PROJECT DETAILS

LOCATION
Name of Project:

Project Scale: 1 Unit


Contract Cost: Php
Date Started: April 05, 2017
Contract Duration: 135 CD
Contractor:
Original Target Date of Completion: August 18, 2017
Contract Allowance for Unworkable Days: 0
Revised Expiry Date: October 03, 2017
Report Period % Projected Accomp % Accomp to Date Slippage

May,2017 0 0.00%
June, 2017 5.00% 5.00%
July, 2017 20.00% 20.00%
August, 2017 28.00% 28.00%
September, 2017 40.00% 40.00%
October, 2017 45.00% 45.00%
November, 2017 56.00% 56.00%

Cumulative Extension Revised Expiry Date


Period Covered # of unworkable days Shutdown Granted
April, 2017 0
May, 2017 5 5 5 August 23, 2017
June, 2017 14 19 19 September 06, 2017
July, 2017 18 37 37 September 24, 2017
August, 2017 9 46 46 October 03, 2017
September, 2017 -
October, 2017 -

TOTAL 46

Date Started: April 05, 2017 Prepared By:


ENGINEER II

Reviewed By:
RAED CHIEF
Original Completion
Date:
Revised Comp. Date: Approved by: