Phase Descripción de la Actividad Activity Description Start Time End Time Huawei Real Start Real End
T(m) Time Time
Trabajos de Planeamiento y coordinacion Planning Work
Solicitar a TDP que configure la transmisión, enviar el Request Customer to configure Transmission, and
DF de Ips. provide the IP DF. 1W Before 3d Before Aymin
1
solicitar a TDP los CELLID 2G/3G/4G Request in advance the CELLID for 2g3g4g 1W Before 1d Before Aymin
2
Confirmar el modelo de sitios para PR y MR, Validacion Site Model Confirmation for PR and MR. Validate the
de Equipment en sitio. Material and equipment list. 4 W Before 4 W Before Felipe
4
Validar accesos validate the access to the site with customer, and
confirm to cooperator. 1 W Before 1 W Before IM / Cooperator
6
Before Before
Revisión de adaptaciones. Site SBE work confirmation. 2-3 days 2 Day
IM / Cooperator
8
Before Before
Validar el escenario de : Trabajo, Banda Base, Radio y Check the target scenario for each criteria: Work type, 2-3 days 2 Day IM / Cooperator /
energía. Baseband, Radio and Power
9
Before Before WL
Enviar los parametros de RF. Los Tilt Azimuth son los Send the RF parameters of the site. Tilt Azimuth keep 2-3 days 2 Day
###
Confirmar con TX la configuración de IP Check with TDP the TX configuration 2-3 days 1 day
###
Before before WL
Before Before IM
Colectar los LOGS. Collect Logs (Current Alarms, VSWR and RTWP values) Integration
###
8:30
Before trace
Confirmar a Huawei la hora de acceso a sitio Confirm Clock in 8:30 9:00 Cooperator
Revisión de material y equipos recibidos. Arrived Material/Equipment Check 9:00 9:30 Cooperator
llamar al CRAT para abrir REMEDY Call CRAT to open REMEDY 9:00 9:05 Cooperator
ectation
Validar el escenario de : Trabajo, Banda Base, Radio y Site SBE work confirmation on site, BB, Radio and
energía. (Longitud de movimiento de fibras, Longitud Energy, (Fiber lenght, power lenght, jumper lenght and
de Jumpers, tipo de antenna, Tipo de conector de type, Fiber Cascade and all necessary material, work or
antenna, Fibras y Cascadas, y todas las factibilidades de equipment on site)
###
9:30 Cooperator
preparar todos los instrumentos y usar los EPP de Prepare all material and tools, and use the EPP
acuerdo a las normas de seguridad de Huawei according Huawei assurance rules.
###
Validar que el nuevo puerto de transmisión esté de Verify the availability of the transmission port
###
Instalar las RRU nuevas hasta su posicion en torre Climb and install all new RRU in tower including SWAP
###
Colectar la Informacion de RET en sitio por cada sector / Collect RET current values on site per TECH and Band.
Banda / Tecnologia y enviar a WL, y Firmar PreCheck
###
Instalar el cable de poder y cables CPRI entre BBU - RRU Do cabling of the Power and CPRI cable between BBU -
###
Instalar Cable de poder y Cables Cascada CPRI, siempre Do cabling of Power and cascade CPRI, DONT
y cuando no implique desconectar RRU en servicio DISCONNECT ANY RRU ON SERVICE)
###
Instalar GND cables para todas las RRU. Install GND cable for all RRU
###
Llamar a CRAT Telefonica para abrir evento REMEDY Call TDP CRAT to open REMEDY
###
Llamar a Wireless de Huawei para empezar el trabajo Call Huawei Wireless to start the work
###
Apagar todas las BBU existentes excepto la que será Turn Off all BBU except Target BBU onebox
### ### ###
Migrar el puerto de transmision Migrate the transmission cable to the target port
###
Enviar Foto frontal de la target BBU a Huawei WL para Send BBU frontal Picture to Huawei WL to validate if
###
la validación del orden de tarjetas the board/slot location is correct. 4:50 4:55 5 Cooperator
Confirmar la Gestion de los equipos con Huawei Call Huawei to confirm the Site OYM chanell is up
###
Jumpers a antennas sin Vulcanizar without vulcanize 4:15 5:35 120 Cooperator
Migrar las fibras al one BOX Move Fibers to BBU target and connecct 4:15 5:35 120 Cooperator
Configurar 2G 3G en controladores Configure 2G 3G in Controllers 4:40 4:50 10 WL
Check Configuration and Clean Pending Configure Pendings Baseline 4:50 5:00 10 WL
Pruebas de Servicio después de Trabajo Service test. 5:35 6:35 60 WL/Cooperator
Vulcanizar y rotular los jumpers migrados Vulcanize and labeling the migrated jumpers 6:35 7:55 80 WL/Cooperator
Limpiar las alarmas y ROE Clean Alarms and ROE 7:55 8:05 10 WL/Cooperator
Conectar alarmas Externas y testear con Huawei connect External alarms and test with Huawei
8:05 8:25 20 WL/Cooperator
confirmar el cierre de trabajo con Huawei Confirm with Huawei the Work clousure 8:25 8:45 20 WL/Cooperator
Rollback Rollback
Confirm with Huawei the Rollback decisison Confirm with Huawei the Rollback decisison
### ### ###
Reconectar los Jumpers o Feeders e// como estaban Reconnect the Jumpers or Feeder cable from E// side
###
Proceder a devolver las tarjetas de banda base a sus Proceed to move back the baseband boards to each
### ### ### ### ### ### ###
Enviar Foto frontal de las BBU Enviar Foto Frontal de las BBU 5:10 5:15 5 Cooperator
Reconectar la Transmisión a cada BBU existente Reconnect the Transmission Cable to original ports
5:15 5:20 5 Cooperator
Confirmar la Gestion de todas las tecnologias Confirm the OMCH of all technologies 5:20 5:30 10 Cooperator
Confirmar con Huawei la estabilidad de los equipos Confirm with Huawei the estability of the equipments
6:15 6:35 20 Cooperator
Phase Descripción de la Actividad Activity Description Start Time End Time Huawei Real Start Real End
T(m) Time Time
Trabajos de Planeamiento y coordinacion Planning Work
Solicitar a TDP que configure la transmisión, enviar el Request Customer to configure Transmission, and
DF de Ips. provide the IP DF. 1W Before 3d Before Aymin
1
solicitar a TDP los CELLID 2G/3G/4G Request in advance the CELLID for 2g3g4g 1W Before 1d Before Aymin
2
Confirmar el modelo de sitios para PR y MR, Validacion Site Model Confirmation for PR and MR. Validate the
de Equipment en sitio. Material and equipment list. 4 W Before 4 W Before Felipe
4
Validar accesos validate the access to the site with customer, and
confirm to cooperator. 1 W Before 1 W Before IM / Cooperator
6
Before Before
Revisión de adaptaciones. Site SBE work confirmation. 2-3 days 2 Day
IM / Cooperator
8
Before Before
Validar el escenario de : Trabajo, Banda Base, Radio y Check the target scenario for each criteria: Work type, 2-3 days 2 Day IM / Cooperator /
energía. Baseband, Radio and Power
9
Before Before WL
Enviar los parametros de RF. Los Tilt Azimuth son los Send the RF parameters of the site. Tilt Azimuth keep 2-3 days 2 Day
###
Confirmar con TX la configuración de IP Check with TDP the TX configuration 2-3 days 1 day
###
Before before WL
Before Before IM
Colectar los LOGS. Collect Logs (Current Alarms, VSWR and RTWP values) Integration
###
8:30
Before trace
Confirmar a Huawei la hora de acceso a sitio Confirm Clock in 8:30 9:00 Cooperator
Revisión de material y equipos recibidos. Arrived Material/Equipment Check 9:00 9:30 Cooperator
llamar al CRAT para abrir REMEDY Call CRAT to open REMEDY 9:00 9:05 Cooperator
ectation
Validar el escenario de : Trabajo, Banda Base, Radio y Site SBE work confirmation on site, BB, Radio and
energía. (Longitud de movimiento de fibras, Longitud Energy, (Fiber lenght, power lenght, jumper lenght and
de Jumpers, tipo de antenna, Tipo de conector de type, Fiber Cascade and all necessary material, work or
antenna, Fibras y Cascadas, y todas las factibilidades de equipment on site)
###
9:30 Cooperator
preparar todos los instrumentos y usar los EPP de Prepare all material and tools, and use the EPP
acuerdo a las normas de seguridad de Huawei according Huawei assurance rules.
###
Validar que el nuevo puerto de transmisión esté de Verify the availability of the transmission port
###
Instalar las RRU nuevas hasta su posicion en torre Climb and install all new RRU in tower including SWAP
###
Colectar la Informacion de RET en sitio por cada sector / Collect RET current values on site per TECH and Band.
Banda / Tecnologia y enviar a WL, y Firmar PreCheck
###
Instalar el cable de poder y cables CPRI entre BBU - RRU Do cabling of the Power and CPRI cable between BBU -
###
Instalar Cable de poder y Cables Cascada CPRI, siempre Do cabling of Power and cascade CPRI, DONT
y cuando no implique desconectar RRU en servicio DISCONNECT ANY RRU ON SERVICE)
###
Instalar GND cables para todas las RRU. Install GND cable for all RRU
###
Llamar a CRAT Telefonica para abrir evento REMEDY Call TDP CRAT to open REMEDY
###
Llamar a Wireless de Huawei para empezar el trabajo Call Huawei Wireless to start the work
###
Apagar todas las BBU existentes excepto la que será Turn Off all BBU except Target BBU onebox
### ### ###
Migrar el puerto de transmision Migrate the transmission cable to the target port
###
Enviar Foto frontal de la target BBU a Huawei WL para Send BBU frontal Picture to Huawei WL to validate if
###
la validación del orden de tarjetas the board/slot location is correct. 6:50 6:55 5 Cooperator
Confirmar la Gestion de los equipos con Huawei Call Huawei to confirm the Site OYM chanell is up
###
Jumpers a antennas sin Vulcanizar without vulcanize 6:15 7:35 120 Cooperator
Migrar las fibras al one BOX Move Fibers to BBU target and connecct 6:15 7:35 120 Cooperator
Configurar 2G 3G en controladores Configure 2G 3G in Controllers 6:40 6:50 10 WL
Check Configuration and Clean Pending Configure Pendings Baseline 6:50 7:00 10 WL
Pruebas de Servicio después de Trabajo Service test. 7:35 8:35 60 WL/Cooperator
Vulcanizar y rotular los jumpers migrados Vulcanize and labeling the migrated jumpers 8:35 9:55 80 WL/Cooperator
Limpiar las alarmas y ROE Clean Alarms and ROE 9:55 10:05 10 WL/Cooperator
Conectar alarmas Externas y testear con Huawei connect External alarms and test with Huawei
10:05 10:25 20 WL/Cooperator
confirmar el cierre de trabajo con Huawei Confirm with Huawei the Work clousure 10:25 10:45 20 WL/Cooperator
Rollback Rollback
Confirm with Huawei the Rollback decisison Confirm with Huawei the Rollback decisison
### ### ###
Reconectar los Jumpers o Feeders e// como estaban Reconnect the Jumpers or Feeder cable from E// side
###
Proceder a devolver las tarjetas de banda base a sus Proceed to move back the baseband boards to each
### ### ### ### ### ### ###
Enviar Foto frontal de las BBU Enviar Foto Frontal de las BBU 7:10 7:15 5 Cooperator
Reconectar la Transmisión a cada BBU existente Reconnect the Transmission Cable to original ports
7:15 7:20 5 Cooperator
Confirmar la Gestion de todas las tecnologias Confirm the OMCH of all technologies 7:20 7:30 10 Cooperator
Confirmar con Huawei la estabilidad de los equipos Confirm with Huawei the estability of the equipments
8:15 8:35 20 Cooperator
Phase Descripción de la Actividad Activity Description Start Time End Time Huawei Real Start Real End
T(m) Time Time
Trabajos de Planeamiento y coordinacion Planning Work
Solicitar a TDP que configure la transmisión, enviar el Request Customer to configure Transmission, and
DF de Ips. provide the IP DF. 1W Before 3d Before Aymin
1
solicitar a TDP los CELLID 2G/3G/4G Request in advance the CELLID for 2g3g4g 1W Before 1d Before Aymin
2
Confirmar el modelo de sitios para PR y MR, Validacion Site Model Confirmation for PR and MR. Validate the
de Equipment en sitio. Material and equipment list. 4 W Before 4 W Before Felipe
4
Validar accesos validate the access to the site with customer, and
confirm to cooperator. 1 W Before 1 W Before IM / Cooperator
6
Before Before
Revisión de adaptaciones. Site SBE work confirmation. 2-3 days 2 Day
IM / Cooperator
8
Before Before
Validar el escenario de : Trabajo, Banda Base, Radio y Check the target scenario for each criteria: Work type, 2-3 days 2 Day IM / Cooperator /
energía. Baseband, Radio and Power
9
Before Before WL
Enviar los parametros de RF. Los Tilt Azimuth son los Send the RF parameters of the site. Tilt Azimuth keep 2-3 days 2 Day
###
Confirmar con TX la configuración de IP Check with TDP the TX configuration 2-3 days 1 day
###
Before before WL
Before Before IM
Colectar los LOGS. Collect Logs (Current Alarms, VSWR and RTWP values) Integration
###
8:30
Before trace
Confirmar a Huawei la hora de acceso a sitio Confirm Clock in 8:30 9:00 Cooperator
Revisión de material y equipos recibidos. Arrived Material/Equipment Check 9:00 9:30 Cooperator
llamar al CRAT para abrir REMEDY Call CRAT to open REMEDY 9:00 9:05 Cooperator
ectation
Validar el escenario de : Trabajo, Banda Base, Radio y Site SBE work confirmation on site, BB, Radio and
energía. (Longitud de movimiento de fibras, Longitud Energy, (Fiber lenght, power lenght, jumper lenght and
de Jumpers, tipo de antenna, Tipo de conector de type, Fiber Cascade and all necessary material, work or
antenna, Fibras y Cascadas, y todas las factibilidades de equipment on site)
###
9:30 Cooperator
preparar todos los instrumentos y usar los EPP de Prepare all material and tools, and use the EPP
acuerdo a las normas de seguridad de Huawei according Huawei assurance rules.
###
Validar que el nuevo puerto de transmisión esté de Verify the availability of the transmission port
###
Instalar las RRU nuevas hasta su posicion en torre Climb and install all new RRU in tower including SWAP
###
Colectar la Informacion de RET en sitio por cada sector / Collect RET current values on site per TECH and Band.
Banda / Tecnologia y enviar a WL, y Firmar PreCheck
###
Instalar el cable de poder y cables CPRI entre BBU - RRU Do cabling of the Power and CPRI cable between BBU -
###
Instalar Cable de poder y Cables Cascada CPRI, siempre Do cabling of Power and cascade CPRI, DONT
y cuando no implique desconectar RRU en servicio DISCONNECT ANY RRU ON SERVICE)
###
Instalar GND cables para todas las RRU. Install GND cable for all RRU
###
Llamar a CRAT Telefonica para abrir evento REMEDY Call TDP CRAT to open REMEDY
###
Llamar a Wireless de Huawei para empezar el trabajo Call Huawei Wireless to start the work
###
Apagar todas las BBU existentes excepto la que será Turn Off all BBU except Target BBU onebox
### ### ###
Migrar el puerto de transmision Migrate the transmission cable to the target port
###
Enviar Foto frontal de la target BBU a Huawei WL para Send BBU frontal Picture to Huawei WL to validate if
###
la validación del orden de tarjetas the board/slot location is correct. 8:50 8:55 5 Cooperator
Confirmar la Gestion de los equipos con Huawei Call Huawei to confirm the Site OYM chanell is up
###
Jumpers a antennas sin Vulcanizar without vulcanize 8:15 9:35 120 Cooperator
Migrar las fibras al one BOX Move Fibers to BBU target and connecct 8:15 9:35 120 Cooperator
Configurar 2G 3G en controladores Configure 2G 3G in Controllers 8:40 8:50 10 WL
Check Configuration and Clean Pending Configure Pendings Baseline 8:50 9:00 10 WL
Pruebas de Servicio después de Trabajo Service test. 9:35 10:35 60 WL/Cooperator
Vulcanizar y rotular los jumpers migrados Vulcanize and labeling the migrated jumpers 10:35 11:55 80 WL/Cooperator
Limpiar las alarmas y ROE Clean Alarms and ROE 11:55 12:05 10 WL/Cooperator
Conectar alarmas Externas y testear con Huawei connect External alarms and test with Huawei
12:05 12:25 20 WL/Cooperator
confirmar el cierre de trabajo con Huawei Confirm with Huawei the Work clousure 12:25 12:45 20 WL/Cooperator
Rollback Rollback
Confirm with Huawei the Rollback decisison Confirm with Huawei the Rollback decisison
### ### ###
Reconectar los Jumpers o Feeders e// como estaban Reconnect the Jumpers or Feeder cable from E// side
###
Proceder a devolver las tarjetas de banda base a sus Proceed to move back the baseband boards to each
### ### ### ### ### ### ###
Enviar Foto frontal de las BBU Enviar Foto Frontal de las BBU 9:10 9:15 5 Cooperator
Reconectar la Transmisión a cada BBU existente Reconnect the Transmission Cable to original ports
9:15 9:20 5 Cooperator
Confirmar la Gestion de todas las tecnologias Confirm the OMCH of all technologies 9:20 9:30 10 Cooperator
Confirmar con Huawei la estabilidad de los equipos Confirm with Huawei the estability of the equipments
10:15 10:35 20 Cooperator
Phase Descripción de la Actividad Activity Description Start Time End Time Huawei Real Start Real End
T(m) Time Time
Trabajos de Planeamiento y coordinacion Planning Work
Solicitar a TDP que configure la transmisión, enviar el Request Customer to configure Transmission, and
DF de Ips. provide the IP DF. 1W Before 3d Before Aymin
1
solicitar a TDP los CELLID 2G/3G/4G Request in advance the CELLID for 2g3g4g 1W Before 1d Before Aymin
2
Confirmar el modelo de sitios para PR y MR, Validacion Site Model Confirmation for PR and MR. Validate the
de Equipment en sitio. Material and equipment list. 4 W Before 4 W Before Felipe
4
Validar accesos validate the access to the site with customer, and
confirm to cooperator. 1 W Before 1 W Before IM / Cooperator
6
Before Before
Revisión de adaptaciones. Site SBE work confirmation. 2-3 days 2 Day
IM / Cooperator
8
Before Before
Validar el escenario de : Trabajo, Banda Base, Radio y Check the target scenario for each criteria: Work type, 2-3 days 2 Day IM / Cooperator /
energía. Baseband, Radio and Power
9
Before Before WL
Enviar los parametros de RF. Los Tilt Azimuth son los Send the RF parameters of the site. Tilt Azimuth keep 2-3 days 2 Day
###
Confirmar con TX la configuración de IP Check with TDP the TX configuration 2-3 days 1 day
###
Before before WL
Before Before IM
Colectar los LOGS. Collect Logs (Current Alarms, VSWR and RTWP values) Integration
###
8:30
Before trace
Confirmar a Huawei la hora de acceso a sitio Confirm Clock in 8:30 9:00 Cooperator
Revisión de material y equipos recibidos. Arrived Material/Equipment Check 9:00 9:30 Cooperator
llamar al CRAT para abrir REMEDY Call CRAT to open REMEDY 9:00 9:05 Cooperator
ectation
Validar el escenario de : Trabajo, Banda Base, Radio y Site SBE work confirmation on site, BB, Radio and
energía. (Longitud de movimiento de fibras, Longitud Energy, (Fiber lenght, power lenght, jumper lenght and
de Jumpers, tipo de antenna, Tipo de conector de type, Fiber Cascade and all necessary material, work or
antenna, Fibras y Cascadas, y todas las factibilidades de equipment on site)
###
preparar todos los instrumentos y usar los EPP de Prepare all material and tools, and use the EPP
acuerdo a las normas de seguridad de Huawei according Huawei assurance rules.
###
Instalar las RRU nuevas hasta su posicion en torre Climb and install all new RRU in tower including SWAP
###
Colectar la Informacion de RET en sitio por cada sector / Collect RET current values on site per TECH and Band.
Banda / Tecnologia y enviar a WL, y Firmar PreCheck Review PRECHECK SHEET and review
###
Instalar el cable de poder y cables CPRI entre BBU - RRU Do cabling of the Power and CPRI cable between BBU -
###
Instalar Cable de poder y Cables Cascada CPRI, siempre Do cabling of Power and cascade CPRI, DONT
y cuando no implique desconectar RRU en servicio DISCONNECT ANY RRU ON SERVICE)
###
Instalar GND cables para todas las RRU. Install GND cable for all RRU
###
Llamar a CRAT Telefonica para abrir evento REMEDY Call TDP CRAT to open REMEDY
###
Llamar a Wireless de Huawei para empezar el trabajo Call Huawei Wireless to start the work
###
Apagar todas las BBU existentes excepto la que será Turn Off all BBU except Target BBU onebox
### ### ###
Migrar el puerto de transmision Migrate the transmission cable to the target port
###
Enviar Foto frontal de la target BBU a Huawei WL para Send BBU frontal Picture to Huawei WL to validate if
###
la validación del orden de tarjetas the board/slot location is correct. 10:50 10:55 5 Cooperator
Confirmar la Gestion de los equipos con Huawei Call Huawei to confirm the Site OYM chanell is up
###
Jumpers a antennas sin Vulcanizar without vulcanize 10:15 11:35 120 Cooperator
Migrar las fibras al one BOX Move Fibers to BBU target and connecct 10:15 11:35 120 Cooperator
Configurar 2G 3G en controladores Configure 2G 3G in Controllers 10:40 10:50 10 WL
Check Configuration and Clean Pending Configure Pendings Baseline 10:50 11:00 10 WL
Pruebas de Servicio después de Trabajo Service test. 11:35 12:35 60 WL/Cooperator
Vulcanizar y rotular los jumpers migrados Vulcanize and labeling the migrated jumpers 12:35 13:55 80 WL/Cooperator
Limpiar las alarmas y ROE Clean Alarms and ROE 13:55 14:05 10 WL/Cooperator
Conectar alarmas Externas y testear con Huawei connect External alarms and test with Huawei
14:05 14:25 20 WL/Cooperator
confirmar el cierre de trabajo con Huawei Confirm with Huawei the Work clousure 14:25 14:45 20 WL/Cooperator
Rollback Rollback
Confirm with Huawei the Rollback decisison Confirm with Huawei the Rollback decisison
### ### ###
Reconectar los Jumpers o Feeders e// como estaban Reconnect the Jumpers or Feeder cable from E// side
###
Proceder a devolver las tarjetas de banda base a sus Proceed to move back the baseband boards to each
### ### ### ### ### ### ###
Enviar Foto frontal de las BBU Enviar Foto Frontal de las BBU 11:10 11:15 5 Cooperator
Reconectar la Transmisión a cada BBU existente Reconnect the Transmission Cable to original ports
11:15 11:20 5 Cooperator
Confirmar la Gestion de todas las tecnologias Confirm the OMCH of all technologies 11:20 11:30 10 Cooperator
Confirmar con Huawei la estabilidad de los equipos Confirm with Huawei the estability of the equipments
12:15 12:35 20 Cooperator
3 Equipos Tarjetas BBU Equipo nuevo para instalar BBU y tarjetas ✘ OK NOK NA
4 Material Energía Revision de Material para energizar las nuevas RRUs ✘ OK NOK NA
5 Fibras RRUs nuevas y existente Revisiond de Material para RRU, Fibras ✘ OK NOK NA
22 Factibilidad Ruta Fibras Validacion de la ruta de las fibras para OneBOX ✘ OK NOK NA
23 Factibilidad de Slots BBU Validación de Slots suficientes en BBU para onebox ✘ OK NOK NA
28 Espacio para RRU nuevas Validación de espacio en torre para RRUs nuevas ✘ OK NOK NA
29 Identificacion de nuevo puerto TX Identificación del puerto de Transmisiones para OneBox ✘ OK NOK NA