INSTITUTO TECNOLOGICO DE DURANGO

UNIDAD 3
MATERIALES Y PROCESOS CONSTRUCTIVOS
NUMEROS GENERADORES

ALUMNO: ADRIAN ROLDAN PALACIOS


PROFESOR: ING. VICTOR MANUEL REVELES CASTAÑEDA
GRUPO: CIVIL 2H

ADRIAN RP.
FIRMA
1 AaF ML 2.7 3 8.1
2 AaC ML 2.7 2 5.4
3 CaF ML 2.7 2 5.4
5 D' a F ML 2.7 1 2.7
6 CaF ML 2.7 2 5.4
1.7 CASTILLOS PLANTA BAJA 7 CaF ML 2.7 2 5.4
8 DaF ML 2.7 2 5.4
9 AaD ML 2.7 2 5.4
A 1 a 13 ML 2.7 5 13.5
C 5a6 ML 2.7 1 2.7
F 1 a 13 ML 2.7 2 5.4
64.8
2 AaF ML 2.7 3 8.1
4 CaF ML 2.7 2 5.4
5 AaB ML 2.7 2 5.4
5 DaF ML 2.7 1 2.7
7 CaF ML 2.7 3 8.1
1.7.1 CASTILLOS SEGUNDA PLANTA 8 AaB ML 2.7 2 5.4
11 CaF ML 2.7 2 5.4
12 AaC ML 2.7 2 5.4
A 1 a 13 ML 2.7 2 5.4
C 4a5 ML 2.7 1 2.7
C 8 a 12 ML 2.7 1 2.7
F 1 a 13 ML 2.7 1 2.7
59.4 124.20
1 AaF ML 5.97 1 5.97
2 AaC ML 2.985 1 2.985
3 CaF ML 2.985 1 2.985
5 D' a F ML 1.13 1 1.13
6 CaF ML 2.985 1 2.985
7 CaF ML 2.91 1 2.91
1.8 DALA DE CERRAMIENTO PLANTA BAJA 8 DaF ML 1.835 1 1.835
9 AaD ML 4.135 1 4.135
A 1 a 13 ML 20.2 1 20.2
C 2a3 ML 1.99 1 1.99
C 5a6 ML 0.97 1 0.97
D 7a9 ML 1.95 1 1.95
F 1 a 13 ML 20.2 1 20.2
70.245
2 AaF ML 5.97 1 5.97
4 CaF ML 3.21 1 3.21
5 AaF ML 5.82 1 5.82
7 CaF ML 2.835 1 2.835
8 AaB ML 2.835 1 2.835
11 CaF ML 2.985 1 2.985
1.8.1 12 AaC ML 2.985 1 2.985
DALA DE CERRAMIENTO PLANTA ALTA
A 2 a 12 ML 12.25 1 12.25
B 4' a 5 ML 0.75 1 0.75
B 8a9 ML 0.75 1 0.75
C 4a5 ML 1.62 1 1.62
C 8 a 11 ML 4.135 1 4.135
E 7 a 7' ML 0.75 1 0.75
F 2 a 11 ML 11.13 1 11.13
58.025 128.27
1 AaF M2 5.97 2.5 1 14.925
2 AaC M2 2.985 2.5 1 5.289 2.1735 Ventana
3 CaF M2 2.985 2.5 1 5.7345 1.728 Ventana
5 D' a F M2 1.13 2.5 1 2.825
6 CaF M2 2.985 2.5 1 7.4625
7 CaF M2 2.91 2.5 1 7.275
1.9 MUROS PLANTA BAJA 8 DaF M2 1.835 2.5 1 4.0715 0.516 Ventana
9 AaD M2 4.135 2.5 1 8.164 2.1735 Ventana
A 1 a 13 M2 20.2 2.5 1 50.5
C 2a3 M2 1.99 2.5 1 2.959 2.016 Puerta
C 5a6 M2 0.97 2.5 1 2.425
D 7a9 M2 1.95 2.5 1 3.3 1.575 Puerta
F 1 a 13 M2 20.2 2.5 1 50.5
165.4305
2 AaF M2 5.97 2.5 1 11.5905 3.3345 Ventanas
4 CaF M2 3.21 2.5 1 7.641 0.384 Ventanas
5 AaF M2 5.82 2.5 1 10.644 3.906 Puerta
7 CaF M2 2.835 2.5 1 5.562 1.5255 Ventana
8 AaC M2 2.835 2.5 1 5.0715 2.016 Puerta
11 CaF M2 2.985 2.5 1 5.7345 1.728 Ventana
1.9.1 MUROS PLANTA ALTA 12 AaC M2 2.985 2.5 1 6.018 1.4445 Ventana
A 2 a 12 M2 12.25 2.5 1 30.625
B 4' a 5 M2 0.75 2.5 1 1.875
B 8a9 M2 0.75 2.5 1 1.875
C 4a5 M2 1.62 2.5 1 4.05
C 8 a 12 M2 4.135 2.5 1 9.0415 1.296 Ventana
E 7 a 7' M2 0.75 2.5 1 1.875
F 2 a 11 M2 11.13 2.5 1 27.825
129.428
294.8585

ADRIAN RP.
CASTILLOS 124.2 ML
Materiales Unidad
Varilla No.4 Pza 496.8 ML 41.40 Pzas 494.8128 KG
Alambron KG 248.4 ML 61.85 KG
Alambre recocido KG 27.83 KG
Cemento Bultos 22.4 Bultos
Grava M3 2.55 m3
Arena M3 1.70 m3

Volumen por 1m3 = 0.0225


CALCULO POR METRO LINEAL Calculos Totales Volumen Total = 2.7945
Varilla No. 4 = 4 ML 496.8 mts
Estribos = 0.4 5 2 mts
Alambron = 248.4
Alambre recocido
100% 556.66
5% 27.83
Concreto de 200 kg/m2
Cemento 8 Bultos 16 Barricas
Grava 6 Barricas 0.912
Arena 4 Barricas 0.608

ADRIAN RP.
DALAS DE CERRAMIENTO 128.27 ML
Materiales Unidad
Varilla No.4 Pza 513.08 ML 42.8 Pzas 287.3248 KG
Alambron KG 384.81 ML 95.82 KG
Alambre recocido KG 19.16 KG
Cemento Bultos 30.78 Bultos
Grava M3 3.51 m3
Arena M3 2.34 m3

CALCULO POR METRO LINEAL Calculos Totales Volumen por 1m3 = 0.03
Varilla No.3 = 4 ML 513.08 mts Volumen Total = 3.85
Estribos = 0.5 6 3 mts
Alambron = 384.81 ML
Alambre recocido
100% 383.14
5% 19.16
Concreto de 200 kg/m2
Cemento 8 Bultos 16 Barricas
Grava 6 Barricas 0.912
Arena 4 Barricas 0.608

ADRIAN RP.
MUROS DE LADRILLO 294.8585 m2
Pzas m3 50.13 m3
Ladrillos 13269
Mortero 16.3 Bultos
Arena 130.4 2.48 m3
Por m2
pza Volumen m3
Ladrillos 45 0.1339 Volumen de muro
Junta 0.17 0.036125 50.13

9 Bultos = 1 m3 de mortero 0.325125


8 Cubetas de arena= 1 bulto de mortero 2.601

ADRIAN RP.