PDT COMPRESORES PARADA DE PLANTA DE LA UNIDAD DE PROCESO POLIETILENO I - 2019 

Activity ID Activity Name Original Start Finish 2019


Duration Feb 11 Feb 18 Feb 25 Mar 04 Mar 11 Mar 18 Mar 25
Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr
UOPII MANTENIMINETO COMPRESOR, REACTOR Y EQUIPOS 376.0h
CRACKING 21-Jan-19
UOP II07:00 27-Mar-19 06:30

UOPII.11 HITOS GENERALES 1314.0h 21-Jan-19 07:00 22-Mar-19 00:00


HITO-00000 INICIO DE ACTIVIDADES DE EQUIPOS ALTERNOS MMTO UOP II. 0.0h 21-Jan-19 07:00

HITO-00010 FIN DE ACTIVIDADES DE EQUIPOS ALTERNOS DE MMTO UOP II. 0.0h 22-Mar-19 00:00 FIN DE ACTIVIDADES DE EQUIPOS ALTERNOS DE MMTO UOP II.,

UOPII.0 MONTAJE DE COMPRESOR C-4201 Y TURBINA 352.0h 21-Jan-19 07:00 22-Mar-19 00:00

UOPII.0.1 C-4201 1314.0h 21-Jan-19 07:00 22-Mar-19 00:00


C-4201-00000 ENTREGA DE COMPRESOR A ECP EN HOUSTON 0.0h 25-Feb-19 20:00* ENTREGA DE COMPRESOR A ECP EN HOUSTON, 25-Feb-19 20:00*

C-4201-00001 EMBALAJE YADUANAS EEUU 24.0h 25-Feb-19 20:00 26-Feb-19 22:00

C-4201-00002 EMBALAJE YADUANAS BOGOTÁ YTRANSPORTE A GRB 52.0h 26-Feb-19 22:00 01-Mar-19 07:00

C-4201-00003 LLEGADA DE COMPRESOR A LA GRB 0.0h 01-Mar-19 07:00 LLEGADA DE COMPRESOR A LA GRB, 01-Mar-19 07:00

C-4201-00004 LLEGADA DE GRUA DE 400Tn 0.0h 26-Feb-19 06:00* LLEGADA DE GRUA DE 400Tn, 26-Feb-19 06:00*

C-4201-00005 ALISTAMIENTO DE GRUA DE 600Tn 48.0h 26-Feb-19 06:00* 28-Feb-19 10:00

C-4201-00010 VALIDARAR/ REGISTRO DE CONTROL CON OPERACIONES 1.0h 21-Jan-19 07:00 21-Jan-19 08:00

C-4201-00020 INSTALAR COMPRESOR EN SU BASE 22.0h 01-Mar-19 07:00 02-Mar-19 07:00

C-4201-00025 ARMADO DE ANDAMIO E INSTALACIÓN DE BARRERA PROTECTORA 24.0h 02-Mar-19 07:00 03-Mar-19 09:00

C-4201-00030 ANCLAJE,ACOPLADO YALINEACION DEL SC4201 96.0h 03-Mar-19 09:00 07-Mar-19 18:00

C-4201-00035 ARMADO DE VIGAS YTECHO 96.0h 03-Mar-19 09:00 07-Mar-19 18:00

C-4201-00040 CONEXIÓN DE TUBERIAS SUCCION/DESCARGA YANEXAS 48.0h 07-Mar-19 18:00 09-Mar-19 22:00

C-4201-00060 INSTALACION DE INSTRUMENTOS Y ELECTRICO ASOCIADOS 96.0h 09-Mar-19 22:00 14-Mar-19 07:00

C-4201-00070 REALIZAR FLUSHING 72.0h 14-Mar-19 07:00 17-Mar-19 14:00

C-4201-00075 PRUEBAS DE LAZOS E IPFs 24.0h 17-Mar-19 14:00 18-Mar-19 16:00

C-4201-00077 PRUEBAS ESPECIALES DEL COMPRESOR 72.0h 18-Mar-19 16:00 21-Mar-19 22:00

C-4201-00080 ENTREGA DE EQUIPO A OPERACIONES 2.0h 21-Mar-19 22:00 22-Mar-19 00:00

C-4201-00090 FIN DE ACTIVIDADES MONTAJE DEL C-4201 0.0h 22-Mar-19 00:00 FIN DE ACTIVIDADES MONTAJE DEL C-4201,

UOPII.0.10 TURBINA 86.7h 22-Feb-19 07:00 08-Mar-19 14:42


NC-4201-00003ARMADO DE TREN DE VALVULAS E INSTALACIÒN EN LA TAPA DE LA 24.0h 22-Feb-19 07:00* 23-Feb-19 18:00
TURBINA
NC-4201-00005ENTREGA Y LLEGADA DE LA TURBINA NC-4201 A LA GRB 0.0h 23-Feb-19 07:00* ENTREGA Y LLEGADA DE LA TURBINA NC-4201 A LA GRB, 23-Feb-19 07:00*

NC-4201-00010TRANSP. ROTOR/TALLER/Planta 2.0h 23-Feb-19 07:00 23-Feb-19 09:00*

NC-4201-00020VERIFICARASENTAMIENTO CHUMAC/AZUL PRUSI 2.0h 23-Feb-19 09:00 23-Feb-19 12:00

NC-4201-00030REVISAR RUN-OUT DEL ROTOR 3.0h 23-Feb-19 12:00 23-Feb-19 15:00

NC-4201-00040PRUEBA TINTAS PENETRANTES AL ROTOR 4.0h 23-Feb-19 15:00 23-Feb-19 20:00

NC-4201-00050CHEQUEO LINEA DEL ROTOR 1.0h 23-Feb-19 20:00 23-Feb-19 21:00

NC-4201-00060REVISIONALABEO RUEDA POR RUEDA 1.0h 23-Feb-19 21:00 23-Feb-19 22:00

NC-4201-00070PULIR EJE AREA CHUMACERAS 2.0h 24-Feb-19 06:00 24-Feb-19 08:00

NC-4201-00080CHEQUEO PERPENDIC/AL PLATO DE EMPUJE 1.0h 24-Feb-19 08:00 24-Feb-19 09:00

NC-4201-00090REVISAR/SUAVIZAR ROSCAS/TUERCAS 1.0h 24-Feb-19 09:00 24-Feb-19 10:00

NC-4201-00100CHEQUEAR BALANCEO DEL ROTOR 4.0h 24-Feb-19 10:00 24-Feb-19 15:00

NC-4201-00110TRANSPORTAR ROTORA LA PLANTA 2.0h 24-Feb-19 15:00 24-Feb-19 17:00

NC-4201-00120PRESENTAR ROTOR EN CARCAZA Y CENTRARLO 4.0h 24-Feb-19 17:00 24-Feb-19 22:00

NC-4201-00130CALIBRAR CHUMACERAS L.A/L.E./JUEGO AXIAL 8.0h 25-Feb-19 06:00 25-Feb-19 15:00

NC-4201-00140DESTAPAR ORIFICIOS DE LUB. A CHUMACERAS 0.5h 25-Feb-19 15:00 25-Feb-19 15:30

NC-4201-00150CALIBRAR DISTANCIA 1 RUEDA/TOBERA Y DIAF 1.0h 25-Feb-19 15:30 25-Feb-19 16:30

NC-4201-00160INSTALAR Y TORQUEAR TAPAS CHUMACERAS 4.0h 25-Feb-19 16:30 25-Feb-19 21:30

NC-4201-00170INST./PRESENTAR TAPA TURBINA/GIRAR ROTOR 2.0h 25-Feb-19 21:30 26-Feb-19 07:30

NC-4201-00180LEVANTAR TAPA/APLICAR SELLANTE/TORQUEAR 12.0h 26-Feb-19 07:30 26-Feb-19 21:30

NC-4201-00190INSTALAR INTOS ASOCIADOA A LA TURBINA 20.0h 26-Feb-19 21:30 28-Feb-19 12:30

NC-4201-00200ACOPLARACTUADOR HIDRAULICO 2.0h 28-Feb-19 12:30 28-Feb-19 14:30

NC-4201-00210ACOPLAR VALVULA TRIP 2.0h 28-Feb-19 14:30 28-Feb-19 16:30

NC-4201-00220CALIBRAR RECORRIDO PISTON DE FUERZA 4.0h 28-Feb-19 16:30 28-Feb-19 21:30

NC-4201-00230ACOPLAR TURBINA 4.0h 28-Feb-19 21:30 01-Mar-19 09:30

NC-4201-00240REALIZAR PROCESO DE ALINEACION/REGISTRAR 6.0h 01-Mar-19 09:30 01-Mar-19 16:30

NC-4201-00250RETIRAR SAS ELECT./PROBAR MOTORT.G. 1.2h 01-Mar-19 16:30 01-Mar-19 17:42

NC-4201-00260CIRCULARACEITE CON MALLA 48.0h 01-Mar-19 17:42 05-Mar-19 08:42

NC-4201-00270RETIRAR MALLAS Y COLOCAR EMPAQUES 2.0h 05-Mar-19 08:42 05-Mar-19 11:42

NC-4201-00280DESACOPLAR PARA PRUEBA DE DISPARO 4.0h 05-Mar-19 11:42 05-Mar-19 15:42

NC-4201-00290CALIBRAR VALTEK 8.0h 05-Mar-19 15:42 06-Mar-19 08:42

NC-4201-00300RETIRAR CIEGOS (SAS) 8.0h 06-Mar-19 08:42 06-Mar-19 17:42

NC-4201-00310PROBAR EN VACIO DISPARO MECANICO/ELECTRO 8.0h 06-Mar-19 17:42 07-Mar-19 11:42

NC-4201-00320ACOPLAR SISTEMA/INSTALAR CANOA 4.0h 07-Mar-19 11:42 07-Mar-19 15:42

NC-4201-00330INST. CHAQUETA TERMICA/INSULAR 6.0h 07-Mar-19 15:42 08-Mar-19 06:42

NC-4201-00340INSULAR Y/O AISLAR TUBERIAS 4.0h 08-Mar-19 06:42 08-Mar-19 11:42

NC-4201-00350REALIZAR LIMPIEZA DEL AREA 1.0h 08-Mar-19 11:42 08-Mar-19 12:42

NC-4201-00360ENTREGAR EQUIPO A OPERACIONES/GUARDIA 2.0h 08-Mar-19 12:42 08-Mar-19 14:42

UOPII.9 ABRIR DOS MANHOLES E INSPECCIONAR SR4201 256.8h 11-Feb-19 07:00 11-Mar-19 12:48
SR4201-000010 ARMARANDAMIOS EXTERIOR DUCTO Y CIMA 0.0h 11-Feb-19 07:00* 11-Feb-19 07:00

SR4201-000020 INST. SAS OPERACIONAL VER DOC. ANEXOS 16.9h 11-Feb-19 07:00 12-Feb-19 15:54

SR4201-000030 ABRIR MANHOLES (2) DESPOJADOR - PIERNAS DE CICLONES 7.9h 12-Feb-19 15:54 13-Feb-19 14:48

SR4201-000040 RETIRAR REFRACTARIO (QUESOS) 9.0h 13-Feb-19 14:48 14-Feb-19 14:48

SR4201-000050 INSTALAR FACILIDAD PARA INGRESO 2.5h 13-Feb-19 14:48 14-Feb-19 07:18

SR4201-000060 INSTALAS ILUMINACIONAREA A INTERVENIR 4.5h 14-Feb-19 07:18 14-Feb-19 12:48

SR4201-000070 SOLICITAR SERVICIO AUTOMOTOR 8.0h 14-Feb-19 07:18 14-Feb-19 16:18

SR4201-000080 ARMARANDAMION INTERNO 0.0h 14-Feb-19 16:18 14-Feb-19 16:18

SR4201-000085 RETIRAR BAYONETA 36.0h 14-Feb-19 16:18 18-Feb-19 16:18

SR4201-000090 RETIRAR CATALIZADOR 24.0h 18-Feb-19 16:18 21-Feb-19 13:18

SR4201-000095 ARMARANDAMIO EN EL RISER 16.0h 22-Feb-19 07:18* 23-Feb-19 15:18

SR4201-000100 INSPECCONARAREAS INTERNA CIE 4.0h 23-Feb-19 15:18 24-Feb-19 09:18

SR4201-000110 EJECUTAR RECOMENDACION CIE 0.0h 24-Feb-19 09:18 24-Feb-19 09:18

SR4201-000120 RETIRAR CABLES ILUMNACIONAREA INTERIOR 4.5h 24-Feb-19 09:18 24-Feb-19 14:48

SR4201-000130 RETIRAR DESARMARANDAMIO INTERIOR 8.0h 24-Feb-19 14:48 25-Feb-19 13:48

SR4201-000135 INSTALAR BAYONETA 20.0h 25-Feb-19 13:48 27-Feb-19 15:48

SR4201-000140 PREFABRICAR QUESOS INSTALAR 20.0h 27-Feb-19 15:48 02-Mar-19 07:48

SR4201-000150 INSTALAR CERRAR MANHOLES 12.0h 02-Mar-19 07:48 03-Mar-19 10:48

SR4201-000152 FIN DE ACTIVIDADES MANTENIMIENTO DEL R-4201 0.0h 03-Mar-19 10:48 FIN DE ACTIVIDADES MANTENIMIENTO DEL R-4201,

SR4201-000155 RECUPERARAISLAMIENTO DEL CAP SUPERIOR DEL REACTOR 100.0h 25-Feb-19 07:48* 08-Mar-19 08:48

SR4201-000160 DESARMARANDAMIO EXTERIOR 30.0h 08-Mar-19 08:48 11-Mar-19 12:48

UOPII.10 ABRIR TRES MANHOLES E INSPECCIONAR SR4202 167.8h 11-Feb-19 07:00 01-Mar-19 13:48
SR4201-160 ARMARANDAMIOS EXTERIOR DUCTO Y CIMA 0.0h 11-Feb-19 07:00* 11-Feb-19 07:00

SR4201-170 INST. SAS OPERACIONAL VER DOC. ANEXOS 16.9h 11-Feb-19 07:00 12-Feb-19 15:54

SR4201-180 ABRIR MANHOLES (3) FASE DILUIDA - COMBUSTOR - DISTRIBUIDOR 7.9h 12-Feb-19 15:54 13-Feb-19 14:48

SR4201-190 RETIRAR REFRACTARIO (QUESOS) 9.0h 13-Feb-19 14:48 14-Feb-19 14:48

SR4201-200 INSTALAR FACILIDAD PARA INGRESO 2.5h 13-Feb-19 14:48 14-Feb-19 07:18

SR4201-210 INSTALAS ILUMINACIONAREA A INTERVENIR 4.5h 14-Feb-19 07:18 14-Feb-19 12:48

SR4201-220 SOLICITAR SERVICIO AUTOMOTOR 8.0h 14-Feb-19 07:18 14-Feb-19 16:18

SR4201-230 ARMARANDAMION INTERNO 20.0h 14-Feb-19 16:18 17-Feb-19 08:18

SR4201-250 INSPECCONARAREAS INTERNA CIE 4.0h 17-Feb-19 08:18 17-Feb-19 13:18

SR4201-255 RETIRAR CATALIZADOR 30.0h 17-Feb-19 08:18 20-Feb-19 11:18

SR4201-260 EJECUTAR RECOMENDACION CIE 30.0h 20-Feb-19 11:18 23-Feb-19 15:18

SR4201-270 RETIRAR CABLES ILUMNACIONAREA INTERIOR 4.5h 23-Feb-19 15:18 24-Feb-19 09:48

SR4201-280 RETIRAR DESARMARANDAMIO INTERIOR 16.0h 24-Feb-19 09:48 26-Feb-19 07:48

SR4201-290 PREFABRICAR QUESOS INSTALAR 20.0h 26-Feb-19 07:48 28-Feb-19 09:48

SR4201-300 INSTALAR CERRAR MANHOLES 12.0h 28-Feb-19 09:48 01-Mar-19 13:48

SR4201-305 FIN DE ACTIVIDADES MANTENIMIENTO DEL R-4202 0.0h 01-Mar-19 13:48 FIN DE ACTIVIDADES MANTENIMIENTO DEL R-4202,

SR4201-310 DESARMARANDAMIO EXTERIOR 0.0h 01-Mar-19 13:48 01-Mar-19 13:48

UOPII.1 SE4264 - MANTENIMIENTO 128.6h 09-Feb-19 07:00 23-Feb-19 09:36


SE-4264-00010 ARMARANDAMIOS PARA INTERVENCION 5.6h 09-Feb-19 07:00* 09-Feb-19 13:36

SE-4264-00020 RETIR.AISLAM. TERM.A BOQUILL. YTAPAS 1.6h 09-Feb-19 13:36 09-Feb-19 15:12

SE-4264-00030 INST. DE CIEGOS DEL SAS VER RTANEXA 5.7h 09-Feb-19 15:12 10-Feb-19 10:54

SE-4264-00040 TRANS./ UBICAR EQUIP. AUTOM./DESARME 13.9h 09-Feb-19 15:12 11-Feb-19 10:06

Actual Work Critical Remaining Work Page 1 of 3

Remaining Work Milestone


PDT COMPRESORES PARADA DE PLANTA DE LA UNIDAD DE PROCESO POLIETILENO I - 2019 
Activity ID Activity Name Original Start Finish 2019
Duration Feb 11 Feb 18 Feb 25 Mar 04 Mar 11 Mar 18 Mar 25
Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr
SE-4264-00050 DESARMADO DE PARTES DEL EQUIPO 21.6h 09-Feb-19 15:12 12-Feb-19 08:48

SE-4264-00060 TRANS./ UBIC. HIDROEXTRACTORA/ SACAR HAZ 8.3h 11-Feb-19 10:06 12-Feb-19 09:24

SE-4264-00070 RETIRAR HAZ DE TUBOS DEL CASCO 3.8h 12-Feb-19 09:24 12-Feb-19 14:12

SE-4264-00080 INST. FACILIDADES HACER PHS 6.0h 12-Feb-19 14:12 13-Feb-19 10:12

SE-4264-00090 TRANS. PARTES Y HAZA PATIO DE LIMPIEZA 0.5h 13-Feb-19 10:12 13-Feb-19 10:42

SE-4264-00100 LIMPIAR CASCO, HAZ DE TUBOS YPARTES 30.0h 13-Feb-19 10:42 16-Feb-19 14:42

SE-4264-00110 TRANS. PARTES Y HAZA PLANTA 1.0h 16-Feb-19 14:42 16-Feb-19 15:42

SE-4264-00120 TRANS./ UBIC. HIDROEXTRACTORA/ METER HAZ 8.3h 16-Feb-19 15:42 17-Feb-19 15:00

SE-4264-00130 METER HAZ DE TUBOS EN EL CASCO 3.8h 17-Feb-19 15:00 18-Feb-19 08:48

SE-4264-00140 TRANS./ UBICAR EQUIP. AUTOM./ARMADO 14.7h 13-Feb-19 10:42 15-Feb-19 07:24

SE-4264-00150 ARMAR PARTES LADO TUBOS PARA P.H. 21.9h 18-Feb-19 08:48 20-Feb-19 13:42

SE-4264-00160 INSTAL. FACILID./ REALIZ. P.H. X TUBOS 3.0h 20-Feb-19 13:42 20-Feb-19 16:42

SE-4264-00170 ARMADO DE PARTES LADO CASCO PARA P.H. 6.5h 20-Feb-19 16:42 21-Feb-19 14:12

SE-4264-00180 INSTAL. FACILID./ REALIZ. P.H. X CASCO 1.7h 21-Feb-19 14:12 21-Feb-19 15:54

SE-4264-00190 RETIRAR CIEGOS CASCO/ CANAL, TORQUEAR 5.8h 21-Feb-19 15:54 22-Feb-19 12:42

SE-4264-00200 RECUP. AISLAM. TERM.A BOQUILLAS Y TAPAS 4.1h 22-Feb-19 12:42 22-Feb-19 16:48

SE-4264-00210 DESARMARANDAMIOS/ RETIRAR MATERIAL 2.8h 22-Feb-19 16:48 23-Feb-19 09:36

UOPII.7 SE4205A - LAVADO HAZ Y CASCO 109.8h 11-Feb-19 13:00 16-Feb-19 11:48

SE4205A-000010 ARMARANDAMIOS PARA INTERVENCION 3.4h 11-Feb-19 13:00* 11-Feb-19 16:24

SE4205A-000020 RETIR.AISLAM. TERM.A BOQUILL. YTAPAS 1.1h 11-Feb-19 16:24 11-Feb-19 17:30

SE4205A-000030 INSTALACION DE CIEGOS DEL SAS 2.4h 11-Feb-19 17:30 11-Feb-19 19:54

SE4205A-000040 TRANS./ UBICAR EQUIP. AUTOM./DESARME 3.6h 11-Feb-19 17:30 11-Feb-19 21:06

SE4205A-000050 DESARMADO DE CAJA Y PARTES DEL EQUIPO 12.0h 11-Feb-19 19:54 12-Feb-19 08:54

SE4205A-000060 TRANS./ UBIC. HIDROEXTRACTORA/ SACAR HAZ 2.8h 12-Feb-19 08:54 12-Feb-19 11:42

SE4205A-000080 RETIRAR HAZ DE TUBOS DEL CASCO 0.9h 12-Feb-19 11:42 12-Feb-19 13:36

SE4205A-000090 TERMINAR DESARMADO DEL HAZ DE TUBOS 2.2h 12-Feb-19 13:36 12-Feb-19 15:48

SE4205A-000100 TRANS. PARTES Y HAZA PATIO DE LIMPIEZA 1.0h 12-Feb-19 15:48 12-Feb-19 16:48

SE4205A-000110 LIMPIAR CASCO, HAZ DE TUBOS YPARTES 25.3h 12-Feb-19 16:48 13-Feb-19 20:06

SE4205A-000120 PREFABRICAR CAJA SI LO REQUIERE EL CIE 24.0h 13-Feb-19 20:06 14-Feb-19 22:06

SE4205A-000130 TRANS./ UBIC. EQUIP. AUTOM./ P.H PRELIM. 5.0h 13-Feb-19 20:06 14-Feb-19 02:06

SE4205A-000140 ARMAR PARTES LADO TUB. PARA P.H. PRELIM. 7.4h 14-Feb-19 02:06 14-Feb-19 09:30

SE4205A-000150 INST. FACIL./ REAL. P.H. X TUB. PRELIM. 1.8h 14-Feb-19 09:30 14-Feb-19 11:18

SE4205A-000160 DESARMADO DE CANAL POR P.H. PRELIMINAR 3.2h 14-Feb-19 11:18 14-Feb-19 15:30

SE4205A-000170 TRANS. PARTES Y HAZA PLANTA 1.0h 14-Feb-19 15:30 14-Feb-19 16:30

SE4205A-000180 TRANS./ UBIC. HIDROEXTRACTORA/ METER HAZ 2.8h 14-Feb-19 16:30 14-Feb-19 19:18

SE4205A-000190 METER HAZ DE TUBOS EN EL CASCO 0.9h 14-Feb-19 19:18 14-Feb-19 20:12

SE4205A-000210 TRANS./ UBICAR EQUIP. AUTOM./ARMADO 1.4h 14-Feb-19 20:12 14-Feb-19 21:36

SE4205A-000220 ARMAR PARTES LADO TUBOS PARA P.H. 2.2h 14-Feb-19 21:36 14-Feb-19 23:48

SE4205A-000230 INSTAL. FACILID./ REALIZ. P.H. X TUBOS 1.8h 14-Feb-19 23:48 15-Feb-19 02:36

SE4205A-000240 INSTAL. FACILID./ REALIZ. P.H. X CASCO 0.9h 15-Feb-19 02:36 15-Feb-19 03:30

SE4205A-000250 RETIRAR CIEGOS CASCO/ CANAL, TORQUEAR 2.5h 15-Feb-19 03:30 15-Feb-19 06:00

SE4205A-000260 INSTALAR SOLDAR CAJA EN BRIDA CANAL 24.0h 15-Feb-19 06:00 16-Feb-19 08:00

SE4205A-000270 RECUP. AISLAM. TERM.A BOQUILLAS Y TAPAS 2.1h 16-Feb-19 08:00 16-Feb-19 10:06

SE4205A-000280 DESARMARANDAMIOS/ RETIRAR MATERIAL 1.7h 16-Feb-19 10:06 16-Feb-19 11:48

UOPII.8 SE4205B - LADADO HAZ Y CASCO 133.4h 12-Feb-19 08:00 18-Feb-19 09:24
SE4205B-000010 ARMARANDAMIOS PARA INTERVENCION 3.4h 12-Feb-19 08:00* 12-Feb-19 11:24

SE4205B-000020 RETIR.AISLAM. TERM.A BOQUILL. YTAPAS 1.1h 12-Feb-19 11:24 12-Feb-19 13:30

SE4205B-000030 INSTALACION DE CIEGOS DEL SAS 2.4h 12-Feb-19 13:30 12-Feb-19 15:54

SE4205B-000040 TRANS./ UBICAR EQUIP. AUTOM./DESARME 3.6h 12-Feb-19 13:30 12-Feb-19 17:06

SE4205B-000050 DESARMADO DE CAJA Y PARTES DEL EQUIPO 12.0h 12-Feb-19 15:54 13-Feb-19 04:54

SE4205B-000060 TRANS./ UBIC. HIDROEXTRACTORA/ SACAR HAZ 2.8h 12-Feb-19 17:06 12-Feb-19 19:54

SE4205B-000070 RETIRAR HAZ DE TUBOS DEL CASCO 0.9h 13-Feb-19 04:54 13-Feb-19 05:48

SE4205B-000080 TERMINAR DESARMADO DEL HAZ DE TUBOS 2.2h 13-Feb-19 05:48 13-Feb-19 08:00

SE4205B-000090 TRANS. PARTES Y HAZA PATIO DE LIMPIEZA 1.0h 13-Feb-19 08:00 13-Feb-19 09:00

SE4205B-000100 LIMPIAR CASCO, HAZ DE TUBOS YPARTES 25.3h 13-Feb-19 09:00 14-Feb-19 13:18

SE4205B-000110 PREFABRICAR CAJA SI LO REQUIERE EL CIE 24.0h 14-Feb-19 22:06 16-Feb-19 01:06

SE4205B-000120 TRANS./ UBIC. EQUIP. AUTOM./ P.H PRELIM. 1.0h 16-Feb-19 01:06 16-Feb-19 02:06

SE4205B-000130 ARMAR PARTES LADO TUB. PARA P.H. PRELIM. 7.4h 16-Feb-19 02:06 16-Feb-19 09:30

SE4205B-000140 INST. FACIL./ REAL. P.H. X TUB. PRELIM. 1.8h 16-Feb-19 09:30 16-Feb-19 11:18

SE4205B-000150 DESARMADO DE CANAL POR P.H. PRELIMINAR 3.2h 16-Feb-19 11:18 16-Feb-19 15:30

SE4205B-000160 TRANS. PARTES Y HAZA PLANTA 1.0h 16-Feb-19 15:30 16-Feb-19 16:30

SE4205B-000170 TRANS./ UBIC. HIDROEXTRACTORA/ METER HAZ 2.8h 16-Feb-19 15:30 16-Feb-19 18:18

SE4205B-000180 METER HAZ DE TUBOS EN EL CASCO 0.9h 16-Feb-19 18:18 16-Feb-19 19:12

SE4205B-000190 ARMAR PARTES LADO TUBOS PARA P.H. 2.2h 16-Feb-19 19:12 16-Feb-19 21:24

SE4205B-000200 INSTAL. FACILID./ REALIZ. P.H. X TUBOS 1.8h 16-Feb-19 21:24 16-Feb-19 23:12

SE4205B-000210 INSTAL. FACILID./ REALIZ. P.H. X CASCO 0.9h 16-Feb-19 23:12 17-Feb-19 01:06

SE4205B-000220 RETIRAR CIEGOS CASCO/ CANAL, TORQUEAR 2.5h 17-Feb-19 01:06 17-Feb-19 03:36

SE4205B-000230 INSTALAR SOLDAR CAJA EN BRIDA CANAL 24.0h 17-Feb-19 03:36 18-Feb-19 05:36

SE4205B-000240 RECUP. AISLAM. TERM.A BOQUILLAS Y TAPAS 2.1h 18-Feb-19 05:36 18-Feb-19 07:42

SE4205B-000250 DESARMARANDAMIOS/ RETIRAR MATERIAL 1.7h 18-Feb-19 07:42 18-Feb-19 09:24

UOPII.3 PRESERVACION CALDERA 307.0h 21-Jan-19 07:00 24-Feb-19 08:00


CAL-000010 REALZAR PH 31.0h 14-Feb-19 12:30* 17-Feb-19 16:30

CAL-000020 APLICAR CAL 20.0h 17-Feb-19 16:30 20-Feb-19 08:30

CAL-000030 RETIRARANDAMIO INTERNO 25.0h 18-Feb-19 08:30 20-Feb-19 16:30

CAL-000040 CIERRE DE MANHOLES CÁMARAS 19 X 19 6.5h 20-Feb-19 16:30 21-Feb-19 14:00

CAL-000050 CIERRE DE MANHOLE TOLVAS 19 X 19. 11.0h 21-Feb-19 14:00 22-Feb-19 16:00

CAL-000060 EJECUTAR RECOMENDACIÒN DEL CHECK YLOS VENTEOS 10.0h 23-Feb-19 07:00 24-Feb-19 08:00

CAL-000070 RETIRAR CIEGOS 2.5h 22-Feb-19 16:00 23-Feb-19 08:30

CAL-000160 RETIRO ANDAMIOS EXTERIORES 9.0h 21-Jan-19 07:00 21-Jan-19 17:00

UOPII.4 BYPASS B-4201 256.0h 11-Feb-19 07:00 27-Mar-19 06:30

UOPII.4.5 GENERALES 42.5h 11-Feb-19 07:00 13-Feb-19 05:30


XBYP-B4201-00010
ARMARANDAMIONS ZONA A REPARAR 6.5h 11-Feb-19 07:00* 11-Feb-19 14:30

XBYP-B4201-00012
VERIFIFCAR MEDIDAS EN CAMPO PREFABRICAR codo y tramo Recto 3.0h 11-Feb-19 14:30 11-Feb-19 17:30
según RECOMENDACIÓN
XBYP-B4201-00014
APOYO AUTOMOTOR GRUA 2.0h 11-Feb-19 07:00 11-Feb-19 09:00

XBYP-B4201-00016
TRANSP LAMINAS AL TALLER para Prefab de Codo y Tramo Recto 13.0h 11-Feb-19 14:30 12-Feb-19 04:30

XBYP-B4201-00030
RETIRARACCESORIOS - Retirar Ducto Existente 36.0h 11-Feb-19 14:30 13-Feb-19 05:30

UOPII.4.4 RETIRO de By Pass 56.0h 11-Feb-19 07:00 15-Feb-19 07:00


30 RETIRARAISLAMIETO 8.0h 11-Feb-19 07:00 11-Feb-19 16:00

32 RETIRAR INSTRUMENTACIÓNASOCIADA 4.0h 11-Feb-19 16:00 11-Feb-19 21:00

34 DESCARBONAR CODOS 24.0h 11-Feb-19 21:00 13-Feb-19 16:00

36 IZAR TRAMOS A RETIRAR 4.0h 13-Feb-19 16:00 13-Feb-19 21:00

38 DESCONTAMINAR, CHICOTEAR Y TRANSPORTARA PATIO DE 16.0h 13-Feb-19 21:00 15-Feb-19 07:00


DESHECHOS
UOPII.4.3 PREFABRICACIÓN de TRES Codos en laminas de 1/2in 420.0h 25-Feb-19 06:30 27-Mar-19 06:30
2 CORTAR LAMINAS SEGUN MEDIDAS para fabricación de codos (3) 420.0h 25-Feb-19 06:30 27-Mar-19 06:30

4 ROLAR LAMINAS para armar codos 250.0h 25-Feb-19 06:30 14-Mar-19 20:30

6 PRESENTAR, PUNTEAR Laminas del Codo 18.0h 14-Mar-19 20:30 16-Mar-19 08:30

8 SOLDAR el Codo 28.0h 16-Mar-19 08:30 18-Mar-19 08:30

UOPII.4.1 PREFABRICACIÓN DOS Tramos Rectos en laminas de 3/8in 520.0h 12-Feb-19 06:00 21-Mar-19 08:00
10 CORTAR LAMINAS SEGUN MEDIDAS para fabricación de Tramo Recto (5) 520.0h 12-Feb-19 06:00 21-Mar-19 08:00

12 ROLAR LAMINAS para Tramo Recto 250.0h 13-Feb-19 06:00 02-Mar-19 20:00

14 PRESENTAR, PUNTEAR Laminas de Tramo Recto 18.0h 02-Mar-19 20:00 04-Mar-19 08:00

16 SOLDAR el Tramo Recto 18.0h 04-Mar-19 08:00 05-Mar-19 13:00

UOPII.4.2 INSTALACIÓN DE CODOS Y TRAMOS RECTOS EN B-4201 54.0h 05-Mar-19 13:00 09-Mar-19 10:00
26 Alistamiento y Preparación de Superficie LADO DUCTO DE CALDERA B-4201 18.0h 05-Mar-19 13:00 06-Mar-19 17:00

28 Alistamiento y Preparación de Superficie LADO DUCTO DE CHIMENEA X- 18.0h 05-Mar-19 13:00 06-Mar-19 17:00

XBYP-B4201-00070
APOYO AUTOMOTOR GRUA 5.0h 06-Mar-19 17:00 07-Mar-19 07:00

XBYP-B4201-00150
SOLICITAR SERVICIO AUTOMOTOR GRUA Y CAMI para Izaje 5.0h 06-Mar-19 17:00 07-Mar-19 07:00

XBYP-B4201-220
IZAJE,ALINEACIÓN Y PUNTEADO DE CODO EN LADO CALDERA 5.0h 07-Mar-19 07:00 07-Mar-19 13:00

XBYP-B4201-230
IZAJE,ALINEACIÓN Y PUNTEADO DE TRAMO RECTO EN LADO CHIMENEA 5.0h 07-Mar-19 13:00 07-Mar-19 18:00

Actual Work Critical Remaining Work Page 2 of 3

Remaining Work Milestone


PDT COMPRESORES PARADA DE PLANTA DE LA UNIDAD DE PROCESO POLIETILENO I - 2019 
Activity ID Activity Name Original Start Finish 2019
Duration Feb 11 Feb 18 Feb 25 Mar 04 Mar 11 Mar 18 Mar 25
Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr Fri Sat Sun Mon Tue Wed Thr
XBYP-B4201-232
SOLDADURA DE CODO EN LADO CALDERA 5.0h 07-Mar-19 19:00 08-Mar-19 08:00

XBYP-B4201-234
SOLDADURA DE TRAMO RECTO EN LADO CHIMENEA 5.0h 07-Mar-19 19:00 08-Mar-19 08:00

XBYP-B4201-236
REALIZAR PRUEBA XXXXX A SOLDADURAS 9.0h 08-Mar-19 08:00 08-Mar-19 18:00

XBYP-B4201-238
ENTREGARA CIE SOLDARARIFICIOS 2.5h 08-Mar-19 19:00 08-Mar-19 21:30

XBYP-B4201-240
DESARMARANDAMIOS 4.5h 08-Mar-19 21:30 09-Mar-19 10:00

UOPII.5 LG ST4253 21.6h 26-Feb-19 07:00 27-Feb-19 06:36


LG ARMARANDAMIOS 1 DE 1 CUERPO 13,23M2 2.4h 26-Feb-19 07:00* 26-Feb-19 09:24
ST4253-000010
LG DESACOPLAR BRIDAS RETIRAR LG 6.0h 26-Feb-19 09:24 26-Feb-19 16:24
ST4253-000020
LG DESARMAR REALIZAR MANTENIMIENTO AL LG 6.0h 26-Feb-19 16:24 26-Feb-19 22:24
ST4253-000030
LG TRANSPORTAR INSTALAR LG PROBAR 6.0h 26-Feb-19 22:24 27-Feb-19 05:24
ST4253-000040
LG DESARMARANDAMIO 1.2h 27-Feb-19 05:24 27-Feb-19 06:36
ST4253-000050
UOPII.6 LG ST4201 21.6h 27-Feb-19 05:24 28-Feb-19 05:00
LG ST4253-50 ARMARANDAMIOS 1 DE 1 CUERPO 13,23M2 2.4h 27-Feb-19 05:24 27-Feb-19 07:48

LG ST4253-60 DESACOPLAR BRIDAS RETIRAR LG 6.0h 27-Feb-19 07:48 27-Feb-19 14:48

LG ST4253-70 DESARMAR REALIZAR MANTENIMIENTO AL LG Y4 VIDRIOS 6.0h 27-Feb-19 14:48 27-Feb-19 20:48

LG ST4253-80 TRANSPORTAR INSTALAR LG PROBAR 6.0h 27-Feb-19 20:48 28-Feb-19 03:48

LG ST4253-90 DESARMARANDAMIO 1.2h 28-Feb-19 03:48 28-Feb-19 05:00

UOPII.2 BYPASS B-4201 INSERTO 90 16.0h 25-Feb-19 07:00 26-Feb-19 00:00


BYP-B4201-00010GRATAR AREAS DE SELLO REMOVIENDO GRAFOI 6.0h 25-Feb-19 07:00* 25-Feb-19 14:00

BYP-B4201-00020RETIRAR EL KAOWOOL 2.0h 25-Feb-19 14:00 25-Feb-19 16:00

BYP-B4201-00030SOLDAR LAMIANS SUELTAS CON ELECTRODO E30 4.0h 25-Feb-19 16:00 25-Feb-19 20:00

BYP-B4201-00040INSTALAR Y TACAR KAOWOOL 4.0h 25-Feb-19 20:00 26-Feb-19 00:00