STRATA TITLE APPLICATION UNDER THE STRATA TITLE ( Amendment ) ACT 2013 ( ACT A1450 ) & STRATA MANAGEMENT

ACT 2013 (ACT 757)

KM (P)
DEVELOPER LOCAL AUTHORITY
Application

KM (P) Approval

DEVELOPER

Buildings Plan (BP)


Application

LOCAL AUTHORITY

Buildings Plan
(BP) Approval
a) Application of Strata Scheme no at JUPEM
(deposit of LJT fees).
DEVELOPER b) Application SiFUS at PTG.
c) File Schedule of Parcel to COB.
Application of
Advertising Permit (AP) &
Developer License (DL)

KPKT

AP & DL
To exhibit Schedule
of Parcel
SALES DEVELOPER

SMA Section 6(5)(a) Construction

SUPER STRUCTURE To provide certification to land


COMPLETION (G12) office within 2 weeks

3 months
LLS

To apply CPSP : Section 8A(1)

JUPEM

1 month
Approved CPSP

LLS

STA Section 8(3) 1 month Apply Strata Title.


* Fines as above
PTG

Approved & Registered


2 months
Strata Title.

DEVELOPER

Total: 7 months

VP WITH STRATA TITLE

Abbreviation : 1. SiFUS < Certificate of Share Units > 5. CPSP < Certificate of Proposed Strata Plan >
2. COB < Commissioner of Building > 6. VP < Vacant Possession >
3. KPKT < Kementerian Perumahan & Kerajaan Tempatan > 7. STA < Strata Title (Amendment) Act 2012 >
4. LLS < Licensed Land Surveyor > 8. SMA < Strata Management Act 2013 (Act 757) >

Prepared by : JURUKUR GENERASI


Date : June 2018