WEEKLY STATUS REPORT

PROJECT NAME DATE PROJECT STATUS % COMPLETE

FOR
RENOVATION OF TDI QUIAPO'S ROOFING October 10, 2022 8%
MOBILIZATION

PROJECT TIMELINE
31-Oct-22 07-Nov-22 14-Nov-22 21-Nov-22 28-Nov-22 05-Dec-22 12-Dec-22 19-Dec-22 26-Dec-22 02-Jan-23 09-Jan-23 16-Jan-23 23-Jan-23 30-Jan-23 06-Feb-23 13-Feb-23 20-Feb-23 27-Feb-23 06-Mar-23 13-Mar-23 20-Mar-23 27-Mar-23 03-Apr-23 10-Apr-23

PATHWAY 3

BUILDING 14 - LABORATORY

BUILDING 12 - BOTTLING/WASHING AREA

BUILDING 12 & 11 - CANOPY

FIRE BRIGADE OFFICE

GYM

ADMIN OFFICE PARKING AREA

ENGINEERING OFFICE CANOPY & GUTTER

BUILDING 3 BARREL STORAGE

BUILDING 9 - GUTTER AT ALCOHOL STORAGE

PATHWAY 1

PATHWAY 2

PROJECT STATUS %
8%

92%

Not Started In Progress Complete


Overdue On Hold
PROJECT DATA

START END DURATION


LOCATION BALL IN COURT STATUS REMARKS
DATE DATE in days

PATHWAY 3 31-Oct-22 21-Nov-22 21 Not Started Need to priotize for preparation for Christmas Party

BUILDING 14 - LABORATORY 22-Nov-22 13-Dec-22 21 Not Started

BUILDING 12 - BOTTLING/WASHING AREA 14-Dec-22 28-Dec-22 14 Not Started

BUILDING 12 & 11 - CANOPY 29-Dec-22 14-Jan-23 16 Not Started

FIRE BRIGADE OFFICE 15-Jan-23 29-Jan-23 14 Not Started

GYM 0 Complete

ADMIN OFFICE PARKING AREA 30-Jan-23 14-Feb-23 15 Not Started

ENGINEERING OFFICE CANOPY & GUTTER 15-Feb-23 22-Feb-23 7 Not Started

BUILDING 3 BARREL STORAGE 23-Feb-23 9-Mar-23 14 Not Started

BUILDING 9 - GUTTER AT ALCOHOL STORAGE 10-Mar-23 17-Mar-23 7 Not Started

PATHWAY 1 18-Mar-23 2-Apr-23 15 Not Started

PATHWAY 2 3-Apr-23 10-Apr-23 7 Not Started

PROJECT STATUS %
STATUS COUNT %

Not Started 11 92%

In Progress 0 0%

Complete 1 8%

Overdue 0 0%

On Hold 0 0%

TOTAL 12 100%