Daily manual excavation Report from 26th July to 29th August 2023 of Rowad

Al Jawadha team worked at 48" pipe project at SUR

Misc.
Rigger & Banks Expn
Permit Holder -A Supervisor-B Man- C workers- D Omani Driver-E 10%.-I
3 ton PDO vehi.-F PDO spec. car-G Back Hoe Loader-H with operator Total Remarks T.workers
DATE No. Rate Total No. Rate Total No. Rate Total No. Rate Total No. Rate Total No. Rate Total No. Rate Total No. Rate Total Daily A+B+C+D+E+F+G+H+I
26-Jul 1 22 22 1 16 16 3 14 42 7 13 91 20 0 25 0 1 20 20 70 0 19.1 210.1 13
27-Jul 1 22 22 1 16 16 3 14 42 7 13 91 20 0 25 0 1 20 20 70 0 19.1 210.1 13
28-Jul 0 0 0 0 0 0 0 0 0 0 FRIDAY 0
29-Jul 2 22 44 1 16 16 3 14 42 10 13 130 20 0 25 0 2 20 40 70 0 27.2 299.2 18
30-Jul 2 22 44 1 16 16 4 14 56 8 13 104 20 0 25 0 2 20 40 70 0 26 286 17
31-Jul 2 22 44 1 16 16 3 14 42 8 13 104 20 0 25 0 2 20 40 70 0 24.6 270.6 16
01-Aug 2 22 44 1 16 16 3 14 42 9 13 117 20 0 25 0 2 20 40 70 0 25.9 284.9 17
02-Aug 2 22 44 1 16 16 3 14 42 9 13 117 20 0 25 0 2 20 40 70 0 25.9 284.9 17
03-Aug 2 22 44 1 16 16 3 14 42 10 13 130 20 0 25 0 2 20 40 1 70 70 34.2 376.2 19
04-Aug 0 0 0 0 0 0 0 0 0 0 FRIDAY 0
05-Aug 2 22 44 1 16 16 4 14 56 9 13 117 20 0 25 0 2 20 40 1 70 70 34.3 377.3 19
06-Aug 2 22 44 1 16 16 4 14 56 9 13 117 20 0 25 0 2 20 40 1 70 70 34.3 377.3 19
07-Aug 2 22 44 1 16 16 4 14 56 9 13 117 20 0 25 0 2 20 40 1 70 70 34.3 377.3 19
Idle 0 0 0 0 0 0 0 0 0 0 0
Idle 0 0 0 0 0 0 0 0 0 0 0
21-Aug 2 22 44 1 16 16 4 14 56 9 13 117 20 0 25 0 20 0 1 70 70 30.3 333.3 17
22-Aug 2 22 44 1 16 16 1 14 14 5 13 65 20 0 25 0 20 0 1 70 70 20.9 229.9 10
23-Aug 2 22 44 1 16 16 4 14 56 9 13 117 20 0 25 0 20 0 1 70 70 30.3 333.3 17
24-Aug 2 22 44 0 16 0 0 14 0 5 13 65 20 0 25 0 20 0 1 70 70 17.9 196.9 8
25-Aug 0 0 0 0 0 0 0 0 0 0 FRIDAY 0
26-Aug 0 0 0 0 0 0 0 1 70 70 7 77 1
27-Aug 0 0 0 0 0 0 0 1 70 70 7 77 1
28-Aug 0 0 0 0 0 0 0 1 70 70 7 77 1
29-Aug 0 0 0 0 0 0 0 1 70 70 7 77 1
GRAND TOTAL 4755.3