RDSS L2 Pert Chart - PKG-02 - Behala..... 21082023
RDSS L2 Pert Chart - PKG-02 - Behala..... 21082023
Total Quantity as
Name of Months
per NoA
sl no Activity description UOM m
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 ###
a
y
Jul'23 Aug'23 Sep'23 Oct'23 Nov'23 Dec'23 Jan'24 Feb'24 Mar'24 Apr'24 May'24 June'24 July'24 Aug'24 Sep'24 Oct'24 Nov'24 Dec'24 Jan'25 Feb'25 Mar'25 Apr'25 May'25 Jun'25 July'25
'
1 2 3 5 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 2
42 ###
0
Erection, Testing & Commissioning
Feeder Bifurcation
Q2 (2023-24) Q3 (2023-24) Q4 (2023-24) Q1 (2024-25) Q2 (2024-25) Q3 (2024-25) Q4 (2024-25) Q1 (2025-26)
New HT Line
z KM
0% 1% 4% 3% 3% 4% 6% 8% 6% 2% 1% 4% 1% 6% 9% 5% 5% 5% 7% 9% 9%
1.4 Stringing & Sagging with HT AB Cable CKM 4 0 0 0 0 0 0.3 0.3 0.3 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.24 0.2 0.4 0.4 0.46
0% 0% 4% 4% 4% 4% 7% 7% 7% 3% 3% 3% 2% 7% 7% 5% 5% 5% 8% 8% 7%
1.5 Laying of 11KV Garde 3X185Sqmm XLPE UG Cable Km 9.99 1.5 0.000 1.000 1.000 0.300 0.300 0.400 0.500 0.500 0.500 0.500 0.500 0.500 0.900 0.900 0.690
0% 0% 0% 0% 0% 0% 0% 9% 9% 9% 9% 9% 0% 9% 9% 9% 9% 9% 4% 4% 3%
Laying of 11KV Garde 3X185Sqmm XLPE UG Cable at
1.6 Highway & Railway Crossing
Km 0.120 0.060 0.060
0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 54% 0% 0% 0% 0% 46% 0% 0% 0% 0%
Feeder Segregation
Q3 (2023-24) Q4 (2023-24) Q1 (2024-25) Q2 (2024-25) Q3 (2024-25) Q4 (2024-25) Q1 (2025-26)
New HT Line
2.01 Survey of 11KV Line KM
Page 1 of 5
Submission of L2 PERT CHART (Erection) as per NOA for RDSS Project under South 24 Parganas District
NOA no: Erection : CE/Project II/RDSS/SOUTH 24 PARGANAS/PKG 02/Erection/T-13/386-Dt.17.07.23
Name of District : South 24 Parganas
Package no.: PKG- 02
Name Of Agency : Polycab India Ltd.
Month wise Plan
Total Quantity as
Name of Months
per NoA
sl no Activity description UOM m
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 ###
a
y
Jul'23 Aug'23 Sep'23 Oct'23 Nov'23 Dec'23 Jan'24 Feb'24 Mar'24 Apr'24 May'24 June'24 July'24 Aug'24 Sep'24 Oct'24 Nov'24 Dec'24 Jan'25 Feb'25 Mar'25 Apr'25 May'25 Jun'25 July'25
'
1 2 3 5 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 2
42 ###
0
2.13 Stringing & Sagging with LT AB Cable CKm
3.2 Erection of 8m Pole No 25644 200 700 900 1300 1500 1800 1800 1800 1800 1300 1600 1300 500 1150 1150 1150 1150 1150 1150 1150 1094
0.7% 2.8% 3.5% 5.2% 5.9% 6.9% 6.9% 6.9% 6.9% 5.2% 6.2% 5.2% 1.7% 4.5% 4.5% 4.5% 4.5% 4.5% 4.5% 4.5% 4.8% 0.0%
3.3 Stringing & Sagging with LT AB Cable CKM 4274 20 120 180 220 220 220 260 260 260 180 180 180 90 180 260 270 260 250 220 220 224
0.4% 2.7% 4.1% 5.2% 5.2% 5.2% 6.2% 6.2% 6.2% 4.1% 4.1% 4.1% 2.1% 4.1% 6.2% 6.2% 6.2% 5.8% 5.2% 5.2% 5.2% 0.0%
Page 2 of 5
Submission of L2 PERT CHART (Supply) as per NOA for RDSS Project under South 24 Parganas District
NOA no : Supply : CE/Project II/RDSS/SOUTH 24 PARGANAS/PKG 02/Supply/T-13/385-Dt.17.07.23
Name of District : South 24 Parganas
Package no.: PKG- 02
Name Of Agency : Polycab India Ltd.
Month wise Plan
Total Quantity as
Name of Months
per NoA
sl no Activity description UOM m
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 ###
a
y
Jul'23 Aug'23 Sep'23 Oct'23 Nov'23 Dec'23 Jan'24 Feb'24 Mar'24 Apr'24 May'24 June'24 July'24 Aug'24 Sep'24 Oct'24 Nov'24 Dec'24 Jan'25 Feb'25 Mar'25 Apr'25 May'25 Jun'25 July'25
'
1 2 3 5 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 2
###
0
Receipt of Materials at site
Feeder Bifurcation
Q3 (2023-24) Q4 (2023-24) Q1 (2024-25) Q2 (2024-25) Q3 (2024-25) Q4 (2024-25) Q1 (2025-26)
1.01 PCC Pole 9 Mtr Long Nos. 1164 40 40 40 40 40 100 40 80 140 40 40 100 40 40 80 80 100 84 0 0 0
1.4% 4.2% 4.4% 4.2% 4.9% 5.6% 5.6% 5.6% 11.3% 4.2% 4.9% 5.6% 1.4% 5.6% 5.6% 7.0% 8.4% 9.8% 0.0% 0.0% 0.0%
0.0% 0.0% 0.0% 16.7% 16.7% 16.7% 0.0% 50.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
0.0% 3.7% 6.2% 3.7% 6.2% 6.2% 6.2% 6.2% 12.4% 3.1% 6.2% 6.2% 3.1% 3.1% 6.2% 6.2% 6.2% 4.9% 4.2% 0.0% 0.0%
0.0% 2.3% 3.9% 5.9% 5.9% 5.9% 5.9% 5.9% 8.2% 5.9% 5.9% 5.9% 0.0% 5.9% 5.9% 5.9% 5.9% 9.4% 5.9% 0.0% 0.0%
0.0% 7.3% 0.0% 7.3% 8.8% 8.8% 8.8% 8.8% 8.8% 8.8% 8.8% 8.8% 0.0% 7.8% 7.3% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
1.06 HT, AB Cable with accessories KM 4.2 0 0 0 0 0 0.5 0.5 0 0.5 0.5 0 0 0.5 0.5 0 0 1.2 0 0 0
0.0% 0.0% 0.0% 0.0% 0.0% 15.9% 0.0% 15.9% 0.0% 15.9% 7.9% 7.9% 0.0% 12.7% 23.8% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
1.07 Pin Insulator with Fittings set 2754 0 80 80 160 160 160 200 250 250 100 160 170 0 170 200 200 200 214 0 0 0
0.0% 3.0% 2.9% 6.0% 6.0% 6.0% 7.2% 9.0% 9.0% 3.6% 6.0% 6.0% 0.0% 6.0% 7.2% 7.2% 7.2% 7.8% 0.0% 0.0% 0.0%
0.0% 2.8% 4.1% 6.9% 6.9% 6.9% 6.9% 8.3% 9.0% 4.1% 4.1% 6.9% 0.0% 6.9% 6.9% 6.9% 7.0% 5.5% 0.0% 0.0% 0.0%
0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 16.7% 0.0% 83.3% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
0.0% 9.5% 0.0% 3.2% 3.2% 7.9% 6.4% 7.9% 9.5% 7.9% 7.9% 7.9% 0.0% 4.8% 4.8% 3.2% 6.3% 4.8% 4.8% 0.0% 0.0%
1.11 GI Wire 4mm MT 2.928 - 0.50 - - 0.50 - 0.43 - - 0.50 - - 0.50 - - 0.50 - - -
0.0% 6.8% 0.0% 0.0% 5.7% 11.4% 0.0% 0.0% 11.4% 5.7% 5.7% 13.7% 0.0% 11.4% 28.3% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
0.0% 13.4% 0.0% 13.4% 13.4% 0.0% 0.0% 13.4% 13.4% 13.4% 0.0% 0.0% 0.0% 6.7% 0.0% 6.7% 0.0% 6.3% 0.0% 0.0% 0.0%
1.13 Stay Wire 7/3.15mm MT 5.816 0.6 0.9 1.5 0.9 1 0.5 0.416
0.0% 8.3% 0.0% 2.8% 2.8% 2.8% 5.5% 5.5% 5.5% 0.0% 11.0% 11.0% 0.0% 8.3% 8.3% 8.3% 9.1% 11.0% 0.0% 0.0% 0.0%
0.0% 6.0% 6.0% 6.0% 6.0% 6.0% 9.0% 9.0% 9.0% 0.0% 0.0% 9.0% 0.0% 6.0% 6.0% 6.0% 6.0% 6.0% 4.2% 0.0% 0.0%
0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 9.6% 9.6% 8.0% 8.0% 8.0% 8.0% 8.0% 8.0% 8.0% 8.0% 8.0% 8.3% 0.0% 0.0% 0.0%
0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 16.7% 0.0% 83.3% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
0.0% 0.0% 0.0% 0.0% 0.0% 28.3% 0.0% 0.0% 0.0% 0.0% 0.0% 28.3% 0.0% 43.4% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
Page 3 of 5
Submission of L2 PERT CHART (Supply) as per NOA for RDSS Project under South 24 Parganas District
NOA no : Supply : CE/Project II/RDSS/SOUTH 24 PARGANAS/PKG 02/Supply/T-13/385-Dt.17.07.23
Name of District : South 24 Parganas
Package no.: PKG- 02
Name Of Agency : Polycab India Ltd.
Month wise Plan
Total Quantity as
Name of Months
per NoA
sl no Activity description UOM m
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 ###
a
y
Jul'23 Aug'23 Sep'23 Oct'23 Nov'23 Dec'23 Jan'24 Feb'24 Mar'24 Apr'24 May'24 June'24 July'24 Aug'24 Sep'24 Oct'24 Nov'24 Dec'24 Jan'25 Feb'25 Mar'25 Apr'25 May'25 Jun'25 July'25
'
1 2 3 5 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 2
###
0
Feeder segregation
Q3 (2023-24) Q4 (2023-24) Q1 (2024-25) Q2 (2024-25) Q3 (2024-25) Q4 (2024-25) Q1 (2025-26)
2.01 PCC Pole 9 Mtr Long Nos.
Page 4 of 5
Submission of L2 PERT CHART (Supply) as per NOA for RDSS Project under South 24 Parganas District
NOA no : Supply : CE/Project II/RDSS/SOUTH 24 PARGANAS/PKG 02/Supply/T-13/385-Dt.17.07.23
Name of District : South 24 Parganas
Package no.: PKG- 02
Name Of Agency : Polycab India Ltd.
Month wise Plan
Total Quantity as
Name of Months
per NoA
sl no Activity description UOM m
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 ###
a
y
Jul'23 Aug'23 Sep'23 Oct'23 Nov'23 Dec'23 Jan'24 Feb'24 Mar'24 Apr'24 May'24 June'24 July'24 Aug'24 Sep'24 Oct'24 Nov'24 Dec'24 Jan'25 Feb'25 Mar'25 Apr'25 May'25 Jun'25 July'25
'
1 2 3 5 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 2
###
0
2.21 Stay Wire 7/3.15mm MT
0.7% 3.5% 3.5% 5.2% 5.2% 10.4% 6.9% 6.9% 8.6% 6.9% 6.9% 6.9% 1.7% 3.5% 4.5% 4.1% 4.1% 4.1% 6.5% 0.0% 0.0%
0.8% 1.9% 2.6% 5.6% 5.6% 9.4% 9.4% 9.4% 9.4% 3.8% 5.6% 5.6% 0.0% 5.6% 5.6% 5.6% 5.6% 5.6% 2.5% 0.0% 0.0%
1.3% 1.9% 3.8% 7.7% 8.3% 9.6% 6.4% 6.4% 6.4% 3.2% 5.8% 6.4% 0.0% 7.7% 7.7% 3.8% 3.8% 5.1% 4.5% 0.0% 0.0%
1.8% 2.7% 4.1% 6.8% 6.8% 6.8% 9.1% 9.1% 9.1% 6.8% 6.8% 6.8% 0.0% 5.9% 5.8% 4.6% 2.3% 2.3% 2.3% 0.0% 0.0%
1.0% 3.0% 4.9% 7.9% 7.9% 8.9% 5.9% 7.9% 7.9% 3.9% 5.9% 5.9% 0.0% 6.9% 6.9% 3.9% 3.9% 3.9% 3.4% 0.0% 0.0%
3.06 Service JB Nos 85480 100 1800 3500 4400 5000 5000 5000 7000 8000 5000 5000 5000 0 5000 5000 5000 5000 5000 5680 0 0
1.0% 2.1% 4.1% 5.2% 6.2% 6.2% 6.2% 8.3% 8.9% 5.7% 5.7% 5.7% 0.0% 5.7% 6.2% 6.2% 6.2% 6.2% 4.1% 0.0% 0.0%
3.07 LT stay Set with Insulator SET 55562 500 1800 2200 2600 4500 5300 2500 2500 2600 2600 2600 3500 900 4200 3500 3500 3500 3500 3262 0 0
0.8% 3.2% 4.0% 4.8% 8.0% 9.6% 4.8% 4.8% 4.8% 4.8% 4.8% 6.4% 1.6% 7.6% 6.4% 6.4% 6.4% 6.4% 4.8% 0.0% 0.0%
3.08 Earth Spike Nos 72658 500 1800 3000 5000 6600 7000 4500 4500 4500 2200 4000 4500 1800 5300 5300 2700 2700 3500 3258 0 0