NANOPORE SETUP GUIDE

To set up a nanopore before proceeding to TRPS analysis, complete the following steps until a stable baseline has been re-
established. In the Exoid Control Suite (ECS) software, these steps are provided on the screen as a walkthrough and contain
some extra characterisation steps to make measurements easier further along the track. This guide should only be followed
in the event that manual nanopore setup is required.

Prepare the solutions Prepare the Fluid Cell Load the Nanopore

Prepare Measurement Electrolyte Soak lower fluid cell for 15 mins in Fit the arms of the nanopore
(ME), Wetting, and Coating 70% EtOH. onto the stretcher jaws and
solutions. apply a stretch of 47 mm. On the
Prepare calibration and sample Exoid, calibration of the stretch is
particles. automatic.

Wetting Protocol Coating Protocol (Biologicals Only) Equilibrate Baseline

Load wetting solution into the Load coating solution into the Load ME into the fluid cell and
fluid cell and apply maximum fluid cell and apply maximum establish a stable baseline.
pressure for 2 minutes. pressure of 10 minutes.

Insert Calibration Particles Optimise Parameters Proceed to TRPS Analysis

Load 35 µL of calibration particles Adjust voltage, pressure and Run calibration and samples
into the upper fluid cell. stretch to achieve current of as required to complete TRPS
120-140 nA, blockade size of analysis.
0.2-2 nA and particle rate of
200-1500 particles per minute.