FACTORY 2

Rehabilitation Project

(PROJECT DISCUSSION)
CLLEVA

20230328

www.acbel.com
CONTENT
1. Overview of Existing Facility
2. Facilitation Layouts and Scopes
A. Civil Works
B. Air Conditioning Requirements
C. Compressed Dry Air
D. Fire Protection
E. Exhaust System
F. Fire Alarm And Detection
G. Electrical System
H. Generator System
I. CCTV System
J. Biometrics Machine System

3. Production Detailed requirement


4. Project Schedule
5. Project Content

2
OVERVIEW:NEW FACTORY SITE LAY OUT PLAN
Current Building Facility

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 4
Current/Existing Floor Plan

Ground Floor Second Floor

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 5
Proposed Ground Floor Layout (Final Layout)

GF Rev3

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 6
Proposed Second Floor Layout

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 7
FACTORY 2
Facilitation Requirements
and Scopes

www.acbel.com
CIVIL WORKS
-EXTERIOR REPAIRS
-EXTERIOR NEW CONSTRUCTION
-INTERIOR REPAIRS/REHAB

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 9
Exterior Repairs –Scope of Work (1/4)
Item Scope of works Photos

Replacement of worn-out
1 gutters, downspouts,
outdoor canopy GI ceilings

Resealing of roof span


2 connection points and
screw points

Waterproofing of Roof deck


3
and drainage repair

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 10
Exterior Repairs –Scope of Work(2/4)
Item Scope of works Details/Photo

Repair of concrete crack


walls, repainting all outdoor
4
walls and resealing of glass
windows

Repainting & resealing of


5
exterior ducting

Restoration of Gates

-Gate 1-Restore only


6 -Gate 2- Restore and relocate the
position of the gate chase.

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 11
Exterior Repairs –Scope of Work(3/4)
Item Scope of works Details/Photo

Replace damage metal fence


7
on the front side.

Replacement of fence at the


back and include the side of
8
the garbage and chem room
(metal)

Repair rest area at left side of


left Gate
9 -Roof gutter
-repainting

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 12
Exterior Repairs –Scope of Work(4/4)

Item Scope of works Details


To recheck all potable water pipes and
10
connections for leak
Canopy installation for exterior facility Including facility located at roof
11 protection such as ACU outdoor units and exterior

-Repainting
12 Rehabilitation of Guard House
-Rehab of CR

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 13
Exterior Constructions -1/4
1. INSTALLATION OF ACBEL LOGO

REMOVE Area Requirement :


1. Remove the SEPHIL label
2. ACBEL LOGO size will follow
the existing LOGO here at
factory 1 site.

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 14
Exterior Constructions -2/4
2. NEW CHEMICAL ROOM

Area Requirement :
1. Demolition of existing building.
2. Area: 10x12m (120 sqm)
3. Estimated height – 6m
4. Roof-Concrete Slab finish
4. Room temp : 23± 3 ˚C/ 40~80 RH
5. Sprinkler Heads: 13pcs (need to verify)

NOTE: Provide detailed plan before and


after the construction.
We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 15
Exterior Constructions -3/4
3. NEW GARBAGE AREA

Area Requirement :
1. Demolition of existing building.
2. Roof only with concrete floor.
3. Estimated height – 6m
5. Sprinkler Heads: 13pcs (need to verify)

NOTE: Provide detailed plan before


and after the construction.

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 16
Exterior Constructions -4/4
3. NEW FACILITY WORKSHOP AREA

Area Requirement :
1. Area: 10mx4.2m= (42 sqm)
2. Estimated height – 3.5m
3. Closed room with Ventilation
3. Power outlets
4. Lightings

NOTE: Provide detailed plan before and


after the construction.

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 17
Interior Repairs/Rehab -1/10
1. MEZZANINE CONSTRUCTION

Mezzanine Specs.

1. Area: 21x21m (441 sqm)


2. Pallet position -134 pcs x 354kg
3. Total max. weight to bear- 47.44 tons
4. Estimated height – 2m
5. Mezzanine Floor = Metal plate with ESD tiles
top finish

NOTE: Provide detailed plan before and


after the construction.
GF Rev3

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 18
Interior Repairs/Rehab -2/10
2. REMOVAL OR DEMOLITION OF CONCRETE WALL

Specification:
1. Length: 24 meters
2. Height: 4.2 meter

Note: Need to verify measurement


on actual during site inspection

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 19
Interior Repairs/Rehab -3/10
3. REMOVAL OR DEMOLITION OF DRY WALLS

Specification:
1. Length: 260 meters
2. Height: 3.3 meter

Note: Need to verify measurement


on actual during site inspection

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 20
Interior Repairs/Rehab -4/10
4. INSTALLATION OF NEW DRY WALL PARTITION
Specification:
1. Length: 109.03meters
2. Height: 2.8 meter
3. Sides: Double wall
4.Brand: Hardiflex, Thickness=1/4”
5. Metal Studs: 4" x 2" x 10‘ x 5mmThick
6. Appearance: Gloss paint finish
3. Doors Width:
4.15m, 2.18m, 1.07m

Note: Need to verify measurement on


actual during site inspection

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 21
Interior Repairs/Rehab -5/10
5. REMOVAL OF EXISTING GI CEILING & Acoustic Ceiling

Specification:
1. AREA: 8,762 SQM

Note: Need to verify measurement


on actual during site inspection

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 22
Interior Repairs/Rehab -6/10
6. INSTALLATION OF NEW ACOUSTIC CEILING

Specification:
1.AREA: 6053 SQM
2.Ceiling board size: 60cm x120cmx10mm
3.Connection Type: T-Grid Suspension
4. Hanger: ¼ Full Threaded Rod
5. Ceiling Height: 2.8 meters

Note: Need to verify measurement on actual


during site inspection

Lower down the existing ceiling


height from 3.22m-2.8m

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 23
Interior Repairs/Rehab -7/10
7. CRYSTAL FLOOR AT WAREHOUSE
Specification & Reqts:
1. AREA: 2130 SQM
2. Removed existing ESD tiles
3. Crystal Flooring

Note: Need to verify measurement on actual


during site inspection

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 24
ESD Floor Layout (Green color) / Crystal Floor (White color)

ESD

ESD
ESD
ESD
ESD

ESD
ESD

ESD

ESD Floor Grounding Impedance Specification: < 1X 10ˆ9Ω


We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 25
Interior Repairs/Rehab -8/10
8. REPLACEMENT OF DAMAGE ESD TILES AND INSTALLATION AT NEW AREAS

Specification:
1. AREA: _______SQM
2. Size of tiles: 60cm x 60cm x 3mm
3. Color : Same color with existing
4. Point to Point Impedance: 1 x 10^9 ohms
5. Test result/report is required.

Note: Need to verify measurement on actual


during site inspection

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 26
Interior Repairs/Rehab -9/10
9. REMOVAL OF AHU DUCTING

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 27
Interior Repairs –10/10
10. OTHERS
Item Scope of works Details

1 Relocation of all single door from right to left. Quantity To verify during site inspection

2 Repainting of ALL indoor walls

3 Recheck all CR Facilities Functionality Conduct repair if necessary and overall clean.

Check the connections , suppression and rehabilitate


4 Canteen LPGAS check (2nd floor)
as possible

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 28
AIR
CONDITIONING

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 29
GROUND FLOOR AIRCONDITIONING LAYOUT -EXISTING

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 30
GROUND FLOOR AIRCONDITIONING LAYOUT -PROPOSED

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 31
SECOND FLOOR , COMPRESSOR ROOM AIRCONDITIONING LAYOUT

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 32
MEZZANINE AIRCONDITIONING LAYOUT
Area Requirement :
Area: 21x21m (441 sqm)
Estimated height – 2m
Room temp : 23± 3 ˚C/ 40~80 RH

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 33
GROUND FLOOR HEATLOADS ON MAJOR AREAS

SMT
Loading Lines HEATLOADS
1.Machines -109kW
2. Area -1064sqm
3. Ceiling Height – 2.6m
HEATLOADS 4. Worker-
1.Machines -460kW
2. Area -1947sqm
3. Ceiling Height – 2.6m
FINAL TEST 4. Worker-
HEATLOADS BBU
1.Machines -kW
MAGNETICS 2. Area -276 sqm
HEATLOADS HEATLOADS 3. Ceiling Height – 2.6m
1.Machines -kW 4. Worker-
1.Machines -240kW
2. Area -1047 sqm
2. Area -1085 sqm
3. Ceiling Height – 2.6m
3. Ceiling Height – 2.6m HEATLOADS ELEC WH
4. Worker- 1. Area -500 sqm
4. Worker- 2. Ceiling Height – 2.2m

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 34
AIR CONDITIONING SPECS PER AREA-Proposed(Vendor to re-compute based on the heatloads provided.
Location W L Area Size of ACU Type Qty Remarks
Training room 1 4.5 7 31.50 6HP Ceiling Mounted 1
Training room 2 3.76 6.77 25.46 6HP Ceiling Mounted 1
Meeting room 1 4.8 7 33.60 6HP Ceiling Mounted 1
Meeting room 2 4.8 7 33.60 6HP Ceiling Mounted 1
Office 6.8 15 102.00 6HP Ceiling Mounted 4
Conference Room 6.41 11.68 74.87 6HP Ceiling Mounted 3
VIP Room 5.43 7.03 38.17 2.5HP Wall mounted 2
Presidents Room 4.85 6.85 33.22 2.5HP Wall mounted 1
Server Room 2.5HP Wall mounted 4
22.62 25.22
Canteen 13.8 20.55 890.00 10 HP Floor Mounted 4
5.28 6.82
34.43 31.25
Floor Mounted
SMT Area 13.86 4.84 1063.55 10 HP 8
9.68 8.21
BBU area 11.42 24.16 275.91 10 HP Floor Mounted 4
Electrical Warehouse 16 31.25 500.00 10HP Floor Mounted 4
Mezzanine 21 21 441.00 10 HP Floor Mounted 4
Electrical Room 10HP Floor Mounted 2
OBA Area, CCTV Room 2.5 HP Wall mounted 3
Receiving and IQC 2.5 HP Window Type 4
Material prep & daughter card 8.8 16 140.80 10 HP Floor mounted 1
Production,Eng'g and QA Office 8.8 16 140.80 10 HP Floor Mounted 1
Loading Lines 33.8 57.6 1946.88 60HP AHU 3 with 1 back-up
Final Test and Packaging Area 30.5 34.34 1047.37 60HP AHU 2 with 1 back-up
Magnetics Area 25.53 42.5 1085.03 60HP AHU 2 with 1 back-up
We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 35
AIRCONDITIONING-Scope of Works
No Description Scope of Works
• To re-compute the capacity needed for the area based on the
headloads provided. Room temp req’t is 23± 3 ˚C/ 40~80 RH
• Removal of the existing AHU Ducting
• Check whether can re-used or not for the new system
1 AHU or Centralized Area
• Removal of the existing AHU indoor & outdoor unit.
• Supply and installation of the brand new unit(DAIKIN Brand)
• Installation includes the wiring from distribution panel to the
outdoor breaker.

• To re-compute the capacity needed for the area based on the


headloads provided. Room temp req’t is 23± 3 ˚C/ 40~80 RH
Individual Aircon • Supply and Installation of brand new unit
2 Brand: Daikin -10hp/6hp/2.5hp
• Installation includes the wiring from distribution panel to the
Panasonic-Window Type
outdoor breaker.

NOTE: Provide detailed plan before and after the installation.


We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 36
COMPRESSED
DRY AIR

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 37
CDA-Scope of Works
No Description Scope of Works
Air Compressor(Existing
1 • Rehabilitation of the existing units.(c/o ACBEL)
Units)
• Installation of new branches on SMT area and BBU
2 CDA Piping
area
• Supply and Installation of air drop piping on
Machine or Line CDA
3 machines and lines as specify on the detailed
supply
layouts.
• Provide detailed plan before and after the
4 Plans
installation for permit application

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 38
COMPRESSED DRY AIR LAYOUT
LEGEND:
Additional requirement
-4 UNITS OF 75HP Existing CDA pipe layout
-1 UNIT OF 50HP
AIRCOMPRESSOR
(OLD UNIT FOR RECONDITION) Specifications:
Pipe size:
-Feeder =50mm dia
-Branches =25mm dia
-Machine Drop-20mm dia
-Output pressure -6 BAR

Pipe type: GI schedule 40.

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 39
FIRE
PROTECTION
SYSTEM

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 40
Fire Sprinkler Layout
Cistern UndergroundTank –option 3
Specifications:
No. of Sprinkler Heads(WH)= 326 pcs
No. of Sprinkler Heads(chem RM) =13pcs
Cistern Vertical Tank No. of Fire Hose Cabinets– 14 pcs
Location-option 2 No. of Fire Hydrant Cabinets– 6pcs
Cistern Tank Size=
Pump Size=

NOTE: NEED TO SIZE-UP THE TANK SIZE AND


Cistern Vertical Tank PUMP SIZE BASED ON THE SPECS PROVIDED.
Location-option 1

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 41
Fire Hose Cabinet Existing Location

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 42
Fire Protection-Scope of Works
No Description Scope of Works
1 Main Fire Protection Pipeline • To recheck the connections

• Supply and installation of Sprinkler heads for warehouse,


2 Sprinkler Heads
Chemical Room , Garbage area and office areas.
• To relocate or remove some of the cabinets that affected
3 Fire Hose Cabinets
by the new layout.
• Supply of labor and materials for the construction of fire
4 Construction of Cistern Tank
protection cistern tank(water storage)

5 Fire Pump • Supply and installation

6 Plans • Provide detailed plan before and after the installation.

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 43
EXHAUST
SYSTEM

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 44
Exhaust System Layout
Exhaust Assembly Specification

Capacity 5HP
1 RPM 1745

Voltage/Phase 380V/3phase
3
Assembly Build Upright

2 No Area Remarks
1 Loading Lines Four(4) system
Magnetics &
2 Six(6) system
4 Varnishing

3 SMT Two(2) system.


1 intake & 1 Exhaust
4 Burn-in ducting for 2 units of BI
chamber

Note: Electrical power of the exhaust/intake motors is connected to the burn-in machine.

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 45
Exhaust System-Scope of Works
No Description Scope of Works

• To recheck existing ducting design if can re-use on the


Ducting works for Loading new required system. If not, follow the design provided on
1
Lines and SMT the layout but need to re-compute the size of the ducting
based on the fan assembly specification provided.

2 Ducting works for Magnetics • Supply and installation

3 Platform • Need to include the platform on the installation cost.

Ducting works for BI • Supply and installation(2 chambers will share for 1 system
4
Chambers of air intake and air exhaust)

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 46
FIRE DETECTION
AND ALARM
SYSTEM

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 47
FDAS-Scope of Works
No Description Scope of Works
• To recheck existing devices if can reuse.
• If yes, provide proposal for the reconditioning and
FDAS devices(Smoke & pull rehabilitation of the system.
1
& bells, door alarms) • If not, provide proposal for new supply and installation.
Need to re-compute the quantity based on the standard
applicable to the building area.

2 Control Panel(4 loops) • Supply and installation

4 Plans • Provide detailed plan before and after the installation.

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 48
FDAS Layout

System Specifications:
• CONTROL PANEL(4 Loops)
• SMOKE DETECTORS
-Ground Floor =550 pcs
-Second Floor= 111 pcs
• PULL STATION & BELLS
-Ground Floor =27pcs
-Second Floor= 6 pcs
• EXIT DOORS ALARMS -6 pcs

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 49
ELECTRICAL
SYSTEM

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 50
ELECTRICAL PANEL LOCATION-1/2

Panel PPAC-2

Transformer,2MVA Panel PPSP13


Panel LV 2-1 Panel PPSP14
Panel LV 2-2 Panel PPSP15
Panel LV2- 3 Panel PPSP16
Panel PPLP3
Panel PPSP5 Panel PPSP1 Panel DP1
Panel PPSP10
Panel PPSP6 Panel PPSP2 Panel PP1
Panel PPSP11
Panel PPSP7 Panel PPSP3 Panel PP2
Panel PPSP12
Panel PPSP8 Panel PPSP4 Panel PP3
Panel PPSP17
Panel PPSP9 Panel PPLP-1 Panel PPLP-4
Panel PPAC-3 Panel PPLP-2 Panel PPLP-5

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 51
ELECTRICAL PANEL LOCATION-2/2

Panel PPAC-2F
Panel PPAC-4
Panel PPAC-5
Panel PPAC-6
Panel LP-2A

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 52
ELECTRICAL PANEL ASSIGNMENTS
LIGHTING PANELS PRODUCTION PANELS NOTE:
Panel PPSP1- Loading Line 1 Most of this panels are
Panel PPLP1- Magnetics/WH
Panel PPLP2- Loading Lines & Final Test
Panel PPSP2- Loading Line 2 existing located at the factory.
Panel PPSP3- Loading Line 3
Panel PPLP3- SMT & Hallways Just only need to Rename and
Panel PPSP4- Loading Line 4
Panel PPLP4- BBU, Mezzanine & Elec WH
Panel PPSP5- Magnetics Line 1 rearrange.
Panel PPLP5- Burn-IN side
Panel PPSP6- Magnetics Line 2
Panel PPLP6- Second Floor
Panel PPSP7- Magnetics Line 3 Copy of Electrical Load Schedule:
Panel PPLP7- Compressor Room
Panel PPSP8- Magnetics Line 4
Panel PPLP8- Electrical, AHU RM,
Panel PPSP9- Magnetics Line 5
Perimeter
Panel PPSP10- Magnetics Line 6
Panel PPSP11- Magnetics Line 7
AIR CONDITIONING PANELS Panel PPSP12- Varnishing & Grinding
Panel PPSP13- SMT(small machines)
Panel PPAC1- AHU Panel PPSP14- SMT(Ovens) Based on the load computation, we will be
Panel PPAC2- ACU SMT Panel PPSP15- BBU Area needing to energized the 2 units of 2MVA
Panel PPAC3- ACU BBU/WH/MEZ Panel PPSP16- BBU Area transformer.
Panel PPAC4- ACU 2F Panel PPSP17-Final Test & Packaging
Panel PPAC5- ACU 2F Panel PPBI-1- Burn In TR #1 = Production Equipment & Lightings
Panel PPAC6- ACU 2F Panel PPBI-2- Burn In TR #2 = Air Conditioning & Burn-In
Panel PPAC7- ACU Chem RM/EE RM Panel PPBI-3- Burn

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 53
ELECTRICAL-Scope of Works
No Description Scope of Works
• Testing of existing electrical facility such as underground cables, transformers and switchgears
1 Electrical Main Feeder
• Rewiring of main power connections.
• Relocation of various panelboard on the designated areas and rewiring in reference to the
2 Secondary Power Supply
Electrical load schedule.
• Power cables, conduits and supporting materials. Connection from distribution panel to machine.
3 Machine or Line power supply
• Machine outlets must be twistlock outlets with plug.
• Grounding cables, conduits, outlets, esd devices
4 ESD Connections • Grounding Impedance Spec.: < 1 ohms
• Ground voltage: < 1 volts
• Replacement of lighting fixtures in production Area (2x28W-T8)
• Replacement of LED Tubes lights at SMT area
5 Lightings
• Installation of hibay lights at warehouse area.
• Illumination requirement 300 ~500 Lux.
• Supply and Installation of emergency lights and outlets on different areas. Quantity is based on the
6 Emergency Lights
standard applicable to the area.
7 Outlet System • Biometrics, canteen, offices
Lighting Surge Protection
8 • To inspect whether it is functional
Check
9 Plans • Provide detailed plan before and after the installation.
We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 54
GENERATOR
SYSTEM

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 55
Standby Generator Load Plan
Capacity: 250KVA, 380V –existing unit

LOADS:

1. Fire Detection And Alarm System


2. Paging System
3. Network Servers
4. CCTV System
5. Battery Warehouse/Electronic Parts

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 56
CCTV SYSTEM

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 57
CCTV-Scope of Works
No Description QTY Scope of Works
1 Bullet type 18pcs

2 Dome type 42pcs


• Supply and Installation
3 Monitor 1

4 NVR 1

5 HDD Storage 1 • Must have one month storage capacity

NOTE: Provide detailed plan before and after the installation.

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 58
Ground Floor Proposed CCTV Layout

Cabling Homerun
NVR + Monitor

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 59
Second Floor Proposed CCTV Layout

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 60
BROADCASTING /PAGING
SYSTEM

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 61
Ground Floor Proposed Paging System Layout

Paging Amplifier /
Controller @ Lobby

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 62
Second Floor Proposed Paging System Layout

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 63
Proposed Paging System

Item/Area Qty Speaker Type


Zone 1 (Perimeter + BI) 3 Paging Horn

Zone 2 (Inside of Building) 31 Ceiling Speaker w/o volume control

Zone 3 (Office/Admin) 2 Ceiling Speaker w/ volume control

Paging Amplifier 1

Wall mount volume control 3

Zone Controller 1

NOTE: Provide detailed plan before and after the installation.

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 64
FACTORY 2
Production(MC Electrical & ESD)
detailed Requirements
(For line or machine facility
supply drop reference)

www.acbel.com
SERVER LINE M/C ALLOCATION PER LINE
LEGEND:
ELECTRICAL EXHAUST
AREA MACHINE RATING QTY CDA LAN
DROP DUCTING
ELEVATOR PA3:3 INDUCTION MOTOR 200V/50HZ/0.40A/1350RPM 1 1 1 1
220V/60HZ/0.36A/1600RPM
PALLET LOADER F2SW-15-10-T60 1
0.75KW 4P RATIO 40:1
200V/50HZ/3.7A/1430 RPM
PALLET CONVEYOR MOTOR F2SM-35-40-075 1
220V/60HZ/3.2A/1730 RPM
200V/50HZ/3.7A/1430 RPM
LOADING CONVEYOR F3SM-35-40-075 1
220V/60HZ/3.2A/1730 RPM

3-PHASE 0.4KW-4P/RATIO 1:25


200/200/220V
BRUSH MOTOR HYPHOID MOTOR
50/60/60 HZ 1
NEAR WAVE SOLDERING M/C HMTA040-30H25J
2.3/2.0/2.0 A
60/72/72 R/MIN
220V/108A/41/KW/3PHASE/2K NET
WAVE SOLDERING M/C SONG-E 1 1 1 3
WEIGHT
3-PHASE 0.4KW-4P/RATIO 1:25
200/200/220V
HYPHOID MOTOR
TOP FIXTURE CONVEYOR 50/60/60 HZ 1
HMTA040-30H25J
2.3/2.0/2.0 A
60/72/72 R/MIN

220V/60HZ/0.36A/1600RPM
OUTPUT UNLOADER F25W-15-10-T60 3 1
0.75KW 4P RATIO 40:1

3-PHASE 0.4KW-4P/RATIO 1:25


200/200/220V
HYPHOID MOTOR
TLA CONVEYOR 50/60/60 HZ 1 2
HMTA040-30H25J
2.3/2.0/2.0 A
60/72/72 R/MIN

200V/50HZ/3.7A/1430 RPM
TLA CONVEYOR F3SM-35-40-075X 1 1 1
220V/60HZ/3.2A/1730 RPM
ICT (IN-CIRCUIT TESTING ) TR518SII AC 100~240V/50~60HZ/1 KVA 2 2

IPC + monitor,ATE machine


ATE TESTER (Ini) 2600 Watts/220VAC/1 Phase 2 2
accessories,Peak power during test

IPC + monitor,ATE machine


ATE TESTER (Cal) 2600 Watts/220VAC/1 Phase 8 8
accessories,Peak power during test

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 66
FINAL TEST, PACKAGING PER LINE & OFFLINE QC
LEGEND:
ELECTRICAL EXHAUST
AREA MACHINE RATING QTY CDA LAN
DROP DUCTING
ELEVATOR PA3:3 INDUCTION MOTOR 200V/50HZ/0.40A/1350RPM 1 1 1 1
220V/60HZ/0.36A/1600RPM
PALLET LOADER F2SW-15-10-T60 1
0.75KW 4P RATIO 40:1
200V/50HZ/3.7A/1430 RPM
PALLET CONVEYOR MOTOR F2SM-35-40-075 1

OFFLINE QC LOADING CONVEYOR F3SM-35-40-075


220V/60HZ/3.2A/1730 RPM
200V/50HZ/3.7A/1430 RPM
220V/60HZ/3.2A/1730 RPM
1

3-PHASE 0.4KW-4P/RATIO 1:25


200/200/220V
BRUSH MOTOR HYPHOID MOTOR
50/60/60 HZ 1
NEAR WAVE SOLDERING M/C HMTA040-30H25J
2.3/2.0/2.0 A
60/72/72 R/MIN

220V/108A/41/KW/3PHASE/2K NET
WAVE SOLDERING M/C SONG-E 1 1 1 3
WEIGHT

3-PHASE 0.4KW-4P/RATIO 1:25


200/200/220V
HYPHOID MOTOR
TOP FIXTURE CONVEYOR 50/60/60 HZ 1
HMTA040-30H25J
2.3/2.0/2.0 A
60/72/72 R/MIN

220V/60HZ/0.36A/1600RPM
OUTPUT UNLOADER F25W-15-10-T60 3 1
0.75KW 4P RATIO 40:1

3-PHASE 0.4KW-4P/RATIO 1:25


200/200/220V
HYPHOID MOTOR
TLA CONVEYOR 50/60/60 HZ 1 2
HMTA040-30H25J
2.3/2.0/2.0 A
60/72/72 R/MIN

200V/50HZ/3.7A/1430 RPM
TLA CONVEYOR F3SM-35-40-075X 1 1 1
220V/60HZ/3.2A/1730 RPM
ICT (IN-CIRCUIT TESTING ) TR518SII AC 100~240V/50~60HZ/1 KVA 1
LEAD HEIGTH VERIFIER LEAD HEIGTH VERIFIER AC220/50HZ/2KW 1
AC 180~230VA
AOI MACHINE JT A518 1
POWER: 0.6KW

ULTRASONIC POWER : 480W


ULTRASONIC CLEANER HEATING POWER: 620W
CALIBRATION 1 1 1 1
DERUI (DR-LD280 ) TOTAL POWER CONSUMPTION: 1100W
220~250VAC/50HZ

CALIBRATION ATE Tester (Cal) 2600/220VAC/1 Phase 8


HIPOT/FINAL TEST/PACKING Hipot ATE 500/220VAC/1 Phase 2 1 1 1
HIPOT/FINAL TEST/PACKING ATE Tester (Final, Mon, Func) 2600/220VAC/1 Phase 6
HIPOT/FINAL TEST/PACKING EEPROM W/R ATE 500/220VAC/1 Phase 2
OFFLINE QC FUNCTIONAL TESTER 2600/220VAC/1 phase 5 1
OFFLINE QC HIPOT TESTER 2600/220VAC/1 phase 1

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 67
SMT LINE M/C ALLOCATION PER LINE LEGEND:

EXHAUST
AREA MACHINE RATING QTY ELECTRICAL DROP CDA LAN
DUCTING
200/220/380/400/420/480V
3~50/60HZ/3.5KVA
CDA: MAX 0.8MPA
AXIAL M/C PANASONIC AV132 WORKING PRESSURE 0.45~0.5 1 1 1
MPA
200L/MIN

OFFLINE MC
SHORT CIRCUIT RATING: 2.5 KA
200/220/380/400/420/480V
3~50/60HZ/3.5KVA
CDA: MAX 0.8MPA
RADIAL M/C PANASONIC RL132 1 1 1
WORKING PRESSURE 0.5 MPA
80L/MIN
SHORT CIRCUIT RATING: 2.5 KA

CO2 Laser Marker (MAG-C5TB)


LASER MARKER 220V/ 3PHASE 1 1 1 1
Martin Trier

STENCIL CLEANING Stencil Cleaning Machine 380V/3 PHASE 1 1 1 1

MAGAZINE LOADER SB-55 POWER 220V 1

220~230V/ 50~60HZ/3KW/15A
PRINTER GL - GKG PRECISION MC CDA: 0.45~0.60MPA 1 1
WEIGHT: 1200 KG
100~120V (15A)
SPI CYBEROPTIC SE600 220~240V (10A) 1
50~60HZ,1 PHASE/10KA
200/220/380/400/420/480V
3~50/60HZ/1.4KVA FULL LOAD
CHIP MOUNTER PANASONIC NM-EJM5B 3 1
AIR: 0.55 MPA
150L/MIN
SHENZEN RDJG AUTOMATIC
REFLOW M/C EQUIPMENT CO.LTD 380 V/ 44KW 1 1 1 1 2
REFLOW MACHINE

AUTOCOOLING
REFLOW AUTO COOLING AC 220V
BC-1500

180~230V
AOI M/C 1 1
JTA-618 1.5KW

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 68
MAGNETICS LINE M/C ALLOCATION PER LINE
LEGEND:

ELECTRICAL EXHAUST
AREA MACHINE RATING QTY DROP
CDA LAN DUCTING

Winding Tisong TSA TA1252 220 VAC / 3 KW / 14 A 5 5 5

Yuyang Stripping Machine


Laser Stripping 220 VAC / 1.2 KW / 6 A 1
CCM-J30

Tisong Auto Soldering


PIN Soldering 220 VAC / 3.6 KW / 16 A 1 1 1 1
machine

Yuyang Auto core tape


CORE TAPING 220 VAC / 2 A 1
machine

Yuyang Auto Hi-Pot Test 220 VAC / 9 A 1


Initial Testing
Yuyang Complex Test 220 VAC / 9 A 1 1 1

Yuyang Auto Hi-Pot Test 220 VAC / 9 A 1


Final Testing
Yuyang Complex Test 220 VAC / 9 A 1 1 1

Yungchia YJ 6340 Printing


Label Printing 220 VAC / 100 W / 0.5A 1
machine

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 69
MAGNETICS OFFLINE PROCESS
LEGEND:
ELECTRICAL EXHAUST
AREA MACHINE RATING QTY CDA LAN
DROP DUCTING
Tisong TS 879-A Varnishing
220 VAC / 2 KW / 9 A 2 1 1 4
Varnishing maachine
E CHUNG Varnishing maachine 220 VAC / 2 KW / 9 A / 3P 2 1
IR Circulation oven 602 with
220 VAC / 65 A / 3P 2 2 2
conveyor
Baking
IR Circulation oven TS 452 Stand
220 VAC / 2 KW / 10 A 10 2
alone
Material Prep Tape Cutting machine 220 VAC / 10 A / 3P 1 1 1
Grinding KENT Grinding machine 250 KHG 220 VAC / 14 A / 3P 4 2
Tisong SEMI Auto Soldering
Final Dipping 220 VAC / 3 KW / 14 A 4 1 1 4
machine TSA 838

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 70
BBU/PDU_MC ALLOCATION
LEGEND:

ELECTRICAL EXHAUST
AREA MACHINE RATING QTY CDA LAN
DROP DUCTING

BATTERY WELDING MIYACHI WELDING M/C 480V/ 0.4~0.6 MPA 1 1 1

BATTERY WELDING VACCUM M/C 220V/2KW 1 1 1

BATTERY WELDING SELECTIVE SOLDERING 200~240V/1PH/50~60HZ/1KVA 1 1 1

TLA LINES TLA GALVANI EINSTEIN 1 1 5 1

TLA LINES TLA NAVIGATOR/TOPAZ 1 1 4 1

TLA LINES TLA GEMINI/TOPAZ 1 1 5 1

TLA LINES TLA INFINITY 1 1 4 1

TLA LINES TLA NAVIGATOR/COPILOT 1 1 5 1

BBU TESTERS ICT Tester 800W/220VAC/1 Phase 2 2

BBU TESTERS ATE Tester (INI, prebatt) 1600W/220VAC/1 Phase 4

BBU TESTERS Charging Bay 3220W/220VAC/1 Phase 4

ATE Tester (Cal,Final, Mon,


BBU TESTERS 1600W/220VAC/1 Phase 10
Func)

BBU TESTERS ATE Tester (post batt, Func)SPS 3220W/220VAC/1 Phase 2

BBU TESTERS EEPROM W/R ATE 500W/220VAC/1 Phase 4

BBU TESTERS Run-In BBU's 9000W/220VAC/1 Phase 4

BBU TESTERS Run-In(SPS) 17400W/220VAC/1 Phase 1

17400W/380VAC/3
BBU TESTERS Run-In(16G) 3
Phase/4Wire

PDU TESTERS Hipot ATE 500W/220VAC/1 Phase 1

PDU TESTERS Ground Band Tester 500W/220VAC/1 Phase 1

BBU TESTERS Vibration test 1000W/220VAC/1 Phase 2

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 71
TS AREA
LEGEND:

ELECTRICAL EXHAUST
2-ELECTRICAL DROP AREA MACHINE RATING QTY DROP CDA LAN DUCTING

10-EXHAUST DUCTING
2400/220VAC/1
TS AREA IPC + monitor 6 2
Phase 1

Bench Test Peak 3600/220VAC/1


TS AREA 4
power during test Phase

EEPROM 300/220VAC/1
TS AREA 3
machine Phase
5000/220VAC/1
TS AREA Accessories 1
Phase

TS AREA Soldering iron 1000/220VAC/1


Phase 10 10
Extra 220VAC 500/220VAC/1
TS AREA 10
outlet Phase

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 72
BURN-IN RM

ELECTRICAL EXHAUST
AREA MACHINE RATING QTY CDA LAN
DROP DUCTING
66900 WATTS/380VAC/3
BURN-IN ROOM Server/PC BI Chamber 32 32 32
Phase/4Wire

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 73
QA/OBA/CALIBRATION RM

Machine Quantity Area Power (Watts) Configuration

AC POWER SUPPLY 1 CAL 2300 220VAC/1 Phase

HIPOT 1 CAL 460 220VAC/1 Phase

AC/DC ELECTRONIC LOAD 1 CAL 230 220VAC/1 Phase

ELECTRONIC LOAD 1 CAL 460 220VAC/1 Phase

DC POWER SUPPLY 1 CAL 230 220VAC/1 Phase

POWER METER 1 CAL 230 220VAC/1 Phase

DIGITAL MULTIMETER 1 CAL 460 220VAC/1 Phase

ICE POINT 1 CAL 115 220VAC/1 Phase

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 74
PROJECT SCHEDULE
1. INVITATION OF BIDDERS/CONTRACTORS -3/27/2023
2. PROJECT DISCUSSION (VIRTUAL) -3/28/2023
3. ON-SITE VISIT FOR VERIFICATION -3/29-3/31
4. PROPOSAL SUBMISSION -4/17/2023
NOTE: PROPOSAL MUST SUBMIT IN CLOSED AND SEALED ENVELOPED

5. PROJECT AWARDING – MAY OR JUNE 2023


6. PROJECT EXECUTION – JUNE 2023

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 75
PROPOSAL CONTENT
1. ITEMIZED PROJECT SCOPE WITH BOM
2. PAYMENT TERMS : 30%DP, 60% PB, 10% Retention
3. PROJECT LEAD TIME
4. ADDRESS TO THE FOLLOWING:
TO: JOHN MARWIN CAPUYAN –OH PURCHASING
CC: ENGR. CRIS LLEVA- FACILITY MANAGER/PIC

We Power The World With Sustainable/Renewable Energy And High Efficiency Power Supply AcBel Confidential 76
THANK YOU
FOR YOUR ATTENTION