solar energy is utilised in the system in order to
maintain a constant voltage profile of the grid. Hence, the solar
frontal area 6 m2 PV panel is connected directly to the grid. Additionally, it is
passenger capacity 35–40 connected to the HCSD so that the EBTS can be supplied by
an additional source of energy.
The energy flow between these subsystems will depend upon the
following factors:
regular demand, but this does not create many effects. This is of the grid (Vpu), SOC of the HCSD and the bus frequency (Bf).
because the energy to be stored in the kth stop, due to C-I, will now Here, it is considered that all the issues appear at the kth stop only
be used to charge the HCSD of the (k − 1) / (k + 1)th stop. and hence the parameters of the kth stop are subjected to decision
S-3: in this case, both the (k − 1)th and (k + 1)th stop share the making. Every EBS includes an FLC and hence represented
load of the kth stop under C-I, i.e. the energy to be stored in HCSD likewise.
of the (k − 1)th stop and the (k + 1)th stop can be given as (see (2) Fig. 13 presents the control algorithm based on which the FLC
and (3)) . Similarly (see (3)) . Next is C-II for which again three will work. The system will first check for the values of the system
sets of the solution are given (S-1, S-2, and S-3). S-1: under C-II, parameters for the kth, (k − 1)th and (k + 1)th stop. For this, the
the energy requirement at the kth stop increases due to the sudden following standards are considered:
traffic conditions. Hence, the kth stop HCSD has to store more
energy to compensate for the change in demand. The sizing of the i. Vpu = 1 is the standard per unit voltage value and therefore the
HCSD for the proposed EBTS is such that after supporting it can condition when Vpu ≪ 1 indicates that the load on the grid is
also support the grid during GPHs. Even if the HCSD stores energy quite large.
from the grid during GOHs, this demand may create a burden on
ii. The standard SOC variation of HCSD is considered to be 20–
the grid. Therefore, in this solution, the stored energy in HCSD
80%. Here, the SOC value of <50% is considered to represent
from the grid and from solar (as in the regular days) as well will be
the condition where the stored energy in HCSD is less.
utilised more for EBTS support and less towards the grid. Thus,
even with the increase in demand, the demand on the grid will not iii. EG represents the grid energy, and here, +EG indicates energy
increase. flow from the grid to HCSD.
S-2: this solution gives an option to the E-buses to charge more iv. In the case of the bus frequency (Bf), the UD bus frequency is
from the (k − 1)th stop to compensate for the increased demand of the standard and FD bus frequency is compared with the
energy raised due to the traffic condition at the kth stop. This can earlier.
be done by utilising most of the HCSDs(k+1) stored energy for
supporting the EBTS and less towards the grid for grid support The FLC compares the system parameter values for the present
until the issue exists. scenario with the standard ones. Based on the variation of the
S-3: this option is similar to the earlier solution and will give an system parameter values, the FLC identifies the particular issues
option to the E-buses to charge more from the (k + 1)th stop. that have occurred. According to the issue, the FLC of the
The last one C-III is the condition when the EBTS requirements corresponding EBS responds. The response of each FLC at EBSs
at the kth stop increases due to a festive season. The solution for follows the set of solutions discussed in this section.
this issue can be given by increasing the rate of charge of the The inputs to the FLC are therefore Vpu, SOC and Bf and the
HCSD placed at the kth stop during the GOHs. Thus, the HCSD output are P+/– and SP+/–. P+ indicates energy flow from the grid
can store enough energy required during the time for supporting the towards HCSD and P− indicates energy flow towards the grid.
increased demand for EBTS. Similarly, SP+ indicates energy flow from the solar PV panel to
All these actions will be decided by the controller discussed in
the next sub-section. HCSD, whereas SP− indicates energy flow from the solar PV panel
to grid. The inputs Vpu and SOC are classified into three MFs high,
medium and low (H, M, L) and Bf into five: very high, high,
4.2 Control algorithm
medium, and very low (VH, H, M, L, VL). The output is defined
In this work, the purpose of the FLC is to decide the control actions by nine: positive very high, positive high, positive low, positive
based upon variations of the system parameters viz., voltage profile very low, zero, negative very low, negative low, negative high and
negative very high (PVH, PH, PL, PVL, Z, NVL, NL, NH, and two conditions, i.e. maximum solar energy (bright sunny day) and
NVH). The inputs to the FLC are presented in Fig. 2. minimum solar energy (cloudy/rainy day).
The proposed EBTS constitutes E-buses, which will drive
through the ring road of Guwahati city using electric energy from 5.1 Analysis of the solutions of C-I
the grid. The energy from the grid is stored in the low HCSDs
placed at each EBS. This indicates that the HCSD is directly S-1: due to transformer/converter failure at the kth stop, the HCSD
connected to the grid via a DN of 11/0.420 kV. is unable to store energy from the grid to support the EBTS. The
To reduce the dependency of the system on the grid, HCSD is solution is that the (k + 1)th stop HCSD will supply the combined
considered to store charge from the grid only during the GOHs and load of the (k + 1)th stop and kth stop. The graphs below show the
from the solar PV during the daytime. The controller, under normal per unit voltage concerning the (k + 1)th stop.
operational conditions, thus has to perform the control actions Fig. 14 presents the voltage profile of the grid for three
based on the following points: conditions represented using different colours. Black colour
represents the per unit voltage of the grid for the actual load on it.
i. Energy from the grid to HCSD will flow during the GOHs Red colour represents the per unit voltage profile when the (k +
only. 1)th load is combined with that of the kth load. The blue line
ii. Energy from solar PV will be stored directly in the HCSD. represents the voltage profile when this combined load is supplied
iii. Energy from solar PV will be utilised for grid support during by the HCSD placed at the (k + 1)th stop.
the GPHs. When the grid supplies the (k + 1)th stop load (black line) only,
per unit voltage maintains at 0.995 during GOHs and comes down
iv. Energy from HCSD will be utilised to support the EBTS for
to 0.985 during GPHs. The red line comes down to a minimum
the entire day.
value of 0.975 when the kth stop load is combined with that of the
v. Energy from HCSD will be utilised to support the grid during (k + 1)th stop. When this load is supplied by the HCSD (blue line),
the GPHs after supporting the EBTS. per unit voltage is seemed to be maintained at a value of 0.985
(approx.). While during the GOHs, when the HCSD stores energy
Now under contingency conditions (described in the earlier sub- from the grid per unit voltage comes down to 0.987 from 0.995.
section), the control actions will be based on the following: support S-2: similar to S-1, when the HCSD of the kth stop is unable to
to the EBTS to maintain continuous service is of most priority and store energy from the grid, the (k − 1)th stop HCSD supports the
hence based on the contingency conditions either of the two load of the kth stop and thus maintains the systematic operation of
sources (grid and solar) will support the EBTS requirement. the EBTS. In Fig. 15, the black line represents the voltage profile
when the (k − 1)th load is supplied by the grid. During the GOHs,
i. The controllers placed at each EBS (k − 1, k and k + 1) will first the voltage seems to be at around 0.99 and 1, and during GPHs the
collect the inputs from solar PV panel, grid, HCSD, and TCC. voltage comes down at 0.98. When the kth stop load is combined
The type of contingency will then be identified by the failure with that of the (k − 1)th load, the voltage comes down to 0.96 (red
sensor. line). The blue line represents the voltage profile when the HCSD
ii. Based on the type of contingency, the control actions will be supplies the combined load by storing energy from the grid during
decided and control signals will be sent to the individual sub- GOHs. The voltage, in this case, is maintained at 0.99 during
systems for further actions. GOHs and at 0.98 during GPHs.
S-3: Fig. 16 presents the voltage profile showing the effect on
Table 4 presents the rule base for the decision making of the FLC the grid voltage when the kth stop load is shared by the (k + 1)th
based on the above normal operating and contingency conditions. and (k − 1)th stop. The black and blue line represents the per unit
The effects of the contingencies and their solutions on the voltage profile when the (k + 1)th and (k − 1)th stop the grid
operation of the entire system can be observed in the results supplies load. The red line presents the condition when the HCSD
section. supplies the (k + 1)th stop load and half of that of the kth stop load.
Similarly, the purple line presents the condition when the HCSD
5 Results and discussion supplies the (k − 1)th stop load and half of that of the kth stop load.
The analysis of the contingencies (discussed in Section 4) of the
proposed EBTS is done in this work. A simulation model of the 5.2 Analysis of the solutions of C-II
system is designed, and an FLC is implemented for control actions. S-1: C-II is the case where a sudden transient appears due to
The results of the analysis are presented in this section. The results congestion in the kth stop. Fig. 17 presents the scenario where in
include the changes in demand on the grid due to different issues order to compensate the sudden rise in energy demand of the
and the per unit voltages of the corresponding issue. The per unit EBTS, the energy stored in the HCSD from the grid and solar is
voltage of the grid represent the effects of the changes in demand utilised more towards the EBTS and for the time being, less
on the voltage profile of the grid. The analysis is done considering
Fig. 14 Vpu of the grid for the (k + 1)th stop during S-1
support is given to the grid. The red line presents the condition of
C-II due to which the Vpu has a value of 0.96 during 15:00–17:00 h
which is the peak duration for both EBTS and grid. The purple line
presents the condition when the demand is supplied by the HCSD
and solar. As the condition is to support more to the EBTS and less
to the grid, hence the grid profile could not be improved during the
GPHs, which appear during 16:00–18:00 h.
Fig. 18 presents the S-2 to the issue of congestion in the kth
stop where the (k + 1)th stop HCSD will support the sudden rise in
energy demand in the kth stop. It can be seen from the weekly grid
profile of the (k + 1)th stop (Fig. 4a), which is a residential
location, the energy demand is similar throughout the day. Since,
due to the occurrence of C-II, less support is given towards the
Fig. 15 Vpu of the grid for the (k − 1)th stop during S-2 grid, the grid Vpu does not seem to improve during the GPHs
(purple line).
S-3: Fig. 19 presents the S-3 to issue C-II where the sudden
increase in EBTS demand is supplied by the kth stop HCSD along
with that of the (k + 1)th stop HCSD. The black and red line
presents the Vpu for actual load on the kth and (k + 1)th stop,
Fig. 19 Vpu of the kth and (k + 1)th stop during S-3
respectively. To study the Vpu of S-3, the Vpu for the following
conditions are checked:
i. The effect on the Vpu of the kth stop when half of the kth stop
EBTS load is supplied by the kth stop grid (blue line).
ii. The effect on the Vpu of the (k + 1)th stop when half of the kth
stop EBTS load is supplied by the (k + 1)th stop grid (pink
line).
iii. The effect on the Vpu of the kth stop when half of the kth stop
EBTS load is supplied by the kth stop HCSD (green line).
iv. The effect on the Vpu of the (k + 1)th stop when half of the kth
stop EBTS load is supplied by the (k + 1)th stop HCSD (dark
blue line).
v. The effect on the Vpu of the kth stop when half of the kth stop Fig. 20 Vpu of the grid for the kth stop on a FD
EBTS load is supplied by the kth stop HCSD and solar (violate
line). reason that more people use EBTS during this interval. Lastly, the
vi. The effect on the Vpu of the (k + 1)th stop when half of the kth purple line presents the condition when the combined load of the
stop EBTS load is supplied by the (k + 1)th stop HCSD and grid and EBTS is supplied by the HCSD of the kth stop. It can be
solar (dark purple line). observed that the Vpu, in this case, seems to maintain at 0.990
during the GOHs and at 0.985 during the GPHs.
The dark purple line seems to maintain a constant Vpu Hence, with the control algorithm and rule-base proposed in the
comparing to that of the other conditions. earlier section, the FLC seems to compensate for the sudden
changes in demand raised due to various issues present in the
5.3 Analysis of the solutions of C-III system. The next section presents the sustainability analysis of the
system in case of severe contingency condition.
C-III presents the issue when the demand on EBTS as well as grid
increases due to FD. The variation of load on EBTS due to the 6 System sustainability in case of severe
festival season is presented in Fig. 20. The black line presents the
Vpu for the actual load on the kth stop grid. contingency conditions
It can be observed that the value of Vpu decreases to 0.975 In the previous sections, contingency analysis of the system
during 15:00–20:00 h. The red line presents the Vpu when a huge towards various energy disruptions that may occur between the
rise in grid demand occurs during 15:00–21:00 h. The Vpu, in this critical energy pathways as mentioned in the earlier sections has
been presented. The proposed system constitutes 60 EBSs and each
case, seems to reduce from 1 to 0.975 (from 15:00 to 21:00 h)
EBS is connected to the grid. The energy disruption conditions
which indicates a huge demand on the grid due to decorations in a
were considered for a particular EBS and therefore the support
locality during this time the FD. The blue line presents the Vpu
required to drive the E-buses from the particular EBS can be
when the EBTS load during the FD is supplied by the kth stop grid. provided from the stored energy at the EBS that is nearest.
The Vpu, in this case, seems to reduce from 1 to 0.970 (from 15:00 Furthermore, the sources (grid energy and solar energy) are also
to 21:00 h), which indicates a huge demand on EBTS due to the available in the nearest stop and so energy compensation is easier.
In this section, the sustainability of the system in the case where iv. When the grid is not stressed and PV generation is unavailable.
80% of the EBSs are disconnected from the sources (grid energy 2 Solar energy is poor and hence no support from solar energy in
and solar energy) for the entire day and for blocks of periods all case of 80% of the EBSs: 48 HCSDs have no energy support from
over the day has been analysed and the results are presented. solar PV and this analysis has been done considering:
The following case scenarios have been considered for this
analysis: i. When the grid is stressed.
ii. When the grid is not stressed.
1 The solar PV and grid are disconnected from 80% of the EBSs: 3 The grid is disconnected from 100% of the EBSs: The HCSDs
The HCSDs placed at each EBS, store energy from the grid and store energy from the grid during the GOHs and this amount of
solar PV to charge the supercapacitors placed at each E-bus. 80% energy is the main support to the TS (if solar energy is not
of the EBSs disconnected from the grid and solar PV indicates that available which depends upon the availability of solar radiation
out of 60, 48 HCSDs are incapable of supplying the E-buses with that may vary based upon conditions of the sky). The following has
the required energy. Only the remaining 12 HCSDs are connected been considered under this case:
to the sources and can supply the TS with energy. To observe the
effects of monthly variations, the following were considered: i. PV generation is good.
ii. PV generation is poor.
i. When the grid is stressed and PV generation is available.
ii. When the grid is stressed and PV generation is unavailable or Table 5 presents the result of the analysis for the sustainability of
poor. the proposed system during conditions of severe contingency
iii. When the grid is not stressed and PV generation is available. conditions that are described in this section.