Production Control: C/T 50 Sec 1 Shift C/T 74 Sec Uptime 96% 1 Shift C/T 85 Sec Scrap 5% 1 Shift

You might also like

You are on page 1of 1

Orange Juice Production Value Stream Map

Production Control Orange Juice


Orange Company
Daily Orders Daily Orders Drinker

T/T = 92 sec

Shipment 1 shift per day 300 unit per shift


Inventory Levels
Production Instructions
Production Instructions

1500 Prepare Orange Make Orange Juice Bottle and Distribute


Drinks
600 300

C/T = 85 sec C/T = 74 sec C/T = 50 sec


5 days scrap = 5% 2 days Uptime = 96% 1 day 1 shift Lead Time = 8 days
1 shift 1 shift
Cycle Time = 209 sec
85 sec 74 sec 50 sec