Purlins Upn Channel
Purlins Upn Channel
Job Ref.
Engineering Consultants Group CHECKING AND PACKING HALL
Bldg. 2, Block 10, El Sefarat District Calc. By Date Checked By Date Rev.
PURLINS ID :- ( P-1 )
Span = 11.00 m
Spacing = 2.00 m
α = 10.00
Using tie rods = No tie rod
1)- APPLIED FORCES :-
DEAD LOAD
O.W of C.sheets = 20.00 Kg/m2
WDL = 40.62 Kg/m\
WXDL = 0.0855 t/m\ WYDL = 0.0151 t/m\
MXDL = 1.2932 m.t MYDL = 0.2280 m.t
QXDL = 0.4702 t
LIVE LOAD
a)Uniform load
Roof is inaccessible
L.L. = 48.24 Kg/m2
WLL = 96.49 Kg/m\
WXLL = 0.0950 t/m\ WYLL = 0.0168 t/m\
MXLL = 1.4372 m.t MYLL = 0.2534 m.t
QXLL = 0.5226 t
b)100 Kg concentrated load
PX = 98.48 Kg PY = 17.36 Kg
MXLL = 0.2708 m.t MYLL = 0.0478 m.t
QXLL = 0.0492 t
MAX LIVE LOAD :-
MXLL = 1.4372 m.t MYLL = 0.2534 m.t
QXLL = 0.5226 t
WIND LOAD
Ce = -0.60
K = 1.10
q = 50.00 Kg/m2
WXWL = -0.3743 t/m\
MXWL = -5.6614 m.t Neglect wind load
QXWL = 0.00 t
2)-CHOICE OF SECTION :-
U.P.N. 300
Shear Stress
qw = 0.26 t/cm2 < 0.35xFy SAFE
h
4)- CHECK DEFLECTION :- X
W
E
B
δL.L = 1.07 cm < span/300 SAFE
ECG Project Name
Job Ref.
Engineering Consultants Group CHECKING AND PACKING HALL
Bldg. 2, Block 10, El Sefarat District Calc. By Date Checked By Date Rev.