VOLUME PEKERJAAN PLUMBING

PROJECT DHAMAR GOLF

No Uraian Pekerjaan Volume


A INSTALASI PIPA AIR BERSIH
A.1 INSTALASI PIPA AIR BERSIH LANTAI GROUND FLOOR
1 Ball valve PPR Ø 2" 1
2 Ball valve PPR Ø 1 - 1/4" 9
3 Ball valve PPR Ø 3/4" 2
4 Ball valve PPR Ø 1" 1
5 Pipa distribusi air bersih - Pipa PPR Ø 2" 3.25 0.30
6 Pipa distribusi air bersih - Pipa PPR Ø 1 - 1/4" 46.81 4.26
7 Pipa distribusi air bersih - Pipa PPR Ø 3/4" 17.05 1.55
8 Pipa distribusi air bersih - Pipa PPR Ø 1/2" 56.34 5.12
9 Shower 1
10 Closet 1
11 Sink 3
12 Water meter 1
13 Multi media filter kap. 90 LPM 2
14 Booster pump kap. 80 LPM, 1 ph-220V-1kW 1
A.2 INSTALASI PIPA AIR BERSIH LANTAI 1
1 Ball valve PPR Ø 3/4" 1
2 Ball valve PPR Ø 1/2" 2
3 Pipa distribusi air bersih - Pipa PPR Ø 1 - 1/4" 8.26 0.75
4 Pipa distribusi air bersih - Pipa PPR Ø 3/4" 7.86 0.71
5 Pipa distribusi air bersih - Pipa PPR Ø 1/2" 122.36 11.12
6 Shower 2
7 Lavatory 2
8 Closet 2
9 Sink 2
10 Selenoid valve 2
A.3 INSTALASI PIPA AIR BERSIH LANTAI 2
1 Ball valve PPR Ø 1" 2
2 Pipa distribusi air bersih - Pipa PPR Ø 1" 46.37 4.22
3 Pipa distribusi air bersih - Pipa PPR Ø 1/2" 79.42 7.22
4 Shower 3
5 Closet 3
6 Lavatory 4
7 Sink 1
8 Selenoid valve 1
A.4 INSTALASI PIPA AIR BERSIH LANTAI ROOF TOP
1 Ball valve PPR Ø 1/2" 1
2 Pipa distribusi air bersih - Pipa PPR Ø 1/2" 11.04 1.00
4 Closet 1
5 Lavatory 1
6 Sink 1
B INSTALASI PIPA AIR PANAS
B.1 INSTALASI PIPA AIR PANAS LANTAI GF
1 Balancing valve Ø 1" 1
2 Pipa distribusi air panas - Pipa PPR Ø 1" 63.65 5.79
3 Pipa distribusi air panas -Pipa PPR Ø 3/4" 5.02 0.46
VOLUME PEKERJAAN PLUMBING
PROJECT DHAMAR GOLF

No Uraian Pekerjaan Volume


4 Pipa distribusi air panas - Pipa PPR Ø 1/2" 29.70 2.70
5 Shower 1
6 Sink 3
7 Elektrik heat pump Kap. 200 Liter, 80 LPM, 1500 Watt 2
B.2 INSTALASI PIPA AIR PANAS LANTAI 1
1 Pipa distribusi air panas - Pipa PPR Ø 1" 7.70 0.70
2 Pipa distribusi air panas -Pipa PPR Ø 3/4" 7.69 0.70
3 Pipa distribusi air panas - Pipa PPR Ø 1/2" 50.22 4.57
4 Shower 2
5 Lavatory 2
6 Sink 2
B.3 INSTALASI PIPA AIR PANAS LANTAI 2
1 Balancing valve Ø 1/2" 1
1 Pipa distribusi air panas - Pipa PPR Ø 1" 16.43 1.49
2 Pipa distribusi air panas -Pipa PPR Ø 3/4" 25.05 2.28
3 Pipa distribusi air panas - Pipa PPR Ø 1/2" 70.74 6.43
4 Shower 3
5 Lavatory 4
6 Sink 1
B.4 INSTALASI PIPA AIR PANAS LANTAI ROOF TOP
1 Balancing valve Ø 1/2"
2 Pipa distribusi air panas - Pipa PPR Ø 1/2" 24.80 2.25
C INSTALASI PIPA AIR BEKAS
C.1 INSTALASI PIPA AIR BEKAS LANTAI GF
1 Pipa air bekas - Pipa PVC AW Ø 2" 45.92 4.17
2 Pipa air bekas - Pipa PVC AW Ø 1/4" 3.30 0.30
3 Clean out Ø 2" 2
4 Grease Trap 1
C.2 INSTALASI PIPA AIR BEKAS LANTAI 1
1 Pipa air bekas - Pipa PVC AW Ø 2" 34.28 3.12
2 Pipa air bekas - Pipa PVC AW Ø 1/4" 3.30 0.30
3 Grease Trap 2
C.3 INSTALASI PIPA AIR BEKAS LANTAI 2
1 Pipa air bekas - Pipa PVC AW Ø 2" 28.53 2.59
2 Pipa air bekas - Pipa PVC AW Ø 1/4" 3.30 0.30
C.4 INSTALASI PIPA AIR BEKAS LANTAI ROOF TOP
1 Pipa air bekas - Pipa PVC AW Ø 2" 4.75 0.43
2 Pipa air bekas - Pipa PVC AW Ø 1/4" 3.30 0.30
3 Grease Trap 1
D INSTALASI PIPA AIR KOTOR
D.1 INSTALASI PIPA AIR KOTOR LANTAI GF
1 Pipa air kotor - Pipa PVC AW Ø 4" 51.18 4.65
2 Clean out Ø 4" 2
3 BIO STP Kap. 3 m3 1
4 Absorption Pit (Sumur Resapan) 1
D.2 INSTALASI PIPA AIR KOTOR LANTAI 1
1 Pipa air kotor - Pipa PVC AW Ø 4" 18.81 1.71
VOLUME PEKERJAAN PLUMBING
PROJECT DHAMAR GOLF

No Uraian Pekerjaan Volume


2 Clean out Ø 4" 1
D.3 INSTALASI PIPA AIR KOTOR LANTAI 2
1 Pipa air kotor - Pipa PVC AW Ø 4" 30.94 2.81
2 Clean out Ø 4" 3
D.4 INSTALASI PIPA AIR KOTOR LANTAI ROOF TOP
1 Pipa air kotor - Pipa PVC AW Ø 4" 5.49 0.50
2 Clean out Ø 4" 1
E INSTALASI PIPA VENT
E.1 INSTALASI PIPA VENT LANTAI GF
1 Pipa vent - Pipa PVC AW Ø 3" 7.79 0.71
2 Pipa vent - Pipa PVC AW Ø 2" 1.70
3 Pipa vent - Pipa PVC AW Ø 1-1/4" 3.88
4 Air Admittance Valve (AVV) - Mini Vent under sink 3
5 Vent Louvre 100 x 100 2
E.2 INSTALASI PIPA VENT LANTAI 1
1 Pipa vent - Pipa PVC AW Ø 1-1/4" 6.00
2 Air Admittance Valve (AVV) - Mini Vent under sink 4
E.3 INSTALASI PIPA VENT LANTAI 2
1 Pipa vent - Pipa PVC AW Ø 1-1/2" 26.05 2.37
2 Pipa vent - Pipa PVC AW Ø 1-1/4" 4.50
3 Air Admittance Valve (AVV) - Mini Vent under sink 3
4 Vent Cap Ø 50 mm 1
E.4 INSTALASI PIPA VENT LANTAI roof top
1 Pipa vent - Pipa PVC AW Ø 1-1/2" 4.40 0.40
2 Pipa vent - Pipa PVC AW Ø 1-1/4" 1.50
3 Air Admittance Valve (AVV) - Mini Vent under sink 1
4 Vent Cap Ø 50 mm 1
F INSTALASI PIPA AIR HUJAN
F.1 INSTALASI PIPA AIR HUJAN LANTAI GF
1 Pipa air hujan - Pipa PVC AW Ø 4" 71.67 6.52
2 Pipa air hujan - Pipa PVC AW Ø 2" 32.19 2.93
3 Garden drain 2
4 Floor drain 1
5 Absorption Pit (Sumur Resapan) Kap. 2 m3 5
F.2 INSTALASI PIPA AIR HUJAN LANTAI 1
1 Pipa air hujan - Pipa PVC AW Ø 4" 9.24 0.84
2 Pipa air hujan - Pipa PVC AW Ø 3" 23.48 2.13
3 Pipa air hujan - Pipa PVC AW Ø 2" 51.23 4.66
4 Garden drain 12
F.3 INSTALASI PIPA AIR HUJAN LANTAI 2
1 Pipa air hujan - Pipa PVC AW Ø 4" 9.24 0.84
2 Pipa air hujan - Pipa PVC AW Ø 3" 10.31 0.94
3 Pipa air hujan - Pipa PVC AW Ø 2" 17.39 1.58
4 Garden drain 5
F.4 INSTALASI PIPA AIR HUJAN LANTAI ROOF
1 Pipa air hujan - Pipa PVC AW Ø 4" 9.24 0.84
2 Pipa air hujan - Pipa PVC AW Ø 3" 73.63 6.69
VOLUME PEKERJAAN PLUMBING
PROJECT DHAMAR GOLF

No Uraian Pekerjaan Volume


3 Garden drain 8
F.5 INSTALASI PIPA AIR HUJAN LANTAI ROOF TOP
1 Pipa air hujan - Pipa PVC AW Ø 4" 2.86 0.26
2 Pipa air hujan - Pipa PVC AW Ø 3" 55.84 5.08
3 Roof drain 10
Vom. aktual
Sat
gambar
Beli
Beli
1 pcs
9 pcs
2 pcs
1 pcs
2.959 meter
42.552 meter
15.500 meter
51.215 meter
1.000 pcs
1.000 pcs
3.000 pcs
1.000 pcs
2.000 unit
1.000 unit
Beli
1 pcs
2 pcs
7.512 pcs
7.149 meter
111.233 meter
2.000 pcs
2.000 pcs
2.000 pcs
2.000 pcs
2.000 pcs
Beli
2 pcs
42.156 pcs
72.198 meter
3.000 pcs
3.000 pcs
4.000 pcs
1.000 pcs
1.000 pcs
Beli
1 pcs
10.036 meter
1.000 pcs
1.000 pcs
1.000 pcs
Beli
Beli
1 pcs
57.861 meter
4.566 meter
Vom. aktual
Sat
gambar
27.003 meter
1.000 pcs
3.000 pcs
2.000 pcs
Beli
7.000 meter
6.989 meter
45.659 meter
2.000 pcs
2.000 pcs
2.000 pcs
Beli
1 pcs
14.932 meter
22.774 meter
64.309 meter
3.000 pcs
4.000 pcs
1.000 pcs
Beli
3
22.545 meter
Beli
Beli
41.749 meter
3 meter
2 meter
1 meter
Beli
31.161 meter
3 meter
2 meter
Beli
25.937 meter
3 meter
Beli
4.317 meter
3 meter
1 meter
Beli
Beli
46.529 meter
2 pcs
1 meter
1 meter
Beli
17.102 meter
Vom. aktual
Sat
gambar
1 pcs
Beli
28.13 meter
3 pcs
Beli
4.991 meter
1 pcs
Beli
Beli
7.085 meter
2 pcs
4 pcs
3 pcs
2 pcs
Beli
6 pcs
4 pcs
Beli
23.68 meter
5 pcs
3 pcs
1 pcs
Beli
4 meter
2 pcs
1 pcs
1 pcs
Beli
Beli
65.159 meter
29.262 meter
2 meter
1 meter
5 meter
Beli
8.4 meter
21.348 meter
46.574 meter
12 meter
Beli
8.4 meter
9.369 meter
15.811 meter
5 meter
Beli
8.4 meter
66.938 meter
Vom. aktual
Sat
gambar
8 meter
Beli
2.6 meter
50.766 meter
10 meter
No : Semarang, 4 Desember 2021

Kepada Yth,

Dengan hormat,

Bersama ini kami berikan informasi harga untuk pekerjaan instalasi pipa air bersih (PVC), dengan rincian sebagai berikut :
Jasa Pasang Total Barang +
No Uraian Pekerjaan Vol Sat Barang Fitting 30% * Total Barang Jasa Fitting 30% * Total Jasa Jasa
A INSTALASI PIPA DARI METERAN AIR PDAM KE GROUND TANK
1 Pipa pvc Ø 1" Rucika / Setara 1 meter 27,338 8,201 35,539 21,250 6,375 27,625 63,164
2 Support 20% ** 1 Lot 5,468 1,640 7,108 4,250 1,275 5,525 12,633
3 Tes tekan 10% ** 1 Lot - - - 2,125 - 2,125 2,125
4 ball valve Ø 1" Kitz / Setara 1 pcs 483,300 - 483,300 37,500 - 37,500 520,800
5 floating valve Ø 1" Yuta / Setara 1 pcs 531,912 - 531,912 37,500 - 37,500 569,412
B INSTALASI PIPA TRASNFER DARI GROUNDTANK SAMPAI LANTAI ROOF
1 Pipa pvc Ø 1" Rucika / Setara 1 meter 27,338 8,201 35,539 21,250 6,375 27,625 63,164
2 Support 20% ** 1 Lot 5,468 1,640 7,108 4,250 1,275 5,525 12,633
3 Tes tekan 10% ** 1 Lot - - - 2,125 - 2,125 2,125
4 ball valve Ø 1" Kitz / Setara 1 pcs 483,300 - 483,300 37,500 - 37,500 520,800
5 Pompa Filter Pedrollo 3 CPM 100 *** 1 Unit 4,298,400 - 4,298,400 625,000 - 625,000 4,923,400
6 Filter Mizuchi DC 30 *** 1 Unit 20,425,500 - 20,425,500 312,500 - 312,500 20,738,000
C ROOF TANK KE HEADER
1 Pipa pvc Ø 1" Rucika / Setara 1 meter 27,338 8,201 35,539 21,250 6,375 27,625 63,164
2 Support 20% ** 1 Lot 5,468 1,640 7,108 4,250 1,275 5,525 12,633
3 Tes tekan 10% ** 1 Lot - - - 2,125 - 2,125 2,125
4 header pvc Ø 2" Rucika / Setara 1 set 3,000,000 - 3,000,000 437,500 - 437,500 3,437,500
5 ball valve Ø 1" Kitz / Setara 1 pcs 483,300 - 483,300 37,500 - 37,500 520,800
6 ball valve Ø 1/2" Kitz / Setara 1 pcs 324,000 - 324,000 25,000 - 25,000 349,000
7 check valve Ø 1" Kitz / Setara 1 pcs 575,100 - 575,100 37,500 - 37,500 612,600
8 pressure gauge Ø 2" 1 pcs 236,250 - 236,250 37,500 - 37,500 273,750
9 Pompa Booster Pedrollo 4 CPM 100 *** 1 set 5,043,600 - 5,043,600 625,000 - 625,000 5,668,600
10 Roof Tank TD 200 kap. 2.000 Liter *** 1 unit 6,800,000 - 6,800,000 625,000 - 625,000 7,425,000
D INSTALASI PIPA AIR PANAS AREA ROOF
1 Pipa ppr pn 20 Ø 3/4" Tigris / Setara 1 meter 31,445 9,434 40,879 20,625 6,188 26,813 67,691
2 Support 20% ** 1 Lot 6,289 1,887 8,176 4,125 1,238 5,363 13,538
3 Tes tekan 10% ** 1 Lot - - - 2,063 - 2,063 2,063
4 ball valve Ø 3/4" Kitz / Setara 1 pcs 418,500 - 418,500 31,250 - 31,250 449,750
5 check valve Ø 1" Kitz / Setara 1 pcs 575,100 - 575,100 37,500 - 37,500 612,600
E INSTALASI PIPA AIR BERSIH PANTRY, LOUNDRY & KRAN TAMAN DARI ROOF TANK KE LANTAI 1 MELALUI GRAVITASI
1 Pipa pvc Ø 1 1/2" Rucika / Setara 1 meter 49,314 14,794 64,108 31,875 9,563 41,438 105,545
2 Pipa pvc Ø 1" Rucika / Setara 1 meter 27,338 8,201 35,539 21,250 6,375 27,625 63,164
3 Pipa pvc Ø 3/4" Rucika / Setara 1 meter 18,799 5,640 24,439 16,250 4,875 21,125 45,564
4 Pipa pvc Ø 1/2" Rucika / Setara 1 meter 15,694 4,708 20,402 10,625 3,188 13,813 34,215
5 Support 20% ** 1 Lot 22,229 6,669 28,898 16,000 4,800 20,800 49,698
6 Tes tekan 10% ** 1 Lot - - - 8,000 - 8,000 8,000
7 Bobokan 1 titik - - - 43,750 - 43,750 43,750
8 ball valve Ø 1 1/2" Kitz / Setara 1 pcs 978,750 - 978,750 46,875 - 46,875 1,025,625
9 Kran *** 1 pcs SBO / Opname - SBO / Opname 18,750 - 18,750 18,750
F KM LANTAI 1
1 Pipa pvc Ø 1 1/2" Rucika / Setara 1 meter 49,314 14,794 64,108 31,875 9,563 41,438 105,545
2 Pipa pvc Ø 1" Rucika / Setara 1 meter 27,338 8,201 35,539 21,250 6,375 27,625 63,164
3 Pipa pvc Ø 3/4" Rucika / Setara 1 meter 18,799 5,640 24,439 16,250 4,875 21,125 45,564
4 Pipa pvc Ø 1/2" Rucika / Setara 1 meter 15,694 4,708 20,402 10,625 3,188 13,813 34,215
5 Support 20% ** 1 Lot 22,229 6,669 28,898 16,000 4,800 20,800 49,698
6 Tes tekan 10% ** 1 Lot - - - 8,000 - 8,000 8,000
7 Bobokan 1 titik - - - 43,750 - 43,750 43,750
8 ball valve Ø 1 1/2" Kitz / Setara 1 pcs 978,750 - 978,750 46,875 - 46,875 1,025,625
G LANTAI 1 (AIR PANAS)
1 Pipa ppr pn 20 Ø 3/4" Tigris / Setara 1 meter 31,445 9,434 40,879 20,625 6,188 26,813 67,691
2 Pipa ppr pn 20 Ø 1/2" Tigris / Setara 1 meter 20,493 6,148 26,641 13,750 4,125 17,875 44,516
3 Support 20% ** 1 Lot 10,388 3,116 13,504 6,875 2,063 8,938 22,441
4 Tes tekan 10% ** 1 Lot - - - 3,438 - 3,438 3,438
5 Bobokan 1 titik - - - 43,750 - 43,750 43,750
6 ball valve Ø 3/4" Kitz / Setara 1 pcs 418,500 - 418,500 31,250 - 31,250 449,750
H INSTALASI PIPA AIR BERSIH KRAN TAMAN & REFLECTING POOL DARI ROOF TANK KE LANTAI 2 MELALUI GRAVITASI
1 Pipa pvc Ø 1 1/2" Rucika / Setara 1 meter 49,314 14,794 64,108 31,875 9,563 41,438 105,545
2 Pipa pvc Ø 1" Rucika / Setara 1 meter 27,338 8,201 35,539 21,250 6,375 27,625 63,164
3 Pipa pvc Ø 3/4" Rucika / Setara 1 meter 18,799 5,640 24,439 16,250 4,875 21,125 45,564
4 Pipa pvc Ø 1/2" Rucika / Setara 1 meter 15,694 4,708 20,402 10,625 3,188 13,813 34,215
5 Support 20% ** 1 Lot 22,229 6,669 28,898 16,000 4,800 20,800 49,698
6 Tes tekan 10% ** 1 Lot - - - 8,000 - 8,000 8,000
7 Bobokan 1 titik - - - 43,750 - 43,750 43,750
8 ball valve Ø 1 1/2" Kitz / Setara 1 pcs 978,750 - 978,750 46,875 - 46,875 1,025,625
9 ball valve Ø 1" Kitz / Setara 1 pcs 483,300 - 483,300 37,500 - 37,500 520,800
10 Kran *** 1 pcs SBO / Opname - SBO / Opname 18,750 - 18,750 18,750
I KM LANTAI 2
1 Pipa pvc Ø 1 1/2" Rucika / Setara 1 meter 49,314 14,794 64,108 31,875 9,563 41,438 105,545
2 Pipa pvc Ø 1" Rucika / Setara 1 meter 27,338 8,201 35,539 21,250 6,375 27,625 63,164
3 Pipa pvc Ø 3/4" Rucika / Setara 1 meter 18,799 5,640 24,439 16,250 4,875 21,125 45,564
4 Pipa pvc Ø 1/2" Rucika / Setara 1 meter 15,694 4,708 20,402 10,625 3,188 13,813 34,215
5 Support 20% ** 1 Lot 22,229 6,669 28,898 16,000 4,800 20,800 49,698
6 Tes tekan 10% ** 1 Lot - - - 8,000 - 8,000 8,000
7 Bobokan 1 titik - - - 43,750 - 43,750 43,750
8 ball valve Ø 1 1/2" Kitz / Setara 1 pcs 978,750 - 978,750 46,875 - 46,875 1,025,625
J LANTAI 2 (AIR PANAS)
1 Pipa ppr pn 20 Ø 3/4" Tigris / Setara 1 meter 31,445 9,434 40,879 20,625 6,188 26,813 67,691
2 Pipa ppr pn 20 Ø 1/2" Tigris / Setara 1 meter 20,493 6,148 26,641 13,750 4,125 17,875 44,516
3 Support 20% ** 1 Lot 10,388 3,116 13,504 6,875 2,063 8,938 22,441
4 Tes tekan 10% ** 1 Lot - - - 3,438 - 3,438 3,438
5 Bobokan 1 titik - - - 43,750 - 43,750 43,750
6 ball valve Ø 3/4" Kitz / Setara 1 pcs 418,500 - 418,500 31,250 - 31,250 449,750
K WATER HEATER
1 Water Heater *** 1 unit SBO / Opname - SBO / Opname 687,500 - 687,500 687,500
2 Rangka dudukan 1 pcs SBO / Opname - SBO / Opname SBO / Opname - - -
L PEMASANGAN SANITARY LANTAI 1 ***
1 kloset duduk 1 buah SBO / Opname - SBO / Opname 625,000 - 625,000 625,000
2 wastafel 1 buah SBO / Opname - SBO / Opname 250,000 - 250,000 250,000
3 zink 1 buah SBO / Opname - SBO / Opname 187,500 - 187,500 187,500
4 mixer shower 1 buah SBO / Opname - SBO / Opname 437,500 - 437,500 437,500
5 head shower 1 buah SBO / Opname - SBO / Opname 87,500 - 87,500 87,500
6 jet shower 1 buah SBO / Opname - SBO / Opname 87,500 - 87,500 87,500
M PEMASANGAN SANITARY LANTAI 2 ***
1 kloset duduk 1 buah SBO / Opname - SBO / Opname 625,000 - 625,000 625,000
2 wastafel 1 buah SBO / Opname - SBO / Opname 250,000 - 250,000 250,000
3 mixer shower 1 buah SBO / Opname - SBO / Opname 437,500 - 437,500 437,500
4 head shower 1 buah SBO / Opname - SBO / Opname 87,500 - 87,500 87,500
5 jet shower 1 buah SBO / Opname - SBO / Opname 87,500 - 87,500 87,500
6 zink 1 buah SBO / Opname - SBO / Opname 187,500 - 187,500 187,500
N Shop Drawing & As Build Drawing
1 Shop Drawing 1 Lantai - - - 300,000 - 300,000 300,000
2 As Build Drawing 1 Lantai - - - 300,000 - 300,000 300,000

Keterangan :
* Harga Fitting dihitung 30% dari harga pipa, sedangkan jasa pasang fitting dihitung 30% dari jasa pasang pipa.
** Jasa Pasang support dihitung 20% dari total pipa, fitting, jasa pasang pipa & jasa pasang fitting per sub judulnya, sedangkan Tes Tekan dihitung 10% dari total jasa pasang pipa saja
per sub judulnya.
*** Harga & Jasa Pemasangan Pompa, Filter, Tandon, Water Heater & Sanitary bisa berubah tergantung spesifikasi, tipe, merk & kapasitas nya.
**** Harga Netto, Harga Exclude PPn & PPh, Harga Franco SEMARANG
**** Material, Barang & Jasa ditagihkan sesuai pemasangan di lapangan.
**** Harga tidak termasuk semua barang dan pekerjaan yang tidak disebutkan dalam informasi harga ini, apabila ada maka akan diperhitungkan sebagai pekerjaan tambahan.
**** Sistem pembayaran : Down Payment : 50 % Pekerjaan selesai : 50 %
**** Informasi harga tidak mengikat , berlaku sesuai tanggal informasi harga tersebut diatas. Harga dapat berubah sewaktu - waktu tanpa pemberitahuan terlebih dahulu.
Demikian informasi harga ini kami sampaikan . Atas perhatiannya kami ucapkan terima kasih.
Hormat kami,

Muchlis
081.5651.5757