USER REQUIREMENT
SPECIFICATION (URS)
APPROVAL OF URS
In-Charge Name & Title Signature Date
Prepared By
Production Department Head
Reviewed By
Maintenance Department Head
Reviewed By
Validation Department Head
Reviewed By
Quality Assurance Department
Head
Approved By
Head – Quality & Technical Affairs
Film coating with organic solvent. Film coating with aqueous coating.
Sugar coating.
SPECIFIC
5
REQUIREMENTS Audiovisual alarms shall be provide for malfunction of critical
operation / critical utilities
Automated process
Conforms to cGMP.
The hot air penetrates through the tablet core layers and is
discharged from the bottom of the layers, so that the coating medium
sprayed on the surface of tablet cores will dry rapidly and evenly, thus
HMI screen shall be displayed all function like inlet , outlet hot air
DATA &
8 temperature , pan speed , atomized pressure batch no. date and time
RPORTS
option shall be provided
Test certificates of the different Materials used in the construction of
TEST the machine (MOC certificates).
9 CERTIFICATES Calibration certificates of the all the instruments
(Hard Copies) Data sheets of all major parts
Start up & Required Start up & technical support on the user site during final
12
Technical support installation and qualification time.
Installation will be done at site by our Maintenance team.