You are on page 1of 7

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/3923696

Gas turbine model using in design of heat and power stations

Conference Paper · February 2001


DOI: 10.1109/PTC.2001.964813 · Source: IEEE Xplore

CITATIONS READS
17 260

2 authors:

Karel Maslo J. Andel


CEPS ÚJV Řež, a. s.
38 PUBLICATIONS   195 CITATIONS    2 PUBLICATIONS   19 CITATIONS   

SEE PROFILE SEE PROFILE

All content following this page was uploaded by Karel Maslo on 02 October 2014.

The user has requested enhancement of the downloaded file.


1

Gas turbine model using in design


of heat and power stations
Karel Maslo, Jan Andel

Calculation step [s] MOPES


13 Stochastic tran. & optimisation
Abstract Paper presents prime mover models suitable for Dynamic stability Scheduling
island operation simulation. It deals with designing principles of 12
mid-term long-term short - term mid-term
power station with gas unit from power station - network ≈ short - term tertiary control
secondary control load diagram
interaction point of view. primary control
1 unit commitement
rotors inertia water reservoir
excitation
Index Terms Dynamic model, Gas turbine (GT), Island 1-1 machines windings unit outages
dispatcher reserve
operation (IO), Network simulator network MODES
ATC
Electromechanic transients
1-2
I. INTRODUCTION SCCalc
elmag. tran. minute hour day week month

I SLAND operation (IO) is rare regime, but prime movers


should be able to pass to the island and operate in it.
Dynamic simulation is a efficient tool for IO investigation,
1-1 1 11

Fig. 1 Time Frame for Power System Dynamics


12 13 14 Calculation period [s]

We introduce prime movers dynamic models implemented


because of field tests and experiments are nearly impossible.
in the MODES suitable for island operation simulation now.
The large voltage and frequency deviations are typical for IO,
so that used models must correspond for true representation of A. Improved steam units models
these phenomena. This paper describes improvements of The speed and pressure controls are crucial for the passing
prime mover models implemented into network simulator to the island and operation into island. The structure of the
called MODES (see [1] -[9]). turbine control usually change from the so called primary
Gas turbines (GT) are used in the industry for producing control (the turbine or boiler follow mode with frequency
heat and electricity and serve as back-up source (in case of correction) to the proportionally speed control. Turbine
network outage) as well. This contribution deals with control switches from the primary control to the speed control
interaction of GT and network. It presents using of dynamic when the frequency deviation is greater then ± 200 mHz. This
model for investigation GT response to network faults. deviation is considered as a symptom of island operation in
Simulation calculations make technical solutions easier and an interconnected system.
can detect weak points of protection and control. The time The negative pressure deviations (steam pressure is greater
and costs are saved during putting GT into operation. then reference value) are solved by steam bypassing and by
boiler/reactor control. The positive pressure deviations may
II.DYNAMIC MODELS USED IN THE MODES be solved by pressure correction in turbine control and by
The MODES is a power system analysis package. It boiler/reactor control as well. The combination of the
contains three basic applications: proportional speed governor with pressure correction together
1. SCCalc for short circuit calculation (see [10]) with boiler controller creates so called island controller
2. MODES for short, mid and long term dynamic simulation depicted in the Fig. 2.
3. MOPES for operation scheduling (see [11]). Speed ω Reference NS Electrohydraulic transducer
power Gmax
These applications are able to cover the time range of ωSET
- +
+ Σ 1
power system dynamic from several milliseconds to several + kp +
Σ Kp2
1+pTEHP
RT
- Governor
weeks according the Fig. 1. Σ
dp
pSET
- Pressure correction Gmin output
We will focus on the same named network simulator
pT Steam generation PI contr. dMP Controller
MODES. The method used for numeric simulation is Steam pressure NR QT output
kpO
described in Appendix 1. + NTmax -
Filtering
+
+
+ + 1 RB
NT 1 NTmax
Σ Σ Σ Σ
+ 1+pTfO 0
Turbine NTmin +
NREF 1
K. Maslo is with the Czech Transmission Company, CEPS, a.s., power pTIO
Argentinska 38, 170 05 Praha, Czech republic (e-mail: maslo@ceps.cz). NTmin
J. Andel is with the ENERGOPROJEKT Praha, a.s., Vyskocilova 3/741,
140 21 Praha, Czech republic (e-mail: andel@egp.cz). Fig. 2 Block scheme of governor and boiler control model in island regime
2

The PI boiler controller controls steam generation to A. Improved hydro units models
reference value NREF. This value correspond the turbine The speed control is important similarly as for steam unit
power (determined by governor) increased by a reserve power for hydro units modeling. The pressure deviations (so called
NR. This additional steam generation flows through the water hammer effect) are solved by co-ordination of gate
bypasses and boiler is able to increase its power immediately opening/closing speed. The turbine model should take into
by bypass valves closing. account friction losses in penstock, self-regulation effect due
The turbine and boiler models are in the following figure: to speed changes and mechanical losses. All this phenomena
High pressure
Steam
part kHP
Turbine is taken into account in the following model.
pressure power
+ bf /(bf -1) Speed
pT Reheater Unit switched Flow Rate
Σ NT off and G>GNL 1 ω
RT Control QT 1 + 1 Π 1 bf
valve Π Σ Low pressure + Rmaxopen Turbine
1+pTHP pTR Gmax
part Head fP Selfregulation power
RNL Q/G Q
1 effect PT
kIV Intercept
Π
k LP Rt
Σ
1 1
.. Π
H
-
Σ
- 1 Π
M
Π
+
Σ
valve + TV p + pTW -
0 1+pTLP - G cf
Torgue
Gmin Gate H0
By pass ω3
QVPS
Steam Flow + Rmaxclose
+
Rate QT Σ Π kPD Rmaxbuff
Gbuff
Steam generation Boiler dynamics
RB -
e -pTD 1 + 1 + - Fig. 5 Block scheme of hydro turbine model
Σ Σ pT
1+pTFUEL 1+pTW pTCB The gate position modeling should into account decreasing
Steam pressure
Fuel dynamics of closing speed for small gate opening (so called buffering).
Fig. 3 Block scheme of steam turbine model
When the unit is switched from the network and gate
position is lesser then some no load value GNL, the gate is
Turbine model takes into account the action of control and
closed by RNL rate.
intercept valves and corresponds to the reference [12]. The
The two types of governor were tested in simulation:
valves are controlled by speed governor.
1. classical mechanical - hydraulic structure (see [3])
The boiler model corresponds to the reference [13], with 2. PIDP controller.
added by pass. The real high pressure by pass valves (which The both models are represented in the following figures.
lead the steam back to the reheater) and low pressure by pass Mechanical - hydraulic governor Rate limiter Gmax Gmax
valves (which lead the steam directly to the condenser) were Speed ωS + Remax RT
modeled by one equivalent by pass valve. + 1 1
ω Σ Σ KS p
1+pTG
The above described models were verified by comparing of - Remin
- +
simulation and field test of 200 MW steam turbine with once Td1p 0
through boiler. The following figures show the results of 1+pTd2 - Σ 0
simulation and measuring. Transient behavior during the bP Permanent droop
+
change from full load to the house consumption was tested. Σ
+ btTdp
The speed deviation is in the following figure. PIDP governor
Transient droop
1+pTd
12 speed deviation [%]
Speed control ωS kP Gmax
10 Speed Gmax +
8 + 1 + 1
Field test - Σ Σ RT
6 ω pTI 1+pTG
4
+
- 0
2 Overspeed control 0
0 Td1p
5 10 15 time [s]
1+pTd2
Fig. 4 Time course of the speed deviation of the steam turbine bp

The first simulation (marked Speed control) shows a large Fig. 6 Block scheme of mechanical - hydraulic governor model
overrun due to the „natural“ behavior of the turbine controlled Due to the feedback (permanent droop bP) has the PIDP
by speed governor only. controller proportional character.
The additional automatics - acceleration relay should be The created model was verified by comparing of simulation
take into account. This relay causes fast temporary closing the and field test 320 MW Kaplan turbine. The following figures
control and intercept valves and decreasing of turbine power. show the results of simulation and measuring. Transient
The effect is shown on the second simulation (marked Over- behavior during the change from full load to the no load and
speed control). the house load was tested. The speed deviations for different
3

controller types is in the following figure. A. Gas turbine model


40 speed deviation [%] Field test Dynamic model was created on the base of simplified
PIDP governor
30 single shaft GT model published in [16] complemented by
Hydraulic governor
self-regulation effect (dependence on speed deviation).
20 House load Governor Control valves Speed deviation
operation output vmax Gmax Fuel Compressor sG kM
10 system discharge
RT AT
1 1 1 1 -
0 +
Σ Σ
0 10 20 30 40 50 60 TV
1+pTF 1+pTCD
+
-10 - p M0 NT
No load operation time [sec] YRVT MTUR
Fuel Turbine
vmin Gmin Valves Turbine
flow rate power
Fig. 7 Time courses of the speed deviations of the hydro turbine opening

As can be seen from this figure the behavior of the both Fig. 11 Block scheme of gas turbine model
controllers is very similar. Turbine is modeled by a static function Nt=f(Fuel flow).
The parameter M0 takes into account compressor power and
A. Diesel engine model
friction losses as well. The parameter kM takes into account
The diesel - generator creates the important reserve source self-regulation effect and ventilation losses as well. The
of energy and can be used as basic source for black start. parameter Gmin corresponds to the minimum gas flow rate
Models created according [15] are in Fig. 8 and Fig. 9. able to guarantee a correct combustion operation. Since M0-
Speed sensor Set value 1 1
ωSET Gmin*AT may be lesser then zero, this value corresponds a
Speed + g
1 + 1 1 + 1 braking power during load rejection. Model involves control
ω Σ Σ Σ KP2 pTI2 Σ valves, delay due to fuel system and compressor discharge.
+ - pTd1 pTd1 - 1+pTd
+ - + Implemented model has been validated by comparison of
0 0
load rejection simulation (from 110 to 4 MW) with reference
Kd1 bP
Permanent droop calculation in [16] – see Fig. 12. A switching from power to
the speed control was carried out when frequency falls down
Fig. 8 Scheme of mechanical -hydraulic governor of diesel-generator
under .49.7 Hz.
The governor has PI character when permanent droop bP=0 YRVT [p.u.] sG [%]
and then is suitable for island operation. MODES
Mechanical k 1.2 6
Fuel rack losses
M
ω
position M0
Fuel flow 1 5
g kG + - Tm
Pd Speed deviation sG
mF
e-pTD Π Σ Π
G0
0.8 4
Engine Engine
torgue Reference
Air em-a(lm-λ) km Power 0.6 Valve position YRVT 3
excess λ η
em Efficiency 0.4 2
lm
0.2 1
1 Ambient pressure K2
K1 Governor output RT
+ + 1 1 K0
Σ p0 0
1+pTt2 1+pTt1
0 2 4 6 8 10 12 14 16 18 time [s]
kL / Fuel flow Compressor M2 M1
mF Fig. 12 Comparison of simulation with reference
1 kTL
Π
1+pTt3 1 Governor output is drawn for reference instead of valve
position in the MODES. Maximal speed deviation depends on
Fig. 9 Block scheme of turbo-diesel engine model closing speed of control valves and switching from power
The dependence of engine efficiency on air excess λ for control to speed control as well. Decrease of speed depends of
combustion is modeled by quadratic (Km=2) or cubic (Km=3) braking power. This power should be about 7% to decrease
form. The following figure shows the results of simulation speed deviation from maximal to steady -state value during 6
and measuring of 7.9 MVA diesel-generator during step sec. The steady-state speed deviation depends on governor
increasing of load from 10 % to 60 %. speed drop bP .
5 speed deviation [%] Oscillation may be caused by governor setting. Linear
time[s]
0 analysis gives relation for oscillation frequency:
0 5 10 15
-5  400A T 
Simulation f =  − 1 / ( 4πTCD ) (1)
-10 Field test T
 M Pb 
This frequency is 0.1Hz for our case. The value in squared
Fig. 10 Time courses of the speed deviations braces must be positive for stable time course.
4

III. ISLAND OPERATION OF HEAT STATION WITH GT station on the Fig. 13.) were analyzed by the MODES
Above mentioned GT model was used for transient stability simulator to clarify reason of unsuccessful island operation
analysis in the Kyjov heat station. Two GT units with nominal and to prepare technical solutions.
power 8.7 MW each and one steam turbine 7.4 MW are There are some results:
installed there. Gas and steam turbines operate in combined 1. The requirement for change over into island operation is
cycle. The heat station should have the functions: „static“ and neglects reason if initiating event. The events
1. supplying of electricity (about 7MW with voltage 22kV) C (switching off the line) corresponds the „static“
and heat to near factory requirement. The event H is more difficult, so that a load
2. delivering of the rest power to the distribution 22 kV in the distribution 22 kV network courses rapid frequency
network decreasing. The short circuits are much more difficult,
3. disconnecting from network when the frequency exceeds because of the GT are rejected during short circuit and
the range 47 – 52 Hz and island operation with the near asynchronous motors are braked due to voltage
factory. decreasing. The most difficult are long term short circuits
The heat station serves in the first and second function with loss of feeding from 110 kV network (events F and I
successfully, but GT outages have occurred during the third and sometimes J).
2. The fast under-frequency load shedding in distribution
function with negative operation and economical effects.
network is a necessary condition for successful change
Reasons of these outages were not clear and they lead to the
over into island operation after transformer 110/22kV
reclamation of electric part due to lack of fault records.
switching off (Events F,G,H,I). The main task of GT in
these cases is not to supply the distribution network, but
J Distribution
H factory load only.
I 110 kV
3. The change over island operation is undesirable for events
G E E and J, when it is possible selective clear these faults by
distribution network protections. The detection of an
Distribution island regime condition should be set-up carefully. The
F D 22 kV network frequency is crucial.
C 4. The factory supply is not possible when events A and B
occur. These fault is necessary to solve on the factory side
A (e.g. by automatic bus transfer).
B 5. Increased attention should be paid to the co-ordination of
Factory
load protection and control between heat station and
GT distribution network. Fast and selective fault clearing is
Fig. 13 One line scheme of possible network faults
necessary on the network side. The GT protections should
be set-up properly, so that they do not detect large
Electromechanical transient phenomena during network
frequency deviations during change over island operation.
faults (depicted A-J in the simplified one line scheme heat
MW mHz MW mHz
20 4000 20 4000
Speed deviation sG
18 3000 18 3000
Electric power PG
16 2000 16 2000

14 1000 14 1000
Speed deviation sG Turbine
12 0 12 output NT 0

10 -1000 10 -1000

8
Turbine output NT -2000 8 -2000

6 Electric power PG -3000 6 -3000

4 -4000 4 -4000

2 -5000 2 -5000

0 -6000 0 -6000
0 1 2 3 4 5 6 7 8 9 10 11 t ime [s] 0 1 2 3 4 5 6 7 8 9 10 11 time [s]

Fig. 14 „Static“ change over island after 22 kV line outage Fig. 15 „Dynamic“ change over island after 1s short circuit
5

Difference between „static“ change over into island (event linkages, Iqd are qd axis components of the stator current, PT
C) and change over into island after short circuit (event F and PG prime mover and generator power, sG is per unit speed.
with clearing time 1s) and switching off the transformer We suppose Xq"= Xd". Meaning of another symbols you can
110/22kV is seen from Fig. 14 and Fig. 9. find in [18].
The events F with short circuit is much more difficult.. Used numerical method is based on simultaneous solution
There is a load rejection during short circuit and speed of the network algebraic equations (1) and rotor circuits
governor closes the valves due to fast speed increasing. After equations (4) and (5). These two equations are chosen,
short circuit clearing the GT speed falls down due to power because the time constant Td0" and Tq0" are very small
deficiency in the island and the under-frequency load compared with another time constants and corresponding
shedding operates at 3s. Then the power balance is recovered variables Eq" and Ed" are changing very fast due to network
and GT accelerates. The power peak at 3.5s is caused by faults in contrast to another state variables Eq', Ed', sG and δ .
asynchronous motor acceleration after short circuit. The synchronous generator can be modeled as a source of
emf E" behind subtransient reactance Xd". When we substitute
VI. CONCLUSIONS dq components of currents by the network voltages we obtain:
The contribution recapitulates same results of island Td"*Eq"°+ Eq" = (1-σd) Uq +σd Eq' σd = Xd"/Xd' (7)
operation analysis of heat station with GT. The network Equation for d axis is analogical due to symmetry. We can
simulator MODES with implemented gas turbine model was find solution taking into account a linear change of the
used for that analysis. The analysis shows that GT technology variables on the right side during the integration step ∆t:
capabilities are crucial for successful island operation Eq"=Hq+kd Uq+σdςd ∆Eq' kd=(1-σd) ςd (8)
disregarding electrical reasons of island origin. There is ςd=1-(1-e-∆τd)/∆τd ∆τd=∆t/Td" Td"=σd*Td0" (9)
necessary to ensure correct detection of island conditions in The first term in (8) is so called historical term containing
electric part. old values of voltage and emf in the beginning of integration
The following steps are necessary for successful supply of step. The second term is created by a new voltage value in the
factory in island operation: end of integration step. The third depends of change of emf
• fast switching off heat station from the network when the Eq' during integration step. This value is not known, but it
network faults are not cleared by a network protection may be well predicted due to its slow changing.
• the GT power should be greater then factory load After transformation from dq reference to the network
• the fast speed control (change the power control to the reference frame (synchronously rotating system) we obtain:
speed control if necessary) E"=U(kd+kd)/2+U*(kd-kd)/2+H+∆' E"=(Eq"+jEd")ejδ (10)
• mutual co-ordination of protection in network, heat station If we involve complex conjugate voltage U* and prediction
and factory. term ∆' (it contains prediction of slowly changing emf Eq' and
The network analysis carried out at the early stage of plant Ed') into one history term H (then the U* must predicted as
design makes possible to understand correctly the project and well), we can write final solution:
discover its weak points. It makes possible to evaluate crucial E"=U kt +H kt=(kd+ kd)/2 (11)
parameters and requirements for technology and to require kt coefficient is a function of integration step ∆t.
them from technology producers. We can calculate injected current for generator nodes as:
IINJ=(E" - U) YG=H YG -U YGt YGt=(1-kt)YG (12)
V.APPENDIX NUMERICAL METHOD USED IN THE MODES YG is generator admitance seen from the network side. After
Power system model consists of four main parts (with some substitution of (12) into (1) we obtain final solution:
simplification): network, generator, prime mover and IEQ=YMOD U YMOD=Y+1 YGt (13)
excitation systems. The passive network (with neglected where injected currents IINJ are replaced by Norton
electromagnetic phenomena) is possible describe by network injection current IEQ=H YG and YMOD is network admittance
admittance matrix Y: matrix with added term YGt to the diagonal elements for the
IINJ=Y U (1) generator nodes. The system (13) can be solved by using LU
where IINJ and U are injected currents and nodal voltages factorization method. This method is very efficient, because
vectors. Park equations of synchronous generator in the form the matrix is recalculated only when a commutation occurs in
published in [17] or [18] and swing equations are: the network or when the integration step must be changed to
Td0'*Eq'° = Ef - Eq' + (Xd-Xd')*Id (2) keep the calculation accuracy.
Tq0'*Ed'° = - Ed' - (Xq-Xq')*Iq (3) The equations (2,3) and as well as transfer functions
Td0"*Eq"°= Eq' - Eq"+ (Xd'-Xd")*Id (4) Y/X=1/(1+pT) used in prime mover and excitation models
Tq0"*Ed"° = Ed' - Ed"- (Xq'-Xq")*Iq (5) can be solved taking into account a linear change of the input
TM* sG° = PT - PG δ° = Ω0 sG (6) variables from xt to xt+1 during the integration step ∆t:
° is time derivation, Eqd' and Eqd" are qd axis components of yt+1= yt e-∆t/T+(xt+xt+1)(1-e-∆t/T)/2 (14)
the transient and subtransient internal emf proportional to flux The integration algorithm can be depicted as follows:
6

1 Prediction ∆E',sG,δ,

2 Prediction UP,IEQP VIII.BIOGRAPHIES


3 NO Voltage calculatin IEQ=YMODU

4 /U-UP/<εU

YES
5 PG, QG,UG,IG,
NO
Excitation and prime
6 mover solution Ef, PT
7 Corrected IEQC
8 /IEQC-IEQP/<ε

YES

Next step
Karel Maslo was born in Jihlava, Czech Republic, on July 1956. He
Upper loop between blocks 4 and 2 is checked only if there received his E.E. diploma from Czech Technical University, Prague, in 1980
are some special load models (depending on voltage). in electrical engineering. In 1985, he received his Ph.D. on stability of
synchronous machine. As a university teacher and research worker he dealt
Iteration process is checked by difference between prediction with power plant and power system protection and reliability,
and corrected values of Norton injection current. electromagnetic and electromechanical transients and dynamic simulation.
He is involved in primary and load frequency control cooperation in frame
of the Study for the Connection of the Czechoslovak Network to the
VII. REFERENCES
UCPTE.. In 1992, he joined Czech main power producer company – CEZ,
[1] K.Máslo and J.Feist, "Power system dynamics behavior, modeling and where was responsible for the creation of dynamic models and dynamic
simulation of the primary control test," in Proc. of the 2nd Int. calculation From 1999 he worked for Czech TSO – CEPS. He is author of
Workshop on El. Power System Control Centers, Alghero, Italy.,1993 the network simulator MODES and deals with problems of Czech Grid
[2] „Long Term Dynamics Phase II“, CIGRE TF 38-02-08 Final Report, Code, system and ancillary services as well. He takes part in several CIGRE
Jan. 1995 and UNIPEDE working groups.
[3] K.Máslo, S.Vnoucek, J.Fantík, "Unit black start and power system
restoration ," presented at the International Symposium MEPS'96,
Wroclaw, Poland, 1996
[4] K.Máslo and J.Fantík: Dynamic analysis of the power system; in Proc.
of the 2nd Int. Conf. ECPS’96, Bratislava, Slovak Rep., pp.230-234
[5] K.Máslo and J.Fantík, "Electromechanical and electromagnetic
phenomena during power system restoration," in Proc. of the IXth Int.
Scientific Conf. EE '98, St.Lesná, Slovak Rep.,1996, pp.185-188.
[6] K.Máslo, I.Petruzela, J.Piroutek, "Nuclear power plant in island
operation, " presented at the UPEC 1997, Manchester, England
[7] K.Máslo and J.Andel,: "Dynamic simulation of Nuclear Power Plant
Auxiliaries," presented at the APSCOM '97, Honkong, China
[8] K.Máslo, "The general purpose network simulator MODES," in Proc.
of the 4h. Int. Workshop on El. Power System Control Centers,
Rethymno, Greece,1997
[9] K.Máslo and P.Neuman: "Power System and Power Plant Dynamic
Simulation," in Proc. of the 15th IFAC World Congress, Beijing,
China, 1999
[10] K.Máslo and S.Vnoucek: "Short Circuit Calculation Analysis,"
presented at the IEEE Power Tech’2001, Porto, Portugal, 2001
[11] K.Máslo and S.Vnoucek, "Modelling of Steam Unit Outages," in Proc.
of the 6th Int. Conference on PMAPS, Funchal, Portugal, 2000
[12] IEEE Working Group Report, "Dynamic Models for Fossil Fuelled
Steam Units in Power System Studies," IEEE Transaction on Power
systems, vol. 6, pp. 753 -761, May 1991
[13] F.P.Mello, "Boiler Models for System Dynamic Performance Studies,"
IEEE Transaction on Power systems, vol. 6, January 1991
[14] IEEE Working Group Report, "Hydraulic Turbine and Turbine Control
Models for System Dynamic Studies," IEEE Transaction on Power
systems, vol. 7.; January 1992
[15] M.Ferenc, "Uproszczony model matematyczny dynamiki
srednoobrotowego silnika," Silniky spalinowe No4; 1989
[16] A.Borghetti, G.Migliavacca, C.A.Nucci, S.Spelta, "Black-start
simulation of a repowered thermoelectric unit,", presentation on IFAC
conference, Brussels, Belgium, 2000
[17] J.Arrillaga at all,. Computer Modelling of Electrical Power System,;
John Willey & Sons; 1983
[18] J.Machowsaki, J,W.Bialek, J.R. Rumby, Power system Dynamics and
Stability; John Wiley & Sons,1997,p. 346

View publication stats

You might also like