BILL OF QUANTITY (upah)

VOLUME
NO ITEM SAT TOTAL UNIT PRICE TOTAL PRICE
T.19 T.72
A PEKERJAAN PONDASI
1 Pembersihan Lokasi m2 125 125 250 4.200 1.050.000
2 Geometry Bowplank (termasuk Stub Setting) m 25 25 50 Include Beton
3 Uji Kubus Beton (15x15x15 cm3) bh 2 2 4 Include Beton
4 Galian Tanah m3 32,0 32,0 64,0 35.000 2.240.000
5 Pengurugan kembali dan Pemadatan per 20cm m3 12,0 12,0 24,0 35.000 840.000
6 Pengurugan dan Pemadatan pasir t=10cm m3 3,6 3,6 7,2 Include Beton
7 Lantai kerja t=5cm m3 1,8 1,8 3,6 Include Beton
8 Beton K.225 m3 31,6 31,6 63,2 800.000 50.585.600
9 Pembesian Tulangan
Screw U32-BJTD32 kg 2.051 2.051 4.101 Include Beton
Plain U24-BJTP24 kg 625 625 1.251 Include Beton
10 Bekisting m2 69 70 140 Include Beton
11 PVC dia 2 inch untuk Grounding Tower m 8 8 16 Include Beton
12 Patok Beton batas lahan bh 4 4 8 34.500 276.000
13 Dewatering ls 1 1 2 196.500 393.000
14 Finishing dan Site Cleaning ls 1 1 2 Include Beton
TOTAL A 55.384.600
Bobokan Beton Bore Pile untuk Pilecup titik 16 16 32 500.000 16.000.000
A 71.384.600

B PEKERJAAN BORE PILE


1 T.19 AA6+3 m 222 222 140.000 31.136.000
Pengeboran dia 40cm m 222 222
Beton K.225 m3 29 29 600.000 17.347.200
Pembesian Tulangan kg 3.709 3.709

2 T.72 AA6+9 m 290 290 140.000 40.544.000


Pengeboran dia 40cm m 290 290
Beton K.225 m3 38 38 600.000 22.588.800
Pembesian Tulangan kg 3.709 3.709
B 71.680.000
C 39.936.000
TOTAL A+B 143.064.600
TOTAL A+C 111.320.600