You are on page 1of 67

BTQS 3024 Professional Practice

(Contract Management)

Week 3(A)
Valuations and Final Account

Sr Ng Chooi Chooi
Semester 3, 2023

BTQS 3024 (Contract Management) - Week 3A : Valuations and


1
Final Account
Section 1:
Valuations

BTQS 3024 (Contract Management) - Week 3A : Valuations and


2
Final Account
Valuations

• Insight of Valuations
• Type of payment
• Type of contract price
• What is interim certificates
• Valuations in standard forms
• In real life practice

BTQS 3024 (Contract Management) - Week 3A : Valuations and


3
Final Account
Insight of valuations

• The main purpose of valuations is to reduce the need for the contractor to
fund the development.

• The contract sum paid to contractor by instalments.

• The primary obligations of the Employer is to PAY the Contractor,


promptly and fully, unless specific reasons for withholding it.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


4
Final Account
Type of payment

• Generally, there are 4 types of payment in construction contract:

1. Advance payment, ie PWD 203A, FIDIC.


2. Payment based on work executed, ie % of work done.
3. Stage payment, ie tied with schedule of payment under the Housing Development
(Control and Licensing) Regulation .
4. Bullet payment, payment upon completion of the project.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


5
Final Account
Type of contract price

• Different contracts deal with the contract price in different ways.

1. Contracts with BQs – paid upon the works described and quantified.
2. Lump Sum Contracts – paid upon the schedule of works.
3. Remeasurement Contracts – paid in full based on the works completed and
quantities actually carried out.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


6
Final Account
Sample of contract with BQs

BTQS 3024 (Contract Management) - Week 3A : Valuations and


7
Final Account
Sample of Lump Sum
Contract

BTQS 3024 (Contract Management) - Week 3A : Valuations and


8
Final Account
Sample of Remeasurement
Contract

BTQS 3024 (Contract Management) - Week 3A : Valuations and


9
Final Account
What is interim certificate

1. A mechanism for conforming an instalment of the contract sum is due to


the contractor.
2. Not conclusive about quality of materials, workmanship, satisfaction
with the work.
3. Only an obligation on the employer to make a payment, failing is a
serious breach of contract.
4. The most issued certificate, ie once at month.
5. As it involves payment of money, always a potential source of
disagreement.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


10
Final Account
Section 2:
Valuations – PAM 2018

BTQS 3024 (Contract Management) - Week 3A : Valuations and


11
Final Account
Contract Sum – PAM 2018

• Contract Sum – the amount of money the employer will pay to the
contractor or other payable amount
• Contract sum defined in Article 2 – Article of Agreement

BTQS 3024 (Contract Management) - Week 3A : Valuations and


12
Final Account
Clause 30 Certificate and Payment – PAM 2018

• Now there is a SPECIFIC REQUIREMENT for the contractor to submit a


PAYMENT APPLICATION at Interim Claim Interval stated in Appendix ,ie 1
month, to the Architect and Quantity Surveyor, (Clause 30.1).

• The details + documentation submitted shall be agreed by the Architect


or Quantity Surveyor.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


13
Final Account
Clause 30 Certificate and Payment – PAM 2018

• Inclusive of complete main contract + NSC’s payment application.

• Upon receipt of the Application (and FULL DETAILS), the Architect (with
Quantity Surveyor’s Certificate), has a MAXIMUM 21 days to issue a
corresponding INTERIM CERTIFICATE to the EMPLOYER, with a copy to
the Contractor.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


14
Final Account
Clause 30 Certificate and Payment – PAM 2018

• The Architect also required to :

a. DIRECT the Contractor as the amounts payable to any of the Nominated Sub-
Contractors and Nominated Suppliers under the Interim Certificate; and

b. INFORM / NOTIFY the relevant Nominated Sub-Contractor and Nominated


Supplier as to the amounts due to them under the Interim Certificate.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


15
Final Account
Clause 30 Certificate and Payment – PAM 2018

• Upon received of the Interim Certificate, the Employer is required to PAY


THE AMOUNTS CERTIFIED in FULL to the Contractor within the Period of
Honouring Certificates; ie 30 days from the Date of the Certificate.
• If the Employer FAILS to honour the Certificate (less any Liquidated
Damages or set-off to which he is entitled to), the Contractor may:
a. SUSPEND the work (Subject to the serving of notice) (Clause 30.7) OR
b. Charge INTEREST based on a rate of 1% + Maybank BLR on the outstanding
amount till the date payment is made (Clause 30.17) OR
c. DETERMINE (Terminate) his own employment (Clause 26.1(a)).
d. Refer to adjudication under Clause 34.1.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


16
Final Account
How to derive the amount due – PAM 2018

✓ Total Value of Work Properly Executed up to the date of the Payment Application.
+
✓ Materials and goods as delivered to site in the percentage value, up to the date of the
Payment Application , not temporary works and not prematurely delivered.
LESS
✓ The Retention Sum (Clause 30.5).
LESS
✓ Previously certified amount.

= AMOUNT DUE to the Contractor.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


17
Final Account
Clause 30 Certificate and Payment – PAM 2018

• Can we deduct Liquidated Damages in interim certificate ??


• No, cannot. Any amounts which the Employer is entitled or claim as Liquidated
Damages (Clause 22.2) or set-off (Clause 30.4) ARE NOT TO BE incorporated or
included into the interim certificate.

• Under PAM 2018, the imposition of Liquidated Damages is the Employer’s


prerogative.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


18
Final Account
Clause 30 Certificate and Payment – PAM 2018

• For set-off by the Employer, this is only allowed under Clause 2.4, 4.4,
5.1, 6.5(e), 6.7, 14.4, 15.3(b), 15.3(c), 15.4, 15.5, 19.5 and 20.A.3.

• This is also subject to the Architect or Quantity Surveyor giving


“Complete Details of their assessment of such set-off” to the Contractor.

• The serving of a written notice (according to the prescribed procedure) is


a condition precedent prior to any deduction for Liquidated damages or
set-off.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


19
Final Account
Retention Fund – PAM 2018

• Who owes the monies in Retention Fund ??


• The Contractor, Nominates Sub-contractor and Nominated Suppliers BUT the monies held in trust
by the Employer until their release as certified by the Architect (Clause 30.6(a)).

• The Employer’s interest as fund trustee and NO OBLIGATION to invest the money.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


20
Final Account
Retention Fund – PAM 2018

• The main purpose of Retention Fund:

a. If the Contractor fails to perform his obligations, ie failure to rectify defects, the
Employer may utilize this fund to pay 3rd party to carry out the defaults works;

b. Recover the Employer’s cost and loss;

c. Safety provision against re-possession of materials and goods by the Contractor’s


suppliers, if the retention of title still not transferred to the Contractor.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


21
Final Account
Retention Fund – PAM 2018

• Release of Retention Fund:


a. Release of 1st moiety – within 14 days upon issuance of Certificate of Practical
Completion(CPC).
b. Release of 2nd moiety – within 14 days upon issuance of Certificate of Making
Good Defects.

• Payment for both within the Period of Honouring Certificates.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


22
Final Account
Final Account – PAM 2018

• Final Account (Clause 30.10):


a. Timeframe for conclude a final account as follow:
Practical Completion QS Complete Final Account Amendment
IF Dispute
Contractor Submit
Final Account

If Agree, conclusive
If not, refer to arbitration
6 months 6 months 3 months 3 months

No Dispute
Conclusive+Agreed

BTQS 3024 (Contract Management) - Week 3A : Valuations and


23
Final Account
Final Account – PAM 2018

• Items in Final Account are:

a. The adjustment made to the Contract Sum.


b. The amounts the Contractor is entitled, ie Vos.
c. The adjustment on P.C. sums and profit based on actual amount payable by the
Employer.
d. The Adjustment of Provisional Sums and omission if not expended.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


24
Final Account
Final Account – PAM 2018

• Items NOT INCLUDED in Final Account are:


a. Liquidated damages imposed by the Employer.
b. Set-off by the Employer expressly provided by Clause 30.4
c. Interest payable by either parties.

• The Final Account can be rectified only if:


a. There is a fraud, dishonestly or fraudulent concealment relating to the Works;
or
b. There is any arithmetical error.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


25
Final Account
Section 3:
Valuations – PWD203A(2010)

BTQS 3024 (Contract Management) - Week 3A : Valuations and


26
Final Account
Contract Sum – PWD 203A(2010)

• Clause 7 stated the consideration of the works or such other sum become
payable.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


27
Final Account
Clause 28 Interim Certificate – PWD 203A(2010)

• Clause 28 regulates the issuance of Interim Certificate of payment by the


Superintending Officer.
• This enable the Contractor to be paid progressively.
• The certificate is the condition precedent to payment.
• The Contractor not able to commence action against the Government for
payment in the absence of a certificate.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


28
Final Account
Clause 28 Interim Certificate – PWD203A(2010)

• When the total value of work has reach the sum referred to in
Appendix, the S.O. is only obliged to carry out valuation for issuing the
1st interim certificate (Clause 28.1).
• For each subsequent valuation, the S.O. obliged to value the work
property executed, and unfixed materials, provided the value is equal
or more than referred in Appendix (Clause 28.2)
• The S.O. to value works properly executed, reject value the work with
patent defect.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


29
Final Account
Appendix to the Conditions – PWD203A(2010)
Amount stated here

BTQS 3024 (Contract Management) - Week 3A : Valuations and


30
Final Account
Clause 28 Interim Certificate – PWD203A (2010)

• The S.O. shall issue an Interim Certificate within 14 days from the date
of valuation .

• Provided THAT
1. The Contractor returned the signed Letter of Acceptance;
2. The Contractor has deposited the relevant insurance policies.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


31
Final Account
Clause 28 Interim Certificate – PWD203A (2010)

• The amount due in the Interim Certificate derived as follow :


✓ Estimated Value of Work Properly Executed
+
✓ 90% value of the unfixed materials and goods delivered to site, not temporary works and not
prematurely delivered.
+
✓ Fluctuation of Price (Clause 30)
LESS
✓ Advance Payment (Clause 69).
LESS
✓ Previously certified amount.
= AMOUNT DUE to the Contractor.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


32
Final Account
Clause 28 Interim Certificate – PWD203A (2010)

• In clause 26.8(a), the Government must pay the Contractor amount


certified as due in the Interim Certificate, within 30 days (if none specific)
from the issuance of certificate; provided:

• The Contractor has furnished performance bond;


• If the Contractor opted for the Performance Guarantee Sum, the Government is
entitled to retain 10% from the amount due. The limit of retention is 5% of the
Contract Sum.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


33
Final Account
Clause 60 Advance Payment – PWD203A (2010)

• The Contractor entitled for advance payment:


✓ 25% x Contract Sum less Provisional Sum (Builder Works).
✓ With Maximum of RM10mil.

• The Conditions for entitlement are :


✓ Return of the duly signed Letter of Acceptance, insurance policies, SOSCO,
receipt on premium paid;
✓ Banker’s/Insurance Guarantee = value of advance payment
✓ Submission Banker’s/Insurance Guarantee not later 3 months after site
possession.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


34
Final Account
Clause 60 Advance Payment – PWD203A (2010)

• Recoupment of advance payment:


✓ Recoup when the Builder work executed and certified up to 25%.
✓ Fully recovered when builder work reaches 75%.
✓ Formula to calculate :

BTQS 3024 (Contract Management) - Week 3A : Valuations and


35
Final Account
Clause 31 Final Account – PWD203A (2010)
• The Contractor must submit final claim with 3 months from Certificate
of Practical Completion.
• The submission must substantiated with relevant documents,
calculation including NSC, NS claims, receipt and vouchers.
• The S.O. is obliged by clause 31.3 to issue the Final Certificate within 3
months after the expiry of the Defects Liability Period or after the
Certificate of Making Good Defects, whichever is the later.
• The form is silent on how long the S.O. needs to complete his
assessment on the final account.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


36
Final Account
Clause 31 Final Account – PWD203A (2010)
• By clause 31.4, the Final Certificate must state the debt payable either by
the Government to the Contractor or vice versa.
• Debt payable = final assessment – permissible deductions

• Clause 31.5 , the Contractor is required to furnish a statutory declaration


on all wages has been paid, before the Government pay.
• The wages include wages of labour employed by all the sub-contractors,
nominated and domestic.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


37
Final Account
Section 3:
Valuations – CIDB(2000)

BTQS 3024 (Contract Management) - Week 3A : Valuations and


38
Final Account
Contract Sum – CIDB (2000)
• CIDB Form 2000, contract sum as defined in Article 2 of Article of
Agreement :-

BTQS 3024 (Contract Management) - Week 3A : Valuations and


39
Final Account
Clause 24 – Payment – CIDB (2000)

• Submission of Claim:

• The Contractor submit the Statement of Work Done to the S.O. at the interval
stated in the Appendix, ie 1 months.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


40
Final Account
Clause 24 - Payment – CIDB (2000)

• Statement of Work Done:


• Stage payment subject to agreement between parties for the Works or any part of
the Works(Clause 42.1(a)).

BTQS 3024 (Contract Management) - Week 3A : Valuations and


41
Final Account
Clause 24 - Payment – CIDB (2000)

• Valuation and Interim Certificate:


• The S.O. to issue an interim certificate within 21 days upon receiving of Statement
of Work Done.
• Amount Due in Interim certificate = :
• Work done less
• Retentions Monies (Clause 42.3) less
• Amount previously certified less
• Any sum certified to be deducted

BTQS 3024 (Contract Management) - Week 3A : Valuations and


42
Final Account
Clause 24 - Payment – CIDB (2000)

• Retention Monies (Clause 42.3):


• 10% retention , up to limit of 5% .
• The Employer shall be fiduciary as trustee.
• The Employer shall place the retention monies in a separate banking account.
The Employer is entitled for full benefit of the interest.
• The Employer has the right’s of deduction.
• Release 1st moiety – upon CPC.
• Release 2nd moiety – upon CMGD.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


43
Final Account
Clause 24 - Payment – CIDB (2000)

• Final Account (Clause 42.8):


• Within 3 months from Date of Practical Completion, the Contractor shall submit
the “Statement of Completion” which set out the final amounts of his
entitlement.
• The SO shall not later than 90 days after the issuance of CMGD, provide the
Final Account.
• The Final account shall show:
1. The adjustment made to contract sum.
2. The Contractor’s entitlement.
3. The Employer’s express entitlement.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


44
Final Account
Payment Bond v Performance Security Deposit
– CIDB (2000)

• What is a Payment Bond ??

• What is a Performance Security Bond ??

BTQS 3024 (Contract Management) - Week 3A : Valuations and


45
Final Account
Payment Bond – CIDB (2000)

• Payment Bond:

• Under Option Module E.


• 5% of Contract Sum.
• The Banker’s bond or insurer’s bond submitted by the Employer to the Contractor
within 14 days upon issuance of the Letter of Award.
• For the due performance and observance by the Employer under Clause 42.
• Valid until final payment made by the Employer.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


46
Final Account
Performance Security Bond – CIDB (2000)

• Performance Security Bond:


• Under Option Module F.
• 5% of Contract Sum.
• The Performance Security Bond in the form of Banker’s bond or insurer’s bond or
cash submitted by the Contractor to the Employer within 14 days upon issuance of
the Letter of Award.
• For the due performance, observance and obligations of the Contractor under the
Contract.
• Valid until issuance of Certificate of Practical Completion.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


47
Final Account
Unfixed equipment stored off site – CIDB (2000)

• Unfixed Equipment Materials or Goods Stored Off Site:


• Under Option Module B.
• The Contractor can claim for unfixed equipment, materials or goods before
delivery to Site ; provided:

1. The invoices and receipts of payment submitted,


2. Intended for the works,
3. In accordance with the Contract,
4. Suitably store, marked or identified at the premises.
5. Cannot fully and properly incorporated into the Works.
6. Not prematurely delivered and adequate storage place.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


48
Final Account
Section 4:
Valuations – IEM CE (2011)

BTQS 3024 (Contract Management) - Week 3A : Valuations and


49
Final Account
Contract Sum – IEM CE (2011)

• Article of agreement
• The Terms – item 2

BTQS 3024 (Contract Management) - Week 3A : Valuations and


50
Final Account
Clause 58 – Interim Certificate – IEM CE (2011)

• Clause 58.1 deals with the Contractor’s interim payment application and
timing.

• The Contractor may submit the Interim payment application at the interval
fixed in the appendix, if not stated is monthly.

• The Contractor include total work done, unfixed materials, completed


Variations, claims from NSC, in the application.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


51
Final Account
Clause 58 – Interim Certificate – IEM CE (2011)

• By clause 58.2 the Engineer must issue Interim Payment Certificate within
21 days after received the Contractor’s application.
• The Employer must pay the Contractor within the Period of Honouring
Certificate , clause 58.3.
• The Employer is entitled to set-off or deduct from the payment.
• If the Employer fails to pay, a simple interest as additional payment will
add to the certified amount.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


52
Final Account
Clause 58 – Interim Certificate – IEM CE (2011)

• Pursuant to clause 58.4, if the Employer fails to pay full amount, and
continue 14 days after Period of Honouring, the Contractor may serve a
written notice.
• Options for the Contractor:
a) Suspend the works;
b) Reduce the rate of construction.
• In either of the above option, the Contractor is entitled for:
• Extension of time; clause 42.2(1)
• Additional costs; clause 42.2(1)

BTQS 3024 (Contract Management) - Week 3A : Valuations and


53
Final Account
Clause 58 – Interim Certificate – IEM CE (2011)

• Retention Monies
• 10% of retention in certified amount.
• Limit of retention 5% of the Contract Sum.

• Release Retention Monies


• 2.5% , issue the Certificate of Completion.
• 2.5%, issue the Certificate of Making Defects.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


54
Final Account
Clause 59 – Final Account – IEM CE (2011)

• Clause 59.1 states, the Contractor must submit proposed final account
within 3 months after Certificate of Making Good Defects.
• The Contractor must substantiate the claim with supporting documents,
quantities, measurement & etc.
• By clause 59.2, the Engineer may issue the final account with 2 months
from the Contractor’s submission.
• The Employer to pay the Contractor the final certified amount within the
Period of Honouring.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


55
Final Account
Clause 60 – Effect of certificate – IEM CE (2011)

• No certificates is conclusion evidence of the acceptability of design.


• No interim payment certificate or Final Payment is final and binding.
• The Contractor is obliged to make good defects.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


56
Final Account
Option Module B – Price Fluctuation IEM CE (2011)

• The Contractor is allow to claim changes price for cement, steel


reinforcement bars, bitumen and diesel.
• The Contractor must include tender base price in his tender submission.
• The Contractor is entitled to claim price fluctuation in the monthly
payment application.
• Adjustment for prices must calculate based on the formula stipulated.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


57
Final Account
Case Law 1 – Issue of certificate

• English case law, London Borough of Camden v Thomas Mclnerny & Sons
Ltd (1986) 9 Con LR 99 held that:
• The mere signature of the architect on a certificate does not amount to its
issue.
• The dictionary meaning of “issue” means “to send forth, to give or send
out officially; to put into circulation”.
• Thus, since the certificate was signed and held back, it was not issued and
had no effect.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


58
Final Account
Case Law 2 – Interim certificate

• Usima Sdn Bhd v Lee Hor Fong, [2018] 1 CIDB-CLR 29.


• Usima was appointed as a main contractor by Jabatan Kerja Raya (JRK).
• Usima appointed a sub-contractor, Lee Hor Fong (“LHF”) to carry and
complete the contract works within the main contract.
• The terms and conditions of main contract using JKR 203A(Rev.10/83)
were deemed the basis of the sub-contract.
• Usima terminated the employment LHF.
• The whole works thereafter completed by Usima.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


59
Final Account
Case Law 2 – Interim certificate

• LHF commenced legal action to claim for payments for works done prior to
its termination.
• The High Court decided in favour of Usima in relation to termination and
counterclaim.
• The Court of Appeal decided other wise and allowed LHF’s claim.
• The Federal Court allowed LHF’s claims based on the interim certificate
jointly and measured and certified by Usima and JKR.
• The Federal Court held that LHF’s silent on the written notice, allowed
Usiam invoke sub-clause 51(c) to terminate his appointment.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


60
Final Account
Case Law 2 – Interim certificate

• Lessons Learnt:

• Contract documentation must be drafted clearly and agreed by both parties.


• For progress claims, the method and formats, the time for claiming must be clear
and consistence.
• Valued jointly by the Employer and the Contractor.
• All progress claim computed in cumulative manner.
• All instructions related to the work, must be in writing.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


61
Final Account
In real life practice – Architect’s Certificate

- Attention to Contractor
- Certificate Number
- Date of Certificate
Certified work done
for NSCs

Certified work done


for Contractor
Materials on Site

Retention Sum

Previously Certified
Amount

BTQS 3024 (Contract Management) - Week 3A : Valuations and


62
Final Account
In real life practice – Architect’s Certificate

Certified work done


to the respective NSCs

BTQS 3024 (Contract Management) - Week 3A : Valuations and


63
Final Account
Recap of lecture week 3A

• The intention of interim certificate.


• Exam relevant clauses in PAM 2018, PWD 203A (2010), CIDB (2000),
IEM CE 2011.
• Retention sum, limit of retention sum.
• Final account.
• Case law
• Architect’s certificate, in real life practice.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


64
Final Account
References

• Agreement and Conditions of PAM Contract 2018 (with quantities).


• Standard Form of Contract to used where Bills of Quantities form part of the
Contract , P.W.D. Form 203A (Rev 1/2020).
• CIDB Standard Form of Contract for Building Works 2000 Edition.
• IEM Form of Contract for Civil Engineering Works, 2011 Edition.
• The Malaysian PWD Form of Construction Contract , 2nd Edition, Lim Chong Fong.
• Guide on the CIDB Standard Form of Contract For Building Works, Ong See Lian,
Tan Swee Im , Ir Oon Chee Kheng.
• CIDB Construction Law Report 2017.

BTQS 3024 (Contract Management) - Week 3A : Valuations and


65
Final Account
Quote of the day

“Count your age by friends, not years.


Count your life by smiles, not tears.”

― John Lennon

BTQS 3024 (Contract Management) - Week 3A : Valuations and


66
Final Account
Thank you for your attention!!

BTQS 3024 (Contract Management) - Week 3A : Valuations and


67
Final Account

You might also like