Doc No: IMS-OM-CL-001-R00

Rev No: R0
PPM CHECKLIST: ACDB PANEL
Date:14/05/2013
Page 1 of 1

Plant Name :250 MW BADWAR REWA M.P


Equipment ID :
Equipment Name : DCDB Panel
Location :
Date :
Frequency :

Sr. No. Maintenance Checklist points Frequency Status

1 Clean the Panel thoroughly. Monthly

2 Check the Voltmeter indication working Monthly

3 Check the panel Earthing. Monthly

6 Check the insulators for any cracks / tracking / burns or any damages. Half Yearly

8 Check all the joints for tightness. Half Yearly

9 Inspect all wires for wear & cuts. Replace if necessary. Half Yearly

11 Check for mechanical damage, distortion of structure & mechanism in general. Yearly

12 Perform Maintenance activity on MCCB & Contactor Yearly

Observations/Suggestions:

Spares Replaced / Required Quantity

PPM Carried Out By : Supervisor Site Engg.


MTPL O&M MTPL (MTPL)