Weekly Status Report
Weekly Status Report
FOR
RENOVATION OF TDI QUIAPO'S ROOFING October 10, 2022 8%
MOBILIZATION
PROJECT TIMELINE
31-Oct-22 07-Nov-22 14-Nov-22 21-Nov-22 28-Nov-22 05-Dec-22 12-Dec-22 19-Dec-22 26-Dec-22 02-Jan-23 09-Jan-23 16-Jan-23 23-Jan-23 30-Jan-23 06-Feb-23 13-Feb-23 20-Feb-23 27-Feb-23 06-Mar-23 13-Mar-23 20-Mar-23 27-Mar-23 03-Apr-23 10-Apr-23
PATHWAY 3
BUILDING 14 - LABORATORY
GYM
PATHWAY 1
PATHWAY 2
PROJECT STATUS %
8%
92%
PATHWAY 3 31-Oct-22 21-Nov-22 21 Not Started Need to priotize for preparation for Christmas Party
GYM 0 Complete
PROJECT STATUS %
STATUS COUNT %
In Progress 0 0%
Complete 1 8%
Overdue 0 0%
On Hold 0 0%
TOTAL 12 100%